Atacs Corp v. Trans World Comm Inc ( 1998 )


Menu:
  •                                                                                                                            Opinions of the United
    1998 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    9-8-1998
    Atacs Corp v. Trans World Comm Inc
    Precedential or Non-Precedential:
    Docket 97-1812,97-1813
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_1998
    Recommended Citation
    "Atacs Corp v. Trans World Comm Inc" (1998). 1998 Decisions. Paper 217.
    http://digitalcommons.law.villanova.edu/thirdcircuit_1998/217
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 1998 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    Filed September 8, 1998
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    Nos. 97-1812 & 97-1813
    ATACS CORPORATION; AIRTACS CORPORATION,
    Appellants in 97-1812
    v.
    TRANS WORLD COMMUNICATIONS, INC.,
    Appellant in 97-1813
    Appeal from the United States District Court
    for the Eastern District of Pennsylvania
    (D.C. No. 92-cv-05064)
    Argued: June 5, 1998
    Before: SCIRICA, NYGAARD and SEITZ, Circuit Judges
    (Opinion filed: September 8, 1998)
    Mark A. Dombroff (Argued)
    Courtney R. Bateman
    DOMBROFF & GILMORE
    1025 Thomas Jefferson Street, NW
    Suite 300 West
    Washington, DC 20007
    Attorneys for Appellants/Cross
    Appellees
    Barbara W. Mather (Argued)
    Robert L. Hickcok
    L. Suzanne Forbis
    Matthew J. Hamilton
    PEPPER HAMILTON LLP
    3000 Two Logan Square
    Eighteenth & Arch Streets
    Philadelphia, PA 19103-2799
    Attorneys for Appellee/Cross
    Appellant
    OPINION OF THE COURT
    SEITZ, Circuit Judge.
    This appeal and cross-appeal primarily present two novel
    issues for review. The first question is whether the parties
    entered into a legally enforceable "teaming agreement." If
    the answer is in the affirmative, we must address how to
    calculate, if at all possible, the damage resulting from a
    breach of that agreement. The district court exercised
    diversity jurisdiction pursuant to 28 U.S.C. S 1332, and our
    jurisdiction arises under 28 U.S.C. S 1291 to consider the
    district court's final orders. The parties agree that the
    substantive contract law of Pennsylvania governs the issues
    raised in this case.
    I. Factual Background
    A. The Parties and Related Entities
    For the most part, the parties do not dispute the relevant
    facts as described by the district court in its detailed
    findings of fact set forth on May 28, 1997 after a bench
    trial. To summarize, ATACS Corporation and AIRTACS
    Corporation ("plaintiffs") engaged in the business of
    integrating or customizing mobile enclosures with
    communications or other equipment for military use. Trans
    World Communications ("defendant") is a subsidiary of
    Datron, Inc., a publicly traded company. Defendant engages
    in designing, manufacturing, and selling of high frequency
    2
    radio equipment into communications shelters and for
    other uses.
    B. The Greek Request for Proposal and
    the Parties' Agreements
    The history underlying the transactions subject to
    dispute in this case begins in October of 1989, when the
    Greek government opened bidding to manufacture 61
    communication shelters for the Hellenic Army General
    Staff. A Request for Proposal ("RFP") prepared by the Greek
    government outlined various specifications for the
    communications shelters as well as certain financial
    requirements for all bidders. Plaintiffs considered bidding
    on the contract as the prime contractor, but they lacked the
    requisite assets to meet the financial obligations
    enumerated in the Greek RFP. Defendant also investigated
    bidding on the project as prime contractor, but it did not
    command significant technical experience in this particular
    field and generally lacked foreign government contracting
    knowledge to bid and perform the contract on its own.
    Given the comparative strengths of the parties, a
    strategic alliance was born on February 26, 1990, where
    defendant wrote plaintiffs stating that "[t]his letter will serve
    as confirmation that Trans World Communications intends
    to team with ATACS Corporation on the Greek Shelter
    program." App. at 1671. While defendant professed that the
    "details need[ed] to be worked out," and that "this [letter] is
    only a preliminary look at our various responsibilities,"
    defendant sought a commitment from plaintiffs before any
    quotations were issued. 
    Id. Further discussions
    proved
    fruitful, and the parties agreed that defendant would bid for
    the Greek RFP as the prime contractor and plaintiffs would
    be the major subcontractor. App. at 1913. By April 25,
    1990, defendant communicated to plaintiffs a basic outline
    for the new arrangement whereby defendant agreed to
    assume the role of prime contractor, assume complete
    responsibility for the financial requirements of the Greek
    RFP, and give plaintiffs a subcontract for the shelter and
    generator systems. In return, plaintiffs were expected to
    "assist in the final proposal preparation," submit a price
    quotation on their portion of the program, and introduce
    3
    defendant to their Greek agent who would facilitate the bid.
    App. at 1913. The parties agreed to circulate a draft
    contract and initiate the process of formalizing this
    agreement.
    For the next three months, the parties circulated draft
    subcontracts, none of which were executed. In the
    exchange of drafts, however, the parties had substantially
    agreed to the basic understanding of the transaction. In
    particular, the parties agreed that:
    1. Transworld will be the Prime Contractor and will
    assume complete responsibility for the Program
    including any Letters of Credit which may be
    required. ATACS will be a sub-contractor to
    Transworld and will be responsible for the shelters
    and generators.1
    2. Axon Inc. will be the sole agent for this program.
    ATACS will introduce Transworld to Axon May 1,
    1990 . . . .2
    3. ATACS has accomplished significant work
    developing a Technical Proposal. In addition,
    ATACS has also reviewed the agent's Consulting
    Agreement and the Offset Agreement. This
    information will be made available to Transworld.
    Transworld will reimburse ATACS for their cost
    associated with our Technical Proposal and for
    legal expenses associated with the review of Offsets
    and Consulting Agreements.3
    4. ATACS will submit a quotation to Transworld for
    the shelters and generators. It is agreed that
    Transworld will flow down to ATACS no less
    favorable payment terms and conditions than it
    _________________________________________________________________
    1. The later documentation reflects that the parties had agreed to give
    defendant an option to purchase the generators directly. Defendant
    exercised this option and accordingly plaintiffs' eventual proposal did
    not
    include generators.
    2. Axon Inc. is plaintiffs' agent in Greece that would facilitate
    defendant's
    bid for the Greek RFP.
    3. The parties agreed that any reimbursement for ATACS' services under
    this provision would be built into the proposal submitted to defendant.
    4
    receives from the Greek Government. ATACS will in
    turn flow down these same terms and conditions to
    its Prime vendors.
    5. ATACS agrees to work exclusively with Transworld
    on this project. Transworld agrees to work
    exclusively with ATACS relative to the ATACS
    Scope of Work set forth in paragraph 1 above.
    . . . .
    7. ATACS agrees to assist Transworld as needed in
    the final proposal preparation.
    App. at 1914-15; see also App. at 1948-49, 1966-69, 2047-
    50, 2059-62. In accordance with their understanding,
    plaintiffs introduced defendant to their Greek agent who
    ultimately proved to be influential in getting defendant the
    final contract.
    After more draft subcontracts and price quotations, none
    of which were executed by the parties, plaintiffs submitted
    their final price proposal to defendant, which totaled
    approximately $3.8 million. On July 16, defendant
    submitted its own proposal to the Greek government. As
    the prime contractor bidding for the Greek RFP, defendant
    represented that plaintiffs would be "the primary
    subcontractor in our proposal," as well as a member of the
    "team" working on the project. App. at 2144-45. It is not
    disputed on appeal that defendant included in its bid
    plaintiffs' final prices plus a 30% profit margin.
    C. Post-Submission Conduct
    Several months after the submission of the bid for the
    Greek RFP, defendant learned that its proposal for the
    project remained competitive. Nevertheless, in early
    December of 1990, defendant contacted Craig Systems
    ("Craig"), a manufacturer of bare shelters, shelter
    integrator, and competitor to plaintiffs. When Craig
    expressed an interest in performing the shelter integration
    work on the Greek project -- the same work that had been
    promised to plaintiffs -- defendant sent to Craig all of the
    information, design notes, general correspondence, and
    plaintiffs' technical proposal regarding the Greek RFP.
    5
    Defendant then asked Craig to submit a bid for the shelter
    work, and Craig ultimately submitted its final proposal and
    price quotation in late January of 1991.
    On January 24, 1991, plaintiffs' Greek agent forwarded
    defendant the results of the Greek government's review of
    the various bids, which indicated that the defendant's bid
    was the lowest among the competitors. Although defendant
    at this point was confident that it would win the contract,
    it realized that the final award would require further
    negotiations with the Greek government.4 For the next
    several months, defendant negotiated with Greek
    authorities to determine the final technical specifications
    and price concessions. Then, on May 13, 1991, defendant
    sent all its potential subcontractors, including plaintiffs, a
    form letter which stated:
    We have recently been called by the Greek government
    to negotiate the final terms and conditions for this
    shelter contract. Therefore, we ask that your firm
    please REQUOTE YOUR OFFER to us as soon as
    possible, and extend the quote validity date to at least
    August 31, 1991.
    . . .
    . . . All outside vendor equipment and service is being
    bid in a competitive environment and Trans World will
    chose the supplier, based on the price of goods,
    quality, service and technical/manufacturing
    capabilities.
    App. at 2413 (emphasis in original). On the same date,
    defendant sent plaintiffs another letter which,"encourage[d]
    you to make your bid as competitive as possible. While we
    were encouraged in our earlier preliminary discussions by
    _________________________________________________________________
    4. Apparently, negotiations between the government and contractors even
    after the unsealing of the bids are typical in thisfield of government
    contracting. See Air Tech. Corp. v. General Elec. Co., 
    199 N.E.2d 538
    ,
    543 (Mass. 1964); Brent E. Newton, Note, The Legal Effect of Government
    Contractor Teaming Agreements: A Proposal for Determining Liability and
    Assessing Damages in Event of Breach, 91 Colum. L. Rev. 1990, 1995
    n.25 (1991); W. Noel Keyes, Government Contracts in a Nutshell 137-69
    (2d ed. 1990).
    6
    the cost estimates you provided us for planning purposes,
    your later formal proposal was disappointingly high and
    was not competitive with other proposals which we have
    received." App. at 2412. This letter was thefirst
    communication to plaintiffs by defendant indicating that
    defendant had in fact been soliciting other proposals for the
    shelter integration and air conditioning portions of the
    project. It was also the first time plaintiffs had learned that
    defendant considered plaintiffs' proposal "disappointingly
    high," even though defendant's bid for the Greek RFP was
    the lowest of all bidders.
    Shocked at defendant's position, plaintiffs responded to
    these letters by confirming the validity of their price
    proposals submitted on June 28, 1990. Although plaintiffs
    indicated that they were "not and never have been unwilling
    to discuss with you an equitable adjustment to our
    proposed pricing if such an adjustment is required in
    obtaining the award," App. at 2432, they emphasized that
    "[t]here was an agreement between Trans World and ATACS
    that ATACS would be the sole source shelter integrator and
    supplier, and . . . AIRTACS [would be the] sole source
    provider of air conditioners . . . ." App. at 2414. Defendant
    did not respond to plaintiffs' letters or other attempts at
    communication.
    By December 11, 1991, defendant completed negotiations
    with the Greek government and executed a contract in the
    amount of $23,006,319, which closely corresponded to the
    original bid from defendant, absent minor adjustments to
    hardware, training, and technical specifications. Nearly a
    month later, defendant sent another letter to potential
    subcontractors, including plaintiffs, explaining the
    technical changes and requesting an updated quote on the
    revised shelter design specifications. While plaintiffs did not
    respond, defendant received quotations from three other
    companies, including Craig, for the shelter integration
    work. These proposals quoted prices significantly lower
    than plaintiffs' final price quote, and included proposals for
    bare shelters, which was not included in the plaintiffs'
    package. Defendant ultimately executed subcontracts with
    Craig for the shelter integration work and Airflow for the air
    conditioner portion of the project. The total price difference
    7
    between the Craig/Airflow contracts and the plaintiffs'
    proposals totaled $1,887,104.
    D. The District Court's Disposition
    In response to these events, plaintiffs sued defendant in
    the district court, alleging breach of contract, detrimental
    reliance, misrepresentation, wrongful interference with
    prospective contractual relations, and unjust enrichment.
    After a bench trial, the district court found that the
    "teaming arrangement" between defendant and plaintiffs
    constituted an enforceable contract with sufficiently definite
    terms for enforcement, notwithstanding the absence of a
    final executed document evincing the parties' agreement.
    The district court relied on the outward manifestation of the
    parties' intent to conclude that the terms of the legally
    binding agreement between defendant and plaintiffs
    entailed a promise by defendant to work exclusively with
    plaintiffs in its bid for the Greek RFP, and to further
    negotiate in good faith the final subcontract prices if the
    Greek government awarded defendant the prime contract.
    In return, plaintiffs promised defendant to assist in the
    preparation of its bid, to work exclusively with defendant,
    and to introduce defendant to its Greek contacts. The
    district court further found that the parties did not agree
    on the price of the subcontract, nor did they come to an
    agreement regarding any fees plaintiffs would receive for
    their services.
    Given these terms of the contract, the district court
    found defendant in breach of contract when it did not work
    exclusively with plaintiffs in arriving at a final price
    agreement for the subcontract. Moreover, the court found
    that defendant's conduct after the Greek government
    awarded it the project did not constitute good faith
    negotiations with plaintiffs. This, the could held, also
    constituted a breach of the teaming agreement between the
    parties.
    Accordingly, the district court next considered what form
    of damages would appropriately compensate plaintiffs.
    While the district court recognized that expectation
    damages, measured in lost profits, ordinarily applies under
    8
    Pennsylvania law, it found that such a calculation, if
    attempted, would lead to mere speculation because the
    parties never agreed on a price for plaintiffs' subcontract.
    Similarly, the district court felt unable to compute lost
    opportunity damages because the plaintiffs had not
    submitted sufficient evidence showing that the parties
    would have come to an agreement on price given the
    different positions on various financing fees, and the
    enormous difference between plaintiffs' final price and the
    ultimate bid submitted by Craig. It therefore held that
    plaintiffs could not receive lost profits as a remedy for
    breach of contract.
    Next, the district court considered whether restitution or
    reliance damages were appropriate, and submitted the
    question to the parties for further briefing. With respect to
    restitution, plaintiffs argued that the value of its services
    rendered to defendant roughly approximate the $1,288,349
    defendant had paid in consulting fees to plaintiffs' Greek
    agent. The district court rejected that argument because it
    found the consulting services provided by plaintiffs' own
    Greek agent differed substantially from the technical
    services provided by plaintiffs. Because the district court
    felt that it had no reasonable basis in calculating the value
    of plaintiffs' service and assistance rendered to defendant,
    it rejected a restitutionary theory as a basis for damages
    and entered into judgment nominal damages of only $1.
    Plaintiffs appeal the district court's calculation of
    damages at $1. Defendant cross-appeals the district court's
    findings to the extent it found the teaming agreement an
    enforceable contract under Pennsylvania law. We address
    these issues in turn.
    II. Was There a Valid and Enforceable Contract?
    The first issue, raised in defendant's cross-appeal, is
    whether there existed a valid and enforceable contract
    between the parties. Defendant argues on appeal that any
    agreement intended between the parties cannot, as a
    matter of law, constitute an enforceable contract because of
    the failure to agree on essential terms of the contract. In
    particular, defendant emphasizes that the parties never
    9
    reached a final agreement on the price of plaintiffs'
    subcontract and the absence of such a term must prove
    fatal to contract formation. Defendant further asserts that
    the teaming agreement at issue in this case is aptly
    characterized, at best, as an "agreement to agree," which is
    incapable of enforcement under Pennsylvania law.
    Plaintiffs dispute defendant's analysis and vigorously
    maintain that the agreement between the parties
    constituted a valid and enforceable contract. Here, plaintiffs
    assert that defendant's conduct through the negotiation of
    subcontracts demonstrates an acceptance of their price
    officer, and therefore the agreement cannot fail for lack of
    definiteness. Moreover, plaintiffs contend that regardless of
    the pricing terms of the subcontract, defendant breached
    its agreement to work exclusively with them in negotiating
    a subcontract and this constituted a breach of the teaming
    arrangement which itself is a binding agreement.
    This issue of contract formation invokes a mixed
    standard of appellate review. The district court's factual
    findings, especially with respect to the parties' intentions,
    will not be reversed unless the record demonstrates that
    they are clearly erroneous. See Fed. R. Civ. P. 52(a).
    Similarly, the interpretation of contractual language to
    discern contractual intent is a factual question, which we
    will accordingly review under a clearly erroneous standard.
    See Painewebber Inc. v. Hartmann, 
    921 F.2d 507
    , 510 (3d
    Cir. 1990). Conclusions drawn with respect to the legal
    effect of any agreement, however, are questions of law and
    therefore subject to plenary review. See Linder v. Inhalation
    Therapy Servs., Inc., 
    834 F.2d 306
    , 310 (3d Cir. 1987).
    A. Elements of Contract Formation and
    Teaming Agreements
    It is by now hornbook law that "the test for enforceability
    of an agreement is whether both parties have manifested an
    intention to be bound by its terms and whether the terms
    are sufficiently definite to be specifically enforced." Channel
    Home Ctrs. v. Grossman, 
    795 F.2d 291
    , 298-99 (3d Cir.
    1986) (citing Lombardo v. Gasparini Excavating Co., 
    123 A.2d 663
    , 666 (Pa. 1956); Linnet v. Hitchcock, 
    471 A.2d 10
    537, 540 (Pa. Super. Ct. 1984)). Consideration is, of course,
    a required element of contract formation. 
    Id. at 299.
    While
    typically analyzed in terms of offer and acceptance, see 1
    Arthur L. Corbin, Corbin on Contracts S 12, at 27 (1963),
    the decisive inquiry in contract formation is the
    "manifestation of assent of the parties to the terms of the
    promise and to the consideration for it . . . ." 1 Samuel
    Williston, A Treatise on the Law of Contracts S 23, at 51
    (Walter H. E. Jaeger ed., 3d ed. 1957); Restatement
    (Second) of Contracts S 22 (1981) ("Restatement"). Thus,
    applying Pennsylvania law, we look to: (1) whether both
    parties manifested an intention to be bound by the
    agreement; (2) whether the terms of the agreement are
    sufficiently definite to be enforced; and (3) whether there
    was consideration. See Channel Home 
    Ctrs., 795 F.2d at 299
    ; Johnston the Florist, Inc. v. Tedco Constr. Corp., 
    657 A.2d 511
    , 516 (Pa. Super. Ct. 1995).
    In the attempt to ascertain the outward manifestation of
    intention expressed by the parties, it is often helpful to
    consider the general usage or custom prevailing in a given
    market. See 5 Samuel Williston, supra, S 648, at 1-2 nn.1-
    2. We therefore consider "teaming agreements," as that
    term is normally understood within the context of
    government contracting. Typically, a teaming agreement is
    an arrangement whereby a subcontractor will "team" with a
    company intending to bid on a government contract as a
    prime contractor in order to pool financial and technical
    resources. See Northrop Corp. v. McDonnell Douglas Corp.,
    
    705 F.2d 1030
    , 1037 n.1 (9th Cir. 1983); Experimental
    Eng'g v. United Tech. Corp., 
    614 F.2d 1244
    , 1245 (9th Cir.
    1980); Air Tech. v. General Elec. Co., 
    199 N.E.2d 538
    , 547
    (Mass. 1964); see also Colsa Corp. v. Martin Marietta Servs.,
    Inc., 
    133 F.3d 853
    , 854 (11th Cir. 1998). The subcontractor
    would ordinarily provide technical expertise and assist in
    the prime contractor's bid submission in return for the
    prime contractor's promise to award the subcontract.
    Parties to such a teaming agreement benefit from the
    arrangement not only as a means of sharing resources, but
    also as a hedge against the many uncertainties involved in
    government contracting.
    In many cases, the finalized subcontract between the
    parties to a teaming agreement will specifically enumerate
    11
    the scope of obligations for each party contingent upon the
    prime contractor winning the RFP so that there is usually
    little need to enforce the teaming arrangement itself. Often,
    however, the parties may reach an understanding to team,
    but fail to execute a subcontract as anticipated in the
    teaming agreement. See McDonnell 
    Douglas, 705 F.2d at 1037
    ; Experimental 
    Eng'g, 614 F.2d at 1245
    ; Air 
    Tech., 199 N.E.2d at 548
    . As with most other "preliminary agreements"
    precedent to an executed contract, see generally E. Allan
    Farnsworth, Precontractual Liability and Preliminary
    Agreements: Fair Dealing and Failed Negotiations, 87
    Colum. L. Rev. 217 (1987), the question arises whether the
    teaming agreement itself, absent an executed subcontract,
    may constitute the basis for contractual liability. Courts
    have generally allowed such a cause of action in contract
    based solely on the teaming agreement, see Brent E.
    Newton, Note, The Legal Effect of Government Contracting
    Teaming Agreements: A Proposal for Determining Liability
    and Assessing Damages in Event of Breach, 91 Colum. L.
    Rev. 1990, 2010-13 (1991) (collecting cases), but not
    without overcoming two major obstacles: (1) the intent of
    the parties to enter into a binding contractual relationship;
    and (2) the existence of sufficiently objective criteria to
    enforce. See, e.g., Allen & Co. v. Occidental Petroleum Corp.,
    
    382 F. Supp. 1052
    , 1057 (S.D.N.Y. 1974), aff'd, 
    519 F.2d 788
    (2d Cir. 1975).
    These two factors for consideration closely track the
    general elements of contract formation. For instance, it is
    well established that evidence of preliminary negotiations or
    a general agreement to enter a binding contract in the
    future fail as enforceable contracts because the parties
    themselves have not come to an agreement on the essential
    terms of the bargain and therefore there is nothing for the
    court to enforce. See Goldman v. McShain, 
    247 A.2d 455
    ,
    458 (Pa. 1968); Reich v. Vegex, Inc., 
    51 F. Supp. 99
    , 103
    (E.D. Pa. 1942) (applying Pennsylvania law); 1 Joseph M.
    Perillo, Corbin on Contracts S 2.8(a), at 131-34 (Rev. ed.
    1993). Conversely, it is equally well established in contract
    law that an agreement with open terms may nevertheless
    constitute an enforceable contract. See Carlos R. Leffler,
    Inc. v. Hutter, 
    696 A.2d 157
    , 163 (Pa. Super. Ct. 1997); 1
    Joseph M. Perillo, supra, S 2.8, at 138-39; cf. Uniform
    12
    Commercial Code S 2-311(1) ("An agreement for sale which
    is otherwise sufficiently definite . . . to be a contract is not
    made invalid by the fact that it leaves particulars of
    performance to be specified by one the parties."). With
    teaming agreements, courts are particularly sensitive to
    what the parties intended in agreeing to "team" -- that is,
    searching for sufficiently definite terms for enforcement
    other than the simple promise to enter into a subcontract
    at a later date -- and whether that teaming agreement was
    intended to bind the parties during the various stages of
    government contract procurement. See, e.g., Occidental
    
    Petroleum, 382 F. Supp. at 1057
    ; Air 
    Tech., 199 N.E.2d at 547-58
    .
    The fact that the parties never finalized an implementing
    subcontract is usually not fatal to enforcing the teaming
    agreement on its own -- if the parties intended the teaming
    agreement itself to constitute a binding agreement that
    enumerated definite terms of behavior governing the parties
    during, or even after, the bidding process. See, e.g., Air
    Technology 
    Corp., 199 N.E.2d at 547-58
    ; Experimental
    
    Eng'g, 614 F.2d at 1246-47
    ; but see W.J. Schafer Assocs.,
    Inc. v. Cordant, Inc., 
    493 S.E.2d 512
    (Va. 1997) (teaming
    agreement standing alone did not create any binding
    obligations). Such terms might include the subcontractor's
    assistance in the prime contractor's proposal in return for
    the prime contractor's delivery of an agreeable subcontract.
    See Experimental 
    Eng'g, 614 F.2d at 1246
    . Or, the parties
    might promise to work exclusively with each other in
    preparing the bid for the government contract. See
    McDonnell 
    Douglas, 705 F.2d at 1038-38
    . Of course, if the
    parties to a teaming agreement do not wish to create
    binding obligations before executing an ultimate
    subcontract, they need only say so. See 1 Joseph M. Perillo,
    supra, S 2.9.
    Pennsylvania law has not to date explicitly recognized the
    validity of teaming agreements as enforceable contracts,
    and the defendant argues that Pennsylvania law would not
    recognize such an arrangement without a finalized
    subcontract because of the absence of an essential term.
    We disagree. Pennsylvania courts have long since
    recognized that "the paramount goal of contractual
    13
    interpretation is to ascertain and give effect to the intent of
    the parties." Greene v. Oliver Realty, Inc. , 
    526 A.2d 1192
    ,
    1194 (Pa. Super. Ct. 1987) (citing Burns Mfg. Co. v. Boehm,
    
    356 A.2d 763
    , 766 (Pa. 1976)). Indeed, the omission of an
    essential term in a contract, such as price, does not vitiate
    contract formation if the parties otherwise manifested their
    mutual assent to the agreement and the terms of that
    agreement are sufficiently definite. See, e.g., Kuss Mach.
    Tool & Die Co. v. El-Tronics, Inc., 
    143 A.2d 38
    , 40 (Pa.
    1958); 
    Greene, 526 A.2d at 1193
    ; cf. Restatement, supra,
    S 204 ("When the parties to a bargain sufficiently defined to
    be a contract have not agreed with respect to a term which
    is essential to a determination of their rights and duties, a
    term which is reasonable in the circumstances is supplied
    by the court."). Analyzing Pennsylvania law, for example, we
    have previously concluded that a "letter of intent" between
    parties to a transaction created a "mutually binding
    obligation," even though the parties never reached a final
    agreement on the terms of the bargain. Channel Home Ctrs.
    v. Grossman, 
    795 F.2d 291
    , 298-99 (3d Cir. 1986). Given
    that the letter of intent possessed sufficient specificity as to
    the underlying transaction, the critical inquiry under
    Pennsylvania law was simply whether the parties had
    intended to be bound by the terms of such a preliminary
    agreement. 
    Id. We conclude
    that Pennsylvania law would
    recognize a teaming agreement as an enforceable contract
    provided that the parties intended to be bound by the
    teaming arrangement and the agreement contains sufficient
    terms for enforcement.
    B. The Teaming Agreement as Contract
    With these principles in mind, we consider whether the
    teaming agreement itself, as expressed in the parties'
    correspondences, constitutes an enforceable contract
    notwithstanding the parties' ultimate failure to execute a
    subcontract for the Greek project. Because no party on
    appeal asserts as a defense a lack of consideration, we look
    to: (1) whether both parties manifested an intention to be
    bound by the teaming agreement; and (2) whether the
    terms of that agreement are sufficiently definite.
    14
    The district court concluded that the parties manifested
    their mutual assent to be bound by the terms of the
    teaming arrangement, as outlined in the various letters
    circulated between plaintiffs and defendant. Wefind
    nothing clearly erroneous with this factual finding. The
    record contains numerous correspondences by both parties
    clearly indicating their "inten[t] to team" and work
    exclusively with each other in preparation for the Greek
    RFP. App. at 1671. Defendant itself represented to the
    Greek government that plaintiffs constituted part of the
    "team" that would undertake the project under defendant's
    auspices as prime contractor. As a result, we conclude, as
    did the district court, that the plaintiffs have met their
    burden in establishing the intention to be bound by the
    terms of the teaming agreement during the negotiations for
    a subcontract to be executed by the parties.
    Even if plaintiffs have established evidence of the parties'
    mutual assent to be bound by the teaming agreement, that
    agreement must contain sufficiently definite terms for
    enforcement or else, as explained above, there is no basis
    for the court to fashion a suitable remedy. After a thorough
    review of the relevant correspondences, the district court
    concluded that the plaintiffs established sufficiently definite
    terms of the teaming arrangement. In particular, the
    district court held that plaintiffs had promised to assist in
    defendant's bid for the Greek RFP, introduce defendant to
    their Greek agent, and work exclusively with defendant in
    return for good faith and exclusive negotiations with
    plaintiffs toward executing a subcontract. We agree that the
    letters of intent and draft subcontracts exchanged between
    the parties clearly outline the terms of this transaction as
    an expression of the parties' intent. This is not, as
    defendant argues on appeal, nothing more than a simple
    "agreement to agree" given the specificity of the duties
    carefully described in the draft subcontracts and letters of
    intent. Nor did the parties indicate that the terms of their
    teaming agreement were subject to final execution of the
    subcontract. See Schermer v. Wilmart, 
    127 A. 315
    , 315-16
    (Pa. 1925). Thus, because the plaintiffs have successfully
    proved the elements of contract formation as applied to
    teaming agreements, we conclude that the teaming
    agreement between plaintiffs and defendant constitutes a
    15
    valid and enforceable contract with the terms found by the
    district court.
    Accordingly, to the extent that defendant's cross-appeal
    challenges the district court's finding that the teaming
    arrangement was an enforceable contract, we will affirm.
    III. Damages
    We now turn to plaintiffs' primary appeal -- that the
    district court erred in assessing nominal damages of $1.
    Plaintiffs press several arguments in their cause. First, they
    contend that the district court erred in looking to calculate
    damages with "reasonable certainty." Plaintiffs maintain
    instead that defendant must shoulder the burden of any
    uncertainty caused by its breach of contract. In the
    alternative, plaintiffs assert that they had proved damages
    with reasonable certainty. Here, plaintiffs claim that they
    should receive approximately $2.3 million in lost profits,
    which they calculate as their 35% profit margin of their
    final price quote in addition to costs and variousfinancing
    fees. Plaintiffs suggest that if this court is unwilling to
    award such an amount in expectation damages, then the
    appropriate remedy would be a remand for furtherfindings
    with respect to reasonable profits or the parties' willingness
    to negotiate the terms of the subcontract.
    In support of the district court's assessment of nominal
    damages, defendant emphasizes that the parties never
    agreed on the price of the contemplated subcontract.
    Because the district court could not evaluate lost profits
    without the agreed upon subcontract price, any expectation
    damages would be based solely on speculation. Defendant
    also objects to plaintiffs' request for a remand for factual
    findings with respect to an alternative measure of damages.
    It notes that plaintiffs have pursued their lost profits theory
    of damages before the district court to the exclusion of
    other possible remedies, and now they must be bound by
    that decision. We face these issues in turn.
    A. Theories of Contract Enforcement by
    an Award of Damages
    In general, contract law espouses three distinct, yet
    equally important, theories of damages to remedy a breach
    16
    of contract: "expectation" damages, "reliance" damages, and
    "restitution" damages. See Trosky v. Civil Serv. Comm'n,
    
    652 A.2d 813
    , 817 (Pa. 1995); Restatement, supra,S 344.
    The preferred basis of contract damages seeks to protect an
    injured party's "expectation interest" -- that is, the interest
    in having the benefit of the bargain -- and accordingly
    awards damages designed to place the aggrieved in as good
    a position as would have occurred had the contract been
    performed. See 
    Trosky, 652 A.2d at 817
    ; Restatement,
    supra, SS 344(a), 347. Toward that end, expectation
    damages are measured by "the losses caused and gains
    prevented by defendant's breach, to the extent that are in
    excess of any savings made possible by nonperformance."
    American Air Filter Co. v. McNichol, 
    527 F.2d 1297
    , 1299
    (3d Cir. 1975) (citations omitted).
    While the traditional law of contract remedies implements
    the policy that goods and services should be consumed by
    the person who values them most highly, and hence the
    preference for expectation damages, other theories of
    damages provide alternative avenues for contract
    enforcement. This is especially so where an injured party is
    entitled to recover for breach of contract, but recovery
    based on traditional notions of expectation damages is
    clouded because of the uncertainty in measuring the loss in
    value to the aggrieved contracting party. See Restatement,
    supra, S 349 cmt. a; 5 Arthur L. Corbin, supra, S 1031, at
    188. Thus, where a court cannot measure lost profits with
    certainty, contract law protects an injured party's reliance
    interest by seeking to achieve the position that it would
    have obtained had the contract never been made, usually
    through the recovery of expenditures actually made in
    performance or in anticipation of performance. See DePaolo
    v. DeRomo, 
    31 A.2d 158
    , 161 (Pa. 1943); In re Kellet Aircraft
    Corp., 
    191 F.2d 231
    , 236 (3d Cir. 1951); 5 Arthur L.
    Corbin, supra, S 1031, at 188.
    Finally, damages under a theory of restitution provides
    an appropriate form of relief in many contract cases. Its
    objective is not the enforcement of contracts through the
    protection of an injured party's expectation or reliance
    interests, but is instead rooted in common notions of equity
    through the protection of the injured's restitution interest.
    17
    See Fidelity Fund, Inc. v. DiSanto, 
    500 A.2d 431
    , 438 (Pa.
    Super. Ct. 1985); 5 Arthur L. Corbin, supra, S 1101, at 548;
    Restatement, supra, Ch. 16, Topic 4, intro. note, at 199.
    Accordingly, restitution damages will require the party in
    breach to disgorge the benefit received by returning it to the
    party who conferred it. See 
    Trosky, 652 A.2d at 817
    .
    Pennsylvania courts will look to traditional principles of
    equity, such as unjust enrichment or forfeiture, in
    considering the propriety of restitution damages. See
    
    DiSanto, 500 A.2d at 438-39
    .
    1. The Standard of Proof
    With these principles in mind, we now address plaintiffs'
    first contention on appeal -- that they need not
    demonstrate damage flowing from breach to a "reasonable
    certainty." Although mathematical certainty is not typically
    required, the general rule in Pennsylvania, as in most
    jurisdictions, is that if damages are difficult to establish, an
    injured party need only prove damages with reasonable
    certainty. See Scobell, Inc. v. Schade, 
    688 A.2d 715
    , 719
    (Pa. Super. Ct. 1997); Sobers v. Shannon Optical Co., 
    473 A.2d 1035
    , 1039 (Pa. Super. Ct. 1984); see also
    Restatement, supra, S 352; 5 Arthur L. Corbin, supra,
    SS 1020, 1022. Doubts are construed against the breaching
    party. See Delahanty v. First Pennsylvania Bank, 
    464 A.2d 1243
    , 1257 (Pa. 1983); Restatement, supra, S 342 cmt. a.
    "Reasonable certainty," as with most other standards of
    proof, is a difficult concept to quantify, but Pennsylvania
    courts have provided guidance as to what the term entails
    for purposes of assessing damages. At a minimum,
    reasonable certainty embraces a rough calculation that is
    not "too speculative, vague or contingent" upon some
    unknown factor. See Spang & Co. v. United States Steel
    Corp., 
    545 A.2d 861
    , 866 (Pa. 1988). Conversely, applying
    the reasonable certainty standard does not preclude an
    award of damages because of "some uncertainty as to the
    precise amount of damages incurred." Pugh v. Homes, 
    405 A.2d 897
    , 909 (Pa. 1979). Pennsylvania jurisprudence
    governing the issue is summarized in Aiken Indus., Inc. v.
    Estate of Wilson, 
    383 A.2d 808
    (Pa. 1978), where the
    Pennsylvania Supreme Court ultimately concluded "that
    18
    compensation for breach of contract cannot be justly
    refused because proof of the exact amount of loss is not
    produced, for there is judicial recognition of the difficulty or
    even impossibility of the production of such proof. What the
    law does require in cases of this character is that the
    evidence shall with a fair degree of probability establish a
    basis for the assessment of damages." 
    Id. at 812.
    Plaintiffs' cited authority is not to the contrary. See
    Spang & Co. v. United States Steel Corp., 
    545 A.2d 861
    (Pa.
    1988); Delahanty v. First Pennsylvania Bank, 
    464 A.2d 1243
    (Pa. 1983); Pugh v. Holmes, 
    405 A.2d 897
    (Pa. 1979);
    Standard Pipeline Coating Co. v. Solomon & Teslovich, Inc.,
    
    496 A.2d 840
    (Pa. Super. Ct. 1985). None of these cases
    establish a more relaxed standard of proof than that
    required by reasonable certainty. The Restatement itself,
    which promulgates a reasonable certainty standard, states
    that "[d]amages need not be calculable with mathematical
    accuracy and are often at best approximate." Restatement,
    supra, S 352 cmt. a. Thus, we conclude that the district
    court correctly applied Pennsylvania law in attempting to
    ascertain damages with reasonable certainty.
    2. Damages Appropriate to the Breach of
    the Teaming Agreement
    Having established the necessary standard of proof to
    recover damages as a consequence to breach of contract,
    we now address whether plaintiffs have met such a burden.
    The district court held that it could not assess expectation
    damages measured in lost profits because the parties never
    agreed to a price on plaintiffs' subcontract. While the
    district court considered the possibility of restitution
    damages, it concluded that it could not place a definite
    value on the benefit realized by defendant as a result of
    plaintiffs' performance. Plaintiffs do not claim reliance
    damages on appeal, nor did the district court address that
    possibility as an alternative measure of damages.
    a. Expectation Damages
    Plaintiffs maintain on appeal that they have met their
    burden of proving expectation damages to a reasonable
    19
    certainty. Although courts have applied expectation
    damages to remedy the breach of a teaming agreement, see
    Air 
    Tech., 199 N.E.2d at 548
    -49, we find the requisite proof
    of plaintiffs' expectation interest, measured in reasonably
    certain lost profits, lacking in this case. Even when
    discounted to reflect uncertainty, there would be absolutely
    no basis for the district court to place a value on plaintiffs'
    subcontract. As the record clearly demonstrates, the parties
    were far from agreeing on a contract price, financing fees,
    and other terms of the subcontract. Indeed, the district
    court found through ample support in the record that
    "significant obstacles" stood in the way of an agreement on
    the subcontract's price, and that the plaintiffs had not
    presented sufficient evidence that further negotiations
    would likely have proven fruitful. It is true, as plaintiffs
    note, that the Pennsylvania law of contracts allows for some
    uncertainty in calculating damages -- perhaps even a
    significant amount of uncertainty -- but a lost profits
    calculus based solely on unsubstantiated speculation and
    conjecture cannot form the basis of recovery. See Spang &
    
    Co., 545 A.2d at 866
    . Such a vague and speculative
    determination would have been necessary in this case if the
    district court assessed lost profits as damages, and
    accordingly the district court correctly declined to award
    expectation damages. See E. Allan 
    Farnsworth, supra
    , 87
    Colum. L. Rev. at 264 (lost profits not appropriate with a
    breach of a preliminary agreement because there is"no way
    of knowing what the terms of the ultimate agreement would
    have been, or even whether the parties would have arrived
    at an ultimate agreement"); Brent E. 
    Newton, supra
    , 91
    Colum. L. Rev. at 2028 (same).
    b. Restitution
    Notwithstanding any uncertainty in assessing lost profits
    as a measure of expectation damages, contract law does not
    preclude an otherwise appropriate remedy under a
    restitution theory of damages. This is especially the case
    where, as here, unknown variables cloud a reasonably
    certain calculation of lost profits stemming from the breach
    of the teaming agreement. See Air 
    Tech., 199 N.E.2d at 549
    .
    Thus, we agree that it would be appropriate for the district
    20
    court to measure "the fair value of [the subcontractor's]
    contribution to [the prime contractor's] agreement," in order
    to protect the subcontractor's restitution interest. 
    Id. As the
    district court properly concluded in this case,
    plaintiffs contributed valuable services to defendant's Greek
    RFP bid and significantly enhanced its chances of winning
    the project. However, the court ultimately held that"it is
    not clear how to quantify the value of those services," and
    therefore denied restitution as a measure of damages. While
    we share the district court's appreciation of the difficulties
    in measuring the benefit conferred on defendant, we believe
    the court's denial of restitution as a possible remedy
    premature without an evidentiary hearing. The district
    court, with characteristic courtesy, did invite the parties to
    further brief the issue of restitution, but it did not offer
    them an opportunity to present additional evidence that
    might shed light on the quantification of restitution
    damages. Such evidence might include the testimony of
    knowledgeable experts in the field who would testify as to
    the reasonable value of plaintiffs' technical and consulting
    services in this market of government contracting.
    Furthermore, as the plaintiffs claimed before the district
    court, defendant saved approximately $2 million by
    subcontracting with Craig and Airflow. See App. at 835. If
    this is indeed the case, the district court may then consider
    how much of that savings reflected preliminary services
    rendered by the plaintiffs that ultimately benefitted the
    Craig proposal. Thus, given the possibility of the plaintiffs'
    proving reasonable restitution damages, we will vacate the
    district court's entry of judgment against defendant for
    nominal damages in the amount of $1. In arriving at this
    conclusion to remand, we believe that equitable
    considerations must predominate over a parochial
    approach to the number of issues properly before us.
    IV. Conclusion
    For the foregoing reasons, the judgment of the district
    court will be affirmed except as to the award of nominal
    damages. The entry of judgment against defendant in the
    amount of $1 will be vacated and the matter remanded to
    21
    the district court in accordance with the directions in this
    opinion.
    A True Copy:
    Teste:
    Clerk of the United States Court of Appeals
    for the Third Circuit
    22