Executive Plaza, LLC v. Peerless Insurance , 717 F.3d 114 ( 2013 )


Menu:
  • 12-1470-cv
    Executive Plaza, LLC v. Peerless Ins. Co.
    U NITED S TATES C OURT OF A PPEALS
    F OR THE S ECOND C IRCUIT
    August Term 2012
    (Argued:     February 20, 2013           Decided:      May 23, 2013)
    Docket No. 12-1470-cv
    _____________________
    E XECUTIVE P LAZA , LLC,
    Plaintiff-Appellant,
    V.
    P EERLESS I NSURANCE C OMPANY ,
    Defendant-Appellee.
    _____________________
    Before:
    W INTER , C HIN , and D RONEY , Circuit Judges.
    _____________________
    Appeal from a judgment of the United States
    District Court for the Eastern District of New York
    (Seybert, J.) dismissing with prejudice plaintiff-
    appellant's complaint seeking, pursuant to an insurance
    policy, indemnification for property loss caused by fire.
    Q UESTION C ERTIFIED .
    _____________________
    D AVID T OLCHIN , Jaroslawicz & Jaros LLC, New
    York, New York, for Plaintiff-
    Appellant.
    S COTT D. S TORM , Mura & Storm, PLLC,
    Buffalo, New York, for Defendant-
    Appellee.
    _____________________
    C HIN , Circuit Judge:
    This case asks us to consider the interplay
    between two provisions in a fire insurance policy.       One
    requires the insured to file suit on the policy within two
    years.   The second requires the insured, when seeking
    replacement costs, to replace the damaged property before
    bringing suit, and to complete the replacement work "as
    soon as reasonably possible."       What happens to insured
    property that cannot reasonably be replaced within two
    years?   As New York case law does not clearly resolve the
    question raised by this appeal, we conclude that
    certification to the New York State Court of Appeals is
    appropriate.
    -2-
    BACKGROUND
    A.   The Facts
    The facts relevant to this appeal are not in
    dispute.   Plaintiff-appellant Executive Plaza, LLC
    ("Executive") owns a building insured at all relevant times
    by defendant-appellee Peerless Insurance Co. ("Peerless").
    The property was insured by a policy providing up to $1
    million of coverage (the "Policy").      On February 23, 2007,
    a fire destroyed the building.      Executive promptly notified
    Peerless of the damage.   Within days, Executive had
    retained both an architect and a construction company.         By
    July 2007, Peerless had paid Executive the actual cash
    value of the property, $757,812.50, less certain
    adjustments.
    In the years after the building was originally
    erected, zoning laws had changed.      To rebuild, Executive
    needed a variance and other forms of consent from local
    governmental entities.    Despite first submitting its
    application for review in June 2007, a final building
    permit was not granted until November 2008, seventeen
    -3-
    months later.    By October 2010, Executive had
    "substantially replaced" the property.
    Two Policy provisions are the focus of this
    appeal.   First, section E.4 required Executive to file suit
    to recover unpaid losses within two years of the fire:
    No one may bring a legal action against us under
    this insurance unless:
    a.    There has been full compliance with all
    of the terms of this insurance; and
    b.    The action is brought within 2 years
    after the date on which the direct
    physical loss or damage occurred.
    Second, section E.6 of the Policy provided that Peerless
    would pay either the actual cash value or the replacement
    cost of the property, up to the policy limit.     It further
    provided that an insured could first receive the actual
    cash value of the property and then later seek the
    replacement cost.     If, however, an insured sought the
    replacement cost, section E.6(d)(1)(b) imposed two
    additional caveats:
    (b)   We will not pay on a replacement cost basis
    for any loss or damage:
    (i)   Until the lost or damaged property is
    actually repaired or replaced; and
    -4-
    (ii) Unless the repairs or replacement are
    made as soon as reasonably possible after
    the loss or damage.
    B.   Procedural History
    On February 23, 2009, before it had completed
    rebuilding the property but within the two-year limitations
    period, Executive filed suit in New York State Supreme
    Court, Nassau County, to recover replacement costs under
    the Policy.    Peerless removed the case to the Eastern
    District of New York on diversity grounds (the "First
    Action").     As construction on the property had not yet been
    completed, the district court (Wexler, J.) dismissed the
    claim as not yet ripe.     Executive did not appeal this
    decision.
    After having substantially replaced the property,
    on October 5, 2010, more than two years after the loss,
    Executive sent Peerless a demand letter to recover an
    additional $242,087.50 (the replacement cost permitted by
    the Policy, less what Peerless had already paid).     Peerless
    rejected the demand.     Executive filed suit in New York
    State Supreme Court, Nassau County, and Peerless again
    -5-
    removed the action to the Eastern District of New York on
    diversity grounds (the "Second Action").    The district
    court below (Seybert, J.) dismissed the Second Action as
    time-barred.   This appeal followed.
    DISCUSSION
    Peerless argues that "full compliance" with the
    terms of the Policy, see Policy § E.4, requires that
    Executive both (1) rebuild the property "as soon as
    reasonably possible" but also (2) before the two-year
    limitations period for filing suit.    By contrast, Executive
    contends that it defies logic to require an insured to
    fully rebuild an insured property before filing a claim and
    to bring suit within two years when rebuilding the property
    within two years is not reasonably possible.    For the
    reasons that follow, we conclude that certification to the
    New York State Court of Appeals is appropriate.    See
    Country Wide Ins. Co. v. Nat'l R.R. Passenger Corp. , 
    407 F.3d 84
    , 85-86 (2d Cir. 2005).
    A.   Applicable Law
    Under Second Circuit Local Rule 27.2, we may
    "certify a question of state law to that state's highest
    -6-
    court."   Local R. 27.2(a); see also 
    N.Y. Comp. Codes R. & Regs. tit. 22, § 500.27
    (a) (allowing courts to certify
    "determinative questions of New York law . . . for which no
    controlling precedent of the Court of Appeals exists").
    Our decision to certify is made after considering three
    questions:
    (1) whether the New York Court of Appeals has
    addressed the issue and, if not, whether the
    decisions of other New York courts permit us to
    predict how the Court of Appeals would resolve it;
    (2) whether the question is of importance to the
    state and may require value judgments and public
    policy choices; and (3) whether the certified
    question is determinative of a claim before us.
    Osterweil v. Bartlett, 
    706 F.3d 139
    , 142 (2d Cir. 2013)
    (quoting Barenboim v. Starbucks Corp., 
    698 F.3d 104
    , 109
    (2d Cir. 2012)).
    B.   Application
    First, we note that the New York State Court of
    Appeals has not resolved this question.   It has interpreted
    the suit limitations provision alone, see Blitman Const.
    Corp. v. Ins. Co. of N. Am., 
    66 N.Y.2d 820
    , 822 (1985)
    (twelve-month suit limitations clauses was enforceable);
    Proc v. Home Ins. Co., 
    17 N.Y.2d 239
    , 243-46 (1966)
    -7-
    (holding that limitations period begins to run on date of
    fire), but never the replacement cost provision. 1    More
    importantly, however, no controlling precedent interprets
    the suit limitations clause in light of the replacement
    cost provision.
    While we may "predict what the New York Court of
    Appeals will do from the decisions of other New York
    courts," see Osterweil, 706 F.3d at 143 (quoting Barenboim,
    698 F.3d at 109) (internal quotation marks and emphasis
    omitted), the few courts to have read the provisions
    together have reached different conclusions.     Compare Bakos
    v. N.Y. Cent. Mut. Fire Ins. Co., 
    920 N.Y.S.2d 552
    , 554
    (4th Dep't 2011) (mem.) (denying insurer's motion to
    dismiss because replacement cost provision was not
    1
    Based, however, on unanimous authority from the
    appellate division, we acknowledge that actual repair of the
    property is a condition precedent to recovering on a replacement
    cost basis. See, e.g., Todd v. Wayne Coop. Ins. Co., 
    819 N.Y.S.2d 179
    , 180 (3d Dep't 2006) ("Under the terms thereof,
    replacement cost value cannot be awarded without plaintiff first
    actually repairing or replacing the property."); Harrington v.
    Amica Mut. Ins. Co., 
    645 N.Y.S.2d 221
    , 225 (4th Dep't 1996)
    (absent a repair requirement, the replacement cost provision
    becomes a "mere wager"); Ferrara v. Ins. Co. of N. Am., 
    521 N.Y.S.2d 668
     (1st Dep't 1987) (mem.) ("unambiguous" replacement
    cost provision requires that repairs be made before
    indemnification).
    -8-
    circumscribed by a temporal limitation), with Il Cambio,
    Inc. v. U.S. Fid. & Guar. Co., 
    920 N.Y.S.2d 305
    , 305-06
    (1st Dep't 2011) (insured barred from asserting a
    replacement cost claim when it had not rebuilt insured
    property and because complaint was barred by two-year
    limitations period).   Hence, we conclude that the cases
    available provide little predictive value as to how the
    Court of Appeals would resolve this issue.      Cf. Amerex
    Grp., Inc. v. Lexington Ins. Co., 
    678 F.3d 193
    , 200 (2d
    Cir. 2012) (where precedents can sufficiently support a
    determination, we need not certify).
    Second, the question certified implicates
    important matters of state law.      These include identifying
    the contours of property insurance policies, see Georgitsi
    Realty, LLC v. Penn-Star Ins. Co., 
    702 F.3d 152
    , 158-59 (2d
    Cir. 2012), and the state's "strong interest in supervising
    highly regulated industries," Benesowitz v. Metro. Life
    Ins. Co., 
    471 F.3d 348
    , 352 (2d Cir. 2006); see also Golden
    v. Winjohn Taxi Corp., 
    311 F.3d 513
    , 524 (2d Cir. 2002)
    (interpreting insurance relationships in the highly -
    regulated taxicab industry).    Moreover, the policy here
    -9-
    insures against fire-related losses, and the legislature's
    codification of a standard fire insurance policy --
    creating a floor for fire insurance coverage throughout New
    York State -- underscores its concern for coverage in this
    field.   
    N.Y. Ins. Law. § 3404
    (e), (f)(1)(A); see also Dean
    v. Tower Ins. Co. of N.Y., 
    19 N.Y.3d 704
    , 709 (2012).
    State courts, we believe, are better equipped to consider
    the ramifications of these issues.
    Third, the question we certify is purely legal,
    and an answer would resolve this appeal.   If the Court of
    Appeals were to decide that the suit limitations clause and
    the replacement value provision, read together, were
    unenforceable as a matter of public policy, then we would
    be obliged to remand to the district court to determine
    whether Executive rebuilt the insured property "as soon as
    reasonably possible."   Policy § E.6(d)(1)(b); cf. Bersani
    v. Gen. Accident Fire & Life Assurance Corp., 
    36 N.Y.2d 457
    , 460 (1975) (agreements that violate public policy are
    unenforceable).   If, however, the Court of Appeals were to
    decide that, read together, the provisions raise no such
    concerns and unambiguously require that an insured property
    -10-
    be rebuilt within a reasonable time that in no event
    exceeds two years, then Executive's claim would be
    foreclosed.    Finally, the Court of Appeals may conclude
    that the suit limitations clause and the replacement cost
    provision, read together, create an ambiguity.    Depending
    on whether (and, if so, how) the court resolves the
    ambiguity, we would remand for further proceedings in the
    district court or decide the appeal, as appropriate.
    CONCLUSION
    Accordingly, we reserve decision and respectfully
    certify the following question to the New York State Court
    of Appeals:
    If a fire insurance policy contains
    (1)     a provision allowing reimbursement of
    replacement costs only after the property
    was replaced and requiring the property to
    be replaced "as soon as reasonably possible
    after the loss"; and
    (2)     a provision requiring an insured to bring
    suit within two years after the loss;
    is an insured covered for replacement costs if the
    insured property cannot reasonably be replaced
    within two years?
    -11-
    We invite the New York State Court of Appeals to expand or
    reformulate the certified question as it deems appropriate.
    This panel retains jurisdiction and will consider any
    issues that remain on appeal after the New York State Court
    of Appeals has either offered its guidance or declined
    certification.
    CERTIFICATE
    The following question is hereby certified to the
    Court of Appeals of the State of New York pursuant to
    Second Circuit Local Rule 27.2 and New York Codes, Rules,
    and Regulations, Title 22, § 500.27(a), as ordered by the
    United States Court of Appeals for the Second Circuit:
    If a fire insurance policy contains
    (1)   a provision allowing reimbursement of
    replacement costs only after the property
    was replaced and requiring the property to
    be replaced "as soon as reasonably possible
    after the loss"; and
    (2)   a provision requiring an insured to bring
    suit within two years after the loss;
    is an insured covered for replacement costs if the
    insured property cannot reasonably be replaced
    within two years?
    -12-