Transcontinental Gas Pipe Line Co. v. Permanent Easement for 2.59 Acres, Temporary Easements for 5.45 Acres & Temporary Access Easement for 2.12 Acres in Pine Grove Township ( 2017 )


Menu:
  •                                                   NOT PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    ___________
    No. 17-1829
    ___________
    TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
    v.
    PERMANENT EASEMENT FOR 2.59 ACRES,
    TEMPORARY EASEMENTS FOR 5.45 ACRES AND
    TEMPORARY ACCESS EASEMENT FOR 2.12 ACRES
    IN PINE GROVE TOWNSHIP, SCHUYLKILL COUNTY, PA,
    TAX PARCEL NUMBER 21-04-0016.000, 361 CHAPEL DRIVE,
    PINE GROVE, PINE GROVE TOWNSHIP, SCHUYLKILL COUNTY, PA;
    RYAN J. REGEC
    Ryan J. Regec,
    Appellant
    ____________________________________
    On Appeal from the United States District Court
    for the Middle District of Pennsylvania
    (D.C. Civil Action No. 4-17-cv-00289)
    District Judge: Honorable Matthew W. Brann
    ____________________________________
    Submitted Pursuant to Third Circuit LAR 34.1(a)
    September 11, 2017
    Before: SHWARTZ, COWEN and FUENTES, Circuit Judges
    (Opinion filed: September 12, 2017)
    ___________
    OPINION*
    ___________
    PER CURIAM
    Ryan J. Regec appeals the District Court’s order granting Appellee
    Transcontinental Gas Pipe Line Company’s motion for partial summary judgment and
    request for a preliminary injunction. For the reasons below, we will affirm the District
    Court’s order as to the preliminary injunction.
    The procedural and factual history of this case are well known to the parties, set
    forth in the District Court’s opinion, and need not be discussed at length. Briefly, in
    February 2017, the Federal Energy Regulatory Commission (FERC) granted Appellee a
    certificate of public convenience and necessity (certificate), authorizing it to construct a
    natural gas pipeline. In order to build the pipeline, Appellee requires rights of way on a
    piece of property Regec owns. The certificate was issued after a lengthy administrative
    review process which included notice to property owners affected and an opportunity to
    respond. Regec did not participate in the administrative proceedings.
    After Regec and Appellee could not agree on the compensation to be paid for the
    needed property interests, Appellee filed a complaint in condemnation for temporary and
    permanent easements against Regec and his land. Appellee moved for partial summary
    judgment, seeking condemnation of the rights of way and leaving the issue of just
    *
    This disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not
    constitute binding precedent.
    2
    compensation for later litigation. It also filed a motion for a preliminary injunction for
    immediate possession of the rights of way. After a hearing at which Regec was
    represented by counsel, the District Court granted both motions, giving Appellee
    possession of the rights of way at issue. Regec filed a pro se notice of appeal.
    The District Court had jurisdiction pursuant to 15 U.S.C. § 717f(h), which
    provides for jurisdiction in the District Court for eminent domain actions under the
    Natural Gas Act. We have jurisdiction over the grant of the preliminary injunction
    pursuant to 
    28 U.S.C. § 1292
    (a)(1). The grant of partial summary judgment, however, is
    not before us as the order did not end the litigation as to all claims and all parties. See
    Andrews v. United States, 
    373 U.S. 334
    , 340 (1963). Nor was the order certified by the
    District Court pursuant to Fed. R. Civ. P. 54(b), which provides that the District Court
    may direct entry of judgment as to fewer than all claims if it “expressly determines that
    there is no just reason for delay.” Fed. R. Civ. P. 54(b).1
    We review the denial of a motion for a preliminary injunction for an abuse of
    discretion but review the District Court’s underlying legal conclusions de novo. Brown
    1
    By its citation of Operating Sys. Support, Inc. v. Wang Labs., Inc., 52 F. App’x 160,
    164-65 (3d Cir. 2002), Appellee appears to argue that we should assert pendent appellate
    jurisdiction over the District Court’s grant of partial summary judgment. “Pendent
    appellate jurisdiction exists where an appealable issue is so inextricably intertwined with
    a nonappealable issue that one cannot resolve the former without addressing the latter.”
    Griswold v. Coventry First LLC, 
    762 F.3d 264
    , 269 (3d Cir. 2014). The doctrine of
    pendent appellate jurisdiction is narrow and should be used sparingly. See 
    id.
     We
    decline to assert pendent appellate jurisdiction to review the District Court’s ruling on the
    merits here. If he chooses, Regec may appeal the grant of partial summary judgment
    when the District Court issues its final order resolving all claims.
    3
    v. City of Pittsburgh, 
    586 F.3d 263
    , 268 (3d Cir. 2009). To obtain injunctive relief, a
    party must show a likelihood of success on the merits, irreparable harm if the injunction
    is not granted, that relief will not cause greater harm to the nonmoving party, and that
    relief is in the public interest. Miller v. Mitchell, 
    598 F.3d 139
    , 147 (3d Cir. 2010).
    Likelihood of success on the merits
    In order to bring suit in federal court under the Natural Gas Act, the plaintiff must
    have been granted a certificate by the FERC, it must have been unable to acquire the
    rights of way by a contract with the property owner, and the value of the property interest
    as claimed by the owner must be more than $3000. 15 U.S.C. § 717f(h). Regec does not
    dispute any of these elements. The Act provides that if the holder of a certificate is
    unable to acquire the needed rights of ways by contract with the landowner, it may
    automatically acquire the rights of way through eminent domain in a United States
    District Court. See 15 U.S.C. § 717f(h); Columbia Gas Transmission, LLC v. 1.01
    Acres, 
    768 F.3d 300
    , 304 (3d Cir. 2014). The only remaining issue to be decided by the
    District Court is the compensation the landowner receives in return for the condemnation.
    Columbia Gas Transmission, LLC, 768 F.3d at 304. As Appellee fulfilled the
    requirements under § 717f(h) for taking the property interests by eminent domain, it has
    demonstrated a likelihood of success on the merits of its condemnation claim.
    While Regec claims that several statutes and rules relied on by the District Court
    violated the United States and Pennsylvania constitutions, the argument underlying these
    claims is that the condemnation of his property interests violated his constitutional right
    4
    to due process. However, Regec received notice that Appellee was seeking a certificate
    that included necessary rights of way on his property. He had the opportunity to
    comment on and intervene in the administrative process before the FERC. He did not do
    so. Because he received notice and the opportunity to respond in the FERC proceedings
    and will have the opportunity to litigate just compensation in the District Court, Regec
    has received the process he was due. See Williamson Cty. Reg’l Planning Comm’n v.
    Hamilton Bank of Johnson City, 
    473 U.S. 172
    , 194 (1985) (“The Fifth Amendment does
    not proscribe the taking of property; it proscribes taking without just compensation. Nor
    does the Fifth Amendment require that just compensation be paid in advance of, or
    contemporaneously with, the taking; all that is required is that a ‘reasonable, certain and
    adequate provision for obtaining compensation’ exist at the time of the taking.”) (internal
    citation omitted); Mullane v. Cent. Hanover Bank & Trust Co., 
    339 U.S. 306
    , 314 (1950)
    (fundamental requirements of due process are notice and opportunity to be heard);
    Elterich v. City of Sea Isle City, 
    477 F.2d 289
    , 290 (3d Cir. 1973) (exercise of eminent
    domain power does not violate due process). Regec’s arguments do not undermine
    Appellee’s likelihood of success on the merits.
    Regec argues that Appellee’s taking of his property goes beyond the reach of the
    FERC certificate because the permanent right of way for the pipeline will cut off his
    access to part of the property not covered by the certificate. Regec also claims that the
    taking of the property constitutes an unreasonable seizure in violation of the Fourth
    Amendment because he will be unable to access the property. However, as noted by the
    5
    District Court, the impact of the taking on the rest of his property is an issue for the
    determination of just compensation. Moreover, we note that Appellee explained at the
    hearing in the District Court the measures it takes to assure that a landowner has access to
    his property during construction. Tr. 3/23/17 at 25-26.
    Because Appellee demonstrated success on the merits of its condemnation claim,
    this factor weighed heavily in favor of the injunction. See also In re Revel AC, Inc., 
    802 F.3d 558
    , 568 (3d Cir. 2015) (when considering motions to stay, the most important
    factor is whether the petitioner has made a strong showing of the likelihood of success on
    the merits).
    Irreparable Harm
    To support its need for immediate possession of the rights of way, Appellee set
    forth in the District Court the significant monetary and contractual harms it would suffer
    if the extensive, complicated construction of the pipeline were to be delayed.2 Regec
    complains that he was not given discovery to determine the veracity of testimony given
    by Appellee’s witnesses at the hearing. However, he does not point to any statements
    that he believes were inaccurate. He also contends that the injunction is premature as
    Appellee needs to complete several field surveys and conditions before construction
    begins. But Appellee requires the right to access the property at issue in order to
    2
    Appellee asserted that unless it was given immediate possession, it would lose $500,000
    per month, and revenues of $33 million per month would be delayed. Delay in
    possession would also cause Appellee to breach contracts with subcontractors and
    vendors. Appellee’s brief at 29.
    6
    complete those field surveys. While generally a harm that can be remedied by monetary
    relief is not considered irreparable, a financial loss may be irreparable if the expenditures
    cannot be recouped. See Philip Morris USA Inc. v. Scott, 
    131 S. Ct. 1
    , 4 (2010) (Scalia,
    J.) (in chambers). We believe such is the case here. The monetary harm the Appellee
    would have suffered if immediate possession had not been allowed weighed in favor of
    the injunction.
    Harm to nonmoving party
    Regec argues several sources of harm to him from the injunction: (1) he will be
    subject to liability if a pipeline worker is hurt on his property; (2) there will be a loss of
    timber during the construction; and (3) he will lose the ability to develop his property.
    However, as noted above, the impact of the condemnation on his property’s value can be
    addressed during the just compensation determination. Further, Regec does not explain
    why he would be held legally liable for an injury during construction by Appellee. And
    while he claims that the District Court’s decision has “stigmatized” him, he does not
    describe how it has hurt his reputation. And even if we were to consider the harm to
    Regec as weighing against the injunction, it would not counterbalance the likelihood of
    success and irreparable harm factors which weigh strongly in favor of the injunction.
    Public Interest
    As noted by the District Court, the public interest factor weighed in favor of
    granting the injunction because the pipeline will give the public access to the natural gas
    carried by the pipeline. Regec argues that a “public need” satisfying the “public use” has
    7
    not been pleaded to support the injunction. However, in its brief in support of its motion
    for the injunction, Appellee clearly set forth the public need for the pipeline.
    Conclusion
    The District Court did not err legally or abuse its discretion in its weighing of the
    relevant factors or in issuing the preliminary injunction. For the reasons above and those
    set forth by the District Court, we will affirm the District Court’s order concerning the
    preliminary injunction.
    8
    

Document Info

Docket Number: 17-1829

Judges: Shwartz, Cowen, Fuentes

Filed Date: 9/12/2017

Precedential Status: Non-Precedential

Modified Date: 11/6/2024