    1                             UNITED STATES COURT OF APPEALS
    2                                   FOR THE SECOND CIRCUIT
    3                                                ------
    4                                         August Term, 2016
    5   (Argued: November 16, 2016                                           Decided: August 18, 2017)
    6                                         Docket No. 16-1568
    7   _________________________________________________________
    8   CONSTITUTION PIPELINE COMPANY, LLC,
    9                                                      Petitioner,
    10                                       - v. -
    11   NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL
    12   CONSERVATION; BASIL SEGGOS, Acting Commissioner, New York State
    13   Department of Environmental Conservation; JOHN FERGUSON, Chief Permit
    14   Administrator, New York State Department of Environmental Conservation,
    15                                                      Respondents,
    16   STOP THE PIPELINE, CATSKILL MOUNTAINKEEPER, INC., SIERRA
    17   CLUB, RIVERKEEPER, INC.,
    18                                             Intervenors.*
    19   _________________________________________________________
    20   Before: KEARSE, WESLEY, and DRONEY, Circuit Judges.
    21                Petition for review of respondents' decision denying application for certification
    *     The Clerk of Court is directed to amend the official caption to conform with the
    above.
    1    pursuant to § 401 of the Clean Water Act, 33 U.S.C. § 1341, that petitioner's proposed interstate
    2    natural gas pipeline would comply with New York State water quality standards ("§ 401
    3    certification"). Respondents denied the application on the ground that petitioner had not complied
    4    with requests for relevant information. Petitioner contends (1) that respondents exceeded the statutory
    5    time limitations for the State's review of the application and that they must therefore be ordered to
    6    notify the United States Army Corps of Engineers ("USACE") that the State waives its right to issue
    7    or deny § 401 certification, thereby allowing USACE to issue a permit to petitioner under § 404 of
    8   the Clean Water Act, see 33 U.S.C. § 1344(a); and (2) alternatively, that respondents' decision should
    9   be vacated on the ground that the denial of the application was arbitrary, capricious, and ultra vires,
    10   and that respondents should be ordered to grant the requested § 401 certification. To the extent that
    11   petitioner challenges the timeliness of respondents' decision, we conclude that we lack jurisdiction
    12   over that challenge. As to the merits, we conclude that respondents' actions were within their
    13   statutory authority and that the decision was not arbitrary or capricious.
    14                  Petition dismissed in part and denied in part.
    15                          JOHN F. STOVIAK, Philadelphia, Pennsylvania (Saul Ewing,
    16                               Philadelphia, Pennsylvania, Elizabeth Utz Witmer, Saul Ewing,
    17                               Wayne, Pennsylvania; Yvonne E. Hennessey, Barclay Damon,
    18                               Albany, New York, on the brief), for Petitioner.
    19                          BRIAN LUSIGNAN, Assistant Attorney General, Albany, New York
    20                               (Eric T. Schneiderman, Attorney General of the State of New
    21                               York, Barbara D. Underwood, Solicitor General, Andrew B.
    22                               Ayers, Senior Assistant Solicitor General, Frederick A. Brodie,
    23                               Assistant Solicitor General, Lisa M. Burianek, Deputy Bureau
    24                               Chief, Albany, New York, on the brief), for Respondents.
    2
    1                          KARA E. PAULSEN**, White Plains, New York (Karl S. Coplan,
    2                              Todd D. Ommen, Anne Marie Garti, Pace Environmental
    3                              Litigation Clinic, Inc., White Plains, New York, on the brief),
    4                              for Intervenor Stop the Pipeline.
    5                         MONEEN NASMITH, New York, New York (Deborah Goldberg,
    6                             Christine Ernst, Earthjustice, New York, New York, on the
    7                             brief), for Intervenors Catskill Mountainkeeper, Inc., Sierra
    8                             Club, and Riverkeeper, Inc.
    9                         SIDLEY AUSTIN, Washington, D.C. (Roger R. Martella, Jr., Ryan C.
    10                              Morris, Tobias S. Loss-Eaton, Washington, D.C.; Linda E.
    11                              Kelly, Quentin Riegel, Leland P. Frost, Manufacturers' Center
    12                              For Legal Action, Washington, D.C.; Steven P. Lehotsky,
    13                              Sheldon B. Gilbert, U.S. Chamber Litigation Center,
    14                              Washington, D.C.; Kevin B. Belford, Michael L. Murray,
    15                              Washington, D.C.; Leslie A. Hulse, Washington, D.C.; Dena
    16                              E. Wiggins, Washington, D.C.; Andrea J. Chambers, Katie
    17                              Leesman, Ballard Spahr, Washington, D.C., of counsel), filed
    18                              a brief for Amici Curiae National Association of
    19                              Manufacturers, Chamber of Commerce of the United States of
    20                              America, Interstate Natural Gas Association of America,
    21                              American Gas Association, American Petroleum Institute,
    22                              American Chemistry Council, Natural Gas Supply Association,
    23                              American Forest & Paper Association, and Process Gas
    24                              Consumers Group, in support of Petitioner.
    25                         Kimberly Ong, New York, New York (Albert K. Butzel, New York,
    26                               New York, of counsel), filed a brief for Amici Curiae Natural
    27                               Resources Defense Council, Water Defense, Waterkeeper
    28                               Alliance, Earthworks, PennEnvironment, Peconic Baykeeper,
    29                               and Chesapeake Bay Foundation, in support of Respondents.
    30   KEARSE, Circuit Judge:
    31                  Petitioner Constitution Pipeline Company, LLC ("Constitution"), petitions pursuant
    32   to 15 U.S.C. § 717r(d)(1) for review of an April 22, 2016 decision of the New York State Department
    33   of Environmental Conservation ("NYSDEC" or the "Department") denying Constitution's application
    **    Law student appearing pursuant to Local Rule 46.1(e).
    3
    1   for certification pursuant to § 401 of the Federal Water Pollution Control Act, more commonly known
    2   as the Clean Water Act (or "CWA"), 33 U.S.C. § 1341 ("§ 401 certification"), that Constitution's
    3   proposed interstate natural gas pipeline would comply with New York State (or "State") water quality
    4   standards (or "WQS"). NYSDEC denied the application on the ground that Constitution had not
    5   provided sufficient information. In its petition, Constitution contends principally (1) that NYSDEC
    6   exceeded the § 401(a) time limitations for the State's review of the application and that NYSDEC
    7   must therefore be ordered to notify the United States Army Corps of Engineers ("USACE" or "Army
    8   Corps of Engineers" or "Army Corps") that the State has waived its right to act upon Constitution's
    9   § 401 certification application, thereby allowing USACE to issue a permit to petitioner under § 404
    10   of the Clean Water Act, see 33 U.S.C. § 1344(a); and (2) alternatively, that Constitution submitted
    11   sufficient information and that NYSDEC's decision should be vacated on the ground that its denial
    12   of the application was arbitrary, capricious, and ultra vires, and that NYSDEC should be ordered to
    13   grant the requested § 401 certification. To the extent that Constitution challenges the timeliness of
    14   the NYSDEC decision, we dismiss the petition for lack of jurisdiction. As to the merits, we conclude
    15   that NYSDEC's actions were within its statutory authority and that its decision was not arbitrary or
    16   capricious, and we deny the petition.
    17                                             I. BACKGROUND
    18                  Constitution proposes to construct a 121-mile interstate natural gas pipeline in
    19   Pennsylvania and New York, approximately 98 miles of which would be in New York. In connection
    20   with this project (the "Project"), Constitution applied for, to the extent pertinent here, a "certificate
    4
    1   of public convenience and necessity" from the Federal Energy Regulatory Commission ("FERC"),
    2   15 U.S.C. § 717f(c), a CWA § 401 water quality certification (or "WQC") from New York State that
    3   the Project would comply with State water quality standards (see 6 N.Y.C.R.R. parts 701 to 704), and
    4   a CWA § 404 permit from the Army Corps of Engineers to allow discharges into United States
    5   navigable waters.
    6    A. Proceedings Before FERC
    7                  In September 2012, FERC announced that it would prepare an environmental impact
    8   statement ("EIS") for Constitution's Project and asked Constitution to submit a feasibility study
    9   explaining how it would install the pipeline across waterbodies (generally using that term to refer to
    10   streams but not wetlands). For such installations, there is a trenched method--a dry open-cut crossing-
    11   -which involves diverting a stream, digging a trench through the banks and stream bed, installing and
    12   burying the pipeline, and then allowing the stream to resume flowing in the stream bed. (See, e.g.,
    13   FERC Final Environmental Impact Statement ("FEIS") pages 2-21 to 2-22.) There are also trenchless
    14   crossing methods--including Horizontal Directional Drill (or "HDD"), Direct Pipe (or "DP"), and
    15   conventional bore--which involve digging pits on either side of a waterbody and boring or drilling
    16   underneath the stream. FERC asked Constitution to provide information with regard to trenchless
    17   construction methods for crossing several categories of streams, including those classified by the
    18   states as sensitive or high quality and those greater than 30 feet wide where a dry construction method
    19   would not be feasible.
    5
    1           1. Constitution's Trenchless Feasibility Study
    2                   Constitution submitted to FERC a study discussing trenchless crossing methods. (See
    3   Constitution, Feasibility Study: Trenchless Construction Methods for Sensitive Environmental
    4   Resource Crossings (Nov. 2013) ("Constitution 2013 Feasibility Study" or "Study") pages 1-3 to 1-5.)
    5   Trenchless methods do not disturb soil or organisms in the stream banks, stream bed, or in the stream
    6   itself, but require disturbing surrounding areas to clear space for installation pits; there are also risks
    7   of mid-project drill breakage, with leakage of drill fluid into the waterbody. (See Constitution 2013
    8   Feasibility Study page 2-3; FEIS page 2-24.) Use of the trenched method does not require as much
    9   installation space or present the risk of drill failure; but it requires stream diversion and digging into
    10   the stream bed and banks. (See, e.g., FEIS pages 2-21 to 2-22.)
    11                   The Constitution feasibility study dealt principally with locations where the waterbody
    12   was designated by New York or Pennsylvania as sensitive or high quality. (See Constitution 2013
    13   Feasibility Study pages 2-2 to 2-3.) As a result, Constitution eliminated from consideration for
    14   trenchless crossings all but 89 of the 251 New York waterbodies that would be crossed by the pipeline
    15   or affected by pipeline construction.
    16                   The remaining 89 locations were addressed in three phases. The Study's "Phase I[]
    17   Desktop Analysis" (
    id. pt. 1.0
    page 1-1) further reduced the number of New York waterbodies
    18   considered by Constitution for trenchless crossings from 89 to 26, in part by eliminating streams less
    19   than 30 feet wide, even if they were classified by New York as sensitive or high-quality (see 
    id. pages 20
      2-1, 2-3). Constitution stated that trenchless crossings for such narrower waterbodies would
    21   potentially require workspace requirements significantly greater than those generally needed for a
    22   conventional dry crossing method. (See 
    id. page 2-3.)
    Thus, unless such a waterbody was
    6
    1    immediately associated with a larger wetland and/or waterway complex crossed by the Project or was
    2    located in the immediate vicinity of a proposed rail or roadway crossing, "Constitution did not
    3    evaluate waterbody crossings less than 30 feet in width" (id.).
    4                  Phase II was a "Cost/Time/Construction Workspace Impact Analysis." (Id. page 3-1;
    5   see also 
    id. pt. 1.0
    page 1-1 ("Trenchless construction methods are limited" not only by such matters
    6   as "underlying geology, available workspace, [and] available time," but also by "available finances
    7   budgeted for a capital project.").) This phase eliminated waterways from trenchless-crossing
    8   consideration largely on the basis of expense; as a result, there remained only 13 waterbody crossings
    9   in New York for which Constitution planned to investigate a "formal trenchless construction design."
    10   (Id. pages 3-2 to 3-4 & tbl.3.2-1.) The Study stated that Phase III, a "geotechnical field analysis" of
    11   each of the 13 locations, was in progress. (Id. page 5-1.) Constitution thus planned to use the
    12   trenched method for 238 of the 251 New York waterbodies to be crossed.
    13          2. NYSDEC Comments and the FEIS
    14                  In connection with FERC's announcement of a planned EIS for the Constitution
    15   pipeline--and its subsequent draft EIS ("DEIS")--NYSDEC submitted numerous letters to FERC. The
    16   first noted that NYSDEC's preferred method for crossing waterbodies is a trenchless method, in
    17   particular
    18                  Horizontal Directional Drilling (HDD) because it has the advantages of
    19                  minimizing land disturbance, avoiding the need for dewatering of the stream,
    20                  leaving the immediate stream bed and banks intact, and reducing erosion,
    21                  sedimentation and Project-induced watercourse instabilities.
    22   (November 7, 2012 Letter from NYSDEC to FERC at 3 (emphasis added).) Stating that the DEIS
    23   should identify the New York classification of each stream the proposed pipeline would cross,
    7
    1   NYSDEC urged FERC to "evaluate cases where other methods are proposed" and have Constitution
    2   "explain why HDD will not work or is not practical for that specific crossing." (Id. (emphasis
    3   added).)
    4                  A May 2013 letter again stated that "NYSDEC's preferred methodology for all stream
    5   crossings is . . . (HDD)"; that letter also stated that "[w]ithin stream crossings, pipelines should be
    6   buried at least 6' below a stream bottom. Minimum cover depth is not subject to variance based on
    7   field conditions." (May 28, 2013 Letter from NYSDEC to FERC ("NYSDEC May 2013 Letter")
    8   at 1-2 (emphasis added).)
    9                  In September 2013, NYSDEC wrote to join a request by the Army Corps for additional
    10   analysis of whether the Constitution pipeline could be routed along a certain interstate highway, a
    11   route referred to as "Alternative M." (September 25, 2013 Letter from NYSDEC to FERC at 1.)
    12   Constitution responded by arguing that Alternative M would have greater environmental impact than
    13   Constitution's proposed route and noting likely difficulties in obtaining highway agencies' approvals.
    14   (See October 22, 2013 Letter from Constitution to NYSDEC at 2-4.)
    15                  In 2014, FERC issued its DEIS, which drew criticism from several sources including
    16   NYSDEC. (See, e.g., March 24, 2014 Letter from NYSDEC to FERC and Army Corps at 1-2 (urging
    17   a revised DEIS to include "geotechnical feasibility studies for all trenchless crossing locations," as
    18   well as "site specific blasting plans that include protocols for in-water blasting and the protection of
    19   aquatic resources and habitats" (emphasis added)); April 7, 2014 Letter from NYSDEC to FERC and
    20   Army Corps ("NYSDEC April 2014 Letter") at 1-5 (adding additional comments and requesting
    21   additional analysis of Alternative M which, in NYSDEC's view, would reduce the amount of
    22   disturbance of higher-quality waterbodies).)
    8
    1                  FERC issued its FEIS in 2014 without significantly expanding on several aspects of
    2   the DEIS. It did not address NYSDEC's concern that Constitution had not developed site-specific
    3   blasting plans. (See FEIS pages 4-15 to 4-16; DEIS page 4-16.) The FEIS added discussion of two
    4   new versions of Alternative M proposed by NYSDEC (see FEIS pages 3-46 to 3-47), but rejected
    5   them without analyzing disturbances to high-quality waterbodies (compare 
    id. pages 3-32
    to 3-47 with
    6   NYSDEC April 2014 Letter at 3-4). And the FEIS stated that the pipeline would be buried 60 inches
    7   below streams in normal soil conditions and 24 inches in areas of "consolidated rock" (FEIS
    8   page 2-16), as contrasted with the NYSDEC May 2013 Letter's statement that the pipe needed to be
    9   buried "at least 6' below a stream bottom" (NYSDEC May 2013 Letter at 2).
    10                  The FEIS expanded on the DEIS's waterbody crossing information but repeated DEIS
    11   explanations for why relatively few crossings were slated to be crossed by trenchless techniques,
    12   stating, inter alia, that "[a]ccording to Constitution, trenchless crossing methods are not practical
    13   [except in limited circumstances] for waterbody crossings less than 30 feet in width" and that
    14   "Constitution indicated that such crossings would be impractical due to minimum length requirements,
    15   depth of pipeline considerations, and workspace requirements," and describing the areas that would
    16   be required for trenchless crossing "[a]ccording to Constitution" (FEIS page 4-50). The FEIS stated
    17   that
    18                  [t]he potential impacts on waterbodies associated with the use of conventional
    19                  bore or Direct Pipe trenchless crossing methods are considered minimal when
    20                  compared to other crossing methods. The waterbody and its banks, and
    21                  typically the entire immediate riparian zone, would not be disturbed by
    22                  clearing or trenching; rather, the pipe would be installed below the feature.
    23   (Id. page 4-56 (emphasis added).) FERC added:
    24                  We concur with Constitution's assessment that it is not practicable to use
    25                  trenchless crossing methods where waterbodies were listed as ephemeral or
    9
    1                 intermittent (because these waterbodies are likely to be dry at the time of
    2                 crossing) or for waterbodies less than 30 feet in width (as extra workspaces
    3                 needed would offset potential benefits). . . .
    4   (FEIS, App'x S, page S-52 (emphases added).) The FEIS noted that Constitution had completed
    5   geotechnical feasibility studies at only two New York sites. (See FEIS page 4-4.)
    6   B. Proceedings Before NYSDEC
    7                 While its application to FERC for a certificate of public convenience and necessity was
    8   pending, Constitution submitted an application to the Army Corps for a CWA § 404 permit for the
    9   discharge of dredged or fill material while constructing the pipeline and to NYSDEC for a CWA
    10   § 401 certification that the Project would comply with State water quality standards. In December
    11   2014, NYSDEC issued a notice that Constitution's application was complete; but on December 31,
    12   it asked Constitution for more information about stream crossings. In January-March 2015,
    13   Constitution submitted more information to NYSDEC, and on April 27, 2015, at NYSDEC's request,
    14   Constitution withdrew and resubmitted its § 401 application. (Constitution had also withdrawn and
    15   resubmitted its § 401 application at NYSDEC's request in May 2014.)
    16          1. Stream-Crossing Information Requests by NYSDEC
    17                 On January 23, 2015, staff from Constitution and NYSDEC met to discuss trenchless
    18   stream-crossing methods (see January 14, 2015 email from NYSDEC Project Manager Stephen M.
    19   Tomasik to Constitution engineering consultant Keith Silliman; January 27, 2015 email from Tomasik
    20   to Constitution Environmental Project Mananger Lynda Schubring ("NYSDEC January 27, 2015
    21   email")). Prior to that meeting, Constitution wrote to NYSDEC stating that it had
    10
    1                  conducted subsurface geotechnical investigations at the majority of the
    2                  proposed . . . (HDD) and . . . (DP) trenchless locations. Results of the
    3                  subsurface geotechnical investigations revealed crossing locations that present
    4                  a high risk of failure if a trenchless method is used. As a result, trenchless
    5                  crossing locations with a high risk of failure are not feasible and have been
    6                  modified to a dry open cut design. Since the last . . . submissions to the
    7                  USACE, three (3) HDD or DP locations affecting six (6) wetlands or
    8                  waterbodies have changed to an open cut construction method . . . .
    9   (January 22, 2015 Letter from Schubring to Tomasik at 1.) Constitution also stated that six other
    10   originally proposed trenchless crossings would be crossed by a trenched method, "to address various
    11   concerns raised by [state and local] authorities relative to the trenchless crossings of specific public
    12   roadways and associated infrastructure." (Id. at 2.) After the January 23 meeting, NYSDEC
    13   requested additional documents that Constitution personnel had said informed its decision to use the
    14   trenched crossing method at two locations, as well as "information about stream crossings that we
    15   requested on 12/31/2014." (NYSDEC January 27, 2015 email).
    16                  In response, Constitution submitted feasibility evaluations based on geotechnical
    17   studies for four locations: two wetlands crossings and two waterbody crossings. One of the
    18   waterbody feasibility evaluations concluded that using either HDD or DP was infeasible due to
    19   subsurface soil conditions; the other did not address the feasibility of trenchless crossing methods, and
    20   instead discussed only a contingency open-cut crossing to be used if the proposed DP crossing failed.
    21                  In February 2015, Constitution submitted to NYSDEC a document titled "Draft
    22   Trenchless Feasibility Study Edits" ("Constitution 2015 Feasibility Draft") that appears to be a version
    23   of part of the 2013 trenchless feasibility study that Constitution had submitted to FERC, merely
    24   expanding on the manner in which each trenchless method operates. Again there was no discussion
    25   of stream crossings site-by-site. The Constitution 2015 Feasibility Draft stated that
    26                  Constitution recognizes that, in general, performing . . . (HDD) for streams
    11
    1                   less than 30 feet in width causes greater net environmental impacts than a dry
    2                   open cut method and this threshold is an industry recognized standard.
    3                   Constitution has not identified any NYSDEC regulation, formally adopted
    4                   policy or guidance document that would warrant deviating from this standard.
    5    (Id. at 1 (emphases added).) It also discussed the Direct Pipe method, stating that "it is likely that
    6    additional forest will require clearing to perform DP for most of the protected stream crossings," and
    7    that "[m]any" streams are in valleys whose slopes make the DP method infeasible. (Id. at 2-3
    8    (emphases added).) In addition, the Constitution 2015 Feasibility Draft stated that DP technology is
    9    of "limited availability," leading Constitution to conclude that using "DP technology for . . . streams
    10   less than 30 feet in width is not a realistic or viable expectation within a reasonable period of time."
    11   (Id. at 3 (emphasis added).)
    12                  In March 2015, NYSDEC sent Constitution a list of 20 waterbody locations that
    13   NYSDEC "wants crossed via HDD," stating that NYSDEC "is still expecting an evaluation as to
    14   whether an HDD is technically feasible for each of these streams." (March 17, 2015 email from
    15   NYSDEC Major Project Management Unit Chief Christopher M. Hogan to Silliman (emphasis
    16   added).) In April 2015, as indicated above, Constitution withdrew and resubmitted its § 401 WQC
    17   request.
    18                  2. Subsequent Discussions
    19                  In May 2015, NYSDEC noted that it had agreed to "eliminate" four streams from
    20   "further consideration for trenchless crossing methods." (May 22, 2015 email from Tomasik to
    21   Schubring, Silliman, et al.)
    22                  In July 2015, a member of NYSDEC's staff emailed to certain Army Corps staff
    23   members a "Confidential" message attaching a "VERY PRELIMINARY version of a Constitution
    12
    1    permit" (July 20, 2015 email from Tomasik to Kevin J. Bruce et al., Army Corps), which included a
    2    table of 19 locations that "shall be crossed using a trenchless construction method"--unless an
    3    "experienced and qualified engineer" concludes that the techniques are "not constructible or not
    4    feasible" (Confidential Draft NYSDEC Certification Conditions at 17). The draft, however, required
    5    Constitution, "[p]rior to beginning construction of any trenchless stream crossing," to "submit a[]
    6    . . . 'Trenchless Crossing Plan' for each trenchless stream crossing," including "detailed engineering
    7    plans" for each location. (Id. at 18 (emphases added).)
    8                     In September 2015, Constitution submitted to NYSDEC an Environmental
    9   Construction Plan, attached to which was a Blasting Plan. (See Constitution, Environmental
    10   Construction Plan 50 (Aug. 2015).) This plan listed 253 "[a]reas of shallow depth to bedrock crossed
    11   by the [pipeline]" in New York, but stated that "[a] final determination on the need for blasting will
    12   be made at the time of construction." (Constitution, Blasting Plan (Aug. 2015) ("Blasting Plan")
    13   pages 1-1, 1-2 & tbl.1.2-2, 4-1.) The Blasting Plan identified regulations and a permit that would
    14   govern blasting in Pennsylvania, but stated that "[a]ll blasting operations in New York will be
    15   conducted in accordance with an in-stream b[l]asting protocol to be prepared by Constitution." (Id.
    16   page 4-1 (emphasis added).)
    17   C. NYSDEC's Decision Denying § 401 Certification
    18                  In a 14-page letter to Constitution dated April 22, 2016, NYSDEC denied
    19   Constitution's application for CWA § 401 certification ("NYSDEC Decision" or "Decision"), stating
    20   that "the Application fails in a meaningful way to address the significant water resource impacts that
    21   could occur from this Project and has failed to provide sufficient information to demonstrate
    13
    1   compliance with New York State water quality standards," NYSDEC Decision at 1. Although also
    2   noting the lack of adequate information as to such issues as the feasibility of the Alternative M route,
    3   blasting information, pipe burial depth, and wetlands crossings, see, e.g., 
    id. at 11-14,
    the Decision
    4   focused principally on Constitution's failure to provide information with respect to stream crossings.
    5                  NYSDEC noted that Constitution's Project "would disturb a total of 251 streams . . . ,
    6   87 of which support trout or trout spawning," and that "[c]umulatively, construction would disturb
    7   a total of 3,161 linear feet of streams and result in a combined total of 5.09 acres of temporary stream
    8   disturbance impacts." NYSDEC Decision at 8. It stated that although
    9                  [f]rom inception of its review of the Application, NYSDEC directed
    10                  Constitution to demonstrate compliance with State water quality standards and
    11                  required site-specific information for each of the 251 streams impacted by the
    12                  Project[, and] NYSDEC informed Constitution that all 251 stream crossings
    13                  must be evaluated for environmental impacts and that trenchless technology
    14                  was the preferred method for stream crossing[, and that t]his information was
    15                  conveyed to Constitution and FERC on numerous occasions since November
    16                  2012[,] . . . Constitution has not supplied the Department with the necessary
    17                  information for decision making.
    18   
    Id. (emphasis in
    original).
    19                  The Decision stated that because some form of trenchless technology is the "most
    20   protective method for stream crossings,"
    21                  NYSDEC directed Constitution to determine whether a trenchless technology
    22                  was constructible for each stream crossing. On a number of occasions
    23                  NYSDEC identified the need to provide information so that it could evaluate
    24                  trenchless stream installation methods (see Table 2, below); however,
    25                  Constitution has not provided sufficient information . . . .
    26   
    Id. (footnote omitted)
    (emphasis added).
    27                  Table 2 in the Decision principally chronicled NYSDEC's requests of Constitution--
    28   both directly and indirectly in its submissions to FERC--and noted Constitution's resistance, including
    14
    1   the following:
    2                 # In June 2012, "NYSDEC stated in a letter to Constitution that for protected
    3          streams and wetlands, trenchless technology is the preferred method for crossing and
    4          should be considered for all such crossings (emphasis added)."
    5                  # On November 7, 2012, "[i]n comments to FERC, NYSDEC stated that for
    6          streams and wetlands the preferred method for crossing is trenchless technology," and
    7          that as to each crossing where another method is proposed "Constitution should
    8          explain why trenchless crossing technology will not work or is not practical for that
    9          specific crossing."
    10                # On April 9, 2013, "FERC[] . . . directed Constitution to address all of the
    11          comments filed in the public record by other agencies . . . including all comments from
    12          the NYSDEC."
    13                  # On May 28, 2013, at a "[m]eeting" of "Constitution and NYSDEC staff . . .
    14          NYSDEC reiterate[d] that acceptable trenchless technology was the preferred
    15          installation method and that stream crossings should be reviewed for feasibility of
    16          using those technologies."
    17                  # In July and August 2013, on "[f]ield visits of proposed stream crossings
    18          prior to permit applications to the Department[, a]t each crossing, NYSDEC
    19          emphasized to Constitution staff that trenchless technology is preferred/most
    20          protective."
    21                  # In its November 2013 Trenchless Feasibility Study, Constitution
    22          "arbitrarily eliminated from any consideration for trenchless crossing methods"
    23          "all streams less than 30' wide."
    24                  # On December 31, 2014, at a meeting with Constitution staff, "NYSDEC
    25          indicated that the Trenchless Feasibility Study was inadequate, e.g. provided
    26          insufficient justification and removed all streams less than 30 feet in width from
    27          analysis." NYSDEC gave Constitution "an informational request table including
    28          required technical information."
    29                 # On January 13, 2015, an "Army Corps of Engineers letter reiterate[d] a
    30          request for a feasibility analysis of trenchless crossings."
    31                   # At a January 23, 2015 "[m]eeting between Constitution and NYSDEC staff
    32          . . . Constitution stated it was unable to complete the [informational request] table
    33          [it received from NYSDEC] on December 31, 2014[]. NYSDEC staff indicated that
    34          the justification for stream crossing methods was insufficient and that appropriate site
    35          specific information must be provided."
    15
    1                  # In a January 28, 2015 "[c]onference call[,] NYSDEC reiterated its request
    2          for a site specific analysis of trenchless stream crossings for all streams including
    3          those under 30 feet wide."
    4                  # On February 5, 2015, "Constitution provided an updated example of
    5          a trenchless feasibility study but that example continued to exclude streams up to
    6          30 feet wide from analysis and did not provide detailed information of the
    7          majority of streams."
    8   NYSDEC Decision at 9-10 (emphases added).
    9                  Although the Decision's Table 2 ended with the February 2015 entry, the Decision
    10   noted that Constitution's "unwillingness to provide a complete and thorough[] Trenchless Feasibility
    11   Study" persisted:
    12                  [I]n May 2015, Constitution provided detailed project plans for 25 potential
    13                  trenchless crossings, but only two of those plans were based on full
    14                  geotechnical borings that are necessary to evaluate the potential success
    15                  of a trenchless design. Detailed project plans including full geotechnical
    16                  borings for the remaining stream crossings have not been provided to the
    17                  Department.
    18   
    Id. at 11
    (emphasis added). The NYSDEC Decision stated that
    19                          [d]ue to the lack of detailed project plans, including geotechnical
    20                  borings, the Department has determined to deny Constitution's WQC
    21                  Application because the supporting materials supplied by Constitution do not
    22                  provide sufficient information for each stream crossing to demonstrate
    23                  compliance with applicable narrative water quality standards for turbidity and
    24                  preservation of best usages of affected water bodies. Specifically, the
    25                  Application lacks sufficient information to demonstrate that the Project will
    26                  result in no increase that will cause a substantial visible contrast to natural
    27                  conditions.10
    28                          Furthermore, the Application remains deficient in that it does not
    29                  contain sufficient information to demonstrate compliance with 6 NYCRR Part
    30                  701 setting forth conditions applying to best usages of all water classifications.
    31                  Specifically, "the discharge of sewage, industrial waste or other wastes shall
    32                  not cause impairment of the best usages of the receiving water as specified by
    33                  the water classifications at the location of the discharge and at other locations
    16
    1                    that may be affected by such discharge."11
    10
    2                                6 NYCRR § 703.2.
    11
    3                                6 NYCRR § 701.1.
    4   NYSDEC Decision at 12 & nn.10-11. The Decision added that
    5                           [c]umulatively, impacts to both small and large streams from the
    6                   construction and operation of the Project can be profound and include loss of
    7                   available habitat, changes in thermal conditions, increased erosion, creation of
    8                   stream instability and turbidity, impairment of best usages, as well as
    9                   watershed-wide impacts resulting from placement of the pipeline across water
    10                   bodies in remote and rural areas (See Project Description and Environmental
    11                   Impacts Section, above). Because the Department's review concludes that
    12                   Constitution did not provide sufficient detailed information including site
    13                   specific project plans regarding stream crossings (e.g. geotechnical borings)
    14                   the Department has determined to deny Constitution's WQC Application for
    15                   failure to provide reasonable assurance that each stream crossing will be
    16                   conducted in compliance with 6 NYCRR §608.9.
    17   NYSDEC Decision at 12; see 6 N.Y.C.R.R. § 608.9(a)(2) ("The applicant" for a CWA § 401
    18   certification "must demonstrate compliance with sections 301-303, 306 and 307 of the Federal Water
    19   Pollution Control Act, as implemented by . . . water quality standards and thermal discharge criteria
    20   set forth in Parts 701, 702, 703 and 704 of this Title . . . .").
    21                                               II. DISCUSSION
    22                   In its petition for review (or "Petition"), Constitution contends principally (1) that
    23   NYSDEC failed to issue its Decision within a reasonable time as required by § 401 and thus must be
    24   required to inform USACE that NYSDEC has waived its right to rule on Constitution's application
    25   for a WQC, thereby enabling the Army Corps to grant Constitution a permit for its pipeline Project,
    26   or (2) alternatively, that Constitution submitted sufficient information and that NYSDEC's decision
    17
    1   should be vacated on the ground that its denial of the application was arbitrary, capricious, and ultra
    2   vires, and that NYSDEC should be ordered to grant the requested § 401 certification. For the reasons
    3   that follow, we (1) conclude that Constitution's first contention, which would have us treat NYSDEC's
    4   Decision as an act that is void, lies beyond the jurisdiction of this Court, and (2) conclude that
    5   NYSDEC's Decision was not ultra vires, arbitrary, or capricious.
    6   A. Constitution's Argument that NYSDEC Waived Its § 401 Authority
    7                   The Natural Gas Act (or "NGA"), 15 U.S.C. §§ 717-717z, sets out provisions with
    8   respect to, inter alia, the construction of transportation facilities for natural gas, see 
    id. § 717f.
    Such
    9   projects are also subject to restrictions under other federal statutes, including provisions of the Clean
    10   Water Act, see, e.g., 
    id. § 717b(d)(3).
    Section 401 of the CWA requires an applicant for a federal
    11   permit to conduct any activity that "may result in any discharge into the navigable waters" of the
    12   United States to obtain "a certification from the State in which the discharge . . . will originate . . . that
    13   any such discharge will comply with," inter alia, the state's water quality standards. 33 U.S.C.
    14   § 1341(a)(1).
    15                   As to petitions for review relating to such applications, § 717r of the NGA divides
    16   jurisdiction between the Circuit in which the facility is proposed to be constructed and the United
    17   States Court of Appeals for the District of Columbia Circuit. It states, in pertinent part, as follows:
    18                            (1) In general
    19                           The United States Court of Appeals for the circuit in which a facility
    20                   subject to . . . section 717f of this title is proposed to be constructed . . . shall
    21                   have original and exclusive jurisdiction over any civil action for the review of
    22                   an order or action of a Federal agency (other than [FERC]) or State
    23                   administrative agency acting pursuant to Federal law to issue, condition, or
    24                   deny any permit, license, concurrence, or approval (hereinafter collectively
    18
    1                  referred to as "permit") required under Federal law . . . .
    2                          (2) Agency delay
    3                         The United States Court of Appeals for the District of Columbia shall
    4                  have original and exclusive jurisdiction over any civil action for the review of
    5                  an alleged failure to act by a Federal agency (other than [FERC]) or State
    6                  administrative agency acting pursuant to Federal law to issue, condition, or
    7                  deny any permit required under Federal law . . . .
    8   15 U.S.C. §§ 717r(d)(1)-(2) (emphases added). We regard subsection (2)--titled "Agency delay"--as
    9   encompassing not only "an alleged failure to act" but also an allegation that a failure to act within a
    10   mandated time period should be treated as a failure to act. This is the nature of Constitution's first
    11   argument.
    12                  Constitution points out that CWA § 401 provides that "[i]f" a "State . . . agency" from
    13   which an applicant for a federal permit has sought a water quality certification "fails or refuses to act
    14   on [the] request for certification, within a reasonable period of time (which shall not exceed one year)
    15   after receipt of such request, the certification requirements of this subsection shall be waived with
    16   respect to such Federal application." 33 U.S.C. § 1341(a)(1). Constitution argues that NYSDEC did
    17   not issue its Decision until 32 months after Constitution submitted its initial application, 16 months
    18   after NYSDEC issued notice that that initial application was complete, 15 months after the deadline
    19   imposed by FERC, nearly a year ("359 days") after Constitution's 2015 withdrawal-and-resubmission
    20   of its application--and eight months after Constitution claims it was advised by NYSDEC that
    21   NYSDEC "had everything it needed to issue a Section 401 Certification." (Constitution brief in
    22   support of Petition at 28-29.) Constitution argues that NYSDEC "waived its right" to rule on the
    23   certification application and must be required to so notify the Army Corps. (Id. at 37.)
    24                  We note first that there is nothing in the administrative record to show that NYSDEC
    19
    1   received the information it had consistently and explicitly requested over the course of several years--
    2   much less anything to support Constitution's claim that NYSDEC said "it had" all of the information
    3   it required "to issue" the requested certification (id. at 29). Although Constitution proffered in this
    4   Court non-record declarations from certain of its personnel, those "outside-the-record declarations and
    5   associated portions of [Constitution]'s brief" were stricken. Constitution Pipeline Co. v. Seggos, No.
    6   16-1568 (2d Cir. Oct. 3, 2016).
    7                   Second, Constitution's "waive[r]" argument is that the NYSDEC Decision must be
    8   treated as a nullity by reason of NYSDEC's "failing to act within the prescribed time period under the
    9   CWA" (Constitution brief in support of Petition at 37 (emphasis added)). Such a failure-to-act claim
    10   is one over which the District of Columbia Circuit would have "exclusive" jurisdiction, 15 U.S.C.
    11   § 717r(d)(2).    See generally Weaver's Cove Energy, LLC v. Rhode Island Department of
    12   Environmental Management, 
    524 F.3d 1330
    , 1332 (D.C. Cir. 2008). Accordingly, we dismiss
    13   Constitution's timeliness argument for lack of jurisdiction.
    14   B. Constitution's Challenge to the Merits of NYSDEC's Decision
    15                   Judicial review of an administrative agency's denial of a CWA § 401 certificate is
    16   limited to grounds set forth in the Administrative Procedure Act, 5 U.S.C. §§ 701-706. We review
    17   the agency's interpretation of federal law de novo; if the agency correctly interpreted federal law, we
    18   review its factual determinations under the arbitrary-and-capricious standard, see 
    id. § 706(2)(A);
    19   Islander East Pipeline Co. v. McCarthy, 
    525 F.3d 141
    , 150 (2d Cir. 2008) ("Islander East II");
    20   Islander East Pipeline Co. v. Connecticut Department of Environmental Protection, 
    482 F.3d 79
    , 94
    21   (2d Cir. 2006) ("Islander East I").
    20
    1           1. Federal Law
    2                   Constitution argues that as a matter of law, NYSDEC's "jurisdiction to review"--and
    3   "in effect, veto"--FERC determinations is preempted by FERC's performance of its obligations under
    4   the National Environmental Policy Act ("NEPA"), 42 U.S.C. §§ 4321-4370h, to prepare a DEIS and
    5   a FEIS. (Constitution brief in support of Petition at 37, 39.) We disagree that NYSDEC's action was
    6   preempted.
    7                   Although NEPA requires federal-agency review of virtually any possible
    8   environmental effect that a proposed action may have, see generally 40 C.F.R. § 1502.16, it does not
    9   impose substantive standards. See Robertson v. Methow Valley Citizens Council, 
    490 U.S. 332
    , 350
    10   (1989). "[T]hrough a set of action-forcing procedures," NEPA "require[s] that agencies take a hard
    11   look at environmental consequences," but it is "well settled that NEPA itself does not mandate
    12   particular results[; it] simply prescribes the necessary process." 
    Id. (internal quotation
    marks omitted).
    13   Thus, NEPA states, in pertinent part, that "[n]othing in section 4332 or 4333 of this title shall in any
    14   way affect the specific statutory obligations of any Federal agency . . . to act, or refrain from acting
    15   contingent upon the recommendations or certification of any . . . State agency." 42 U.S.C. § 4334.
    16                   We note also that while the Natural Gas Act generally preempts state laws, it states that
    17   "[e]xcept as specifically provided[,] . . . nothing" in the NGA "affects the rights of States under . . .
    18   the [CWA] (33 U.S.C. § 1251 et seq.)," 15 U.S.C. § 717b(d). CWA § 511, in turn, preserves the
    19   states' authority to determine issues of a planned project's effect on water quality. See 33 U.S.C.
    20   § 1371(c)(2)(A). CWA § 401(a)(1) requires that an entity such as Constitution, proposing to construct
    21   an interstate pipeline, obtain from each state in which the pipeline is to be constructed a certification
    22   that "any . . . discharge" from a proposed activity "will comply with the applicable provisions of [33
    21
    1   U.S.C. §§] 1311, 1312, 1313, 1316, and 1317." 33 U.S.C. § 1341(a)(1). Sections 1311, 1312, 1316,
    2   and 1317 establish, and allow the Environmental Protection Agency ("EPA") to establish, standards
    3   governing numerous aspects of water quality; and § 1313 allows states to develop their own water
    4   quality standards and submit them to the EPA for approval. If the EPA approves a state's water
    5   quality standards, it publishes a notice of approval and they become the state's EPA-approved
    6   standards, regulating water quality in that state. See 33 U.S.C. §§ 1313(a), (c).
    7                  The New York State water quality standards, approved by the EPA, see generally 42
    8   Fed. Reg. 56,786, 56,790 (Oct. 28, 1977), are found in 6 N.Y.C.R.R. parts 701 to 704, and were
    9   invoked by the NYSDEC Decision, which stated that "[d]enial of a WQC may occur when an
    10   application fails to contain sufficient information to determine whether the application demonstrates
    11   compliance with the above stated State water quality standards and other applicable State statutes and
    12   regulations due to insufficient information." NYSDEC Decision at 7; see also 
    id. at 12
    nn.10-11 and
    13   accompanying text (quoted in Part I.C. above). The State standards classify waterbodies in terms of,
    14   inter alia, potability and their suitability for various activities such as swimming and fishing, see 6
    15   N.Y.C.R.R. pt. 701; they set standards for characteristics such as water odor, color, and turbidity, see
    16   
    id. pt. 703;
    and they regulate thermal discharges into waterbodies, see 
    id. pt. 704.
    17                  Thus, the relevant federal statutes entitled NYSDEC to conduct its own review of the
    18   Constitution Project's likely effects on New York waterbodies and whether those effects would
    19   comply with the State's water quality standards.
    20                  CWA § 401(a)(1), as pertinent here, states that "[n]o license or permit shall be granted
    21   if [a § 401] certification has been denied by the State," 33 U.S.C. § 1341(a)(1). Thus, we have indeed
    22   referred to § 401 as "a statutory scheme whereby a single state agency effectively vetoes an energy
    22
    1   pipeline that has secured approval from a host of other federal and state agencies." Islander East II,
    
    2 525 F.3d at 164
    (emphases added); accord Keating v. FERC, 
    927 F.2d 616
    , 622 (D.C. Cir. 1991)
    3    ("Through [the § 401 certification] requirement, Congress intended that the states would retain the
    4    power to block, for environmental reasons, local water projects that might otherwise win federal
    5    approval." (emphasis added)).
    6                   Constitution also argues that NYSDEC's demands for information with regard to, e.g.,
    7   possible alternative routes for the planned pipeline (see, e.g., NYSDEC Decision at 3 (NYSDEC
    8   "asked Constitution to analyze alternative routes that could have avoided or minimized impacts to an
    9   extensive group of water resources")), as well as Constitution's planned blasting sites and the depth
    10   at which the pipe would be buried, exceeded NYSDEC's authority (Constitution brief in support of
    11   Petition at 38). We need not address all of these contentions. A state's consideration of a possible
    12   alternative route that would result in less substantial impact on its waterbodies is plainly within the
    13   state's authority. See, e.g., Islander East 
    II, 525 F.3d at 151-52
    . And where an agency decision is
    14   sufficiently supported by even as little as a single cognizable rationale, that rationale, "by itself,
    15   warrants our denial of [a] petition" for review under the arbitrary-and-capricious standard of review.
    16   See, e.g., 
    id. at 158.
    17           2. Application of the Arbitrary-and-Capricious Standard
    18                   Under the arbitrary-and-capricious standard, "[a] reviewing court may not itself weigh
    19   the evidence or substitute its judgment for that of the agency." Islander East 
    II, 525 F.3d at 150
    .
    20   "Rather," we "consider[] whether the agency 'relied on factors which Congress has not intended it to
    23
    1   consider, entirely failed to consider an important aspect of the problem, offered an explanation for its
    2   decision that runs counter to the evidence before the agency, or is so implausible that it could not be
    3    ascribed to a difference in view or the product of agency expertise.'" 
    Id. at 150-51
    (quoting Motor
    4    Vehicle Manufacturers Ass'n of the United States, Inc. v. State Farm Mutual Automobile Insurance
    5    Co., 
    463 U.S. 29
    , 43 (1983) ("State Farm")).
    6                   [W]ithin the prescribed narrow sphere, judicial inquiry must be searching and
    7                   careful. . . . Notably, a court must be satisfied from the record that the agency
    8                   . . . examine[d] the relevant data and articulate[d] a satisfactory explanation for
    9                   its action. . . . Further, the agency's decision must reveal a rational connection
    10                   between the facts found and the choice made.
    11   Islander East 
    II, 525 F.3d at 151
    (internal quotation marks omitted). If there is "sufficient evidence
    12   in the record to provide rational support for the choice made by the agency," we must uphold its
    13   decision. 
    Id. at 152.
    14                   Usually, the agency's choice concerns whether the applicant's submission of the
    15   relevant information warrants the granting of the application. In the present case, as summarized in
    16   Part I.C. above, NYSDEC denied Constitution's application because Constitution refused to provide
    17   information that NYSDEC had repeatedly requested with regard to, inter alia, issues such as those
    18   just discussed in Part II.B.1. above, and issues as to the feasibility, site-by-site, of trenchless methods
    19   for most of the 251 stream crossings planned in New York. Constitution does not contend that those
    20   requests were not made. Indeed, in its own brief in this Court, Constitution acknowledges that the
    21   NYSDEC Decision (the "Denial") explained that NYSDEC had requested but had not received
    22   sufficient information with regard to:
    23                   Ë construction methods and site-specific project plans for stream crossings
    24                   (Denial at 8-11 . . .);
    25                   Ë alternative routes (
    Id. at 11
    . . .);
    24
    1                  Ë pipeline burial depth in stream beds (Id. at 12-13 . . .);
    2                  Ë procedures and safety measures Constitution would follow in the event that
    3                  blasting is required (Id. at 13 . . .);
    4                  Ë Constitution's plans to avoid, minimize, or mitigate discharges to navigable
    5                  waters and wetlands (Id. at 13-14 . . .); and
    6                  Ë cumulative impacts (Id. at 3, 5, 7, 14 . . .).
    7   (Constitution brief in support of Petition at 21-22.) Nowhere does Constitution claim to have
    8   provided the above categories of information; rather, it insists that it provided NYSDEC with
    9   "sufficient" information (id. at 52-62) because use of trenchless crossing methods for streams less than
    10   30 feet wide is not "an industry recognized standard" (Constitution 2015 Feasibility Draft at 1).
    11                  However, in order to show that an agency's decision--or its request for additional
    12   information as to alternative methods--is arbitrary and capricious, "it is not enough that the regulated
    13   industry has eschewed a given [technology]." State 
    Farm, 463 U.S. at 49
    . Industry preferences do
    14   not circumscribe environmental relevance.
    15                  In Marsh v. Oregon Natural Resources Council, 
    490 U.S. 360
    (1989), the Supreme
    16   Court considered whether a federal agency, presented with new evidence, should have been required
    17   to file a new supplemental environmental impact statement; the Court stated that the matter of whether
    18   additional information is "significant" is "a classic example of a factual dispute the resolution of
    19   which implicates substantial agency expertise," as to which the courts "must defer to the informed
    20   discretion of the responsible . . . agencies," 
    id. at 376-77
    (internal quotation marks omitted). We
    21   cannot conclude that any less deference is due an agency's determination that it should not grant a
    22   permit application where it has already determined that additional information is needed, and the
    23   applicant refuses to supply it. Cf. University of Iowa Hospitals & Clinics v. Shalala, 
    180 F.3d 943
    ,
    25
    1    955 (8th Cir. 1999) (where agency regulations required substantiation of costs for which
    2    reimbursement was sought, denial of reimbursement based on inadequate documentation was not
    3    arbitrary and capricious); Mendoza v. Secretary, DHS, 
    851 F.3d 1348
    , 1356 (11th Cir. 2017) (denial
    4    of visa application where applicants declined to answer relevant questions relating to eligibility was
    5    not arbitrary and capricious; the applicants "were free to refuse to answer [the agency's] questions
    6    . . . but they did so at their own peril"). Indeed, an agency's decision may be found "arbitrary and
    7    capricious" for "issuing a permit with insufficient information." Utahns For Better Transportation
    8    v. United States Department of Transportation, 
    305 F.3d 1152
    , 1192 (10th Cir. 2002) (emphasis
    9    added).
    10                   Here, the record amply shows, inter alia, that Constitution persistently refused to
    11   provide information as to possible alternative routes for its proposed pipeline or site-by-site
    12   information as to the feasibility of trenchless crossing methods for streams less than 30 feet wide--i.e.,
    13   for the vast majority of the 251 New York waterbodies to be crossed by its pipeline--and that it
    14   provided geotechnical data for only two of the waterbodies.
    15                   In sum, NYSDEC is responsible for evaluating the environmental impacts of a
    16   proposed pipeline on New York waterbodies in light of the State's water quality standards. Applying
    17   the arbitrary-and-capricious standard of review, we defer to NYSDEC's expertise as to the
    18   significance of the information requested from Constitution, given the record evidence supporting the
    19   relevance of that information to NYSDEC's certification determination. We conclude that the denial
    20   of the § 401 certification after Constitution refused to provide relevant information, despite repeated
    21   NYSDEC requests, was not arbitrary or capricious.
    26
    1                                              CONCLUSION
    2                  We have considered all of Constitution's arguments and have found in them no basis
    3   for granting the petition for review. Insofar as the petition contends that the NYSDEC Decision is
    4   a nullity on the ground that it was untimely, the petition is dismissed for lack of jurisdiction; to the
    5   extent that the petition challenges the NYSDEC Decision on the merits, the petition is denied.
    27