Linan v. Housing Auth. /Camden ( 1995 )


Menu:
  •                                                                                                                            Opinions of the United
    1995 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    2-13-1995
    Linan v Housing Auth. /Camden
    Precedential or Non-Precedential:
    Docket 94-5193
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_1995
    Recommended Citation
    "Linan v Housing Auth. /Camden" (1995). 1995 Decisions. Paper 45.
    http://digitalcommons.law.villanova.edu/thirdcircuit_1995/45
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 1995 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    No. 94-5193
    LINAN-FAYE CONSTRUCTION CO., INC.
    Appellant
    v.
    HOUSING AUTHORITY OF THE CITY OF CAMDEN
    Appeal from the United States District Court
    for the District of New Jersey
    (D.C. Civ. No. 90-cv-04651)
    Argued: September 23, 1994
    BEFORE: BECKER, COWEN and GARTH,
    Circuit Judges
    (Filed February 13, 1995)
    Cary L. Flitter (argued)
    Lundy, Flitter & Beldecos
    450 North Narberth Avenue
    P.O. Box 278
    Narberth, PA 19072-0278
    Counsel for Appellant
    Linan-Faye Construction Co., Inc.
    Mark D. Caswell (argued)
    Freeman, Zeller & Bryant
    Ten Melrose Avenue
    Woodcrest Pavilion, Suite 400
    Cherry Hill, NJ 08003-3647
    Counsel for Appellee
    Housing Authority of the
    City of Camden
    OPINION
    COWEN, Circuit Judge.
    Linan-Faye Construction Company Co., Inc. ("Linan-
    Faye"), a public housing contractor, appeals from orders of the
    district court that granted summary judgment for the Housing
    Authority of the City of Camden ("HACC") on Linan-Faye's claims
    under public contract law and 42 U.S.C. § 1983.   Because the
    district court erred in applying federal common law rather than
    state law to resolve this dispute, we will reverse and remand to
    the district court for further proceedings.   Nevertheless, since
    we conclude that in the absence of New Jersey law which
    specifically interprets "termination for convenience" clauses New
    Jersey courts would look to federal common law for guidance, we
    will limit the triable issues on remand to a determination of:
    (1) the definition of "work performed" for purposes of paragraph
    17 of Linan-Faye's contract with HACC; (2) the pre-termination
    expenses incurred by Linan-Faye that may be compensable as "work
    performed" under paragraph 17 of the contract; and (3) HACC's
    liability, if any, for damages resulting from HACC's withholding
    of Linan-Faye's performance bond after termination.   Finally,
    because the district court did not err in determining that Linan-
    Faye failed to demonstrate a protectible property or liberty
    interest sufficient to support its § 1983 claim, we will affirm
    the district court's grant of summary judgment on this claim.
    I. FACTS & PROCEDURAL HISTORY
    On August 11, 1988, HACC advertised for bids on a
    housing modernization project.   The project involved the
    renovation and rehabilitation of 244 housing units and was to be
    funded in substantial part by a grant from the United States
    Department of Housing and Urban Development pursuant to the
    Public and Indian Housing Comprehensive Improvement Assistance
    Program ("CIAP").   Plaintiff, Linan-Faye, attended all required
    pre-bid meetings and submitted a bid of $4,264,000, together with
    supporting documentation which included a bid bond, performance
    bond, qualification statement, and required affidavits.     Linan-
    Faye was the lowest responsible bidder for the job, underbidding
    its nearest competitor by $600,000.    Accordingly, HACC informed
    Linan-Faye that the contract was to be forthcoming.
    Linan-Faye engaged in preparatory activities in
    connection with the contract, including meeting with prospective
    subcontractors, job planning and pricing, talking with relevant
    inspectors, and securing insurance.   Also, on several occasions,
    representatives of Linan-Faye met with HACC and its architect to
    discuss specifications and make preparations for the commencement
    of physical construction.   Linan-Faye, however, never began
    physical construction because numerous disputes broke out between
    the parties over interpretation of the specifications.
    Linan-Faye contends that HACC demanded concessions
    before permitting work to begin.   HACC maintains that the parties
    arrived at different interpretations of the project plans and
    specifications, and this conflict became evident at pre-
    construction meetings.   On November 29, 1988, as the result of
    these disputes, HACC advised Linan-Faye that it was going to
    rebid the project.   Linan-Faye filed suit to enjoin this
    rebidding and allow it to complete the project as bid.
    The district court entered a temporary restraining
    order to prevent HACC from accepting further bids.   Subsequently,
    the court approved a Stipulation of Settlement and Order of
    Dismissal with Prejudice, under which the parties agreed to
    execute the contract and proceed with the project as originally
    planned.   Nevertheless, disputes soon broke out again.
    On November 22, 1989, HACC issued a Notice to Proceed.
    Linan-Faye contends that the notice was limited to an order to
    correct certain plumbing problems that were a portion of the
    original contract.   Linan-Faye refused to proceed in a piecemeal
    fashion, and insisted that it would not begin work until a
    certain number of vacant buildings were available at the same
    time so that it could achieve economies of scale.    HACC responded
    that it had scattered vacant units available, but not rows of
    units.
    Subsequently, HACC attempted first to extract the
    plumbing segment from the contract and, when that failed,
    proposed a complete buy-out of Linan-Faye's contract.     The
    parties entertained the possibility of a buy-out until July of
    1990, at which time HUD informed HACC that it would not approve a
    buy-out.    HACC reinstated the previous Notice to Proceed by
    letter dated July 23, 1990.
    At a preconstruction meeting on September 6, 1990,
    Linan-Faye informed HACC that it would not start work until the
    contract price was increased to reflect the costs incurred by the
    delay in commencing construction.    HACC responded that Linan-Faye
    had to begin work before it would address the issue of the price
    increase.
    HACC elected to terminate Linan-Faye's contract by
    letter dated September 25, 1990.    In that letter, Gregory Kern,
    the Interim Executive Director of HACC, stated that HACC would
    instruct the Modernization Office to assist Linan-Faye in
    reclaiming its performance bonds.    While the letter did not
    mention the terms "breach" or "default," it did state that Linan-
    Faye "had continually failed to demonstrate its intent to perform
    under the public contract."    Letter from Kern to Norman Faye
    (September 25, 1990); App. Vol. I at 114-115.    HACC confirmed its
    decision to terminate by letter dated October 23, 1990.
    Linan-Faye objected to the termination and filed the instant
    action on October 26, 1990, setting forth theories of recovery
    under New Jersey public contracts law and 42 U.S.C. § 1983.
    Linan-Faye served HACC with a complaint in December of 1990
    seeking specific performance and damages.    HACC did not surrender
    Linan-Faye's performance bond until July of 1991, after the
    district court determined that specific performance was not
    available to Linan-Faye.
    In April of 1992, HACC filed a motion for summary
    judgment on Linan-Faye's civil rights claim and for the first
    time argued, in that same motion, that the "termination for
    convenience" clause set forth in paragraph 17 of the General
    Conditions of their contract limited Linan-Faye's damages under
    the contract.1   The district court granted HACC's motion for
    1
    . Paragraph 17 of this contract's General Conditions of the
    Contract for Construction states in relevant part:
    a.   Subject to the approval of HUD, the performance of work
    under this contract may be terminated by the PHA in
    accordance with this paragraph in whole, or from time
    to time in part, whenever the Contracting Officer shall
    determine that such termination is in the best interest
    of the PHA. Any such termination shall be effected by
    delivery to the Contractor of a Notice of Termination
    specifying the extent to which the performance of the
    work under the contract is terminated, and the date
    upon which such termination becomes effective.
    b.   If the performance of the work is terminated, either in
    whole or in part, the PHA shall be liable to the
    Contractor for reasonable and proper costs resulting
    from such termination, which costs shall be paid to the
    Contractor within 90 days of receipt by the PHA of a
    properly presented claim setting out in detail: (1) the
    total cost of the work performed to date of termination
    less the total amount of contract payments made to the
    contractor . . .; and (5) an amount constituting a
    reasonable profit on the value of work performed by the
    Contractor.
    App. Vol. II at 45.
    summary judgment on the § 1983 claim, but deferred decision on
    the effect of the termination of convenience clause pending
    further discovery.
    Upon a renewed motion for summary judgment, the
    district court held for HACC, determining that Linan-Faye's
    damages would be limited to those compensable under the
    contract's termination for convenience clause.    The district
    court left open, however, the possibility of recovery for damages
    accruing from HACC's initial failure to identify specifically the
    termination as one of convenience.
    HACC filed its third motion for summary judgment on
    October 27, 1993.    In that motion, HACC contended that since
    Linan-Faye never began work under the contract, it could not
    recover any damages under the termination for convenience clause.
    Linan-Faye responded that it could recover damages for: (1)
    preparatory costs such as soliciting subcontractors, pricing, and
    pre-construction meetings; (2) improper notice of termination;
    (3) pre-termination delay by HACC; and (4) HACC's refusal to
    relinquish Linan-Faye's performance bond.   Determining that
    federal common law applied in interpreting this contract, the
    district court held that Linan-Faye incurred no compensable
    damages under the termination for convenience clause.   The court,
    therefore, entered an order granting summary judgment for HACC.
    This appeal followed.
    Following oral argument before this Court, HACC and
    Linan-Faye agreed to participate in non-binding mediation of the
    controversy before the Honorable Max Rosenn, Senior Circuit
    Judge.   By memorandum dated November 9, 1994, Judge Rosenn
    informed us that efforts to reach a settlement of the controversy
    through mediation were unsuccessful.
    II. JURISDICTION & OVERVIEW OF ISSUES RAISED IN THIS APPEAL
    The district court exercised jurisdiction in this
    matter by virtue of the diversity of citizenship of the parties
    with the requisite amount in controversy pursuant to 28 U.S.C. §
    1332 (1988).   This Court has jurisdiction pursuant to 28 U.S.C. §
    1291 (1988).   Linan-Faye essentially raises six issues on
    appeal:2 (1) whether the district court erred in applying
    federal common law and not the law of New Jersey to interpret
    this contract; (2) whether New Jersey law precludes retroactive
    application of a termination for convenience clause; (3) whether
    the district court was correct in its application of the
    constructive termination for convenience doctrine; (4) whether
    the district court erred by engaging in impermissible fact
    2
    . Linan-Faye styles its appeal as containing seven issues.
    Brief of Appellant at ix-x. The first of these issues, according
    to Linan-Faye, is that the district court engaged in
    impermissible fact finding on contested matters. Given our
    conclusion concerning the application of the termination for
    convenience clause, however, this issue is best resolved in
    conjunction with a discussion of the proper application of that
    clause. See discussion infra part VI.
    finding so as to deny Linan-Faye all compensation; (5) whether
    Linan-Faye has an actionable claim for violation of its civil
    rights; and (6) whether HACC's position that the termination for
    convenience clause denies any recovery is barred by principles of
    equitable and judicial estoppel.
    III. CHOICE OF LAW
    Linan-Faye contends that the district court erred in
    applying federal common law and not the law of New Jersey to
    resolve this dispute.   According to Linan-Faye, this action
    involves a contract dispute between a private contractor and an
    autonomous public housing authority created pursuant to New
    Jersey law.   Where such parties enter federal court based upon
    diversity of citizenship, Linan-Faye argues, the federal courts
    presumptively apply state law.   See Erie R. Co. v. Tompkins, 
    304 U.S. 64
    , 78, 
    58 S. Ct. 817
    , 822 (1938).   We agree.
    Our review of a district court's determination as to
    choice of law is plenary.   Louis W. Epstein Family Partnership v.
    Kmart Corp., 
    13 F.3d 762
    , 766 (3d Cir. 1994) (citing Universal
    Minerals, Inc. v. C.A. Hughes & Co., 
    669 F.2d 98
    , 102 (3d Cir.
    1981)).   This Court's recent decision in Virgin Islands Housing
    Authority v. Coastal General Construction Services Corp., 
    27 F.3d 911
    (3d Cir. 1994), strongly indicates the proper result in this
    case.   In Coastal General, we determined, in the context of
    deciding a question of federal jurisdiction, that local law, not
    federal law, governs a dispute over the termination provisions of
    a contract between a public housing authority and a private
    construction company.    
    Id. at 917.
      As we stated in Coastal
    General, "[t]he fact that a contract is subject to federal
    regulation does not, in itself, demonstrate that Congress meant
    that all aspects of its performance or nonperformance are to be
    governed by federal law rather than state law applicable to
    similar contracts in businesses not under federal regulation."
    
    Id. at 916
    (quoting Lindy v. Lynn, 
    501 F.2d 1367
    , 1369 (3d Cir.
    1974)).    In addition, we explained that even if the contractor's
    complaint contained assertions respecting the use of federal
    funds in a construction project and the adoption of contractual
    forms authorized by HUD, there would be no difference in outcome.
    
    Id. at 917.
    Similar to Coastal General, in the instant case a
    public housing authority contracted with a private construction
    company.   Linan-Faye, the construction company, did not contract
    directly with the United States government.     While HUD funded the
    construction project in part, and HUD forms were used in the
    contract, Coastal General teaches that these facts do not dictate
    application of federal common law.     Rather, the holding of
    Coastal General indicates that in construing termination clauses
    such as the one at issue in this case, courts must look to local
    law.   Thus, the district court was incorrect in applying federal
    common law and not the law of New Jersey to resolve this dispute.
    The district court erred in deviating from the
    generally applicable Erie doctrine.    The Supreme Court, in Boyle
    v. United Technologies Corp., 
    487 U.S. 500
    , 
    108 S. Ct. 2510
    (1988), set forth a two-pronged inquiry for determining whether
    to apply federal common law in the absence of an express
    Congressional grant of such authority.    According to the Supreme
    Court, a court must first determine whether the action involves
    "``uniquely federal interests.'"     
    Id. at 504,
    108 S. Ct. at 2514
    (citing Texas Industries Inc. v. Radcliff Materials, Inc., 
    451 U.S. 630
    , 640, 
    101 S. Ct. 2061
    , 2067 (1981)).    Once a court
    identifies a uniquely federal interest, the court must then
    determine whether a "significant conflict" exists between an
    identifiable "federal policy or interest and the [operation] of
    state law."     
    Id. at 507,
    108 S. Ct. at 2516 (quoting Wallis v.
    Pan American Petroleum Corp., 
    384 U.S. 63
    , 68, 
    86 S. Ct. 1301
    ,
    1304 (1966)).
    Relying on American Pipe & Steel Corp. v. Firestone
    Tire & Rubber Co., 
    292 F.2d 640
    (9th Cir. 1961), and United
    States v. Taylor, 
    333 F.2d 633
    (5th Cir. 1964), the district
    court concluded that the government's interest in ensuring a
    uniform interpretation of the termination for convenience
    provisions in this contract provided the "significant federal
    interest" necessary to pre-empt state law.     Linan-Faye
    Construction Co. v. Housing Authority of Camden, 
    847 F. Supp. 1191
    , 1197 (D.N.J. 1994).     These cases, however, do not dictate
    this result.   While both of these cases applied federal law in
    interpreting a contract, the government interest was far more
    significant in those cases than in the case at hand.     In American
    Pipe & Steel, the Court of Appeals for the Ninth Circuit stated,
    "we agree generally with appellee that the construction of
    subcontracts, let under prime contracts connected with the
    national security, should be regulated by a uniform federal law."
    American Pipe & 
    Steel, 292 F.2d at 644
    .    The instant case
    involves no matter of national security.    Further, the court in
    American Pipe & Steel expressly acknowledged that the development
    of the law in this area was "still uncertain and unclear."     
    Id. Similarly, in
    Taylor, the contract at issue involved the
    construction of an atomic energy plant, a matter intricately
    involved with national security during the 1950's and 1960's.
    
    Taylor, 333 F.2d at 635
    .   The Taylor court also explicitly
    referred to the fact that American Pipe & Steel dictated
    application of federal common law in such a case.     
    Id. at 637.
    Thus, both of these decisions concerned matters of national
    security that are simply not present in this case.3
    3
    . Still another distinction exists between the instant case and
    the cases the district court relied upon in applying federal
    common law to interpret this contract. American Pipe & Steel and
    Taylor involved direct United States government procurement
    contracts, or a subcontract with a United States government prime
    contractor. American Pipe & 
    Steel, 292 F.2d at 641
    ; 
    Taylor, 333 F.2d at 635
    . Neither of these situations involved, as is the case
    here, the outright grant of funds to a public agency. The closer
    nexus to the United States government in American Pipe & Steel
    and Taylor heightens the federal government's interest. The
    weaker link in this case diminishes the significance of the
    Moreover, the district court erred in finding a
    conflict between federal and state law that would endanger any
    federal interest involved.    The district court correctly
    recognized the proposition that a lawsuit which involves a
    federal interest is a "necessary, not a sufficient, condition for
    the displacement of state law."    Linan-Faye Construction 
    Co., 847 F. Supp. at 1198
    (quoting Boyle 487 U.S. at 
    507, 108 S. Ct. at 2516
    ).   The court, however, failed to identify a significant
    conflict.    In the only paragraph that attempts to identify a
    conflict, the court stated:
    We find it implausible that the federal government
    would require all CIAP contracts in excess of
    $10,000.00 to contain a termination for convenience
    clause, and then leave interpretation of that clause to
    the vagaries of state law, particularly where, like New
    Jersey, there are few or no state law cases
    interpreting this type of provision. Rather, we
    believe that the decision to include a termination for
    convenience clause in the "Uniform Requirements"
    section of the C.F.R. reflects a federal interest in a
    consistent interpretation of that clause.
    
    Id. The first
    sentence of this paragraph merely assumes the
    answer to the question the court is wrestling with: whether
    Congress left interpretation of clauses in these types of
    contracts to state law.    The second sentence of the above quoted
    (..continued)
    government interest. Thus, the district court was incorrect in
    finding a government interest significant enough to warrant
    deviating from Erie and applying federal common law.
    paragraph simply reidentifies the interest involved, it does not
    point out a conflict with state law.
    The problem with the district court's reasoning is
    highlighted by its own analysis of what the outcome would be
    under state law.   The court states, "[e]ven assuming that New
    Jersey law were to apply, we have no basis for believing that New
    Jersey courts would look elsewhere than to federal common law for
    guidance."   
    Id. If New
    Jersey courts, as is likely, would look
    to federal common law to decide this question for which there is
    little state law precedent on point, then the court is incorrect
    in its assertion that a conflict exists.      The outcome would be
    the same under both federal and state common law.      Thus, the
    court erred in applying federal common law and not the law of New
    Jersey to resolve this dispute and we must reverse with the
    direction that the district court resolve all remaining issues in
    accordance with New Jersey law.
    IV. NEW JERSEY LAW
    Having decided that it is the law of New Jersey that
    governs the interpretation of this contract, we must now decide
    whether Linan-Faye is correct when it argues that the general
    principles of contract damages under New Jersey law would permit
    Linan-Faye to recover full expectation damages under this
    contract rather than those damages provided for under the
    contract's termination for convenience clause.   Citing A-S
    Development, Inc. v. W.R. Grace Land Corp., 
    537 F. Supp. 549
    , 557
    (D.N.J. 1982), aff'd 
    707 F.2d 1388
    (3d Cir. 1983), and other
    cases,4 Linan-Faye states that under New Jersey law one who
    breaches an agreement must compensate the injured party in order
    to put the non-breaching party in as good a position as he would
    have been in had performance been rendered as promised.   Further,
    Linan-Faye argues that New Jersey courts have declined to import
    federal procurement concepts into their contract law
    jurisprudence. See Edwin J. Dobson, Jr., Inc. v. Rutgers, 
    157 N.J. Super. 357
    , 418, 
    384 A.2d 1121
    , 1152 n.10 (1978) ("The
    policy factors that have lead [sic] to the development of this
    concept in federal contracts, such as a need to expand or abandon
    a particular arms program with consequent economic impact on
    contractors and subcontractors, do not warrant state courts
    adopting it wholesale by judicial fiat when traditional remedies
    for breach of contract are available."), aff'd sub nom., Broadway
    Maintenance Corp. v. Rutgers, 
    180 N.J. Super. 350
    , 
    434 A.2d 1125
    (A.D. 1981), aff'd, 
    90 N.J. 253
    , 
    447 A.2d 906
    (1982).     While the
    cases Linan-Faye cites stand for these general propositions, such
    4
    . Linan-Faye also cites Donovan v. Bachstadt, 
    91 N.J. 434
    , 
    453 A.2d 160
    (1982), for the proposition stated above. Further,
    Linan-Faye cites In Re Merritt Logan, Inc., 
    901 F.2d 349
    , 357-58
    (3d Cir. 1990) and Sandler v. Lawn-A-Mat Chemical & Equipment
    Corp., 
    141 N.J. Super. 437
    , 454, 
    358 A.2d 805
    (A.D.),
    certification denied, 
    71 N.J. 503
    , 
    366 A.2d 658
    (1976), for the
    proposition that the courts of New Jersey have long maintained a
    liberal rule of damages to a non-breaching party.
    generalities provide insufficient guidance in deciding the proper
    construction of a contract that contains a termination for
    convenience clause.5
    It is undisputed that there are no cases in New Jersey
    construing the effect of termination for convenience clauses.    It
    is also undisputed that there are numerous federal cases dealing
    specifically with termination for convenience clauses and, in
    particular, with the doctrine of constructive termination for
    convenience.   Therefore, as the district court stated, "courts in
    New Jersey would recognize that where the parties have
    incorporated a particular clause pursuant to federal regulation,
    they do so against the backdrop of federal case law addressing
    the clause."   Linan-Faye Construction 
    Co., 847 F. Supp. at 1198
    .
    Accordingly, we align ourselves with the district court in its
    determination that if New Jersey law were to apply, New Jersey
    courts would look to this rich body of federal common law
    concerning the termination for convenience doctrine, unless to do
    so would violate some enshrined principle of New Jersey law.    
    Id. Like the
    district court, we are unable to discern such a
    principle.6
    5
    . Additionally, the quoted language in Dobson represents only
    the opinion of a single judge on this matter. The relevant issue
    was not addressed in the New Jersey Supreme Court opinion
    affirming this case.
    6
    . Linan-Faye argues that decisions of the New Jersey Supreme
    Court such as W.V. Pangborne & Co. v. New Jersey Dept. of
    Transportation, 
    116 N.J. 543
    , 
    562 A.2d 222
    (1989), where the
    court has found against governmental entities, are inconsistent
    V. TERMINATION FOR CONVENIENCE
    Because the New Jersey Supreme Court would likely look
    to federal common law as persuasive authority in order to
    construe this contract's termination for convenience clause, we
    must examine the parties' contentions in light of the relevant
    federal case law.7   As a preliminary matter, we must determine
    the method HACC used to terminate Linan-Faye.   HACC argues that
    it terminated Linan-Faye by letter of September 25, 1990, and
    this letter constituted a termination for convenience.   Linan-
    Faye, on the other hand, argues that this letter constituted a
    default termination.   Linan-Faye has the better of this argument.
    (..continued)
    with the broad discretion federal courts have conferred on the
    government in cases concerning termination for convenience
    clauses. Pangborne, however, involved a failure of a
    governmental entity to deal in good faith. 
    Id. at 562,
    562 A.2d
    at 231 ("DOT's failure . . . to deal expressly and clearly with
    this material term constitutes a breach of an implied duty of
    good faith and fair dealing and the supervening obligation of the
    government to deal scrupulously with the public."). Federal
    common law also looks disfavorably on the government in cases of
    governmental bad faith. See infra Part V. Therefore, Linan-
    Faye's argument is unpersuasive.
    7
    . We recognize that the district court also applied federal
    common law to resolve this dispute. Linan-Faye Construction 
    Co. 847 F. Supp. at 1198
    . Nevertheless, there is a difference
    between looking to federal common law as persuasive authority and
    being bound by federal law. The district court opted for the
    latter approach and determined that construction of the
    termination for convenience clause was purely a matter of federal
    common law. In light of our previous holding in Coastal 
    General, 27 F.3d at 917
    , we opt for the former approach.
    HACC's letter of September 25, 1990 is replete with
    references to defaults on the part of Linan-Faye.    HACC stated in
    the letter that Linan-Faye's correspondence evidences Linan-
    Faye's "intent to avoid compliance with the specifications."
    Letter from HACC to Norman Faye (September 25, 1990);    App. Vol.
    I at 114.    Further, HACC stated in its letter that Linan-Faye had
    "continually failed to demonstrate its intent to perform under
    the public contract" and that "it is clear" Linan-Faye is "no
    closer to performing its contract obligations then it was in
    September of 1988."   
    Id. at 114,
    115.   Nowhere in this letter
    does HACC state that it is terminating Linan-Faye simply for
    convenience.    It is apparent from this document that HACC
    originally terminated Linan-Faye for default.8
    Given HACC's original termination of Linan-Faye for
    default, the question that we must reach is whether the court
    should retroactively convert this termination for default into a
    8
    . HACC argues that the last paragraph of this letter which
    states that HACC has "instructed the Modernization Office to
    assist [Linan-Faye] as needed in obtaining release of [Linan-
    Faye's Bond]," App. at 115, is inconsistent with a default
    termination because if HACC had terminated for a default it was
    entitled to hold onto the bond. Just because HACC had the right
    to hold onto the bond under the contract, however, does not mean
    that it intended to exercise this right at the time of the
    letter. HACC may not have felt that the defaults it cited, such
    as a failure to begin work, were compensable via the bond, or it
    may have decided that it did not wish to encourage litigation
    over the bond issue. In any event, this paragraph provides
    insufficient support for HACC's argument that this letter
    constituted a termination for convenience.
    termination for convenience.     HACC argues, based on a number of
    cases from the United States Court of Claims and the Court of
    Appeals for the Federal Circuit,9 that the district court did not
    err in invoking the constructive termination for convenience
    doctrine in order to convert this default termination into a
    termination for the convenience of the Housing Authority.     Linan-
    Faye argues that under federal common law the doctrine of
    constructive termination for convenience has no application to
    this case.     According to Linan-Faye, Federal Acquisition
    Regulations (FAR's) applicable to direct procurement contracts
    provide for a "conversion clause," a clause that automatically
    converts a termination for default into a termination for
    convenience.    48 C.F.R. § 49.401(b) (1993).   Linan-Faye suggests,
    therefore, that because no such regulations exist in grant
    situations10 such as this, there is an expressed intent that such
    a conversion not be allowed.     We find Linan-Faye's argument
    unpersuasive.
    9
    .    See discussion infra this part.
    10
    . HACC received a grant pursuant to the Public and Indian
    Housing Comprehensive Improvement Assistance Program ("CIAP").
    CIAP grants, which are administered by HUD, require recipients to
    set forth various terms and conditions in their agreements with
    contractors. 24 C.F.R. § 968.110(j) (1994). The regulations
    concerning CIAP grants, collected at 24 C.F.R. § 85.1 et seq.,
    differ from the FAR's applicable to direct government procurement
    contracts. The CIAP grant regulations do not provide for a
    mandatory conversion clause.
    The absence of a conversion provision in regulations
    concerning CIAP grants does not preclude application of federal
    common law.   While the FAR's have an explicit conversion clause,
    it was the federal common law that originally developed the
    concept of termination for convenience, and later developed the
    concept of constructive termination for convenience.      We find it
    appropriate to apply federal common law.
    The idea that the government can, under certain
    circumstances, terminate a contract without paying full
    expectation damages, dates from the winding down of military
    procurement following the civil war.   Torncello v. United States,
    
    681 F.2d 756
    , 764 (Ct. Cl. 1982).   The termination for
    convenience doctrine originated "in the reasonable recognition
    that continuing with wartime contracts after the war was over
    clearly was against the public interest."   
    Id. Where the
    government terminates a private contractor pursuant to a
    termination for convenience clause in a contract, instead of
    receiving full expectation damages the contractor's recovery is
    defined by the termination for convenience clause.    Recovery is
    limited to "``costs incurred, profit based on the work done, and
    the costs of preparing the termination settlement proposal.'"
    Maxima Corp. v. United States, 
    847 F.2d 1549
    , 1552 (Fed. Cir.
    1988) (quoting R. Nash & J. Cibinic, Federal Procurement Law 1104
    (3d ed. 1980))   After World War II, termination for convenience
    came to be applied to peacetime non-military procurement.    
    Id. (citing Torncello,
    681 F.2d at 765-66).
    Constructive termination for convenience, an outgrowth
    of termination for convenience, is a judge-made doctrine that
    allows an actual breach by the government to be retroactively
    justified.11   Maxima 
    Corp., 847 F.2d at 1553
    .   This doctrine has
    its origins in the Supreme Court's decision in College Point Boat
    Corp. v. United States, 
    267 U.S. 12
    , 
    45 S. Ct. 199
    (1925).    In
    that decision, the Supreme Court held:
    A party to a contract who is sued for its breach may
    ordinarily defend on the ground that there existed, at
    the time, a legal excuse for nonperformance by him,
    although he was then ignorant of the fact. He may,
    likewise, justify an asserted termination, rescission,
    or repudiation, of a contract by proving that there
    was, at the time, an adequate cause, although it did
    not become known to him until later.
    College 
    Point, 267 U.S. at 15-16
    , 45 S. Ct. at 200-01 (footnotes
    omitted) (emphasis added).
    The decision of the Court of Claims in John Reiner &
    Company v. United States, 
    325 F.2d 438
    (Ct. Cl. 1963), cert.
    11
    . The "government" involved in these cases is typically the
    United States government. In the instant case, the entity
    seeking to terminate for convenience is the Housing Authority of
    Camden. While the doctrine of constructive termination for
    convenience originally developed to allow the United States
    government maximum flexibility to deal with military contractors
    during times of war, the expansion of this doctrine into areas
    other than those involving military contracts suggests that its
    precepts should be applied to all government entities that
    provide services to the public. Of course, the final word on
    this issue rests with the New Jersey Supreme Court.
    denied, 
    377 U.S. 931
    , 
    84 S. Ct. 1332
    (1964), demonstrates the
    operation of this doctrine.     In John Reiner, the plaintiff
    contracted with the government to supply generator sets to the
    Army.   
    Id. at 439.
      Following delivery of a written contract, but
    before performance commenced, the government notified the
    plaintiff that the contract was canceled and that the contract
    would be rebid because of an impropriety in the original bidding
    procedure identified by a competitor.     
    Id. Nevertheless, no
    such
    impropriety was found to exist.     
    Id. at 442.
      The Court of
    Claims, therefore, was forced to consider the proper measure of
    damages to the contractor.     In answering this question, the court
    determined that while the government did not rely on the
    termination for convenience clause in canceling the contract with
    the plaintiff, because it could have so relied, the measure of
    damages was limited to the damages provided for in that clause.
    
    Id. at 443.
       According to the court, even though the excuse
    originally offered was not a "valid justification," a "good
    ground did exist in the far-reaching right to terminate under the
    termination article."    
    Id. This case
    granted the government
    great latitude in retroactively terminating contracts for
    convenience.
    Perhaps the high-water mark of courts' permissiveness
    in allowing the government to terminate for convenience,
    constructively or otherwise, was Colonial Metals Co. v. United
    States, 
    494 F.2d 1355
    (Ct. Cl. 1974), overruled in part by
    Torncello v. United States, 
    681 F.2d 756
    (Ct. Cl. 1982).     In that
    case, a dealer in copper contracted with the government to sell
    copper ingot to the Navy.   
    Id. at 1357.
      The government
    terminated this contract to obtain the copper ingot from other
    sources at a cheaper price.   
    Id. The court
    held that even where
    the government knew of the better price elsewhere at the time it
    awarded the contract and then later decided to terminate the
    contract to pursue the better price, in the absence of proof of
    malice or conspiracy, termination was not improper.     
    Id. at 1361.
    Termination for convenience, and its expansion into the
    constructive termination for convenience doctrine, however, does
    not confer upon the government a discretion that is unbounded.
    In granting the government the privilege of constructive
    termination for convenience, courts brush up against the problem
    of allowing the government to create an illusory contract.      See
    
    Torncello, 681 F.2d at 769
    (when evaluating a termination for
    convenience, one cannot ignore hornbook law that "a route of
    complete escape vitiates any other consideration furnished and is
    incompatible with the existence of a contract.").     Accordingly,
    courts have articulated limits on the use of the constructive
    termination for convenience doctrine in various ways.    For
    instance, in Torncello the Court of Claims stated that the
    constructive application of a termination for convenience clause
    requires "some kind of change from the circumstances of the
    bargain or in the expectations of the parties"    
    Id. at 772.
       In
    Kalvar Corp. v. United States, 
    543 F.2d 1298
    , 1301 (Ct. Cl.
    1976), cert. denied, 
    434 U.S. 830
    , 
    98 S. Ct. 112
    (1977), by
    contrast, the court's inquiry into whether to prevent the
    government from receiving the benefit of the termination for
    convenience clause focused on whether the government evidenced
    any bad faith in terminating the contract.   Pointing out that the
    court is required to presume good faith on the part of public
    officials, the court in that case determined that the contractor
    could not avoid the application of the termination for
    convenience clause.   
    Id. at 1301-02;
    see also SMS Data Products
    Group, Inc. v. United States, 
    19 Cl. Ct. 612
    , 617 (1990) ("This
    court presumes that Government officials act in good faith.").
    In this matter, the district court concluded that under
    the bad faith test it was proper to allow HACC to invoke the
    doctrine of constructive termination for convenience.
    Additionally, the district court commented that even under the
    changed circumstances test of Torncello, the deterioration in the
    relationship between HACC and Linan-Faye would constitute
    sufficiently changed circumstances to apply this doctrine.    We
    agree with the district court's decision that it was appropriate
    to apply the constructive termination for convenience doctrine in
    this case for two reasons.   First, Linan-Faye has produced
    insufficient evidence of bad faith on the part of HACC to
    overcome the presumption that public officials act in good faith.
    Second, this case is very different from Torncello.
    In Torncello, the government awarded a private
    contractor the right to service all of the Navy's pest control
    needs.     
    Torncello, 681 F.2d at 758
    , 762.   However, after awarding
    the contract to this contractor, the Navy called the Department
    of Navy Public Works to perform the task because this
    organization, from its initial bid, appeared to be able to do the
    work cheaper.    
    Id. at 758.
      The government invoked the
    constructive termination for convenience doctrine arguing that
    since it had never called the private contractor to perform any
    actual work, the private contractor was not entitled to any
    damages.    
    Id. at 759.
      Limiting its decision in Colonial Metals,
    the court held, in an opinion joined by only three of six judges,
    that the requirement of the government's good faith is not
    sufficient and that without other checks, free termination for
    convenience is not supportable. 
    Id. at 771.12
    In the matter at hand, Linan-Faye does not claim that
    HACC terminated its contract to obtain the work at a cheaper
    price.   Linan-Faye also does not claim that HACC terminated the
    contract in order to obtain work from a lower bidder who was
    known to HACC at the time it contracted with Linan-Faye.      Indeed,
    12
    . Notably, the disagreement among the judges in that case was
    on the precise issue of whether it was appropriate to create a
    stricter test for convenience terminations by the government.
    
    Id. at 773-774
    (Friedman, C.J., Davis, J., and Nichols, J.
    concurring) While all the judges agreed on the result in that
    case, the court could not muster a majority to embrace the new
    "changed circumstances" test.
    Linan-Faye points out in its brief that it was the low bidder for
    the project.    Brief of Linan Faye at 1.   Thus, the divisive facts
    presented in Torncello are not present here.
    Moreover, subsequent cases have limited the scope of
    Torncello.     The Court of Appeals for the Federal Circuit, for
    example, has stated that Torncello "stands for the unremarkable
    proposition that when the government contracts with a party
    knowing full well that it will not honor the contract, it cannot
    avoid a breach claim by adverting to the convenience termination
    clause."   Salsbury Industries v. United States, 
    905 F.2d 1518
    ,
    1521 (Fed. Cir. 1990), cert. denied, 
    498 U.S. 1024
    , 
    111 S. Ct. 671
    (1991); see also T.I. Construction Co. v. Kiewit Eastern Co.,
    No. 91-2638, 
    1992 WL 382306
    , at *9 (E.D.Pa. Dec. 10, 1992)
    (citing language in Torncello indicating that its holding was
    limited to the facts presented); Modern Systems Technology Corp.
    v. United States, 
    24 Cl. Ct. 699
    , 704 (Cl. Ct. 1992) (applying
    bad faith test and reading Torncello to stand only for the above
    stated proposition), aff'd, 
    980 F.2d 745
    (Fed. Cir 1992).     In
    addition, in a subsequent case, the United States Claims Court
    stated that "Torncello did not change the traditional
    understanding" that the "Government could invoke the clause so
    long as it did not act in bad faith or clearly abuse its
    discretion."    SMS Data 
    Products, 19 Cl. Ct. at 619-20
    .   In light
    of these developments, and considering the division among the
    court in Torncello, we decline to read that case as significantly
    limiting the power of the government in terminating for
    convenience.13
    As the district court recognized, the post award
    deterioration of the relationship between HACC and Linan-Faye
    which included conflict over the specifications would likely
    constitute sufficiently changed circumstances to justify
    application of the doctrine of constructive termination for
    convenience even under the reasoning in Torncello.   See Embrey v.
    United States, 
    17 Cl. Ct. 617
    , 624-25 (1989) (deterioration of
    business relations considered sufficiently changed circumstances
    to allow government to terminate for convenience);   see also SMS
    Data 
    Products, 19 Cl. Ct. at 621
    (genuine concern that contractor
    could not meet the contract's mandatory requirements constituted
    changed circumstances).   Without establishing a litmus test as to
    what constitutes changed circumstances, which is unnecessary in
    view of subsequent limits on Torncello, we hold that New Jersey
    courts, looking to federal law as persuasive authority, would
    permit HACC to invoke the constructive termination for
    13
    . Linan-Faye also cites a law review note written shortly
    after the Torncello decision in support of its claims. Stephen
    N. Young, Note, Limiting the Government's Ability to Terminate
    For Its Convenience Following Tornecello [sic], 52 Geo. Wash. L.
    Rev. 892 (1984). In that note, the author suggests that
    Torncello provides a reason to eliminate the government's right
    to constructively terminate for convenience. 
    Id. at 911.
    As
    this author was writing without the benefit of recent decisions,
    all that can be said of his recommendation is that future courts
    declined to take the hint.
    convenience doctrine in this instance.14   Accordingly, damages
    will be limited by the termination for convenience clause of the
    contract.15
    14
    . The dissent states that the majority "holds that a
    deterioration in business relations, demonstrated in not
    insignificant part by a dispute over specifications, constitutes
    such a change in circumstances." See infra at 12 (emphasis
    added). The dissent is incorrect insofar as it reads this to be
    the holding of our decision. As we have already explained,
    Torncello, and its changed circumstances approach, has been
    sharply limited by more recent cases. See 
    discussion supra
    this
    Part. We have therefore declined to endorse wholeheartedly the
    changed circumstances approach. Accordingly, an accurate
    statement of our position is that (1) Linan-Faye has not
    demonstrated actual bad faith on the part of HACC and (2) this
    case does not present the divisive facts presented in Torncello
    that warranted finding against the government.
    15
    . At oral argument, Linan-Faye suggested that the application
    of paragraph 16(d) of the General Conditions of this Contract
    "trumps" the constructive application of the paragraph 17
    termination for convenience clause. Paragraph 16(d) states, in
    pertinent part:
    The Contractor's right to proceed shall not be terminated or
    the Contractor charged with damages under this clause
    if:
    (1) The delay in completing the work arises from
    unforeseeable causes beyond the control and without the
    fault or negligence of the Contractor. Examples of
    such causes include (1) acts of God, or of the public
    enemy, (ii) acts of the PHA or other governmental
    entity in either its sovereign or contractual capacity
    (iii) acts of another contractor in the performance of
    a contract with the PHA (iv) fires . . . .
    App. Vol II at 45.
    This subsection of paragraph 16 carves out an exception to when
    HACC can terminate for default.
    While Linan-Faye's argument goes to whether HACC breached
    the agreement in terminating for default, it cannot prevent
    application of the constructive termination for convenience
    VI.   COMPENSATION IN LIGHT OF THE TERMINATION
    FOR CONVENIENCE CLAUSE
    Having determined that the termination for convenience
    clause is applicable in this case, we must next decide whether
    the district court erred in granting summary judgment for HACC
    and denying Linan-Faye all compensation.   Linan-Faye contends
    that the district court exceeded its role at the summary judgment
    stage because there still remain six contested issues concerning
    its contract claim.   According to Linan-Faye, the district court
    erred in determining: (1) the definition of "work performed"
    under the contract; (2) there was no evidence of compensable pre-
    termination expenses under the contract; (3) the reason why HACC
    retained Linan-Faye's performance bond; (4) that Linan-Faye
    "refused" to begin work; (5) that Linan-Faye misunderstood the
    contract specifications; and (6) that there was proper HUD
    approval of the contract's termination.
    Our scope of review is plenary in determining the
    propriety of summary judgment.   Oritani Savings & Loan Ass'n v.
    Fidelity & Deposit Co., 
    989 F.2d 635
    , 637 (3d Cir. 1993).
    Summary judgment is proper only "if the pleadings, depositions,
    answers to interrogatories, and admissions on file, together with
    (..continued)
    doctrine. The very premise of the College Boat decision is that
    a party may defend a suit for breach on the grounds that a legal
    excuse existed at the time of the alleged breach. College 
    Boat, 267 U.S. at 15-16
    , 
    45 S. Ct. 200-01
    . Thus, whether HACC breached
    its agreement by terminating the contract for default is largely
    beside the point.
    the affidavits, if any, show that there is no genuine issue as to
    any material fact and that the moving party is entitled to
    judgment as a matter of law."   Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 322, 
    106 S. Ct. 2548
    , 2552 (1986).   Further, at the summary
    judgment stage, "the judge's function is not himself to weigh the
    evidence and determine the truth of the matter but to determine
    whether there is a genuine issue for trial."    Anderson v. Liberty
    Lobby, Inc., 
    477 U.S. 242
    , 249, 
    106 S. Ct. 2505
    , 2511 (1986).
    Three of the issues that Linan-Faye raises are
    genuine issues of material fact in dispute.    The other issues
    concern facts that are either not material, or are not in
    dispute.   We will reverse the decision of the district court
    granting summary judgment on those issues where there is a
    genuine issue of material fact in dispute.
    A.   Definition of "Work Performed" under the Contract
    Linan-Faye argues that the trial court improperly
    selected isolated phrases from correspondence between the parties
    in its determination that the phrase "work performed" in
    paragraph 17 of the contract16 refers only to "physical
    construction" and not to preparatory work.     The district court
    conceded that the contract documents, which include the
    contract's General Conditions and its Supplement to the Standard
    Form Agreement, failed to define the term "work."     Linan-Faye
    16
    .   See supra note 1 for the text of paragraph 17.
    Construction 
    Co., 847 F. Supp. at 1206
    .   Based on an analysis of
    the word "work" as used in several paragraphs of the contract,
    the district court concluded that "work" could not include
    "preparatory work" until after Linan-Faye began physical
    construction on the project.   
    Id. at 1207.
      We conclude that the
    district court erred in determining this disputed issue of fact.
    Paragraph 8(a) of the General Conditions of this
    contract is the paragraph from which the district court draws the
    most support for its conclusion that "work" under the termination
    for convenience clause does not include "preparatory work."     The
    court's reading of this paragraph, however, is too strained to
    support a grant of summary judgment.   Paragraph 8(a) of the
    General Conditions states:
    Progress payments will be made at approximately thirty
    (30) day intervals; and in preparing estimates,
    acceptable work in place, material delivered to and
    properly stored on the site, and preparatory work done
    will be taken into consideration. If the contract
    covers more than one project, a separate estimate shall
    be furnished for each.
    App. Vol. II at 42.   From this paragraph, the district court
    deduced that expenses for preparatory work were recoverable only
    if the contractor begins the physical construction required under
    the contract.   Linan-Faye Construction 
    Co., 847 F. Supp. at 1207
    .
    This conclusion is unjustified.
    There is nothing in the language of paragraph 8(a) that
    speaks to situations where HACC terminates Linan-Faye for
    convenience after Linan-Faye has performed preparatory work, but
    before it has begun physical construction.    If anything, the
    language of this paragraph demonstrates that both parties
    considered preparatory work to be a compensable cost because the
    paragraph states that preparatory work will be taken into
    consideration in preparing estimates for compensation.     Thus, the
    district court erred in concluding that this paragraph is
    dispositive.
    The district court's survey of numerous other
    paragraphs containing the word "work" also produces inconclusive
    results.   According to the court, paragraph 2 which requires the
    contractor to "furnish all necessary labor, materials, tools,
    equipment, water, light, heat, power, transportation, and
    supervision necessary for performance of the work," and paragraph
    22 which allows the contractor to request from the architect
    drawings "which will [be required] in the planning and production
    of the work" somehow indicate that "work performed" under
    paragraph 17 does not include preparatory work.     
    Id. at 1206
    (emphasis added).   These provisions, on their face, do not appear
    to support any such conclusion.    In addition, the district court
    determined that paragraphs 26, 29 and 35, which refer to the
    contractor's obligation to protect "work completed to date" and
    to the warranty as to "work done," support the conclusion that
    work performed under the termination for convenience clause does
    not include preparatory work.     Once again, if anything, these
    provisions merely beg the question of how to define "work" under
    paragraph 17 of the contract.    Finally, the court refers to
    paragraphs 7 and 31 that speak to obligations of the contractor
    before and shortly after "commencing work" under the contract.
    Unfortunately, these paragraphs also do not illuminate whether
    the parties considered preparatory work to constitute compensable
    work for purposes of the termination for convenience clause.17
    Linan-Faye asks for the opportunity to present
    testimony and cross-examine witnesses concerning the intent of
    the parties in using the phrase "work performed" in paragraph 17
    of the contract.    Based on the evidence mustered by the district
    court, we cannot conclude that there is no dispute as to this
    issue.   Further, this issue is material to the question of what
    constitutes proper compensation under paragraph 17.       Therefore,
    Linan-Faye should be allowed to present the evidence that it
    feels is appropriate to determine the intent of the parties.
    Accordingly, we hold that the district court erred in granting
    summary judgment for HACC on this disputed issue.
    B.    Evidence of Pre-Termination Expenses
    17
    . The district court also refers, in a footnote, to letters
    exchanged between the parties that purportedly explain the
    understanding of the parties concerning the definition of "work
    performed." The fact that the court goes beyond the contract and
    looks to these letters to reinforce its conclusion demonstrates
    the impropriety of granting summary judgment and the need to make
    such decisions on a more fully developed record.
    Related to the disputed issue of the definition of
    "work performed" under the contract is the issue of whether
    Linan-Faye produced any evidence of pre-termination expenses
    compensable as "work-performed."   The district court determined
    that Linan-Faye "had presented no evidence of expenses that would
    merit an equitable adjustment to the contract."   
    Id. at 1208
    n.22.   Linan-Faye argues that the certification which it
    submitted in opposition to HACC's third motion for summary
    judgment provides the requisite evidence.   Linan-Faye is correct.
    The district court, at this early stage of the
    litigation, improperly concluded that there was "no evidence" of
    expenses compensable under the termination for convenience
    clause.   Linan-Faye described 15 types of expenses that Linan-
    Faye incurred preparing for work on the HACC contract.
    Certification of Norman Faye (October 21, 1993); App. at 231-33.
    While many of these "expenses" may not be compensable, some of
    the stated expenses, such as time spent "with municipal building,
    plumbing and electrical inspectors regarding job phasing,
    contract details, code requirements, and problem solving," may be
    compensable if the parties so intended under the termination for
    convenience clause of the contract.   Cf. ITT Defense
    Communications Division, Nos. 11858, 13439, 1970 ASBCA Lexis 29,
    at *56 (July 29, 1970) (cost of work done by appellant in
    preparing and submitting configurations that were never used
    still properly compensable under the termination for convenience
    clause); Navgas, Inc., No. 9240, 1964 ASBCA Lexis 1139, at *29
    (November 18, 1964) (costs of investigating work to be done, and
    determining the best way to perform the contract, if awarded, are
    properly compensable under termination for convenience clause).
    Although, on the whole, the evidence produced by Linan-Faye in
    this certification appears meager, by granting summary judgment
    for HACC the district court improvidently prevented the plaintiff
    from developing the record more fully.   There was not a complete
    lack of evidence.   Accordingly, we must reverse the grant of
    summary judgment on this issue and remand for trial.
    In remanding for trial on this issue, however, it is
    important to explain precisely the scope of our holding.    We do
    not hold that Linan-Faye is entitled to pre-termination expenses
    that accrued as the result of any alleged pre-termination
    breaches of contract by HACC.   As the district court correctly
    held, cases that have addressed the issue of pre-termination
    breaches have concluded that claims for such damages are subsumed
    in the termination for convenience clause.   Linan-Faye
    Construction 
    Co., 847 F. Supp. at 1203
    , 1204 (citing Nolan
    Brothers, Inc. v. United States, 
    405 F.2d 1250
    (Ct. Cl. 1969));
    Descon System Ltd. v. United States, 
    6 Cl. Ct. 410
    (1984)).     Pre-
    termination expenses that accrued as the result of any alleged
    pre-termination breaches by HACC are not compensable.     On remand,
    the triable issue is limited to a determination of the pre-
    termination expenses which Linan-Faye incurred that the parties
    intended to be compensable as "work performed" under the
    termination for convenience clause of the contract.
    C. Why HACC Retained Linan-Faye's Performance Bond
    Linan-Faye next contends that the trial court
    improperly resolved a factual dispute as to why HACC retained
    Linan-Faye's performance bonds after terminating Linan-Faye.
    According to Linan-Faye, it is entitled to damages arising from
    HACC's failure to return this performance bond.    Linan-Faye
    alleges that by retaining its bond, HACC prevented it from
    accepting other construction contracts and used the bond as an
    inducement to force Linan-Faye to accept an unreasonable
    resolution of this dispute.   HACC argues that it retained Linan-
    Faye's performance bond because Linan-Faye instituted a suit
    seeking specific performance and if Linan-Faye were successful,
    HACC would need Linan-Faye's bond.
    This issue is not resolved solely by reference to the
    termination for convenience clause because the events that give
    rise to this claim occcured after termination.18   Recognizing
    18
    . Linan-Faye argues that it is entitled to damages because of
    HACC's improper withholding of its performance bond both before
    and after termination. Concerning Linan-Faye's claim for damages
    for pre-termination withholding of the bond, we agree with the
    district court that such damages are not recoverable because the
    termination for convenience clause controls and does not provide
    for such recovery. Claims arising from events following
    termination, however, would not be governed by the termination
    for convenience clause.
    this, the district court decided the issue by concluding that
    keeping the bonds during the pendency of the litigation was the
    "logical response" to the plaintiff's lawsuit.     Linan-Faye
    Construction 
    Co., 847 F. Supp. at 1205
    .
    Unfortunately, there is no testimony or record evidence
    to support the conclusion that HACC engaged in the "logical
    response" posited by the district court.     No one from HACC ever
    indicated that it was Linan-Faye's suit for specific performance
    that prevented HACC from returning the bond.     Counsel for HACC
    simply raised this argument when the case took on a litigation
    posture.    This naked assertion by counsel, without record
    support, is not sufficient to warrant a grant of summary
    judgment.
    The district court attempts to justify its decision to
    accept HACC's argument by referring to the September 25, 1990
    termination letter sent by Gregory Kern, the Interim Executive
    Director of HACC.    Nevertheless, its reasoning is unpersuasive.
    According to the court, Mr. Kern's letter which indicated that
    HACC would return the bonds was sent before Linan-Faye instituted
    suit.   
    Linan-Faye, 847 F. Supp. at 1205
    n.16.   Therefore, the
    court reasoned, "[t]he decision of the HACC to depart from Mr.
    Kern's original plan only supports [the] finding that HACC felt
    compelled to hold onto the bonds until the Court had disposed of
    plaintiff's claims for specific performance." 
    Id. (emphasis added).
        The court in this passage, however, merely assumes its
    conclusion.    What eludes the district court is any evidence
    indicating that it was the suit for specific performance that
    caused retention of the bond.   In effect, what the district court
    stated is that the decision of HACC to depart from Kern's
    original plan supports HACC's decision to depart from Kern's
    original plan -- a statement without significance.
    Moreover, even taking HACC's view of the timing of the
    relevant events, there was an unjustified gap of over one month
    between the time HACC terminated Linan-Faye and the time Linan-
    Faye served its complaint seeking specific performance.
    According to HACC, after it issued its September 25, 1990 letter
    of termination, Linan-Faye sought reversal of HACC's decision to
    terminate.    HACC states that it sent a letter to Linan-Faye on
    October 23, 1990 confirming its decision to terminate.    Linan-
    Faye did not serve its complaint for specific performance until
    early in December of 1990, however, and the bond had not yet been
    returned.    This unexcused delay strengthens Linan-Faye's argument
    that HACC did not decide to hold onto the performance bond as the
    result of the specific performance suit.    In light of these
    facts, we will reverse the district court's grant of summary
    judgment for HACC and remand for trial on this disputed issue.19
    19
    . We recognize that Linan-Faye's complaint in this matter does
    not set forth a theory of recovery for damages due to improper
    retention of the performance bond following termination. Indeed,
    the complaint could not set forth such a theory because the
    events giving rise to this aspect of Linan-Faye's claim (i.e.,
    HACC's continued refusal to relinquish the bond during the
    pendency of the specific performance action) did not occur until
    D.   Whether Linan-Faye "Refused" to Begin Work.
    Linan-Faye asserts that the district court improperly
    found it "refused" to begin work.   According to Linan-Faye, it
    did not refuse to begin work, but merely wanted to agree on any
    changes that HACC desired before it began construction.     Linan-
    Faye contends that there is no basis in the record for the
    district court's finding that it flatly refused to begin work.
    We find that the question of whether Linan-Faye flatly
    refused to begin work is immaterial to this case.   Whether Linan-
    (..continued)
    after the complaint was filed. Nevertheless, the district court
    made findings on this issue. 
    Linan-Faye, 847 F. Supp. at 1205
    .
    Further, both parties briefed and argued the issue before this
    Court and HACC did not argue that the issue was not properly
    before the district court. Accordingly, we find it appropriate
    to set forth the applicable theory of recovery on remand.
    On remand, the theory upon which damages would be predicated
    is the common law action of detinue (or its modern counterpart).
    According to the New Jersey Supreme Court, "[t]he gist of the
    common law action of detinue was that [the] defendant originally
    had and acquired possession of the chattels lawfully, as by
    finding or bailment, but holds them subject to the plaintiff's
    superior right to immediate possession which has been asserted by
    a demand." Baron v. Peoples National Bank of Secaucus, 
    9 N.J. 249
    , 256, 
    87 A.2d 898
    , 901 (1952). At common law, the
    appropriate remedy in a detinue action where property has been
    unlawfully detained is a judgment for the value of the property
    and damages in detention. 
    Id. Here, HACC
    lawfully received Linan-Faye's performance bond
    pursuant to a contract between the parties. Following
    termination, however, HACC's legal right to retain the bond is
    the subject of the dispute that must be resolved on remand. If
    the jury were to find HACC liable for improper retention of the
    bond, the appropriate measure of damages would be compensation
    for jobs lost by Linan-Faye (after termination) that resulted
    from HACC's improper action.
    Faye actually "refused" to begin work would be relevant if it was
    necessary to decide if Linan-Faye defaulted on its obligations.
    The district court, however, based its holding on the doctrine of
    constructive termination for convenience.     Linan-Faye
    Construction 
    Co., 847 F. Supp. at 1203
    .    The constructive
    termination for convenience doctrine makes the original reason
    for termination relevant only to the extent that it evidences the
    government's bad faith or a change in circumstances from the time
    of contracting.20    The issue of whether there was an actual
    default by Linan-Faye in refusing to begin work is immaterial.
    In this case the default termination is converted into a
    termination for convenience of the government by operation of
    law.    Since we agree with the district court that it was
    appropriate to apply the constructive termination for convenience
    doctrine, we hold that this issue is immaterial.
    E.   Whether Linan-Faye Misunderstood the Specifications
    Linan-Faye argues that the district court improperly
    concluded that it misunderstood the contract specifications
    because the court indicated in a footnote that "[a]t the very
    least, plaintiff misinterpreted the architect's specifications"
    for the project.     Linan-Faye Construction 
    Co., 847 F. Supp. at 1203
    n.13.    According to Linan-Faye, it was HACC who
    20
    . See infra Part V for analysis of the constructive
    termination for convenience doctrine.
    "misinterpreted" the contract specifications.   The dispute over
    proper interpretation of the contract specifications, argues
    Linan-Faye, prevented the court from resolving this issue at the
    summary judgment stage.
    Linan-Faye's argument misinterprets the district
    court's reasoning.   The relevant statement the court made in this
    footnote is merely that there was discord between the parties
    over interpreting their agreement.   The district court mentioned
    the discord to support its conclusion concerning the constructive
    termination for convenience doctrine.   Whether Linan-Faye
    actually misunderstood the specifications, or whether it was
    HACC's misunderstanding, is irrelevant where there is a
    termination for convenience.    As the district court held, the
    constructive termination for convenience doctrine operates to
    allow the government to extricate itself from contractual
    relationships without arguing as to which party was in default.
    
    Id. at 1203.
      Accordingly, the issue of who misunderstood the
    contract specifications is not material, and played no part in
    the order granting summary judgment.
    F.   Whether HUD Approval was Necessary for Termination
    Linan-Faye suggests that whether HUD approved a
    termination for convenience is a disputed issue that precludes
    summary judgment.    It concedes that HACC obtained HUD's general
    approval to terminate the contract, but argues that HUD never
    approved a termination for convenience.   Linan-Faye contends that
    HUD approval of a termination for convenience was a condition
    precedent to invoking that clause, and failure to obtain such
    approval precludes summary judgment.   Linan-Faye does not succeed
    in raising a disputed material issue on this point.
    For the purposes of deciding this case, the district
    court did not assume that HACC originally terminated for
    convenience.   While there is a dispute as to whether the original
    letter of termination constituted a default termination or a
    termination for convenience, HACC prevails under the district
    court's reasoning without having to prove that it obtained HUD
    approval of a termination for convenience.   The court proceeded
    on a constructive termination for convenience theory.   Linan-Faye
    does not dispute that HUD had approved HACC's right to terminate
    generally.   Thus, concerning the original termination, HACC
    fulfilled its obligations by informing HUD, and obtaining from
    HUD a general approval for the termination of the contract.
    Because HACC received general HUD approval to terminate, there is
    no bar to this court's using the constructive termination for
    convenience doctrine to convert this into a termination for
    convenience by operation of law.   Further, and most importantly,
    there is simply no dispute as to the material facts of what
    approval HACC obtained.   Indeed, both parties concede that HACC
    obtained HUD approval to terminate generally, but did not obtain
    specific HUD approval of a termination for convenience.
    Therefore, this cannot be a disputed factual issue as Linan-Faye
    erroneously contends.
    Accordingly, we will reverse the district court's grant
    of summary judgment and remand for trial on the issues of: (1)
    the definition of "work performed" under paragraph 17 of the
    contract; (2) the pre-termination expenses incurred by Linan-Faye
    that are compensable as "work performed" under the termination
    for convenience clause; and (3)   HACC's possible liability for
    damages resulting from its retaining Linan-Faye's bond after
    termination.
    VII. SECTION 1983
    Linan-Faye next asserts that the district court erred
    in granting summary judgment against it on its claim under 42
    U.S.C. § 1983.   Linan-Faye argues it has a protectible property
    interest in its contract with HACC that is entitled to Fourteenth
    and Fifth Amendment protection.   Further, Linan-Faye contends
    that HACC's retention of its performance bond implicates a
    liberty interest entitled to constitutional protection.   In
    granting summary judgment, the district court held that whatever
    property interest Linan-Faye may have had, it does not rise to a
    sufficient level of certainty or dependency to merit
    constitutional protection.   Linan-Faye Construction Co. v.
    Housing Authority of Camden, 
    797 F. Supp. 376
    , 380 (D.N.J. 1992).
    We agree with the district court's resolution of this
    matter.   This Court recently surveyed the law concerning
    Fourteenth Amendment claims based on contracts with state
    entities.   Unger v. National Residents Matching Program, 
    928 F.2d 1392
    (3d Cir. 1991).   We stated in Unger that it is beyond
    dispute today that a contract with a state entity can give rise
    to a property right protected under the Fourteenth Amendment.
    
    Id. at 1397
    (citing Perry v. Sindermann, 
    408 U.S. 593
    , 599-601,
    
    92 S. Ct. 2694
    , 2698-2700 (1972)).   Nevertheless, we stated that
    the Supreme Court has never held that every state contract gives
    rise to such a protectible property interest.   
    Id. As we
    explained in Unger, relevant Supreme Court cases
    and cases from other courts of appeals instruct that two general
    types of contract rights are recognized as property protected
    under the Fourteenth Amendment: (1) where "the contract confers a
    protected status, such as those ``characterized by a quality of
    either extreme dependence in the case of welfare benefits, or
    permanence in the case of tenure, or sometimes both, as
    frequently occurs in the case of social security benefits'"; or
    (2) where "the contract itself includes a provision that the
    state entity can terminate the contract only for cause."      
    Id. at 1399
    (citing S & D Maintenance Co. v. Goldin, 
    844 F.2d 962
    , 966-
    67 (2d Cir 1988)).   In Unger, a physician licensed to practice
    medicine in Pennsylvania was admitted into Temple University
    Hospital's dermatology residency program through the National
    Resident Matching Program.    
    Id. at 1393.
      Shortly before Unger
    was to begin the program, she received a letter stating that the
    University had decided to discontinue the program.    
    Id. Unger filed
    suit under 42 U.S.C. § 1983.    
    Id. Declaring that
    the contract in Unger did not fall into
    either of the two protected categories, we dismissed Unger's §
    1983 claim.   
    Id. at 1402.
      We relied in part on the reasoning of
    our previous decision in Reich v. Beharry, 
    883 F.2d 239
    (3d Cir.
    1989), where we stated:
    Many . . . courts have observed that if every breach of
    contract by someone acting under color of state law
    constituted a deprivation of property for procedural
    due process purposes, the federal courts would be
    called upon to pass judgment on the procedural fairness
    of the processing of a myriad of contract claims
    against public entities. We agree that such a
    wholesale federalization of state public contract law
    seems far afield from the great purposes of the due
    process clause.
    
    Reich, 883 F.2d at 242
    (citations omitted).
    Linan-Faye's contract with HACC does not fall into
    either of the two categories we delineated in Unger.    The
    contract does not confer a protected status on the plaintiff and
    the state entity could terminate the contract for reasons other
    than for cause.   Indeed, it could be terminated for convenience.
    To grant Linan-Faye a remedy under § 1983 would create the
    wholesale federalization of state public contract law that
    concerned us in Unger and Reich.    Accordingly, the district court
    did not err in granting summary judgment for HACC on Linan-Faye's
    claim.
    Turning to Linan-Faye's assertion that it has been
    deprived of a constitutionally protected liberty interest, we
    also find that the district court did not err in granting summary
    judgment for HACC.   The Court of Appeals for the Second Circuit
    addressed a case factually similar to the one at hand in S & D
    Maintenance Co. v. Goldin, 
    844 F.2d 962
    (2d Cir. 1988).   In that
    case, a contractor brought a § 1983 claim against the City of New
    York, claiming that the City's withholding of payments under a
    contract to maintain parking meters resulted in the contractor
    being left with insufficient capital to pursue other work.      
    Id. at 963,
    970.   The court held that although the consequential
    damages of an alleged breach may be severe, this fact alone
    cannot convert a contract claim into a deprivation of liberty.
    
    Id. at 970.
       We agree with the reasoning of the Court of Appeals
    for the Second Circuit, and conclude that Linan-Faye fails to
    establish a claim of constitutional magnitude.   We will affirm
    the district court's grant of summary judgment to HACC on Linan-
    Faye's § 1983 claim.
    VIII. ESTOPPEL CLAIMS
    Linan-Faye's final contention is that HACC is precluded
    from refusing to pay compensation by reason of principles of
    equitable and judicial estoppel.   Linan-Faye argues that HACC
    could have terminated for convenience in 1988 but that it did
    not, and it breached a duty of fairness by waiting two years
    before deciding to terminate.    Linan-Faye relies on a single
    case, M. & O. Disposal Co. v. Township of Middletown, 100 N.J.
    Super. 558, 
    242 A.2d 841
    (A.D. 1967), aff'd, 
    52 N.J. 6
    , 
    242 A.2d 841
    (1968), to support its equitable estoppel argument.
    Additionally, Linan-Faye argues that because HACC asserted in
    prior judicial proceedings that there would be a "defined measure
    of damages" under the termination for convenience clause, HACC is
    now judicially estopped from arguing that it owes Linan-Faye
    nothing.
    We find Linan-Faye's equitable estoppel claim
    unpersuasive. HACC could have terminated for convenience in 1988,
    but it also could have pursued completion of the contract
    according to its terms.    HACC's decision to terminate after an
    inability to agree to such terms does not breach a duty of
    fairness.    Indeed, this termination was within HACC's rights
    under the contract and, as explained above, the constructive
    termination for convenience doctrine allows HACC to convert its
    original termination into a termination for convenience.
    Moreover, Linan-Faye's reliance on M. & O. Disposal is
    misplaced.    That case involved the question of whether a
    municipality impliedly ratified a contract for extra work which
    was outside the scope of contract to dispose of garbage.     
    Id. at 560,
    567, 242 A.2d at 841
    , 846.    In that case, the New Jersey
    court merely stated the general precept that equitable principles
    of estoppel will be applied against municipalities where the
    interests of justice, morality, or common fairness clearly
    dictate this course.   
    Id. at 567,
    242 A.2d at 846.    Beyond the
    obvious fact that the timing problem presented here has almost
    nothing to do with the ratification issue presented in M. & O.
    Disposal, Linan-Faye has failed to demonstrate how HACC's
    exercise of its rights under this contract violates principles of
    justice, morality, or common fairness.     Thus, we find Linan-
    Faye's equitable estoppel argument unconvincing.
    Linan-Faye's argument for judicial estoppel is also
    unpersuasive.   Judicial estoppel precludes a party from assuming
    a position in a legal proceeding inconsistent with one previously
    asserted to the prejudice of an adverse party.     Brown v. Allied
    Plumbing & Heating Co., 
    129 N.J.L. 442
    , 446, 
    30 A.2d 290
    , 292
    (Sup. Ct.), aff'd 
    130 N.J.L. 487
    , 
    33 A.2d 813
    (E. & A. 1943);
    Chattin v. Cape May Greene, Inc., 
    243 N.J. Super. 590
    , 620, 
    581 A.2d 91
    , 107 (A.D. 1990) (citations omitted), aff'd, 
    124 N.J. 520
    , 
    591 A.2d 943
    (1991).     There is no inconsistency in taking
    the position that HACC took in prior proceedings.     HACC merely
    argued that the termination for convenience clause provided the
    defined measure of damages.    After the district court decided the
    difficult question of whether the termination for convenience
    clause defines the measure of damages, it was not only
    appropriate, but necessary, for HACC to address the question of
    what the measure of damages is under that clause.   At this later
    stage, HACC may contend that this clause provides no compensation
    for Linan-Faye in this instance.   The attempt by Linan-Faye to
    describe a contradiction in HACC's legal position has no force
    under the facts presented in this case.
    IX. CONCLUSION
    In sum, we find that the district court erred in its
    decision to apply federal common law and not the law of New
    Jersey to resolve this dispute.    Applying New Jersey law, we will
    reverse the district court's grant of summary judgment and remand
    for trial on the issues of material fact that are in dispute.
    The three issues that remain in dispute in this case are the
    definition of "work performed" under paragraph 17 of the
    contract, whether and to what extent Linan-Faye incurred
    preparatory expenses prior to termination that are compensable as
    "work performed" under paragraph 17, and HACC's possible
    liability for damages resulting from its withholding of Linan-
    Faye's performance bond after termination.   Finally, we will
    affirm the district court's grant of summary judgment in favor of
    HACC on Linan-Faye's § 1983 claim.
    Linan-Faye Construction Co., Inc. v. Housing Authority of the
    City of Camden, No. 94-5193.
    BECKER, Circuit Judge, Concurring and Dissenting.
    I join in Parts I, II, and III of the majority opinion.
    However, I dissent from Part IV because I do not agree that New
    Jersey would apply to this garden variety construction dispute
    between a builder and a local governmental agency precepts drawn
    from a potpourri of federal cases which amount at best to a hodge
    podge, and at worst to a regime so inhospitable and unfair to
    small contractors who deal with government agencies as to be
    inconsistent with New Jersey jurisprudence.    Rather, I believe
    that New Jersey would apply its own law, which would not
    recognize the doctrine of "constructive termination for
    convenience" but rather would apply the normal rule of contract
    breach which, on this record, would unquestionably render HACC
    liable.   Moreover, even if the New Jersey Supreme Court were to
    assimilate federal law, I do not think that it would read that
    law in the matter predicted by the majority.    The precepts that
    the majority applies are gleaned from cases that have been
    excoriated in critical commentary because they are in
    considerable measure poorly reasoned.
    I also find myself unable to join in Part VII, dealing
    with Linan-Faye's 42 U.S.C. § 1983 claims.    I cannot agree with
    the majority that HACC's arguably improper retention of Linan-
    Faye's performance bond, which the company requires in order to
    engage in any business, did not impair Linan-Faye's liberty
    interest.   I do, however, join the majority with respect to its
    rejection of Linan-Faye's property interest claim.21
    I. WHAT LAW WOULD NEW JERSEY APPLY?
    The majority, notwithstanding the considerable
    authority of the Dobson 
    case, supra
    Maj. Op. at 13, reasons that
    because there are no cases in New Jersey construing the effect of
    termination for convenience clauses, "courts in New Jersey would
    recognize that where the parties have incorporated a particular
    clause pursuant to federal regulation, they do so against the
    backdrop of federal case law addressing the clause," and hence
    would adopt federal law, whatever that may be.           That is the sum
    and substance of the majority's argument.       It is, I suggest,
    pretty "thin soup," neither documented nor reasoned.
    The majority's prediction also ignores the facts that
    should govern the analysis required in such circumstances.          A
    review of the facts Linan-Faye has advanced and supported in
    connection with the summary judgment motion -- which are glossed
    over by the majority -- will illuminate the correct prediction of
    New Jersey law.   At this stage, these facts must obviously be
    21
    . I take no position on Parts VI.B through F and VIII of the
    majority opinion, as they are outside the ambit of this effort,
    except to note that the discussion of HACC's delay in invoking
    the termination for convenience clause, see Part VIII, supports
    my views insofar as it highlights the dubiousness of HACC's ex
    post reliance thereon.
    viewed in the light most favorable to Linan-Faye, the non-moving
    party.   See Goodman v. Mead Johnson & Co., 
    534 F.2d 566
    , 573 (3d
    Cir. 1976).
    A.     The Facts Viewed in the Light
    Most Favorable to Linan-Faye
    It is undisputed that the parties had a binding
    $4,264,000 contract for the rehabilitation of 244 housing units.
    Linan-Faye, with declarations cognizable in summary judgment
    proceedings: (1) represents itself to be an experienced, highly
    regarded contractor that was ready, willing, and able to perform
    the job in a timely fashion; (2) states that through
    incompetence, poor planning, or other contractors' delay, the
    HACC failed or refused to give Linan-Faye even a Notice to
    Proceed for a full year; and (3) submits that after finally
    giving that Notice, HACC then proceeded, without justification,
    to delay Linan-Faye for almost another year.     Linan-Faye also
    represents that HACC never supplied Linan-Faye with a list of
    which vacant units to work on; that turmoil reigned at HACC as
    the Executive Director was replaced by a new Acting Executive
    Director, Gregory Kern, in July 1990; and that Kern decided to
    "clean house" by, inter alia, summarily terminating Linan-Faye's
    contract.
    It is also undisputed that in the course of the
    termination dialogue, HACC never suggested that the termination
    was "for convenience."    All the discussion and written notices
    instead alleged contractor default, which Linan-Faye staunchly
    denied.   Moreover, whether or not it was legally required, HACC
    never got HUD approval to terminate for convenience.             Indeed,
    HACC did not invoke the termination for convenience clause until
    two years after termination, when the litigation began.             Most
    importantly, during the period from September 1988 through August
    1991, HACC held Linan-Faye's performance bonds, effectively
    precluding Linan-Faye from bidding any other significant work.
    Linan-Faye has proffered evidence that it suffered damages of
    $1,492,000 as a result of HACC's breach of the contract and a
    further loss of $1,249,999 from its inability to use its bonding
    line.
    B.   General New Jersey Contract Law Principles
    Under general common law contract principles,
    applicable in New Jersey and elsewhere, one who breaches a
    contract must compensate the injured non-breaching party so as to
    put it in the position it would have occupied had performance
    been rendered as promised.     Donovan v. Bachstadt, 
    453 A.2d 160
    ,
    165 (N.J. 1982); 5 ARTHUR L. CORBIN, CORBIN     ON   CONTRACTS § 992 (1951).
    A court in a breach of contract case aims to fashion a remedy in
    order to compensate the non-breaching party fully.             
    Donovan, 453 A.2d at 165
    ; 5 ARTHUR L. CORBIN, CORBIN   ON   CONTRACTS § 992 (1951).
    The New Jersey courts have long maintained a liberal
    rule that non-breaching parties are entitled to damages.      Cf. In
    re Merritt Logan, Inc., 
    901 F.2d 349
    , 357 (3d Cir. 1990)
    (interpreting New Jersey contract damages law); Sandler v. Lawn-
    A-Mat Chem.& Equip. Corp., 
    358 A.2d 805
    , 814 (N.J. Super. Ct.
    App. Div.), cert. denied, 
    366 A.2d 658
    (N.J. 1976) (non-breaching
    party "presumptively" entitled to damages, with doubts resolved
    against the breaching party).   New Jersey courts have also
    narrowly construed clauses that tend to restrict a party's right
    to recover its full common law damages.   See American Sanitary
    Sales Co. v. State, 
    429 A.2d 403
    , 407 (N.J. Super. App. Div.),
    cert. denied, 
    434 A.2d 1094
    (N.J. 1981) (narrowly interpreting a
    "no damage for delay" clause in a New Jersey state contract).
    The reluctance of the New Jersey Courts to give
    expansive effect to exculpatory clauses extends to cases
    involving its own government agencies.    See, e.g., Buckley & Co.,
    Inc. v. State, 
    356 A.2d 56
    , 62 (N.J. Super. Ct. Law Div. 1975);
    Ace Stone, Inc. v. Township of Wayne, 
    221 A.2d 515
    , 518-19 (N.J.
    1966); American Sanitary Sales 
    Co., 429 A.2d at 407
    ; see also
    Department of Transp. v. Arapaho Constr., Inc., 
    357 S.E.2d 593
    ,
    594-95 (Ga. 1987) (relying in part on Ace Stone).   Moreover,
    under New Jersey law there is a presumption against finding a
    contractual intent to alter common law rights and remedies.     See,
    e.g., Gibraltar Factors Corp. v. Slapo, 
    125 A.2d 309
    , 310 (N.J.
    Super. Ct. Law Div. 1956) (parties presumed to contract with
    reference to existing law), aff'd, 
    129 A.2d 567
    (N.J. 1957),
    appeal dismissed, 
    355 U.S. 13
    (1957); see also Rescigno v.
    Picinich, 
    377 A.2d 733
    , 739 (N.J. Super. Ct. Law Div. 1977)
    (applying a presumption against a statutory intent to alter
    common law rights); Blackman v. Iles, 
    71 A.2d 633
    , 636 (N.J.
    1950) (same).    Indeed, New Jersey courts commonly award
    contractors common law contract damages against the State,
    including damages for delay.    See, e.g., American Sanitary Sales
    
    Co., 429 A.2d at 407
    ; Buckley & 
    Co., 356 A.2d at 65
    (see also
    cases cited therein).
    C.     New Jersey and the Federal Law Alternative
    This is not the first case in which a court applying
    New Jersey law has had to adjudicate a contract dispute with some
    federal connection.    In Edward J. Dobson, Jr., Inc. v. Rutgers,
    
    384 A.2d 1121
    (N.J. Super. Ct. Law Div. 1978), aff'd sub nom.
    Broadway Maintenance Corp. v. Rutgers, 
    434 A.2d 1125
    (N.J. Super.
    Ct. App. Div. 1981), aff'd, 
    447 A.2d 906
    (N.J. 1982), plaintiff-
    contractors sought to avoid the impact of a "no-damage for delay"
    clause by asserting their claim for delay as an "equitable
    adjustment."    The court traced the history of the "equitable
    adjustment" provisions in federal construction contracts and
    federal regulations.    But the court refused to import this wholly
    federal concept into the New Jersey law of public construction
    contracts.    Finding that the term "equitable adjustment" had
    become a term of art in federal contracts, the court held:
    The policy factors that have lead [sic] to
    the development of this concept in federal
    contracts, such as a need to expand or
    abandon a particular arms program with
    consequent economic impact on contractors and
    subcontractors, do not warrant state courts
    adopting it wholesale by judicial fiat when
    traditional remedies for breach of contract
    are available. 
    Id. at 1153
    n.10.
    This holding was affirmed by both the intermediate appellate
    court and Supreme Court of New Jersey and strongly suggests that
    New Jersey courts would not import the federal concept of
    constructive termination for convenience into its public
    construction contracts jurisprudence.
    As the majority correctly points out, because there is
    no reported New Jersey precedent interpreting a "termination for
    convenience" clause, it is the function of this court to predict
    how the New Jersey Supreme Court would rule if confronted with
    this issue.   In my view, there is no reason to believe that that
    court, if called upon to resolve the question, would jettison a
    century of settled contract law supporting liberal contract
    remedies and narrowly construing similar exculpatory provisions
    in order to adopt a harsh -- and harshly criticized, see infra --
    federal interpretation of the clause at issue here.    In this
    case, the retroactive application of this dramatic change in the
    law imposed by the majority to the factual scenario described
    above not only exacerbates the harshness of the result but also
    increases my confidence that the New Jersey Supreme Court would
    never have adopted this interpretation.
    D.    The Termination of Convenience Provision and Its
    Harsh Construction by the Majority
    The termination for convenience clause has, as the
    majority explains, a long lineage, dating from the Civil War era.
    During that era federal government contracting was attended by
    much impropriety and scandal.      See generally CARL SANDBURG, ABRAHAM
    LINCOLN, THE WAR YEARS (1948).   The modern (post-1970) incarnation
    of the clause is ensconced in the Code of Federal Regulations:
    If the contractor can establish, or if it is
    otherwise determined that the contractor was
    not in default or that the failure to perform
    is excusable; i.e., arose out of causes
    beyond the control and without the fault or
    negligence of the contractor, the [prescribed
    default clauses] provide that a termination
    for default will be considered to have been a
    termination for the convenience of the
    Government . . . .
    Federal Acquisition Regulations ("FAR's"), 48 C.F.R. § 49.401(b)
    (1993).     The FAR's apply to direct United States government
    procurement (including HUD procurement).       They do not apply to
    grants of federal funds to local public housing authorities.         The
    district court acknowledged this undisputed point.        (Dist. Ct.
    Op. at 18 n.7)
    Moreover, regulations that govern grants to local
    housing agencies contain their own specific scheme and procedures
    for federally funded contracts made by state and local housing
    authorities that are separate and distinct from the FAR's.        These
    "CIAP" requirements mandate a variety of terms and provisions
    that must be set forth in such contracts, including a termination
    for convenience clause.    See 24 C.F.R. § 85.36(i)(2).     In
    contrast to the FAR's, however, the Administrative Requirements
    for CIAP Grants do not include any counterpart to the automatic
    conversion language of 48 C.F.R. § 49.401(b), or the other
    specific termination provisions found in HUD's own FAR's.        This
    is consistent with the mandate of the CIAP enabling statute,
    which is designed to allow the housing authority grantees maximum
    discretion and individualized judgment.      42 U.S.C.S. § 14371(e)E,
    (e)(4)(D) (1994).
    The absence of an express conversion clause in the
    Administrative Requirements for Grants is significant because,
    under the venerable maxim of statutory construction, expressio
    unius est exclusio alterius, the inclusion of one is the
    exclusion of another.    As I see it, the exclusion of an automatic
    conversion provision in the Requirements for Public Housing
    Authority Contracts (when specifically included in HUD's own
    FAR's) expresses an intent to exclude such a provision, unless
    local PHA administrators choose to include it.       Cf. Marshall v.
    Western Union Tel. Co., 
    621 F.2d 1246
    , 1251 (3d Cir. 1980)
    (refusing to apply a Department of Labor standard in one
    subsection of a regulation where it had been excluded when it was
    included elsewhere); SUTHERLAND STATUTORY CONSTRUCTION § 31.06 (4th
    ed.).   Moreover, without the conversion clause, HACC's initial
    failure to allege that it was terminating the contract with
    Linan-Faye for convenience prevents HACC from subsequently
    embracing that argument.
    Before contracts with the federal government included
    automatic conversion clauses, courts did not permit government
    agencies to use the termination for convenience clauses to escape
    from a breach.     In Klein v. United States, 
    285 F.2d 778
    (Ct. Cl.
    1961), for example, the Court of Claims rejected the government's
    argument that, because it had a contractual right to terminate
    for convenience, its illegal breach of contract should be
    disregarded.     
    Id. at 784.
      Accord Goldwasser v. United States,
    
    325 F.2d 722
    , 725 (Ct. Cl. 1963); Dynalectron Corp. v. United
    States, 
    518 F.2d 594
    , 604 (Ct. Cl. 1975); Torncello v. United
    States, 
    681 F.2d 756
    , 771-72 (Ct. Cl. 1982); Rogerson Aircraft
    Corp. v. Fairchild Indus.Inc., 
    632 F. Supp. 1494
    , 1499 (C.D. Cal.
    1986) (changed circumstances required).
    The problems confronted by government contracting
    officers operating under the Klein rule resulted in the adoption
    of the automatic conversion clause by regulation, 48 C.F.R. §
    49.401(b).    The clause now appears in most direct federal
    government procurement contracts.      However, as the Rogerson court
    noted in footnote 5 of its opinion, where the "automatic
    conversion clause" is not made part of the contract, either
    expressly or by regulation, the Klein rule remains fully
    applicable and bars the implication of such clause.     
    Rogerson, 632 F. Supp. at 1500
    n.5.   Although the contract in Rogerson
    appears more specific than the instant contract in its
    requirement that the agency elect its basis for termination
    (i.e., default or convenience), the Rogerson decision remains
    important and persuasive.   Without a conversion clause, HACC
    cannot invoke the termination for convenience provision to cure
    its improper default termination.    And a wrongful termination for
    default constitutes a breach of the contract entitling the
    wrongly terminated subcontractor to state law damages for the
    breach, including lost profits.     
    Id. at 1500-01;
    Clay Bernard
    Sys. Int'l, Ltd. v. United States, 
    22 Cl. Ct. 804
    , 810-11 (1991)
    (holding that absent a "conversion clause" a wrongful termination
    for default is a breach, entitling contractor to recovery under
    federal procurement law).
    But even if HACC had initially invoked its termination
    for convenience clause, thus avoiding the issue of the absence of
    a conversion clause, HACC could not avoid liability in this case.
    The majority acknowledges that the case law construing the
    termination for convenience clause has retrenched from its high
    water mark.   While the majority's discussion does not clearly
    depict the current state of the law, the leading cases appear to
    hold that government agencies can only invoke the clause where
    there has been some change in the circumstances of the parties.
    See 
    Torncello, 681 F.2d at 772
    .     The majority holds that a
    deterioration in business relations, demonstrated in not
    insignificant part by a dispute over specifications, constitutes
    such a change in circumstances.   In my view, such a rule would
    largely eviscerate the limitation.   As lawyers who have dealt
    with construction disputes know, these contracts almost always
    generate some dispute over specifications, and any construction
    dispute rancorous enough to spawn litigation will almost
    certainly have led to the requisite deterioration in business
    relations.   The facts of this case illustrate how circular a
    deterioration-of-business-relations test can be, for HACC did not
    even attempt to invoke the clause until litigation began.
    The majority constructs a regime under which a dispute
    arising out of a garden variety contract between a builder and a
    local housing authority, which is not a federal government
    contract but only a local agency contract to which certain
    federal regulations apply, has been severed from its common law
    roots.   The majority's application of selected federal cases
    renders these local agency contracts virtually illusory by giving
    an arguably defaulting local agency the right to avoid its own
    breach, and sharply limit its liability simply by incanting the
    termination for convenience clause two years after the fact.     In
    my view, it is inconceivable that the New Jersey Supreme Court,
    which has so consistently supported liberal awards of contract
    damages, would countenance that result, especially in the fact
    scenario at bar.
    This conclusion is strongly buttressed by the scathing
    criticism that has been levied at Torncello and the cognate
    jurisprudence.   See, e.g., Stephen N. Young, Note, Limiting the
    Government's Ability To Terminate for Convenience Following
    Tornecello, 52 GEO. WASH. L. REV. 892 (1984) (suggesting that the
    Torncello decision provides a reason to eliminate the
    government's ability to terminate for convenience entirely).
    Because I do not believe that the New Jersey Supreme
    Court would adopt the federal interpretation but would instead
    continue to give exculpatory clauses such as the termination for
    convenience clause only narrow -- if any -- effect, I dissent.22
    II. THE § 1983 CLAIM
    I also dissent from the majority's affirmance of the
    summary judgment granted on Linan-Faye's § 1983 claim.   While I
    agree that Linan-Faye's interest in the contract did not rise to
    a property interest protected by the Constitution, I cannot agree
    that HACC's unjustified retention of Linan-Faye's performance
    bond did not deprive Linan-Faye of a protected liberty interest.
    The majority dismisses Linan-Faye's claim rather
    summarily, overlooking precedent which would, in my view, require
    22
    . As my discussion explains, I believe that this result would
    follow even if New Jersey were to look to federal law, for I do
    not think New Jersey would read federal law so expansively as
    does the majority.
    reversal.     The right to follow a chosen profession free from
    unreasonable interference comes within both the liberty and
    property concepts of the Fifth and Fourteenth Amendments.     See
    Greene v. McElroy, 
    360 U.S. 474
    , 492 (1959); Piecknick v.
    Commonwealth of Pennsylvania, 
    36 F.3d 1250
    , 1259 (3d Cir. 1994);
    Bernard v. United Township High Sch. Dist. No. 30, 
    5 F.3d 1090
    ,
    1092 (7th Cir. 1993).    It is true that the Constitution protects
    only the right "to pursue a calling or occupation, and not the
    right to a specific job."    
    Bernard, 5 F.3d at 1092
    (quoting
    Wroblewski v. City of Washburn, 965 f.2d 452, 455 (7th Cir.
    1992)).   Nevertheless, the majority and the sole case on which it
    relies, S & D Maintenance Co. v. Goldin, 
    844 F.2d 962
    (2d Cir.
    1988), fail to consider how disputes over specific jobs can,
    under certain circumstances, affect a party's pursuit of its
    occupation.
    In S & D, although the Court of Appeals for the Second
    Circuit framed the § 1983 claim as one challenging the
    plaintiff's dismissal from government employment, which clearly
    did not rise to a constitutional violation, the true basis of the
    plaintiff's liberty claim was that New York City's refusal to pay
    amounts already due had essentially forced the company out of
    business and left it "tottering near bankruptcy, unable to get
    work, as a direct result of the city's alleged breach of the
    contracts and withholding of payments."    S & 
    D, 844 F.2d at 970
    .
    While I believe that S & D may be in error to the extent it
    denies that the plaintiff's claim implicated a protected liberty
    interest, the instant case provides an even stronger claim.
    Whereas the city defendant in S & D could argue that the
    plaintiff was not entitled to the amounts that it alleged it had
    already earned, HACC cannot make any such argument about its
    (arguably unjustified) failure to return Linan-Faye's own
    performance bond.    Also, when HACC interfered with Linan-Faye's
    (pre-existing) capacity to obtain large construction contracts,
    the core of its business, it brought this case into close
    resemblance to those cases where the state actors are held liable
    under § 1983 for revoking or interfering substantially with a
    person's license to pursue a chosen occupation.    Cf. Herz v.
    Degnan, 
    648 F.2d 201
    (3d Cir. 1981) (finding violation of a
    property interest in the revocation of a professional license).
    Without the use of its bonding line, Linan-Faye was
    paralyzed:   It could not bid on any significant contracts and
    thus could not replace the business lost through the government's
    breach.   Hence, because HACC's arguably unjustified retention of
    the bond did impinge on protected liberty interests, the district
    court erred by awarding the defendant summary judgment on this
    claim.    I therefore also dissent from the portion of the majority
    opinion that affirms this ruling.