Green Island Power Authority v. Federal Energy Regulatory Commission , 497 F. App'x 127 ( 2012 )


Menu:
  •          11-1960 (L)
    Green Island Power Authority v. Federal Energy Regulatory Comm’n
    UNITED STATES COURT OF APPEALS
    FOR THE SECOND CIRCUIT
    SUMMARY ORDER
    RULINGS BY SUMMARY ORDER DO NOT HAVE PRECEDENTIAL EFFECT. CITATION TO A SUMMARY ORDER FILED ON OR AFTER JANUARY 1,
    2007, IS PERMITTED AND IS GOVERNED BY FEDERAL RULE OF APPELLATE PROCEDURE 32.1 AND THIS COURT’S LOCAL RULE 32.1.1.
    WHEN CITING A SUMMARY ORDER IN A DOCUMENT FILED WITH THIS COURT, A PARTY MUST CITE EITHER THE FEDERAL APPENDIX OR AN
    ELECTRONIC DATABASE (WITH THE NOTATION “SUMMARY ORDER”). A PARTY CITING A SUMMARY ORDER MUST SERVE A COPY OF IT ON
    ANY PARTY NOT REPRESENTED BY COUNSEL.
    1            At a stated term of the United States Court of Appeals
    2       for the Second Circuit, held at the Daniel Patrick Moynihan
    3       United States Courthouse, 500 Pearl Street, in the City of
    4       New York, on the 25th day of September, two thousand twelve.
    5
    6       PRESENT: BARRINGTON D. PARKER,
    7                RICHARD C. WESLEY,
    8                         Circuit Judges,
    9                JOHN GLEESON,*
    10                         District Judge.
    11
    12
    13       Green Island Power Authority,
    14
    15                                                    Petitioner,
    16
    17                      v.                    11-1960 (Lead)
    18                                            11-3792 (Con)
    19       Federal Energy Regulatory Commission,
    20
    21                                                    Respondent,
    22
    23       Erie Boulevard Hydropower, L.P.
    24
    25                                                    Intervenor-Respondent.
    26
    27
    28
    29       FOR PETITIONER:               WILLIAM S. HUANG (Rebecca J. Baldwin,
    30                                     Katharine M. Mapes, on the brief),
    31                                     Spiegel & McDiarmid, LLP, Washington, DC.
    *
    The Honorable John Gleeson, of the United States District
    Court for the Eastern District of New York, sitting by
    designation.
    1   FOR RESPONDENT:    HOLLY E. CAFER (Micahel A. Bardee,
    2                      General Counsel, Robert H. Solomon,
    3                      Solicitor, on the brief), Federal Energy
    4                      Regulatory Commission, Washington, DC.
    5
    6   FOR INTERVENOR:    ROY T. ENGLERT, JR., Robbins, Russell
    7                      Englert, Orseck, Untereiner & Sauber LLP,
    8                      Washington, DC (William J. Trunk,
    9                      Robbins, Russell, Englert, Orseck,
    10                      Untereiner & Sauber LLP, Washington,
    11                      D.C.; John A. Whittaker, IV, Katherine L.
    12                      Konieczny, Winston & Strawn, LLP,
    13                      Washington, DC; David A. Bono, Mel R.
    14                      Jiganti, Brookfield Renewable Power,
    15                      Marlborough, MA, on the brief).
    16
    17       Appeal from the Federal Energy Regulatory Commission.
    18
    19       UPON DUE CONSIDERATION, IT IS HEREBY ORDERED, ADJUDGED
    20   AND DECREED that the orders of the Federal Energy Regulatory
    21   Commission are AFFIRMED.
    22       Petitioner Green Island Power Authority ("GIPA")
    23   appeals from three orders issued by Respondent Federal
    24   Energy Regulatory Commission ("FERC") following this Court's
    25   decision in Green Island Power Authority v. F.E.R.C., 577
    
    26 F.3d 148
     (2d Cir. 2009) ("GIPA I").     In GIPA I, we vacated a
    27   license issued by FERC to Intervenor-Respondent Erie
    28   Boulevard Hydropower, L.P. ("Erie") for the School Street
    29   Project, an existing hydroelectric project on the Mohawk
    30   River.   
    Id. at 149-50
    .    On remand, FERC was required to
    31   determine, inter alia, whether Erie's 2005 Offer of
    32   Settlement ("2005 Settlement"), which proposed changes to
    2
    1    the 1991 license application for the School Street Project
    2    ("1991 Application"), "materially amended" the 1991
    3    Application within the meaning of FERC's regulations.     
    Id.
    4    at 168; 
    18 C.F.R. § 4.35
    (f)(1).     We assume familiarity with
    5    the facts, the procedural history, and the issues presented
    6    for review.
    7        We defer to an agency's interpretation of its own
    8    regulation unless its interpretation is "plainly erroneous
    9    or inconsistent with the regulation" or there is any other
    10   "reason to suspect that the interpretation does not reflect
    11   the agency's fair and considered judgment on the matter in
    12   question."     Chase Bank USA, N.A. v. McCoy, 
    131 S. Ct. 871
    ,
    13   880-81 (2011) (quoting Auer v. Robbins, 
    519 U.S. 452
    , 461-62
    14   (1997)).     We accept as conclusive FERC's findings of fact if
    15   they are "supported by substantial evidence."     
    16 U.S.C. § 16
       825l(b).     Substantial evidence means "such relevant evidence
    17   as a reasonable mind might accept as adequate to support a
    18   conclusion."     Friends of Ompompanoosuc v. F.E.R.C., 
    968 F.2d 19
       1549, 1554 (2d Cir. 1992) (quoting Allegheny Elec. Co-op.,
    20   Inc. v. F.E.R.C., 
    922 F.2d 73
    , 80 (2d Cir. 1990)).
    21       We defer to FERC's interpretation of its own regulation
    22   and conclude that substantial evidence supported its
    23   decision that the 2005 Settlement did not materially amend
    3
    1    the 1991 Application.     A material amendment is defined in
    2    FERC's regulations as "any fundamental and significant
    3    change" to "plans of development proposed in an application
    4    for a license."   
    18 C.F.R. § 4.35
    (f)(1).   One example of a
    5    "material amendment" is “[a] change in the installed
    6    capacity, or the number or location of any generating units
    7    of the proposed project if the change would significantly
    8    modify the flow regime associated with the project.”       18
    9   
    C.F.R. § 4.35
    (f)(1)(i).     In GIPA I, we examined FERC's
    10   determination that the changes proposed to the 1991
    11   Application in 1995 (elimination of the 21-MW turbine) and
    12   2001 (re-addition of that turbine) were not material
    13   amendments under this regulation.     FERC's position was that
    14   while the change in installed capacity "would result in a
    15   change in flows," this would not significantly affect the
    16   project's flow regime because "the project would still be
    17   required to operate in a run-of river mode, and to provide
    18   the same minimum flows in the bypassed reach."      Erie
    19   Boulevard Hydropower, L.P., 120 F.E.R.C. ¶ 61,267, 62,184
    20   (2007).   We affirmed FERC's decisions because GIPA
    21   "offer[ed] no actual evidence to demonstrate that FERC's
    22   conclusion was flawed."     577 F.3d at 163.
    23
    4
    1        On remand, FERC applied the same analysis to determine
    2    that the 2005 Settlement did not materially amend the 1991
    3    Application.   Considering past precedent, it concluded that
    4    a project's flow regime "is the set of rules governing how
    5    flows are to be managed and released from the project," and
    6    that its primary elements "are its mode of operation and
    7    conditions that specify the amount, location, and timing of
    8    any required flow releases."   Order on Remand and
    9    Reinstating New License, 131 F.E.R.C. 61,036, 61,228 (2010).
    10   Furthermore, FERC construed the regulation to ask whether
    11   the change in installed capacity itself would “cause [or]
    12   require a corresponding change” to the flow regime.     Id. at
    13   61,229.   Applying this framework, FERC concluded that the
    14   proposed changes in installed capacity in the 2005
    15   Settlement did not materially amend the 1991 Application
    16   because "the project would still be required to operate in
    17   run-of-river mode and could provide the same minimum flows
    18   to the bypassed reach of the Mohawk River" proposed in the
    19   1991 Application.   Order Denying Rehearing, 134 F.E.R.C.
    20   61,205, 62,017 (2011).
    21       FERC has consistently interpreted the material
    22   amendment regulation to ask whether there is a causal
    23   relationship between the change in the installed capacity
    5
    1    and the flow regime associated with the project.     Its
    2    conclusions that the 1995 and 2001 proposed changes "would
    3    still . . . provide the same minimum flows in the bypassed
    4    reach," Order on Remand and Reinstating New License, 131
    5    F.E.R.C.     61,036, 61,224 (2010) (emphasis added), whereas
    6    the 2005 changes "could provide the same minimum flows to
    7    the bypassed reach," Order Denying Rehearing, 134 F.E.R.C.
    8    61,205,     62,017 (2011) (emphasis added), are not to the
    9    contrary.     That the proposed project would and could provide
    10   the same minimum flows despite the proposed change in
    11   capacity are simply different ways of illustrating why the
    12   changed capacity is not causally linked to the minimum
    13   flows.
    14       GIPA I thus requires that we once again affirm FERC's
    15   determination with respect to the 2005 Settlement. The
    16   changes to the minimum flows proposed in the 2005 Settlement
    17   were not caused by the proposed changes in installed
    18   capacity.     Rather, the changes in minimum flows were
    19   independent of the changes in installed capacity.     There was
    20   no material amendment because "the project would still be
    21   required to operate in run-of-river mode and could provide
    22   the same minimum flows to the bypassed reach of the Mohawk
    23   River" proposed in the 1991 Application.     Order Denying
    6
    1    Rehearing, 134 F.E.R.C. at 62,017.     Indeed, it would make
    2    little sense if both the removal of the 21-MW unit in 1995
    3    and re-addition of the unit in 2001 were not material
    4    amendments (as we held in GIPA I), but the re-removal of the
    5    21-MW unit in 2005 was a material amendment merely because
    6    of an unrelated proposed increase in minimum flows.
    7        We similarly leave undisturbed FERC’s determination
    8    that the powerhouse changes associated with substituting the
    9    21-MW unit proposed in the 1991 Application with either an
    10   11- MW unit or with no additional unit did not constitute a
    11   material amendment under FERC's regulations.     Under 18
    
    12 C.F.R. § 4.35
    (f)(1)(ii), a material amendment includes “[a]
    13   material change in . . . the location of the powerhouse,. .
    14   . if the change would . . . [c]ause adverse environmental
    15   impacts not previously discussed in the original
    16   application.”
    17       Here, the 2005 Settlement did not propose a material
    18   change in the location of the powerhouse.     The 1991
    19   Application proposed to house the new 21-MW unit in an
    20   addition to the existing powerhouse.     The 2005 Settlement
    21   proposed either no new generation unit or a new 11-MW
    22   generation unit, to be housed in a new powerhouse or
    23   powerhouse addition at the same location.     In either
    7
    1    scenario, the location of the powerhouse would not change
    2    because it "would continue to exist at the same location,
    3    either with or without a new powerhouse or an addition."
    4    Order Denying Rehearing, 134 F.E.R.C. at 62,022.
    5        Moreover, FERC did not abuse its discretion with
    6    respect to various evidentiary rulings.   For each piece of
    7    evidence that GIPA contends was improperly excluded, 
    FERC 8
      offered thorough explanations to support its decision to
    9    exclude the evidence as unreliable, unpersuasive and/or
    10   irrelevant.   Moreover, even where evidence was excluded as
    11   untimely, FERC considered whether the evidence was relevant
    12   to the issues being reviewed.
    13       Finally, we deny GIPA’s motion to take judicial notice
    14   of three documents relating to the physical changes to
    15   School Street that occurred due to its excavation by Erie
    16   between 2007 and 2010.   These letters do not, as GIPA
    17   contends, contradict FERC’s position on appeal.    FERC's 2007
    18   License Order authorized Erie to excavate the power canal
    19   without necessarily installing the potential new turbine.
    20   The letters merely seek additional information from Erie and
    21   question whether an amendment might be required.    Erie
    22   provided the requested information, and no further action
    23   has been taken.   This does not contradict FERC’s position on
    8
    1    appeal that the excavation "fell within the range of canal
    2    capacity considered in the 2007 License Order."    FERC Br. at
    3    61.   Accordingly, we decline to take judicial notice of the
    4    letters.
    5          Because we affirm FERC’s determination that the 2005
    6    Settlement did not materially amend the 1991 Application, we
    7    need not review FERC’s alternative conclusion that the
    8    Cohoes Falls Project is not a feasible alternative to School
    9    Street.    We have considered GIPA’s remaining arguments and,
    10   after a thorough review of the record, find them to be
    11   without merit.
    12         For the foregoing reasons, the orders of the Federal
    13   Energy Regulatory Commission are hereby AFFIRMED.
    14
    15                                FOR THE COURT:
    16                                Catherine O’Hagan Wolfe, Clerk
    17
    18
    19
    9
    

Document Info

Docket Number: 11-1960 (L)

Citation Numbers: 497 F. App'x 127

Judges: Parker, Wesley, Gleeson

Filed Date: 9/25/2012

Precedential Status: Non-Precedential

Modified Date: 11/6/2024