Telenor Mobile Communications AS v. Storm LLC ( 2009 )


Menu:
  •      07-4974-cv(L); 08-6184-cv(CON); 08-6188-cv(CON)
    Telenor Mobile Communications AS v. Storm LLC
    1                         UNITED STATES COURT OF APPEALS
    2                             FOR THE SECOND CIRCUIT
    3                                August Term, 2008
    4    (Argued:    February 4, 2009                      Decided: October 8, 2009)
    5                           Docket Nos. 07-4974-cv(L);
    6                       08-6184-cv(CON); 08-6188-cv(CON)
    7                    -------------------------------------
    8                       TELENOR MOBILE COMMUNICATIONS AS,
    9                               Petitioner-Appellee,
    10                                      - v. -
    11                                    STORM LLC,
    12                             Respondent-Appellant,
    13                  ALTIMO HOLDINGS & INVESTMENTS LIMITED,
    14                     ALPREN LIMITED, HARDLAKE LIMITED,
    15                      Additional Contemnors-Appellants.
    16                   -------------------------------------
    17   Before:     SACK and PARKER, Circuit Judges, and STANCEU, Judge.*
    18               Consolidated appeals from a judgment and post-judgment
    19   orders of the United States District Court for the Southern
    20   District of New York.      In the judgment, the district court
    21   (Gerard E. Lynch, Judge) confirmed a final arbitral award in
    22   favor of the petitioner and denied the respondent's cross-motion
    23   to vacate.    We agree with the district court that the arbitration
    24   panel did not "manifestly disregard" the law either by failing to
    *
    The Honorable Timothy C. Stanceu, of the United States
    Court of International Trade, sitting by designation.
    1    give preclusive effect to Ukrainian court judgments that the
    2    parties' dispute was not arbitrable because the respondent's
    3    agent lacked authority to execute the agreement giving rise to
    4    the dispute, or by failing to require a trial to determine the
    5    agreement's arbitrability pursuant to Sphere Drake Ins. Ltd. v.
    6    Clarendon Nat'l Ins. Co., 
    263 F.3d 26
     (2d Cir. 2001).   We also
    7    agree with the district court that the agreement was arbitrable
    8    as a matter of law because the respondent's agent had the
    9    apparent authority to execute it.
    10             Affirmed.
    11                            ROBERT L. SILLS, Orrick, Herrington &
    12                            Sutcliffe LLP (Jay K. Musoff, of
    13                            counsel), New York, NY, for Petitioner-
    14                            Appellee.
    15                            PIETER VAN TOL, Lovells LLP (Gonzalo S.
    16                            Zeballos, of counsel), New York, NY, for
    17                            Respondent-Appellant.
    18                            RONALD S. ROLFE, Cravath, Swaine & Moore
    19                            LLP, New York, NY, for Additional
    20                            Contemnors-Appellants.
    21   SACK, Circuit Judge:
    22             Telenor Mobile Communications AS ("Telenor"), a
    23   Norwegian company, and Storm LLC ("Storm"), a Ukrainian company,
    24   own Kyivstar G.S.M. ("Kyivstar"), a Ukrainian mobile
    25   telecommunications company.   A shareholders agreement among the
    26   three companies dated January 30, 2004 (the "2004 Agreement")
    27   sets forth the terms of such ownership and provides that any
    28   disputes that arise in connection with the agreement will be
    2
    1    submitted to arbitration.   The present consolidated appeals1
    2    result from an arbitration, commenced by Telenor, seeking relief
    3    for Storm's alleged breach of the 2004 Agreement.
    4              This opinion addresses appeal No. 07-4974-cv, in which
    5    Storm challenges a judgment of the United States District Court
    6    for the Southern District of New York.2   The district court
    7    (Gerard E. Lynch, Judge) granted Telenor's petition to confirm
    8    the arbitral award in its favor and denied Storm's cross-motion
    9    for vacatur.
    10             On appeal, Storm argues that the arbitration panel
    11   "manifestly disregarded" the law in two respects.   First, Storm
    12   contends it was reversible error for the panel to fail to give
    13   preclusive effect to Ukrainian court judgments concluding that
    14   the 2004 Agreement was not arbitrable because, according to the
    15   Ukrainian courts, the agent who signed the agreement on behalf of
    16   Storm was not authorized to do so.   In the alternative, Storm
    17   contends, the panel manifestly disregarded our decision in Sphere
    18   Drake Ins. Ltd. v. Clarendon Nat'l Ins. Co., 
    263 F.3d 26
     (2d Cir.
    19   2001), by failing to require a trial on the arbitrability issue
    20   in the district court.   We conclude that the panel had colorable
    1
    On October 5, 2009, the parties sought by stipulation to
    "withdraw [this appeal] from active consideration." We decline
    to do so. Cf. Khouzam v. Ashcroft, 
    361 F.3d 161
    , 167 (2d Cir.
    2004) ("Action by the court is not a subject that the parties may
    negotiate among themselves, and a judicial act, such as a
    dismissal of a petition, is normally taken only when the
    appellate court determines that such action is warranted on the
    merits.")
    2
    We address appeals from post-judgment orders of the
    district court in an accompanying summary order.
    3
    1    reasons for rejecting both arguments and it therefore did not
    2    manifestly disregard the law in either respect.     Storm also
    3    contends, on the merits, that the 2004 Agreement is not
    4    arbitrable.    We conclude, as did the arbitration panel and the
    5    district court, that Storm's agent had at least the apparent
    6    authority to execute the 2004 Agreement on behalf of Storm, and,
    7    therefore, that the agreement is arbitrable.
    8                The judgment of the district court is therefore
    9    affirmed.
    10                                BACKGROUND
    11               Events Prior to 2004
    12               In 2002, a shareholders agreement dated March 26, 1998,
    13   (the "1998 Agreement") set forth the terms of the ownership of
    14   Kyivstar's shares.    The 1998 Agreement contemplated the existence
    15   of five stakeholders, including Telenor and Storm.     At some point
    16   in early 2002, however, Telenor and Storm agreed to attempt to
    17   buy out the other three stakeholders.     By August of that year,
    18   they had nearly succeeded: only Omega JSC ("Omega") remained.       In
    19   light of Kyivstar's newly altered ownership structure and in
    20   anticipation of Omega's eventual capitulation, Storm and Telenor
    21   negotiated an interim voting agreement between themselves (the
    22   "Voting Agreement"), which supplemented and altered their rights
    23   and obligations as to each other under the 1998 Agreement.
    24               The Voting Agreement was executed on September 2, 2002.
    25   Valeriy Nilov, Storm's "General Director," signed for Storm.
    26   Three days earlier, Storm had sent Telenor a copy of a unanimous
    4
    1    resolution by Storm shareholders authorizing Nilov to do so.     See
    2    Storm LLC, Notice Regarding Resolutions Adopted by Written
    3    Polling, Aug. 30, 2002, at 2-3 ("Authorization of the General
    4    Director of . . . 'Storm', Nilov Valeriy Vladimirovich, to
    5    execute and deliver [inter alia, the Voting Agreement]
    6    and . . . take or cause to be taken any and all other actions, as
    7    are required or desirable in connection with this Resolution and
    8    the above-referenced agreements.").
    9              The Voting Agreement contained a promise by each of the
    10   parties to execute a new shareholders agreement once Storm bought
    11   Omega's shares or the 1998 Agreement was terminated, whichever
    12   occurred first.   See Voting Agreement § 2.05 (providing that,
    13   within three days after the earlier of either condition, "the
    14   Shareholders [viz., Telenor and Storm] agree to, and to cause
    15   [Kyivstar] to, execute and deliver the New Shareholders
    16   Agreement").   A form for the contemplated new shareholders
    17   agreement was attached to the Voting Agreement as an exhibit.     It
    18   was in all substantive respects but one -- a provision setting
    19   forth the terms of material breach, which was later amended at
    20   Storm's request identical to what would be the 2004 Agreement.
    21             On October 29, 2002, Storm sent Telenor a document,
    22   signed by Nilov, entitled "Certificate of Senior Officer of
    23   Purchaser."    The Certificate included, among other things, a copy
    24   of the Storm shareholders resolution authorizing Nilov to execute
    25   the Voting Agreement, and minutes of a meeting occurring on
    26   October 7, 2002, which confirmed the resolutions adopted by
    5
    1    written polling on August 30, 2002.   The Certificate provided
    2    that those documents "constitute[] valid approval under the laws
    3    of Ukraine of [Storm's] execution, delivery and performance of
    4    [inter alia, the Voting Agreement] and any other documents in
    5    implementation of [inter alia, the Voting Agreement]."
    6              The 2004 Agreement
    7              In January 2004, Storm purchased the outstanding
    8    Kyivstar shares from Omega.    After negotiations between Storm and
    9    Telenor about possible alteration of the material breach
    10   provision of the contemplated new shareholders agreement, a
    11   negotiator for Storm wrote to Telenor by email on January 29,
    12   saying: "Storm reviewed the language of the New Shareholders
    13   Agreement that you distributed yesterday and agreed to it.     We
    14   are ready to sign it tomorrow."
    15             The following day, Nilov and representatives from
    16   Telenor and Kyivstar signed the 2004 Agreement.   Storm sent
    17   Telenor two documents, each entitled "Certificate of Incumbency
    18   and Authority of Storm," which were signed by the chairman of
    19   Storm and another Storm official, respectively.   The documents
    20   each certified that Nilov was "duly authorized to sign, on behalf
    21   of Storm[,] . . . the Shareholders Agreement dated January 30,
    22   2004 between and among Telenor, Storm, Omega and Kyivstar."
    23   Unlike the 2002 "Certificate of Senior Officer of Purchaser,"
    24   however, the "Certificate[s] of Incumbency and Authority of
    25   Storm" did not attach or incorporate by reference copies of
    26   documentation of the shareholder authorization.
    6
    1                The 2004 Agreement contains an arbitration provision
    2    stating that "[a]ny and all disputes and controversies arising
    3    under, relating to or in connection with this Agreement shall be
    4    settled by arbitration by a panel of three (3) arbitrators under
    5    the United Nations Commission on International Trade Law
    6    (UNCITRAL) Arbitration Rules then in force."    2004 Agreement §
    7    12.01(a).    It precludes any other sort of action "in connection
    8    with any matter arising out of or in connection with this
    9    Agreement," except for actions in connection with arbitration.
    10   Id. § 12.01(b).
    11               The Arbitration and the Ukrainian Proceedings
    12               Pursuant to the 2004 Agreement's arbitration provision,
    13   Telenor instituted an arbitration against Storm on February 7,
    14   2006, alleging that Storm had breached the 2004 Agreement by (1)
    15   violating its obligation thereunder not to frustrate Kyivstar
    16   board activities through Storm's absence; (2) violating a
    17   noncompete provision therein by "acquiring an equity interest in
    18   at least one other company engaged in the mobile
    19   telecommunications business in Ukraine"; and (3) violating the
    20   arbitration provision therein by "prosecut[ing] a series of court
    21   actions throughout Ukraine, attacking provisions of the
    22   Shareholders Agreement and Kyivstar's charter."    Telenor sought,
    23   among other relief, a declaration that Storm had breached the
    24   2004 Agreement, an injunction requiring Storm to participate in
    25   the governance and management of Kyivstar, an anti-suit
    26   injunction, and damages.
    7
    1                On April 14, 2006 -- the day of the first conference of
    2    the arbitration panel -- Alpren Limited ("Alpren"), a Cyprus-
    3    based subsidiary of Altimo Holdings & Investment Limited
    4    ("Altimo"), brought suit in a Ukrainian court against Storm.
    5    Alpren and Altimo are the owners of Storm, and Alpren, Altimo,
    6    and Storm all belong to the same Russian corporate group, the
    7    Alfa Group Consortium.    Alpren applied to the Ukrainian court for
    8    a declaration that the 2004 Agreement was invalid because Nilov
    9    lacked the authority to execute it on Storm's behalf.
    10   Apparently, neither Telenor nor the arbitration panel were
    11   notified of the Alpren lawsuit.
    12               Storm retained no counsel and submitted no written
    13   defense to the Alpren suit.    Instead, Vadim Klymenko, an Altimo
    14   officer responsible for that company's "litigation" and
    15   "arbitration" but who is not an attorney-at-law, appeared for
    16   Storm and registered an oral opposition on the ground that the
    17   arbitration panel had jurisdiction over Alpren's claim.    The
    18   proceeding lasted approximately 20 minutes.
    19               On April 25, 2006, the Ukrainian court concluded that
    20   Nilov lacked the authority to execute the 2004 Agreement on
    21   behalf of Storm.    The court's decision "rendered" that agreement
    22   "null and void in full, including the arbitration clause, from
    23   the time of [Nilov's] execution [of the document]."    Storm
    24   appealed.    On May 25, 2006, the Ukrainian appeals court affirmed.
    8
    1              Five days later, Storm filed a statement of defense in
    2    the arbitration panel arguing, among other things, that Telenor's
    3    claims were not arbitrable in light of the Ukrainian judgment.
    4    Storm also moved before the panel to dismiss the arbitration.    On
    5    October 22, 2006, the panel issued a partial final award and
    6    denied the motion.    The panel concluded that it had jurisdiction
    7    to determine the 2004 Agreement's arbitrability.    It also
    8    concluded that the dispute was arbitrable, notwithstanding the
    9    Ukrainian decision in the Alpren suit, because it found that
    10   Storm and Telenor "had a clear intent to have their disputes
    11   resolved through arbitration," and that the arbitration provision
    12   of the 2004 Agreement was severable and thus not subject to the
    13   Ukrainian judgment.   Partial Final Award 11-13.   The panel noted
    14   that the Ukranian court did not address the severability
    15   question, because Alpren and Storm did not present the question
    16   to the court and because Telenor was never even notified of the
    17   proceeding.   Id. at 14.
    18             Shortly thereafter, Storm asked the Ukrainian court of
    19   appeals to clarify whether, in the court's opinion, the
    20   arbitration provision of the 2004 Agreement and the agreement as
    21   a whole were invalid in light of the potential severability of
    22   the arbitration clause.    On November 8, 2006, the court
    23   concluded, by now unsurprisingly, that the arbitration agreement
    24   was invalid and that any arbitration pursuant to it was in
    25   violation of the court's prior order.
    9
    1               On November 13, 2006, Storm applied in New York State
    2    Supreme Court for an injunction terminating the arbitration
    3    proceedings and vacating the partial final award in light of the
    4    Ukrainian decisions.    Telenor removed the New York lawsuit to the
    5    United States District Court for the Southern District of New
    6    York.   Storm then made a motion in that forum seeking a
    7    preliminary injunction.    The district court denied the motion on
    8    the grounds that the panel's order was interlocutory and
    9    therefore not ordinarily subject to appeal, and that Storm was
    10   unlikely to prevail on the merits.
    11              A Ukrainian court then, upon Alpren's application,
    12   enjoined Telenor, Storm, and Klymenko from participating in the
    13   arbitration.   Telenor received no notice of the injunction and
    14   was not a party to this new Alpren lawsuit.    Storm twice applied
    15   to the arbitration panel to stop the arbitration pursuant to the
    16   Ukrainian injunction, but the panel denied each application.
    17              In an attempt to put a stop to the Ukrainian
    18   litigation, Telenor applied in these federal district court
    19   proceedings for an anti-suit injunction against Storm and its
    20   related entities.    The district court issued such a temporary
    21   restraining order.
    22              Following an evidentiary hearing, the district court
    23   issued an anti-suit injunction, writing that "there is no doubt
    24   that [the Ukrainian] litigation has been designed to, and has had
    25   the effect of, interfering in the arbitration process" -- indeed,
    26   that it was "conducted in the most vexatious way possible" -- and
    10
    1    that the court substantially agreed that "Nilov . . . had at
    2    least apparent authority to sign the [2004 Agreement]" under
    3    either New York or federal law.    Storm LLC v. Telenor Mobile
    4    Commc'ns AS, No. 06 Civ. 13157(GEL), 
    2006 WL 3735657
    , at *8-*9,
    5    
    2006 U.S. Dist. LEXIS 90978
    , at *23-*26 (S.D.N.Y. Dec. 18, 2006).
    6               With the injunction in place, the arbitration hearings
    7    continued.   Storm refused to participate.
    8               On July 2, 2007, the arbitration panel issued a final
    9    award, which reaffirmed the partial final award's findings in
    10   light of subsequent events.   See Final Award 33-36.   The panel
    11   held, as relevant to this appeal, that Nilov had both actual and
    12   apparent authority under New York law to execute the 2004
    13   Agreement on Storm's behalf, see id. at 36, 43-53, and that Storm
    14   was in breach of the agreement in several respects, see id. at
    15   55.   Telenor was granted injunctive relief but no damages.   See
    16   id. at 65-68.
    17              The Confirmation of the Award
    18              Telenor petitioned the district court for a
    19   confirmation of the final arbitral award.    Storm cross-moved for
    20   vacatur.   With a lengthy opinion that appears to reflect
    21   decreasing patience with Storm's tactics, Telenor Mobile Commc'ns
    22   AS v. Storm LLC, 
    524 F. Supp. 2d 332
     (S.D.N.Y. 2007), the court
    23   granted Telenor's application and denied Storm's.    The court
    24   rejected Storm's contentions that the panel had manifestly
    25   disregarded the law by failing to give determinative effect to
    26   the Ukrainian judgments that the 2004 Agreement was never
    11
    1    executed by Storm and thus not arbitrable.    After conducting its
    2    own independent assessment of arbitrability, the district court
    3    concluded that Storm had proffered insufficient evidence to
    4    warrant a trial on the issue.   The court wrote:
    5             Storm provided every conceivable assurance to
    6             Telenor that its signatory officers were
    7             empowered to bind it to [the 2004 Agreement].
    8             When Storm breached the agreement, it was
    9             provided with precisely the fair and
    10             impartial hearing it had bargained for . . .
    11             despite making repeated efforts to renege on
    12             its agreement and to torpedo the proceeding
    13             by collusive and vexatious litigation.
    14   
    Id. at 369
    .
    15             Storm appeals.
    16                              DISCUSSION
    17             I. Governing Legal Standards
    18   A. Review of Arbitral Awards Under the New York Convention
    19             Federal jurisdiction over the final arbitral award in
    20   favor of Telenor arises from Chapter 2 of the Federal Arbitration
    21   Act ("FAA"), 
    9 U.S.C. §§ 201-08
    , which empowers the federal
    22   courts to enforce arbitrations, such as this one, governed by the
    23   New York Convention on the Recognition and Enforcement of Foreign
    24   Arbitral Awards, June 10, 1958, 21 U.S.T. 2517, 330 U.N.T.S. 38
    25   (the "New York Convention" or the "Convention").   See 9 U.S.C.
    26   § 201 ("The Convention . . . shall be enforced in United States
    27   courts in accordance with this chapter."); id. § 203 ("An action
    28   or proceeding under the Convention shall be deemed to arise under
    29   the laws and treaties of the United States.   The district courts
    30   of the United States . . . shall have original jurisdiction over
    12
    1    such an action or proceeding . . . ."); Vaden v. Discover Bank,
    2    
    129 S. Ct. 1262
    , 1271 n.9 (2009).3
    3              "Given the strong public policy in favor of
    4    international arbitration, review of arbitral awards under the
    5    New York Convention is very limited in order to avoid undermining
    6    the twin goals of arbitration, namely, settling disputes
    7    efficiently and avoiding long and expensive litigation."
    8    Encyclopaedia Universalis S.A. v. Encyclopaedia Britannica, Inc.,
    9    
    403 F.3d 85
    , 90 (2d Cir. 2005) (citation, internal quotation
    10   marks, and ellipsis omitted).   Storm's arguments on appeal
    11   implicate three types of such limited review.
    12             1. Defenses to Enforcement of the Arbitral Award.
    13   Pursuant to the New York Convention as incorporated by the FAA, a
    14   district court, upon petition by a party to a qualifying arbitral
    15   award, "shall confirm the award unless it finds one of the
    16   grounds for refusal or deferral of recognition or enforcement of
    17   the award specified in the . . . Convention."   
    9 U.S.C. § 207
    .
    18   The Convention sets forth seven grounds for denial of
    19   confirmation, including, of relevance to this appeal, if
    3
    The parties assume that the New York Convention governs
    this commercial dispute, and, because the dispute is between two
    foreign corporations, we conclude that that assumption is
    correct. See Yusuf Ahmed Alghanim & Sons, W.L.L. v. Toys "R" Us,
    Inc., 
    126 F.3d 15
    , 19 (2d Cir. 1997) (holding that New York
    Convention governed dispute involving conduct occurring in the
    Middle East between nondomestic parties and a domestic
    corporation, because Convention encompasses awards "pronounced in
    accordance with foreign law or involving parties domiciled or
    having their principal place of business outside the enforcing
    jurisdiction" (quoting Bergesen v. Joseph Muller Corp., 
    710 F.2d 928
    , 932 (2d Cir. 1983)), cert. denied, 
    522 U.S. 1111
     (1998).
    13
    1   "recognition or enforcement of the award would be contrary to the
    2   public policy of [the] country [in which that relief is sought],"
    3   New York Convention, art. V(2)(b).4
    4
    The grounds are:
    (a) The parties to the agreement [to
    arbitrate] were, under the law applicable to
    them, under some incapacity, or the said
    agreement is not valid under the law to which
    the parties have subjected it or, failing any
    indication thereon, under the law of the
    country were the award was made; or
    (b) The party against whom the award is
    invoked was not given proper notice of the
    appointment of the arbitrator or of the
    arbitration proceedings or was otherwise
    unable to present his case; or
    (c) The award deals with a difference not
    contemplated by or not falling within the
    terms of the submission to arbitration, or it
    contains decisions on matters beyond the
    scope of the submission to arbitration,
    provided that, if the decisions on matters
    submitted to arbitration can be separated
    from those not so submitted, that part of the
    award which contains decisions on matters
    submitted to arbitration may be recognized
    and enforced; or
    (d) The composition of the arbitral authority
    or the arbitral procedure was not in
    accordance with the agreement of the parties,
    or, failing such agreement, was not in
    accordance with the law of the country where
    the arbitration took place; or
    (e) The award has not yet become binding on
    the parties, or has been set aside by a
    competent authority of the country in which,
    or under the law of which, that award was
    made.
    New York Convention art. V(1).   And:
    (a) The subject matter of the difference is
    not capable of settlement by arbitration
    14
    1              "The party opposing enforcement of an arbitral award
    2    has the burden to prove that one of the seven defenses under the
    3    New York Convention applies."    Encyclopaedia Universalis, 403
    4    F.3d at 90.    "The burden is a heavy one, as the showing required
    5    to avoid summary confirmance is high."    Id. (citations, ellipsis,
    6    and internal quotation marks omitted); see also Zeiler v.
    7    Deitsch, 
    500 F.3d 157
    , 164 (2d Cir. 2007) (same).
    8              2. Arbitrability.    A dispute is arbitrable only if the
    9    parties contractually bind themselves to arbitrate it.    See,
    10   e.g., AT&T Techs., Inc. v. Commc'ns Workers of Am., 
    475 U.S. 643
    ,
    11   648 (1986) (noting that "arbitration is a matter of contract");
    12   see also First Options of Chicago, Inc. v. Kaplan, 
    514 U.S. 938
    ,
    13   943 (1995) ("[T]he arbitrability of the merits of a dispute
    14   depends upon whether the parties agreed to arbitrate that
    15   dispute.").    A question of arbitrability is therefore raised
    16   when, as here, someone asserts that an arbitral award should not
    17   be enforced because there was no effective agreement to arbitrate
    18   the dispute.
    19             Review of arbitrability questions is subject to two
    20   important presumptions:   First, "the federal policy in favor of
    21   arbitration requires that 'any doubts concerning the scope of
    under the law of that country [i.e., the
    country where recognition and enforcement is
    sought]; or
    (b) The recognition or enforcement of the
    award would be contrary to the public policy
    of that country.
    
    Id.
     art. V(2).
    15
    1    arbitrable issues' be resolved in favor of arbitration.'"   Shaw
    2    Group Inc. v. Triplefine Int'l Corp., 
    322 F.3d 115
    , 120 (2d Cir.
    3    2003) (quoting Moses H. Cone Mem. Hosp. v. Mercury Constr. Corp.,
    4    
    460 U.S. 1
    , 24-25 (1983)).   Second, arbitrability questions are
    5    presumptively to be decided by the courts, not the arbitrators
    6    themselves.   See 
    id.
     ("[W]hen the doubt concerns who should
    7    decide arbitrability . . . [t]he law [presumptively] favor[s]
    8    judicial rather than arbitral resolution."); see also First
    9    Options, 
    514 U.S. at 944-45
    .   We have written that the latter
    10   presumption can be rebutted only by "clear and unmistakable
    11   evidence from the arbitration agreement, as construed by the
    12   relevant state law, that the parties intended that the question
    13   of arbitrability shall be decided by the arbitrator."   Bell v.
    14   Cendant Corp., 
    293 F.3d 563
    , 566 (2d Cir. 2002) (internal
    15   quotation marks and emphasis omitted); see also Shaw Group, 322
    16   F.3d at 120-21.5
    5
    In Buckeye Check Cashing, Inc. v. Cardegna, 
    546 U.S. 440
    (2006), the Supreme Court made clear that in light of the
    severability of agreements to arbitrate generally, see 
    id. at 445
    , the presumption of judicial resolution of arbitrability
    applies only when a party has specifically challenged the
    arbitration agreement -- "unless the challenge is to the
    arbitration clause itself, the issue of the contract's validity
    is considered by the arbitrator in the first instance," 
    id. at 445-46
    . But Buckeye expressly limited its holding to challenges
    to a "contract's validity," as distinguished "from the issue
    whether any agreement between the alleged obligor and obligee was
    ever concluded," including, as relevant to this appeal, "whether
    the signor lacked authority to commit the alleged principal."
    
    Id.
     at 444 n.1.
    We have not modified our previous ruling that such questions
    about whether a contract was ever made -- like the question
    before us in the instant case -- are presumptively to be decided
    by the court even without a specific challenge to the agreement
    16
    1               The presumption that the court should decide
    2    arbitrability questions also applies when a party seeks to compel
    3    arbitration under the New York Convention.    See New York
    4    Convention, art. II(3) (providing that the court "shall, at the
    5    request of one of the parties, refer the parties to arbitration,
    6    unless it finds that the . . . agreement is null and void,
    7    inoperative or incapable of being performed").    We addressed such
    8    a motion to compel in Sphere Drake Ins. Ltd. v. Clarendon Nat'l
    9    Ins. Co., 
    263 F.3d 26
     (2d Cir. 2001), writing that when "the
    10   making of the agreement to arbitrate is placed in issue . . . the
    11   court must set the issue for trial," so long as "the party
    12   putting the agreement to arbitrate in issue . . . present[s]
    13   'some evidence' in support of its claim."    
    Id. at 30
     (quoting
    14   Interocean Shipping Co. v. Nat'l Shipping & Trading Corp., 462
    
    15 F.2d 673
    , 676 (2d Cir. 1972)).   Depending on the type of claimed
    16   inarbitrability, we noted that the party might also be required
    17   to make a specific challenge to the arbitration clause.      See 
    id.
    to arbitrate. See Sphere Drake Ins. Ltd. v. Clarendon Nat'l Ins.
    Co., 
    263 F.3d 26
    , 31-32 (2d Cir. 2001) (holding that if a party
    alleges that an agreement is "void" -- as distinct from
    "voidable" -- the agreement's validity is subject to judicial
    resolution by "trial" without the party's having to challenge the
    arbitration clause in particular, so long as the party alleges
    "that [the] contract is void and provides some evidence in
    support"). Because we conclude below that even if Storm
    challenged the arbitration clause of the 2004 Agreement in
    particular, it has still failed to provide sufficient evidence
    that this dispute was not arbitrable, we need not decide whether
    this aspect of Sphere Drake survives Buckeye. Cf. Rubin v. Sona
    Int'l Corp., 
    457 F. Supp. 2d 191
    , 193 (S.D.N.Y. 2006) (concluding
    that, in light of Buckeye, "[whether a party] argues that [an]
    agreement is void or voidable, [the party] may only avoid
    arbitration if it can successfully challenge the validity of the
    arbitration clause itself").
    17
    1    at 31-32 (noting that in setting an arbitrability issue for
    2    trial, a party alleging that a contract is void need not
    3    challenge the arbitration clause, but a party alleging that a
    4    contract is voidable must challenge the arbitration clause in
    5    particular); see also supra n.[4].
    6              3. Manifest Disregard.   Federal courts with
    7    jurisdiction to enforce an arbitral award may also consider
    8    whether the award was in "manifest disregard" of the law.   See
    9    Stolt-Nielsen SA v. Animalfeeds Int'l Corp., 
    548 F.3d 85
    , 91-92,
    10   94-95 (2d Cir. 2008).6   The boundaries of the manifest disregard
    6
    In Hall St. Assocs., L.L.C. v. Mattel, Inc., 
    128 S. Ct. 1396
     (2008), the Supreme Court observed that the "manifest
    disregard" doctrine might be a ground for review independent of
    the FAA, or might instead be a name for some, or all, of the
    grounds for vacatur of arbitral awards set forth in Section 10(a)
    of the FAA, 
    9 U.S.C. § 10
    (a), including circumstances "where the
    arbitrators were guilty of misconduct," 
    id.
     § 10(a)(3), or
    "exceeded their powers, or so imperfectly executed them that a
    mutual, final, and definite award upon the subject matter
    submitted was not made," id. § 10(a)(4). See Hall St. at 1403-04
    ("Maybe the term 'manifest disregard' was meant to name a new
    ground for review, but maybe it merely referred to the § 10
    grounds collectively, rather than adding to them."). In Stolt-
    Nielsen, we read Hall St. to hold that the FAA set forth the
    "exclusive" grounds for vacating an arbitration award, and that
    the term "manifest disregard" was merely a "judicial gloss" on
    some of those grounds. Stolt-Nielsen, 
    548 F.3d at 94
    .
    The Supreme Court has granted certiorari to review Stolt-
    Nielsen explicitly on another issue, see 
    129 S. Ct. 2793
     (2009),
    but even if it confirms or rejects our interpretation of the term
    "manifest disregard," that will not affect this appeal. If the
    Stolt-Nielsen interpretation is correct, we may review this
    arbitral award for manifest disregard because the arbitration
    took place in the United States and therefore is "subject to the
    FAA provisions," like Section 10(a), "governing domestic
    arbitration awards." See Zeiler, 
    500 F.3d at 164
    ; see also 
    9 U.S.C. § 208
    . If our interpretation was incorrect, this opinion
    will be applying a judicially created "non-statutory defense to
    enforcement." Telenor Mobile Commc'ns AS v. Storm LLC, 
    524 F. Supp. 2d 332
    , 344 (S.D.N.Y. 2007).
    18
    1    concept are not precisely defined, but the term "clearly means
    2    more than error or misunderstanding with respect to the law."
    3    Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Bobker, 
    808 F.2d 4
        930, 933 (2d Cir. 1986).   A mere demonstration that an
    5    arbitration panel made "the wrong call on the law" does not show
    6    manifest disregard; "the award should be enforced . . . if there
    7    is a barely colorable justification for the outcome reached."
    8    Wallace v. Buttar, 
    378 F.3d 182
    , 190 (2d Cir. 2004) (emphasis in
    9    original) (internal quotation marks omitted).   Examples of
    10   manifest disregard therefore tend to be extreme, such as
    11   "explicitly reject[ing] controlling precedent" or otherwise
    12   reaching a decision that "strains credulity" or lacks even a
    13   "barely colorable" justification.    Stolt-Nielsen, 
    548 F.3d at
    92-
    14   93 (internal quotation marks omitted).   It is, in a word, "rare"
    15   to obtain relief from an arbitral award under this doctrine.    
    Id.
    16   at 91 & n.7 (internal quotation marks omitted).
    17             The "manifest disregard" inquiry has three steps:
    18             First, we must consider whether the law that
    19             was allegedly ignored was clear, and in fact
    20             explicitly applicable to the matter before
    21             the arbitrators. . . .
    22             Second, once it is determined that the law is
    23             clear and plainly applicable, we must find
    24             that the law was in fact improperly applied,
    25             leading to an erroneous outcome. . . .
    26
    27             Third, once the first two inquiries are
    28             satisfied, we look to the subjective element,
    29             that is, the knowledge actually possessed by
    30             the arbitrators. In order to intentionally
    31             disregard the law, the arbitrator must have
    32             known of its existence, and its applicability
    33             to the problem before him.
    19
    1    
    Id. at 93
     (quoting Duferco Int'l Steel Trading v. T. Klaveness
    2    Shipping A/S, 
    333 F.3d 383
    , 389-90 (2d Cir. 2003)).
    3    B. Standard of Review
    4              As a general matter, "[w]e review a district court's
    5    decision to confirm an arbitration award de novo to the extent it
    6    turns on legal questions, and we review any findings of fact for
    7    clear error."   Duferco, 
    333 F.3d at 388
    .   Accordingly, here we
    8    review de novo the question whether the arbitration panel erred
    9    in a respect explicitly set forth by the FAA as a ground for
    10   vacatur of an arbitral award.   See, e.g., Westerbeke Corp. v.
    11   Daihatsu Motor Co., 
    304 F.3d 200
    , 219-23 (2d Cir. 2002).
    12             Similarly, "'[w]hen a party challenges the district
    13   court's review of an arbitral award under the manifest disregard
    14   standard, we review the district court's application of the
    15   standard de novo.'"   Wallace, 
    378 F.3d at 189
     (quoting The GMS
    16   Group, LLC v. Benderson, 
    326 F.3d 75
    , 77 (2d Cir. 2003)).
    17             II. Analysis
    18   A. The Ukrainian Judgments
    19             Storm argues that the arbitration panel manifestly
    20   disregarded the law governing the preclusive effect of foreign
    21   judgments when it failed to give such effect to the Ukrainian
    22   court judgments holding that the 2004 Agreement was never
    23   executed by Storm and is therefore not arbitrable.    Storm also
    24   argues that its compliance with the arbitral award as enforced by
    25   the district court would entail actions that would place it in
    20
    1    contempt of the Ukrainian courts, contrary to New York public policy.
    2               1. Manifest Disregard.   In Ackermann v. Levine, 788
    
    3 F.2d 830
     (2d Cir. 1986), we reiterated the "well-settled rule"
    4    that
    5              a final judgment obtained through sound
    6              procedures in a foreign country is generally
    7              conclusive as to its merits unless (1) the
    8              foreign court lacked jurisdiction . . . ; (2)
    9              the judgment was fraudulently obtained; or
    10              (3) enforcement of the judgment would offend
    11              the public policy of the state in which
    12              enforcement is sought.
    13   Id. at 837 (emphasis in original).    Storm contends that the
    14   arbitration panel manifestly disregarded this rule by failing to
    15   give conclusive weight to the Ukrainian judgments that the 2004
    16   Agreement is not arbitrable.7
    17              The district court disagreed.   It concluded that the
    18   judgments obtained by Alpren against Storm had contravened the
    19   rule against "friendly litigation," see Lord v. Veazie, 
    49 U.S. 20
       (8 How.) 251, 256 (1850) (concluding that such litigation results
    21   in a judgment which "is a mere form" and is therefore "a
    22   nullity").   The district court remarked that it and the
    23   arbitration panel had both previously found the Alpren litigation
    24   to have been collusive.   Telenor, 
    524 F. Supp. 2d at 346-47
    .     The
    25   district court also concluded that the Ukrainian proceedings had
    26   afforded Telenor no notice or opportunity to be heard prior to
    27   the entry of the judgment, and that they were intended to
    7
    The first and third steps of the manifest disregard
    inquiry -- that the Ackermann rule was clear, plainly applicable,
    and made known to the arbitration panel -- are undisputed.
    21
    1    undermine a possible confirmation of an award in Telenor's favor.
    2    
    Id. at 347
    .    In light of those conclusions, the court found that
    3    the Ukrainian procedures were not "sound" for Ackermann purposes
    4    and therefore not binding on the arbitration panel.    
    Id. at 348
    .
    5              Storm argues that the arbitration panel did not
    6    actually find that the Ukrainian actions by Alpren were
    7    collusive.    To be sure, the panel did not employ the word
    8    "collusive" in its partial or final award.    But the panel does
    9    mention, repeatedly, that the Alpren litigation was conducted
    10   among related corporate entities, see, e.g., Final Award 21 ("As
    11   previously noted, Alpren and Storm were under the direct or
    12   indirect control of Altimo, and the ultimate control of Alfa."),
    13   without notice to or appearance by Telenor, see, e.g., 
    id.
     at 17
    14   ("Telenor . . . had no notice of the Ukrainian proceedings until
    15   after the order of the Ukrainian appellate court . . . ."); id.
    16   ("[T]he April-May 2006 Ukrainian court proceedings came as a
    17   surprise to both the Tribunal and to Telenor . . . .").    The
    18   panel's repeated observations along these lines make clear that
    19   the panel considered the Ukrainian proceedings to have been
    20   collusive, even though the panel understandably elected to avoid
    21   using that term in relation to proceedings before a duly
    22   constituted foreign court.    See id. at 25 (noting that the panel
    23   had previously "made clear" that it was not "ignoring the
    24   decisions of the Ukrainian courts . . . [or] impugning the
    25   integrity of those courts or their decisions").
    22
    1               Politic or not, in light of the "strong presumption
    2    that an arbitration tribunal has not manifest[ly] disregarded the
    3    law," Westerbeke, 
    304 F.3d at
    212 n.8, the panel's multiple
    4    references to the Alfa-internal and ex parte nature of the Alpren
    5    litigation supply a sufficiently "colorable" justification for
    6    its refusal to give the Ukrainian judgments controlling weight.
    7    Cf. Motorola Credit Corp. v. Uzan, 
    388 F.3d 39
    , 60-61 (2d Cir.
    8    2004) (affirming denial of comity to injunctions entered by
    9    Turkish courts that "were the product of collusion").
    10              Storm does not seriously dispute that the Alpren
    11   litigation was a cooperative venture among allied interests.8     It
    12   argues, instead, that Storm "had no contact" with its adversary
    13   during the litigation, that it "presented a defense" in the
    14   proceedings, and that it "appealed."   Appellant Br. 42.    But
    15   these assertions, if true, would not refute the panel’s finding
    16   of collusion on the facts of this case and would not be a basis
    17   upon which the district court was required to overturn that
    18   finding.   The panel was not obliged to interpret Storm's
    19   decidedly modest efforts in the Alpren suit to be material or
    20   meaningful.9
    8
    Storm does rely upon a declaration from Klymenko,
    submitted after judgment was entered by the district court, which
    says that Storm, Alpren, and Altimo are not "the same entities."
    We decline to find clear error on the basis of a self-serving
    declaration that the district court had no opportunity to
    consider.
    9
    Moreover, Storm offers no good reason why we should not
    affirm on the district court's finding of collusion. See
    Telenor, 
    524 F. Supp. 2d at 346-47
    .
    23
    1              Moreover, "the force of" the Ukrainian judgments as
    2    against Telenor is "further reduced" by the fact that Telenor was
    3    not a party to the Alpren litigation and was continually denied
    4    notice of the proceedings.   Final Award 34; see also 
    id.
     at 21-
    5    22, 25-27; Telenor, 
    524 F. Supp. 2d at 346-47
    .   The failure of
    6    the Ukranian court to afford Telenor what we would regard as
    7    rudimentary due process, see Parklane Hosiery Co. v. Shore, 439
    
    8 U.S. 322
    , 327 n.7 (1979) ("It is a violation of due process for a
    9    judgment to be binding on a litigant who was not a party or privy
    10   and therefore never had an opportunity to be heard."), provides
    11   an independent colorable justification for the panel's conclusion
    12   that the Ukrainian proceedings were unsound for Ackermann
    13   preclusion purposes.
    14             It was the opinion of a witness whom Storm proffered as
    15   an expert that "Telenor . . . could have intervened" in the
    16   Alpren litigation after it was notified of the judgment against
    17   it "for purposes of filing an appeal to Ukraine's highest court"
    18   but "chose not to do so."    That is beside the point for at least
    19   two reasons.   First, this opinion testimony, if assumed to
    20   constitute competent evidence of the process actually available
    21   to Telenor in the Alpren litigation, would fail to demonstrate
    22   that Telenor, after intervening solely for purposes of appeal,
    23   would have been afforded a full and fair opportunity to be heard
    24   on the merits of the issues decided in that litigation.   Second,
    25   it would not in any event be sufficient to have warranted a
    26   reversal by the district court under the "manifest disregard"
    24
    1    standard.    See Stolt-Nielsen, 
    548 F.3d at 91
     ("We do not . . .
    2    'recognize manifest disregard of the evidence as proper ground
    3    for vacating an arbitrator's award.'" (quoting Wallace, 
    378 F.3d 4
     at 193) (emphasis added in Stolt-Nielsen)).
    5                The Ukrainian decisions therefore provide no basis for
    6    a denial of enforcement of the final arbitral award on "manifest
    7    disregard" grounds.
    8                2. Public Policy.
    9                Storm argues that the arbitral award should nonetheless
    10   be vacated pursuant to Article V(2)(b) of the New York Convention
    11   because, Storm says, it is contrary to New York public policy to
    12   force a party to comply with an arbitral award that will cause it
    13   to violate a foreign judgment.    We do not think that Storm can
    14   properly invoke the protection of any such policy.
    15               Two factfinders have concluded that Storm brought the
    16   Ukrainian judgments upon itself through use of highly
    17   questionable litigation tactics.       See Final Award 21, 25;
    18   Telenor, 
    524 F. Supp. 2d at 346-47, 356-58
    .       Storm's situation,
    19   like that of the apocryphal parricide seeking mercy because he
    20   had been orphaned, is entirely of its own making.
    21               Our view, in light of the findings of the arbitration
    22   panel and the district court, is that it is Storm's improper
    23   collateral litigation, not the arbitral award, that is contrary
    24   to public policy, viz., the well-established federal public
    25   policy in favor of arbitration.    See, e.g., Chelsea Square
    26   Textiles, Inc. v. Bombay Dyeing & Mfg. Co., 
    189 F.3d 289
    , 294 (2d
    25
    1    Cir. 1999) ("Through the FAA, Congress has declared a strong
    2    federal policy favoring arbitration as an alternative means of
    3    dispute resolution."   (internal quotation marks omitted)).
    4    Collateral and unilateral litigation of arbitrability – or any
    5    other issue pertinent to an arbitration, for that matter --
    6    undertaken in a foreign forum by a party to that arbitration in
    7    an attempt to protect itself from an adverse arbitral award
    8    would, if indulged, tend seriously to undermine the underlying
    9    scheme of the FAA and the New York Convention.
    10              Article V(2)(b) must be "construed very narrowly" to
    11   encompass only those circumstances "where enforcement would
    12   violate our most basic notions of morality and justice."
    13   Europcar Italia S.p.A. v. Maiellano Tours, Inc., 
    156 F.3d 310
    ,
    14   315 (2d Cir. 1998) (internal quotation marks omitted).
    15   Consistent with that rule, we conclude that enforcing the
    16   arbitral award as against Storm would not be contrary to public
    17   policy.
    18   B.   Sphere Drake and Arbitrability
    19              Storm argues that the panel manifestly disregarded
    20   Sphere Drake when it failed to arrange for a trial to be held on
    21   the arbitrability of the 2004 Agreement.   Storm also argues that
    22   the district court erred in making its own determination, de
    23   novo, that the 2004 Agreement was executed by Storm.   We conclude
    24   to the contrary that Storm failed to present "some evidence" of a
    25   dispute as to arbitrability so as to warrant a trial under Sphere
    26
    1    Drake.10    In particular, Storm has not provided sufficient
    2    evidence to support its allegation that Nilov lacked apparent
    3    authority to execute the agreement on behalf of Storm.
    4                Under New York law,11 an agent has apparent authority
    5    if "a principal places [the] agent in a position where it appears
    6    that the agent has certain powers which he may or may not
    7    possess."    Masuda v. Kawasaki Dockyard Co., 
    328 F.2d 662
    , 665 (2d
    8    Cir. 1964).    The apparent authority question is susceptible to
    9    judgment as a matter of law against the principal.    See, e.g.,
    10   Warnock Cap. Corp. v. Hermitage Ins. Co., 
    21 A.D.3d 1091
    , 803
    
    11 N.Y.S.2d 606
     (2d Dep't 2005).    Here, there is no genuine issue of
    12   fact, let alone a material one, as to Nilov's apparent authority:
    13   There is substantial evidence that Telenor received multiple
    14   notices from Storm that Nilov had the authority to execute the
    15   2004 Agreement and there is no evidence, at least that has been
    10
    We do not reach the question of   whether Storm was
    required to challenge the arbitrability   of the arbitration
    clause, in particular, or whether it in   fact did so. Even if
    Storm challenged the arbitration clause   itself, as it contends,
    we would reach the same result.
    11
    The 2004 Agreement provides that it "shall be governed
    by, and construed in accordance with," New York law, "without
    giving effect to any conflicts of laws principles . . . which
    would result in the application of the laws of another
    jurisdiction." 2004 Agreement § 13.06. This choice of law
    clause governs Storm's arbitrability challenge. See Motorola
    Credit Corp. v. Uzan, 
    388 F.3d 39
    , 50 (2d Cir. 2004) ("[A]
    choice-of-law clause in a contract will apply to disputes about
    the existence or validity of that contract."), cert. denied, 
    544 U.S. 1044
     (2005). By the terms of the clause, Storm is incorrect
    that Ukrainian law applies to the dispute as a matter of New York
    conflicts principles.
    27
    1    brought to our attention, that Telenor should have thought
    2    otherwise.
    3              The record reflects that Storm sent Telenor a variety
    4    of signals that Nilov had the authority to execute the 2004
    5    Agreement.   Among them:
    6             ! In 2002, Telenor received a copy of the August 20,
    7             2002 Storm shareholders resolution, which referenced
    8             both the Voting Agreement and the draft shareholders
    9             agreement that ultimately became the 2004 Agreement and
    10             authorized Nilov "to execute and deliver [those]
    11             agreements" and to "take or cause to be taken any and
    12             all other actions, as are required or desirable in
    13             connection with this Resolution and the above-
    14             referenced agreements." Storm LLC, Notice Regarding
    15             Resolutions Adopted by Written Polling, Aug. 30, 2002,
    16             at 3.
    17             ! Nilov executed -- with actual authority -- the
    18             Voting Agreement providing that Storm "agree[d]
    19             to . . . execute and deliver the New Shareholder
    20             Agreement." Voting Agreement § 2.05.
    21             ! Telenor received an email from a Storm negotiator
    22             stating that Storm was "ready to sign" the 2004
    23             Agreement, and discussing Nilov's availability to sign
    24             it, the day before Nilov actually signed it.
    25             ! Telenor received documentation from Storm signed by
    26             Storm's chairman and another official, stating that
    27             Nilov was "duly authorized" to execute the agreement on
    28             Storm's behalf. See Storm LLC, Certificate of
    29             Incumbency and Authority of Storm, Jan. 30, 2004.
    30             Storm does not challenge the validity of these
    31   representations to Telenor of Nilov's apparent authority to
    32   execute the agreement.     Rather, Storm argues that Telenor should
    33   have deduced from the Storm charter and from having not received
    34   documentation of any shareholder meeting specifically authorizing
    35   Nilov to sign the 2004 Agreement, despite Storm's repeated
    36   statements that he was so authorized, that Nilov's execution
    28
    1    required a shareholder meeting for authorization.   This fails to
    2    raise a genuine issue of material fact.   For one thing, Storm
    3    cites nothing in the record (including in the charter) to support
    4    the proposition that Nilov required shareholder approval to
    5    execute the 2004 Agreement on his company's behalf.   For another,
    6    there is no evidence from which a rational juror might infer that
    7    Telenor should have concluded that there was no such meeting, in
    8    light of Storm's repeated assurances that Nilov was indeed duly
    9    authorized.
    10             Storm has, moreover, failed to explain why Nilov would
    11   sign the agreement without authorization.
    12             In any event, the record evidence shows that everyone
    13   at the relevant time, including Storm, thought that Nilov had the
    14   authority to execute the agreement.   That is sufficient ground on
    15   which to conclude that Storm has failed to proffer sufficient
    16   evidence from which a rational juror could conclude that Nilov
    17   lacked apparent authority to execute the 2004 Agreement and that
    18   no trial was required to find out if the agreement was, or was
    19   not, arbitrable.
    20                              CONCLUSION
    21             For the foregoing reasons, the judgment of the district
    22   court is affirmed.
    29
    

Document Info

Docket Number: 07-4974-cv(L) 08-6184-cv(CON) 08-6188-cv(CON)

Filed Date: 10/8/2009

Precedential Status: Precedential

Modified Date: 3/3/2016

Authorities (26)

the-shaw-group-inc-stone-webster-inc-and-stone-webster-asia-inc , 322 F.3d 115 ( 2003 )

Sameh Sami S. Khouzam, A/K/A Sameh Sami Khouzam, A/K/A ... , 361 F.3d 161 ( 2004 )

Stuart L. Bell v. Cendant Corporation, American Arbitration ... , 293 F.3d 563 ( 2002 )

Yusuf Ahmed Alghanim & Sons, W.L.L. v. Toys \"R\" Us, Inc. ... , 126 F.3d 15 ( 1997 )

H. Masuda v. Kawasaki Dockyard Company, Ltd. , 328 F.2d 662 ( 1964 )

Zeiler v. Deitsch , 500 F.3d 157 ( 2007 )

Sigval Bergesen, as Owners of the M/t Sydfonn, Frostfonn ... , 710 F.2d 928 ( 1983 )

Michael E. Wallace, David Jacaruso and Joseph Scotti v. ... , 378 F.3d 182 ( 2004 )

Sphere Drake Insurance Limited v. Clarendon National ... , 263 F.3d 26 ( 2001 )

Duferco International Steel Trading v. T. Klaveness ... , 333 F.3d 383 ( 2003 )

Stolt-Nielsen SA v. AnimalFeeds Intern. Corp. , 548 F.3d 85 ( 2008 )

Europcar Italia, S.P.A. v. Maiellano Tours, Inc. , 156 F.3d 310 ( 1998 )

Chelsea Square Textiles, Inc., Kenneth Lazar, Lester ... , 189 F.3d 289 ( 1999 )

motorola-credit-corporation-and-nokia-corporation , 388 F.3d 39 ( 2004 )

Warnock Capital Corp. v. Hermitage Insurance , 803 N.Y.S.2d 606 ( 2005 )

Encyclopaedia Universalis S.A. v. Encyclopaedia Britannica, ... , 403 F.3d 85 ( 2005 )

Westerbeke Corporation v. Daihatsu Motor Co., Ltd. , 304 F.3d 200 ( 2002 )

The Gms Group, LLC and Joseph Costa v. Nathan Benderson , 326 F.3d 75 ( 2003 )

Telenor Mobile Communications AS v. STORM LLC , 524 F. Supp. 2d 332 ( 2007 )

Rubin v. Sona International Corp. , 457 F. Supp. 2d 191 ( 2006 )

View All Authorities »