In Re: Chambers Dev ( 1998 )


Menu:
  •                                                                                                                            Opinions of the United
    1998 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    5-22-1998
    In Re: Chambers Dev
    Precedential or Non-Precedential:
    Docket 97-3145
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_1998
    Recommended Citation
    "In Re: Chambers Dev" (1998). 1998 Decisions. Paper 119.
    http://digitalcommons.law.villanova.edu/thirdcircuit_1998/119
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 1998 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    Filed May 22, 1998
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    No. 97-3145
    IN RE: CHAMBERS DEVELOPMENT COMPANY, INC.,
    Petitioner
    On Petition for a Writ of Mandamus from the
    United States District Court for the Western
    District of Pennsylvania
    (Civil No. 92-509J)
    Argued: June 13, 1997
    Before: STAPLETON and McKEE, Circuit Judges, and
    ROSENN, Senior Circuit Judge
    (Opinion filed: May 22, 1998)
    MICHAEL R. COLE, ESQ. (Argued)
    DAVID FERNANDEZ, ESQ.
    GREGORY BEVELOCK, ESQ.
    Riker, Danzig, Scherer, Hyland
    & Perretti LLP
    Headquarters Plaza
    One Speedwell Avenue
    Morristown, NJ 07962-1981
    Attorneys for Petitioner
    BENJAMIN CLARKE, ESQ. (Argued)
    JONATHAN L. WILLIAMS, ESQ.
    DeCotiis, Fitzpatrick & Gluck
    500 Frank W. Burr Boulevard
    Teaneck, New Jersey 07666
    Attorneys for Respondent,
    Passaic County Utilities Authority
    OPINION OF THE COURT
    McKEE, Circuit Judge.
    Chambers Development Company, Inc., petitions for a
    writ of mandamus following our remand in Chambers
    Development Co., Inc., v. Passaic County Utilities Authority,
    
    62 F.3d 582
     (3d Cir. 1995) ("Chambers I"). Chambers
    argues that mandamus is necessary because the district
    court ignored that mandate. We agree, and will therefore
    grant a writ of mandamus and remand this matter once
    again for proceedings consistent with this opinion.
    I.
    When this matter was initially before us we observed that
    "[t]he parties and the court . . . plunged into a procedural
    miasma which is virtually impenetrable." 621 F.3d at 583.
    The case is now more confused than ever. It has evolved
    from miasma to a jurisprudential Rubik's cube, becoming
    more jumbled at each turn. The dispute arises from a
    breach of contract action between Chambers and Passaic
    County Utilities Authority ("PCUA"). We detailed the
    intricacies leading up to the dispute in Chambers I. We will
    now summarize the background only insofar as is
    necessary to resolve the issues raised by the mandamus
    petition before us.
    In 1987, Chambers and PCUA entered into a contract for
    Passaic County's waste disposal. The contract was divided
    into three parts: an Agreement for the Grant and
    Acquisition of a License ("Initial Agreement"); a Long-Term
    Agreement for the Grant and Acquisition of a License for
    2
    Ash Residue Waste Disposal ("Long-Term Agreement"); and
    an Easement and License Agreement. The Initial Agreement
    governed the rights and duties of the parties from
    December 1, 1987, until December 1, 1992. The Long-Term
    Agreement governs the rights and duties of the parties from
    December 1, 1992 until December 1, 2002.
    The Initial Agreement required PCUA to deposit all of its
    municipal solid waste ("MSW") in Chambers' landfills in
    Pennsylvania and required Chambers to reserve airspace
    for up to a maximum of 2.25 million tons of MSW in the
    first five year period. PCUA paid Chambers $51,225,000 in
    advance for its first period disposal rights. Performance of
    the Initial Agreement is not in dispute.
    The Long-Term Agreement covered ash residue waste and
    non-processible and bypass solid waste generated by a
    mass burn incinerator or "resource recovery facility" ("RRF")
    that PCUA originally intended to have in place by 1992.
    However, construction of the RRF was not a condition
    precedent to either party's obligations under the Long Term
    Agreement. The Long-Term Agreement also provided that
    Chambers' landfills would serve as the primary disposal
    site for all solid waste for any period in which the RRF was
    not in operation. As it happened, the New Jersey
    Department of Environmental Protection and Energy
    ("NJDEPE") disapproved PCUA's proposed construction of
    an RRF and PCUA has no plans to construct one in the
    foreseeable future. However, the only significance of the
    cancellation of the RRF was that Chambers would be
    receiving ordinary MSW rather than receiving ash and by-
    pass waste.
    New Jersey's environmental law required that NJDEPE
    approve the contract with Chambers. Accordingly, on June
    24, 1987, Passaic County adopted Plan Amendment 4-1987
    which sought approval of the County's Plan to:
    include the Chambers Development Company, Inc.,
    landfill system in Pennsylvania and other states, to be
    utilized as primary landfills for the disposal of Passaic
    County solid waste from 1987 to 1992. In addition, this
    landfill system is designated under the plan as the
    primary landfill system for the disposal of ash, bypass
    3
    and non-processible waste associated with the
    operation of the resource recovery facility in the City of
    Passaic from the time the facility is operational until
    the year 2002.
    On September 1, 1987, the Commissioner of NJDEPE,
    Richard T. Dewling, certified Passaic County's Plan
    Amendment 4-1987 in part (hereinafter "Dewling
    Certification"). Dewling approved the use of Chambers'
    landfills from 1987 through 1992. However, he rejected
    PCUA's plan to rely on Chambers' landfills as the primary
    site for waste disposal between 1992 and 2002 because the
    Plan's dependence on an out-of-state landfill for long-term
    solid waste disposal was contrary to Passaic County's
    obligation to develop in-county facilities for waste disposal.
    Commissioner Dewling explained:
    N.J.S.A. 13:1E-21(b)3 places a legal obligation on each
    district to plan for sufficient available suitable in-
    county disposal sites. . . . [T]he only solution to the
    long-term disposal needs of Passaic County is the
    development of in-county facilities or to secure
    interdistrict agreement with other New Jersey counties.
    In light of these factors, and [to] the extent that Passaic
    County has failed to meet its planning obligations
    pursuant to N.J.S.A. 13:1E-21(b)3, the Department
    cannot approve primary dependence upon out-of-state
    residual disposal capacity for the period 1993 to 2002.
    ******************************
    Amendment 4-1987 is hereby modified and approved to
    include within the district plan the designation of the
    Chambers Development Company, Inc., landfill system
    to Pennsylvania and other states as a component of
    Passaic County's contingency plan for the disposal of
    ash, by-pass and non-processible waste associated
    with the operation of the Passaic County resource
    recovery facility from the time the facility is operational
    until the year 2002. Further, within forty-five days of
    the date of this certification, Passaic County is directed
    to submit the remainder of its solid waste contingency
    plan in plan amendment form for state level review in
    consideration of the Department's comments of May 7,
    4
    1987 concerning the county's draft submission. More
    specifically, the remainder of the plan should address
    in-county residual landfill development, the
    development of interdistrict agreements on an
    interim/emergency basis, and the identification of
    alternate land filling options.
    From 1987 through 1992, PCUA utilized Chambers'
    landfills as Passaic County's primary solid waste disposal
    site in accordance with the fully approved Initial
    Agreement. Apparently, during most of the period of the
    Initial Agreement, Passaic County never proposed any
    subsequent plan amendment or attempted to remedy the
    deficiency identified by Commissioner Dewling.
    Consequently, PCUA had no in-state primary plan to
    present to NJDEPE despite the approach of the end of the
    Initial Term of the agreement with Chambers.
    In early 1992, PCUA began soliciting interest from
    disposal companies including Chambers, for a new 15-year
    disposal agreement which would handle the county's
    municipal waste. In addition, PCUA asked Chambers to
    renegotiate the disposal rates set forth in the Long-Term
    Agreement. Although renegotiations did begin, they proved
    fruitless.
    On August 15, 1992, PCUA entered into a Memorandum
    of Understanding ("MOU") with Empire Sanitary Landfill,
    Inc. Under the MOU, PCUA agreed to deliver all Passaic
    County solid waste to Empire's landfill in Eastern
    Pennsylvania for a period of 15 years. The Empire MOU,
    like the prior agreement with Chambers, was subject to the
    review, amendment and approval of NJDEPE.
    While the Passaic County Freeholders and PCUA were
    preparing to submit the Empire MOU to NJDEPE,
    Chambers learned of the Empire MOU and filed a complaint
    in the district court for the Western District of Pennsylvania
    seeking to enjoin the PCUA from proceeding with Empire.
    Chambers alleged that the MOU amounted to an
    anticipatory breach by PCUA of the Long Term Agreement
    it had with Chambers. Chambers also alleged that PCUA
    was equitably estopped from entering into a contract with
    Empire.
    5
    Chambers and PCUA filed cross-motions for summary
    judgment. The PCUA's motion was based on its argument
    that the Dewling Certification was a rejection of the Long-
    Term Agreement and that PCUA was free to explore
    alternative landfill options pursuant to the directive
    contained in Commissioner Dewling's certification.
    On November 20, 1992, the district court granted
    summary judgment in favor of Chambers on its anticipatory
    breach of contract claim. The district court held that the
    Long-Term Agreement's validity did not depend upon
    whether the RRF was ever built. It then held:
    Because use of Chambers' landfills is approved as a
    contingency, and because NJDEPE has approved no
    other plan for disposal of solid waste in the 1992-2002
    period, PCUA is obligated both under its Long-Term
    Agreement and under New Jersey state law to continue
    to use Chambers' landfills.
    (November 11, 1992 Dist. Ct. Opn. at 9). The district court
    noted that no damages for breach had occurred because
    the Long-Term Agreement was not to take effect until
    December 1, 1992, and it granted a permanent injunction,
    with the following caveat:
    This Court cannot and is not attempting, by issuance
    of a permanent injunction, to bind NJDEPE, which has
    the statutory duty to regulate the disposal of solid
    waste in New Jersey. NJDEPE approved the use of
    Chambers' landfill as a contingency for the period
    1992-2002 and there is nothing of record to indicate
    that until November 6, 19921, PCUA has attempted to
    obtain approval for any other method of disposal.
    Absent a contrary direction from NJDEPE, Passaic
    County is bound to honor its contract with Chambers. 2
    _________________________________________________________________
    1. November 6, 1992 is the date when PCUA submitted the MOU with
    Empire to NJDEPE for approval.
    2. Since the district court clearly stated that its order could not be
    interpreted to bind the NJDEPE to take any action, the doctrine of
    primary jurisdiction is not implicated here. See MCI v. Teleconcepts,
    Inc.,
    
    71 F.3d 1086
     (3d. Cir. 1995).
    6
    Accordingly, the court worded its injunctive order as
    follows:
    [A] permanent injunction is granted to Plaintiff,
    Chambers Development Corporation and against
    Defendant, Passaic County Utilities Authority. Unless
    and until directed to the contrary by a valid
    certification of the [NJDEPE], PCUA shall continue
    operating under the terms and conditions of the Long-
    Term Agreement for the grant and acquisition of a
    license of ash residue waste disposal. Provided,
    however, that nothing in this order shall be construed
    as restricting any proceeding by any party before
    NJDEPE seeking approval or disapproval of any
    primary long-term plan for the disposal of municipal
    solid waste by PCUA.
    The district court entered summary judgment in favor of
    PCUA on Chambers' equitable estoppel claim because
    Chambers could not demonstrate reasonable reliance.
    [A]ny reliance by Chambers on the Long-Term
    Agreement being the primary solid waste disposal plan
    for the entire 1992-2002 period is unreasonable.
    Chambers, as a sophisticated corporation involved in
    negotiations with two governmental entities, could not
    rely on the contingent approval of the Long-Term
    Agreement as the equivalent of primary approval.
    Neither party appealed any portion of the district court's
    November 20, 1992 decision.
    Before the district court issued its injunction, NJDEPE
    notified PCUA that it had not yet come forward with an in-
    state, primary disposal solution. Commissioner Scott
    Weiner wrote:
    Passaic County currently has no disposal plan in place
    and the long-term use of out-of-state disposal was
    authorized only within the context of contingency plan
    backup use as stated within the Department's
    September 1, 1987 certification. Therefore, the Passaic
    County Plan is deficient with respect to N.J.S.A. 13:1E-
    21(b)3.
    7
    Despite this reminder that it was not in compliance with
    the requirement for an in-state disposal facility, PCUA
    submitted the Empire MOU to NJDEPE for review and
    approval on November 6, 1992. On December 7, 1992, the
    Commissioner of NJDEPE formally ordered PCUA to:
    Submit to the Department all supporting documents
    with respect to its proposed plan certification including
    the Memorandum of Understanding and contract with
    Empire as well as the long-term disposal strategy
    previously required by the Department's September 11,
    1992 Plan Certification and any other justifications to
    support this contract by January 9, 1992.
    On the same day, the Commissioner extended the
    Chambers arrangement for one year until the regulatory
    process was completed, and PCUA executed a contract with
    Empire.
    On or about December 4, 1992, Chambers filed an
    application for post judgment relief with the district court
    seeking a temporary restraining order against PCUA's
    approval of a contract with Empire. In an Order, dated
    February 1, 1993, the district court denied the restraining
    order, but indicated that it would entertain a motion
    seeking the revocation of PCUA's action or another remedy.
    While Chambers was proceeding on its "post-judgment"
    actions, PCUA was proceeding with the approval process
    with NJDEPE for the Empire Contract. On December 17,
    1992, Passaic County submitted a Verified Petition to
    NJDEPE seeking approval of Empire as Passaic County's
    primary disposal plan. In seeking that approval, PCUA took
    the position that Commissioner's Dewling Certification
    approved Chambers "only as a contingency plan in the
    absence of any other disposal strategy approved by the
    DEP."
    On April 8, 1993, NJDEPE agreed to review the Empire
    arrangement, contingent upon PCUA also submitting a
    long-term, in-state disposal plan. On August 20, 1993,
    PCUA participated in a status conference with the then
    Acting Commissioner of NJDEPE, Jeanne M. Fox. At that
    conference, PCUA stated that "[t]here is no existing out-of-
    state contract [with Chambers] and that fact has been
    8
    recognized by Passaic County in its submission of this new
    plan."
    On October 7, 1993, Commissioner Fox approved PCUA's
    proposal to designate Empire's out-of-state landfill as
    Passaic County's primary disposal mechanism. In
    approving the Empire arrangement, Commissioner Fox
    stated: "In comparison to the Chambers' Agreement, the
    Empire Agreement offers significant savings in the form of
    avoided costs for the transportation and disposal of
    municipal waste." The Commissioner also wrote that the
    Chambers-PCUA Long-Term Agreement "was merely a
    contingent arrangement which, for Department purposes,
    never took effect." Nonetheless, the Commissioner did
    indicate that the Long-Term Agreement was not a
    completely dead issue. She wrote: "If . . . legislation is
    imposed which renders the Empire Agreement void or
    voidable, the Chambers Long-Term Agreement contingency
    plan can be activated, pending the institution of the in-
    state long-term disposal solution."
    Chambers did not seek to have PCUA's contract with
    Empire rescinded as suggested in the district court's
    February 1, 1993, Order. Instead, Chambers filed a
    supplement to the previous summary judgment motion
    contending that execution of the MOU and contract with
    Empire constituted an actual, rather than an anticipatory,
    breach of contract and a breach of the covenant of good
    faith and fair dealing. Chambers argued that the law of the
    case was that the Long-Term Agreement had been declared
    a binding and enforceable contract and that in order to
    comply with the district court's order, PCUA was required
    to seek approval of the Chambers-PCUA Agreement, not
    present a competing contract to NJDEPE for approval. This
    time Chambers sought damages in the amount of its
    expected lost profits from the balance of the Chambers-
    PCUA contract.
    PCUA responded that the Initial Agreement was the law
    of the case as it was the only plan approved by NJDEPE,
    and the district court's order gave it the right to seek
    NJDEPE approval of the Empire plan.
    The matter was referred to a magistrate judge whofiled
    a Report and Recommendation in which he recommended
    9
    that Chambers' motion for summary judgment be denied
    and that summary judgment be granted in favor of PCUA
    even though PCUA never moved for summary judgment.
    On June 29, 1994, the district court adopted the Report
    and Recommendation of the magistrate judge. However,
    while adopting the magistrate's report and
    recommendation, the district court wrote:
    [I]f there were evidence in the record to support
    Chambers' . . . assertion that "[PCUA], as late as 1992
    indicated that the contract would be performed on a
    long-term basis". . . I would find that New Jersey
    precedent on the scope of the duty of good faith
    required a hearing into whether the [PCUA] breached a
    duty of good faith performance of its contract with
    Chambers.
    Chambers responded to this statement by filing a motion
    under Fed. R. Civ. P. 59(e) seeking to amend the judgment
    so as to order an evidentiary hearing on the duty of good
    faith performance. That motion was denied on July 19,
    1994, and Chambers appealed. (Chambers I).
    II.
    In Chambers I, a panel of this court unanimously
    concluded that the district court's grant of summary
    judgment to PCUA was improper because PCUA had never
    moved for summary judgment. Id. at 584. The panel
    majority also agreed that "there are unresolved material
    issues of fact regarding [PCUA's] obligations under the
    Chambers unaltered and unrescinded long-term agreement
    which can only be resolved by an evidentiary hearing." Id.
    at 588. The majority noted that, while the long-term
    agreement did not expressly state that it was subject to the
    approval of NJDEPE, it nonetheless could not be
    implemented unless NJDEPE approved PCUA's amended
    plan. Id. Since NJDEPE did not approve PCUA's plan "in
    toto", the Dewling Certification was "enigmatic" and "left the
    meaning of the Chambers Long-Term Agreement
    susceptible to more than one interpretation." Id.
    Accordingly, we vacated the district court's grant of
    summary judgment and remanded "for further proceedings
    10
    consistent with this opinion, with the privilege to Chambers
    to amend its complaint to enable it to present the case in
    its current status." Id., at 589. In doing so, we instructed
    the district court as follows:
    On remand, the district court should first determine
    the effect of the [Dewling Certification] on the
    Chambers long-term agreement. In connection, it
    should ascertain whether the Authority evinced an
    understanding that the Chambers long-term agreement
    was still binding by commissioning the 1991 Alaimo
    report and other similar reports.3 It should also
    determine as a fact that the Authority's purpose in
    filing its complaint in the New Jersey State Court and
    whether it supported Chambers' contention that it and
    the Authority knew they had a binding contract in
    place, subject only to the Authority's compliance with
    [NJDEPE] certification.4 Finally, the court must
    factually determine whether the Authority was
    _________________________________________________________________
    3. According to Chambers, PCUA required that Chambers formally
    certify, on an annual basis, that its facilities could accommodate the
    volume of solid waste contemplated by the full fifteen-year term of the
    contract. Chambers claims that it has done so. In any event, in 1991,
    PCUA challenged the certifications and an independent consultant,
    Alaimo Engineering, was retained to perform a study. The report sought
    to determine the capacity of the Chambers landfills. The Report was
    prepared for PCUA and it clearly shows that it covered the time period
    from 1987 to 2002, the time period of both the Initial Agreement and the
    Long-Term Agreement. Chambers argued that the Alaimo report
    demonstrates that PCUA expected to use Chambers for waste disposal
    after the short-term contract expired. PCUA did not address this
    argument in the appeal.
    4. In September, 1992, PCUA filed a state court declaratory judgment
    action, naming as defendants Chambers, Empire and NJDEPE, seeking
    a declaration that it is not liable to perform under the contract after
    1992 if such performance is due to the existence of a later-approved
    primary disposal alternative; declaring that PCUA may terminate its
    contract with Chambers upon payment of damages in accordance with
    section 9.3 of the contract; and restraining Chambers from interfering
    with PCUA's obligation to secure contractual arrangements to provide
    safe, adequate and economical services to its ratepayers and citizens.
    Chambers argued that this action demonstrates that PCUA believed that
    its contract with Chambers was valid and enforceable.
    11
    attempting to disengage itself from obligations under
    its long-term contract with Chambers because in 1992
    it could secure a contract with Empire at better prices
    and whether it violated the covenant of good faith and
    fair dealing in so doing.
    Id.
    III.
    On remand, Chambers filed a two count amended
    complaint per our opinion. App. at 26-40. Count One
    alleged that the Dewling Certification directed PCUA to
    identify a New Jersey disposal facility by 1992 and
    approved Chambers as the contingent alternative in the
    event PCUA failed to identify an in-state disposal facility.
    Chambers averred that, by choosing to perform with these
    qualifications, PCUA assumed a contractual obligation to
    use Chambers as the exclusive out-of-state alternative.
    Count Two alleged that PCUA breached the duty of good
    faith and fair dealing by convincing NJDEPE to approve the
    Empire contract, thus destroying the fruits of the
    Chambers-PCUA contract.
    PCUA eventually filed a motion for summary judgment in
    which it argued that Chambers' amended complaint must
    be dismissed on the basis of judicial estoppel. The judicial
    estoppel argument had two facets. PCUA first argued that
    Chambers had asserted inconsistent positions in two
    separate lawsuits. In a lawsuit against another utility
    authority involving a Chambers competitor, Chambers had
    argued that the contract in question was invalid because it
    was made in the absence of public bidding.5 The Chambers-
    _________________________________________________________________
    5. According to PCUA, in January of 1994, Chambers began suit against
    a competitor, Waste Management of Pennsylvania, Inc., in New Jersey
    state court, seeking to invalidate a long-term ash disposal contract
    between Waste Management and the Essex County Utilities Authority.
    Chambers contended that under New Jersey law, county utility
    authorities are required to adhere to public-bidding procedures in
    awarding any long-term ash disposal contracts. Thus, argued Chambers,
    because the Essex County-Waste Management contract was awarded
    without public bidding, it was illegal and void. Chambers prevailed in the
    trial court and the parties ultimately agreed to dismiss an appeal filed
    with the New Jersey appellate court.
    12
    PCUA contract was also reached without public bidding,
    and PCUA asserted that Chambers should therefore be
    judicially estopped from asserting the validity of its
    "contract" with PCUA. Second, PCUA argued that the
    amended complaint should be dismissed because
    Chambers had represented that it was not seeking
    interpretation of the Dewling Certification in an earlier
    phase in the lawsuit. PCUA argued that Count One of
    Chambers' amended complaint did exactly that and it
    should therefore be dismissed.
    The summary judgment motion was referred to the
    magistrate judge, who recommended that Count One of the
    amended complaint be dismissed under the doctrine of
    judicial estoppel. He concluded that Chambers had
    previously represented that it was not seeking to have the
    court interpret the Dewling Certification, but that
    Chambers' amended complaint sought just such an
    interpretation. Id. at 7-8. The magistrate judge rejected the
    first judicial estoppel argument, because the validity of the
    agreement had already been established by the district
    court and was thus the law of the case.
    However, the magistrate judge went even further. He
    ruled that Count One should be dismissed "as barred by
    the plain meaning of the 1987 certification." Id. at 8 n.7.
    The magistrate judge opined that the Dewling Certification
    "did not give Chambers an exclusive contract in the 1992-
    2002 period" as the out-of-state alternative. Id., at 3 n.2.
    The district court adopted the Report and
    Recommendation as its opinion and entered an order
    dismissing Count One of the amended complaint. As a
    result, only the breach of good faith claim asserted in
    Count Two remained. Thereafter, the district court denied
    requests by both Chambers and PCUA to certify the matter
    for immediate interlocutory appeal pursuant to 28 U.S.C.
    S 1292(b). Once again, the district court referred the matter
    to the magistrate judge, who recommended that
    certification be denied, and reiterated his view that the
    "plain meaning of the Dewling Certification precludes the
    claim asserted in Count One." February 11, 1997 Report
    and Recommendation at 1. He stated:
    13
    Neither side sets forth any evidence they have obtained
    in discovery, evidence they have sought in discovery, or
    any suggestion as to what evidence might exist that
    would allow a court to construe Dewling's certification
    in any manner other than by examining the four
    corners of the certification.
    Id.
    This Report and Recommendation was also adopted by
    the district court. Thereafter, Chambers filed this petition
    for mandamus, asserting that the district court's holding
    that the "plain meaning of the Dewling Certification"
    precludes its breach of contract action ignored our mandate
    in Chambers I.
    IV.
    We have authority to issue writs of mandamus pursuant
    to the All Writs Act, 28 U.S.C. S 1651(a). Hahnemann
    University Hospital v. Edgar, 
    74 F.3d 456
    , 460 (3d Cir.
    1996). That Act states "[t]he Supreme Court and all courts
    established by Act of Congress may issue all writs
    necessary or appropriate in aid of their respective
    jurisdictions and agreeable to the usages and principles of
    law." 28 U.S.C. S 1651(a). Traditionally, the writ of
    mandamus has been used "to confine an inferior court to a
    lawful exercise of its prescribed jurisdiction or to compel it
    to exercise its authority when it is its duty to do so." Will v.
    Calvert Fire Ins. Co., 
    437 U.S. 655
    , 661 (1978). The writ is
    a drastic remedy that "is seldom issued and its use is
    discouraged." Lusardi v. Lechner, 
    855 F.2d 1062
    , 1069 (3d
    Cir. 1988). Moreover, it is within a court's discretion to
    refrain from issuing the writ even when the requirements
    for mandamus are technically satisfied. The availability of
    the writ "does not compel its exercise." 
    Id. at 1070
    .
    The writ of mandamus is a drastic remedy that a court
    should grant only in extraordinary circumstances in
    response to an act amounting to a judicial usurpation
    of power. Given its drastic nature, a writ of mandamus
    should not be issued where relief may be obtained
    through an ordinary appeal. Thus, in addition to the
    jurisdictional prerequisite inherent in the language of
    14
    section 1651(a),6 two additional prerequisites for
    issuance of a writ are: (1) that petitioner have no other
    adequate means to attain the desired relief, and (2)
    that petitioner meets its burden of showing that its
    right to the writ is clear and indisputable. Even when
    these prerequisites are met, issuance of the writ is
    largely discretionary, bearing in mind the unfortunate
    consequence of making the judge a litigant.7
    Hahnemann University Hospital v. Edgar, 
    74 F.3d at 462
    (citations and internal quotations omitted).
    Nonetheless, in appropriate circumstances, the issuance
    of the writ is the "obvious" remedy. Blasband v. Rales, 979
    _________________________________________________________________
    6. Under the All Writs Act, the writ of mandamus can be issued where
    "necessary or appropriate in aid of [the court's] jurisdiction." 28 U.S.C.
    S 1651(a). However, to satisfy the jurisdictional prerequisite, it is not
    necessary that the action in which the writ is sought be pending in the
    court asked to issue the writ. United States v. Christian, 
    660 F.2d 892
    ,
    894 (3d Cir. 1981). Rather, it is only required that the case may at some
    future time come within the court's appellate jurisdiction. 
    Id.
     Here, the
    district court has diversity jurisdiction over the underlying breach of
    contract action and, therefore, this court "potentially has jurisdiction
    over the case and therefore has jurisdiction under the All Writs Act to
    consider" Chambers' petition for a writ of mandamus. Hahnemann
    University Hospital v. Edgar, 
    74 F.3d at 460
    .
    7. The "unfortunate consequence of making the judge a litigant" is no
    longer a factor to be considered in exercising our discretion whether to
    grant the writ. The 1996 amendments to Fed. R. App. P. 21 eliminated
    the role of the district court judge as a respondent. The Advisory
    Committee Notes to the 1996 amendments provide:
    In most instances, a writ of mandamus . . . is not actually
    directed to a judge in a more personal way than is an order
    reversing a court's judgment. Most often a petition for a writ of
    mandamus seeks review of the intrinsic merits of a judge's action
    and is in reality an adversary proceeding between the parties. See,
    e.g., Walter v. Columbia Broadcasting System, Inc., 
    443 F.2d 33
    (7th
    Cir. 1971). In order to change the tone of the rule and of mandamus
    proceedings generally, the rule is amended so that the judge is not
    treated as a respondent.
    However, the court of appeals can "invite or order the trial judge to
    respond," and the trial judge "may request permission to respond. . . ."
    Fed. R. App. P. 21(b)(4).
    
    15 F.2d 324
    , 328 (3d Cir. 1992). For example, mandamus is
    appropriate when a district court has failed to adhere to the
    mandate of an appellate court.8Id.; see also Delgrosso v.
    Spang & Co., 
    903 F.2d 234
    , 237 (3d Cir. 1990); Citibank,
    N.A. v. Fullam, 
    580 F.2d 82
    , 86-87 (3d Cir. 1978). Appellate
    courts "have uniformly granted such writs where .. . the
    district court has failed to adhere to an order of the court
    of appeals." Citibank, N.A. v. Fullam, 
    580 F.2d at 86-87
    .
    A federal district court has a clear duty to comply
    with an order decreed by a panel of this circuit. Where
    the district court has failed to comply with such an
    order, we have authority under S 1651 to issue a writ of
    mandamus to compel the district court to follow our
    previous order. Any other rule would severely jeopardize
    the supervisory role of the courts of appeals within the
    federal judicial system.
    
    Id.
     Moreover, district courts "must implement both the
    letter and spirit of the mandate, taking into account [our]
    opinion and the circumstances it embraces." Delgrosso v.
    Spang & Co., 
    903 F.2d at 240
    . When we direct the district
    court "to act in accordance with [our] opinion . . . the
    _________________________________________________________________
    8. The mandate of an appellate court establishes the law binding further
    action in the litigation by another body subject to its authority. Finberg
    v. Sullivan, 
    658 F.2d 93
    , 97 n.5 (3d Cir. 1981) (citation and internal
    quotations omitted). Functionally, the mandate is"the formal vehicle for
    conveying the terms of our disposition to the District Court." Clarke v.
    United States, 
    915 F.2d 699
    , 716 (D.C. Cir. 1990). As a procedural
    matter, the mandate is issued by the Clerk of Court and usually consists
    of a certified copy of the judgment, a certified copy of the opinion of
    the
    court, if any, and any directions as to costs. Fed. R. App. P. 41(a).
    Thus,
    the issuance of the mandate "is largely a ministerial function," Finberg
    v. Sullivan, 
    658 F.2d at
    97 n.5, that follows automatically 7 days after
    the expiration of the time for filing of a petition for rehearing, unless
    stayed. Fed. R. App. P. 41(a). As a practical matter, "[f]or most
    purposes,
    the entry of judgment, rather than the issuance of the mandate, marks
    the effective end to a controversy on appeal." Finberg, at 97 n.5; see
    also
    Clarke v. United States, 
    915 F.2d at 716
     ("[O]ur issuance of the mandate
    is wholly separate from our consideration of the merits. . . .").
    Therefore,
    "our circuit recognizes the minimal role a court ordinarily plays between
    the filing of a decision and the issuance of a mandate." Humphreys v.
    Drug Enforcement Administration, 
    105 F.3d 112
    , 117 (3d Cir. 1996).
    16
    opinion becomes part of the mandate and must be
    considered together with it." 
    Id.
    Here, on remand, the district court held that the"plain
    meaning" of the Dewling Certification precludes Chambers'
    breach of contract claim. As noted above, in Chambers I, we
    held that the Dewling Certification "left the meaning of the
    Chambers long-term contract susceptible to more than one
    interpretation." Chambers, 
    62 F.3d at 588
    . To illustrate the
    ambiguity in the Certification we posed the following query:
    Did the certification mean that the Chambers contract
    would be effective in all its terms in the event PCUA
    failed to develop in-state waste disposal options? Or
    did it mean the certification effectively rendered the
    long-term agreement a nullity permitting it to be
    replaced at the will and whimsy of the Authority? This
    ambiguity creates questions of fact susceptible to more
    than one meaning which preclude summary judgment.
    Therefore, extrinsic evidence that objectively will
    illuminate its meaning, especially the conduct of the
    parties, will be helpful.
    
    Id.
     (emphasis added). We instructed the district on remand
    to "first determine the effect of the [Dewling Certification] on
    the Chambers long-term agreement" and to "ascertain
    whether the [PCUA] evinced an understanding that the
    Chambers long-term agreement was still binding by
    commissioning the 1991 Alaimo report and other similar
    reports." 
    Id. at 589
    . It should be obvious that, had we
    concluded that the contract could be enforced as a matter
    of law with no extrinsic evidence as to intent, we would not
    have held as we did. On the contrary, we determined that
    the Dewling Certification was ambiguous and that extrinsic
    evidence was necessary to determine its meaning insofar as
    the Long Term Agreement between Chambers and PCUA
    was concerned. Despite that holding, the district court
    ruled that the "four corners of the [Dewling] certification,"
    were so clear as to bar Chambers' breach of contract claim
    as a matter of law. That holding is so clearly contrary to
    our mandate that very little further discussion is required.
    Thus, in the usual situation, we could end our analysis
    having concluded that the district court ignored both the
    letter and spirit of our mandate.
    17
    This is not, however, the usual situation, and we must go
    further if we are to properly align the facts in this "cube."
    The district court dismissed the breach of contract action
    on the alternative theory of judicial estoppel. In fact, the
    Report and Recommendation that the district court adopted
    relied almost exclusively upon that doctrine to justify the
    dismissal of Count One. The magistrate judge stated:
    PCUA is correct in asserting that judicial estoppel
    requires dismissal of Count One of the Amended
    Complaint on grounds other than Chambers' assertion
    in New Jersey state court that solid waste disposal
    contracts require public bidding. To avoid dismissal or
    transfer of this matter, Chambers represented to the
    Court that it was not seeking interpretation of
    Commissioner Dewling's 1987 certification of the Short-
    Term Agreement and contingent approval of the Long-
    Term Agreement in a manner that would obstruct the
    NJDEPE from determining where Passaic County's solid
    waste should go in the 1992-2002 period. Count One of
    the Amended Complaint asks exactly that. Chambers
    should be held bound by its representations, and the
    Court should dismiss Count One of the Amended
    Complaint.
    December 11, 1996 Report and Recommendation at 7-8.
    The magistrate judge's erroneous conclusion that the
    Dewling Certification could be enforced as a matter of law
    was discussed in only two footnotes. See 
    Id.
     at 3 n.2 and 8
    n.7; see also February 11, 1997 Report and
    Recommendation at 1.
    It is "axiomatic" that, on remand for further proceedings,
    the "trial court must proceed in accordance with the
    mandate and law of the case as established on appeal."
    Bankers Trust Co. v. Bethlehem Steel Corp., 
    761 F.2d 943
    ,
    949 (3d Cir. 1985). However, our mandate does not prohibit
    the district court from considering new issues raised after
    remand. A district court "may consider, as a matter of first
    impression, those issues not expressly or implicitly
    disposed of by the appellate decision." 
    Id. at 950
    . Therefore
    the district court was "free to make any order or direction
    in further progress of the case, not inconsistent with [our]
    decision . . . as to any question not settled by the decision"
    18
    on remand. 
    Id.
     The doctrine of judicial estoppel was only
    asserted after our remand. Nevertheless, Chambers argues
    that the district court's ruling on judicial estoppel is
    inconsistent with our mandate and that we can therefore
    address the merits of that decision under our mandamus
    jurisdiction. Chambers' Br. at 30-32. Chambers relies upon
    the following language from Chambers I:
    The concurrence attaches some significance to DEP's
    1993 approval of the Empire contract. This approval
    had no effect on the Authority's obligations under the
    Chambers long-term contract. DEP's approval of the
    Empire contract signifies only that the Empire contract
    conforms to the New Jersey waste disposal plan.
    Chambers, 
    62 F.3d at
    588 n.13. In contrast, the district
    court adopted the following statement of the magistrate
    judge:
    For a Court to tell a party that despite the real world
    approval of the Empire Agreement by the NJDEPE the
    NJDEPE is judicially deemed to have approved
    Chambers interferes with the validity of the operations
    of the NJDEPE every bit as much as injunctive relief,
    since it essentially tells the solid waste authorities that
    NJDEPE certification is worthless unless approved by
    the court.
    December 11, 1996, Report and Recommendation, at 8 n.8.
    Chambers now argues that this statement is inconsistent
    with our conclusion that its breach of contract claim does
    not interfere with NJDEPE's approval of the PCUA-Empire
    contract. However, we can not address Chambers'
    argument unless it comes within our mandamus
    jurisdiction.
    A.
    Our jurisdiction to review the propriety of the district
    court's grant of summary judgment on a petition for a writ
    of mandamus is a difficult question. Since the court
    granted summary judgment on Count One of Chambers'
    amended complaint, Count Two (breach of good faith and
    fair dealing) remains. Mandamus is an appellate power,
    19
    that is "realistically a form of interlocutory appeal," Martin
    v. United States, 
    96 F.3d 853
    , 854 (7th Cir. 1996). However,
    it is "different in kind from an appeal." Madden v. Myers,
    
    102 F.3d 74
    ,77 (3d Cir. 1996). Mandamus "constitutes a
    procedural mechanism through which a court of appeals
    reviews a carefully circumscribed and discrete category of
    district court orders." 
    Id.
     In distinguishing between
    mandamus and appellate jurisdiction, we have said:
    The practical difference between appellate jurisdiction
    and mandamus jurisdiction is the standard of review.
    Our standard of review under mandamus jurisdiction
    is exceedingly narrow; our standard of review under
    appellate jurisdiction varies depending on the issue
    that we are called upon to review. Accordingly,
    mandamus jurisdiction affords an appellate court less
    opportunity to correct district court error in the case
    before it and less opportunity to provide guidance for
    future cases. Moreover, comity between the district and
    appellate courts is best served by resort to mandamus
    only in limited circumstances. Review under appellate
    jurisdiction is therefore preferable to review under
    mandamus jurisdiction.
    In re Ford Motor Co., 
    110 F.3d 954
    , 964 (3d Cir.
    1997)(citation omitted). Thus, mandamus is not a
    substitute for appeal and a writ of mandamus will not be
    granted if relief can be obtained by way of our appellate
    jurisdiction. 
    Id. at 957
    . Mandamus is "disfavored because
    its broad use would threaten the [congressional] policy
    against piecemeal appeals." In re School Asbestos Litigation,
    
    977 F.2d 764
    , 772 (3d Cir. 1992)(citing Kerr v. United
    States District Court, 
    426 U.S. 394
    , 403 (1976). 9 Here, the
    _________________________________________________________________
    9. For example, discovery orders are generally not appealable, Smith v.
    BIC Corp., 
    869 F.2d 194
    , 198 (3d Cir. 1989). Therefore, mandamus is
    the appropriate jurisdictional vehicle to review disclosure of documents
    and information when privilege is asserted. See Rohne-Poulenc Rorer Inc.
    v. Home Indemnity Co., 
    32 F.3d 851
    , 861 (3d Cir. 1994) (discussing
    privilege or other interests of confidentiality); Haines v. Liggett Group,
    Inc., 
    975 F.2d 81
    , 89 (3d Cir. 1992) (discussing attorney-client privilege
    and work product doctrine protections); Westinghouse Elec. Corp. v.
    Republic of the Philippines, 
    951 F.2d 1414
    , 1422 (3d Cir. 1991)(same);
    20
    grant of summary judgment was interlocutory and notfinal
    within the meaning of 28 U.S.C. S 1291. See Communication
    Workers of America, AFL-CIO v. American Telephone &
    Telegraph Co., 
    932 F.2d 199
    , 205 (3d Cir. 1991) ("[A]
    decision is final within section 1291 when it ends the
    litigation on the merits and leaves nothing for the court to
    do but execute the judgment.").10 Further, the district court
    _________________________________________________________________
    Sprock v. Peil, 
    759 F.2d 312
    , 314-15 (3d Cir. 1985)(discussing work
    product doctrine protections); Bogosian v. Gulf Oil Corp., 
    738 F.2d 587
    ,
    591 (3d Cir. 1984)(same); see also Hahnemann Univ., 
    74 F.3d at 461
    (discussing possible mandamus jurisdiction to review claim that
    documents were protected by, inter alia, a state law psychotherapist-
    patient privilege); Glenmede Trust Co. v. Thompson, 
    56 F.3d 476
    , 483-84
    (3d Cir. 1995) (discussing mandamus jurisdiction over review of terms of
    a protective order); Smith v. BIC Corp., 
    869 F.2d at 198-99
     (discussing
    the collateral order doctrine in the context of a review of a claim that
    disputed documents contained trade secrets requiring protection);
    Cippolone v. Liggett Group, Inc., 
    822 F.2d 335
    , 340 (3d Cir. 1987)
    (discussing mandamus jurisdiction over review of a protective order).
    We have exercised mandamus jurisdiction over privilege and work
    product issues because we have found that "appealing [those] issues
    after final judgment is ineffective," In re Ford Motor Co., 
    110 F.3d at 962
    ,
    for the simple and obvious reason that "compliance with the production
    orders . . . destroys the right sought to be protected." Bogosian, 
    738 F.2d at 591
    . In other words, mandamus review is appropriate because,
    without it, the petitioner has no other remedy.
    Recently, we have adopted the view that we do have appellate
    jurisdiction over attorney-client privilege and work product doctrine
    protection issues under the collateral order doctrine. In re Ford Motor
    Co., at 964. Nonetheless, our decision in Ford Motor Co. makes it clear
    that mandamus remains an appropriate jurisdictional mechanism to
    review orders compelling the disclosure of privileged and confidential
    information. Id.; see also Smith v. BIC Corp., 
    869 F.2d at 198
     (holding
    that discovery orders can, assuming the respective requirements are
    met, be reviewed either under the collateral order doctrine or by way of
    a petition for a writ of mandamus).
    10. Both Chambers and PCUA agree that Count Two of the amended
    complaint remains outstanding. Nonetheless, we have a conceptual
    problem in understanding how a count alleging a breach of good faith
    and fair dealing, which is inherent in the contract claim, can survive a
    finding that the breach of contract claim is barred by the plain meaning
    21
    declined to certify the summary judgment order as to Count
    One for immediate interlocutory appeal pursuant to 28
    U.S.C. S 1292(b). The district court's order dismissing
    Count One is not a collateral order under Cohen v.
    Beneficial Industrial Loan Corp., 
    337 U.S. 541
     (1949), and
    its progeny.11 Moreover, Chambers has an adequate
    remedy. It can seek appellate review of the judicial estoppel
    ruling when Count Two is finally adjudicated. The only
    consequence of our refusal to review the dismissal of Count
    One now is that Chambers will incur further expense and
    delay if it were to prevail in an appeal of the judicial
    estoppel ruling following resolution of Count Two. We have
    never rested the exercise of our jurisdiction upon such
    inconvenience. Standing alone, Chambers' inconvenience
    does not justify our review of the summary judgment
    decision on a petition for mandamus. Mandamus is
    generally an inappropriate vehicle to review the district
    court's denial of a summary judgment motion because the
    litigation continues. Communication Workers of America,
    
    932 F.2d at 210
    .
    Admittedly, Chambers faces the reverse of the situation
    faced by the petitioner in Communication Workers.
    Chambers seeks mandamus relief from an order granting
    summary judgment to PCUA on one of its claims, while the
    petitioner in Communication Workers, sought review of an
    order denying its motion for summary judgment. However,
    _________________________________________________________________
    of the Dewling Certification and by judicial estoppel. The obligation to
    deal in good faith arises out of the underlying contract. Thus, if the
    breach of the underlying contract claim no longer survives, we are at a
    loss to understand how the duty to deal in good faith survives
    independently of the breach of contract action. However, Chambers does
    not argue that this dismissal of Count One was tantamount to a final
    order dismissing the entire contract action. Thus, we do not consider
    this conceptual problem here.
    11. The collateral order doctrine "provides a narrow exception to the
    general rule permitting appellate review only offinal orders. An appeal of
    a nonfinal order will lie if (1) the order from which the appellant
    appeals
    conclusively determines the disputed question; (2) the order resolves an
    important issue that is completely separate from the merits of the
    dispute; and (3) the order is effectively unreviewable on appeal from a
    final judgment." In re Ford Motor Co., 
    110 F.3d 954
    , 958 (3d Cir. 1997).
    22
    for purposes of our jurisdictional analysis here, that is a
    distinction without a difference. The order before us, and
    the one at issue in Communication Workers, are both
    interlocutory in nature. Hence, the general policy against
    granting mandamus review to an order denying a motion
    for summary judgment applies with equal force here.
    Normal appellate review is available upon the completion of
    this litigation.
    We did review a district court's denial of a summary
    judgment motion in a petition for mandamus in In re
    Asbestos School Litigation, 
    46 F.3d 1284
     (3d Cir. 1994).
    There, petitioner asserted that the district court's denial of
    its motion for partial summary judgment "has caused and
    is continuing to cause irreparable harm to its First
    Amendment rights." 
    Id. at 1286
    . We relied upon N.A.A.C.P.
    v. Claiborne Hardware Co., 
    458 U.S. 886
     (1982), to hold
    that the petitioner could not, "consistent with the First
    Amendment," be held liable. 
    Id.
     Accordingly, we held that
    the district court's denial of Pfizer's partial summary
    judgment motion was "clearly in error," and found that the
    issuance of a writ of mandamus was "appropriate to
    prevent the harm to First Amendment rights that would
    occur if review . . . had to wait until a final judgment" is
    entered. 
    Id.
    Chambers does not, and cannot, claim that any
    constitutional right is being impaired by the district court's
    judicial estoppel decision. Thus, the extraordinary
    circumstances present in In re Asbestos School Litigation
    are not present here. In fact, in In re Asbestos School
    Litigation we reaffirmed our general rule that mandamus is
    not the appropriate mechanism for review of a district
    court's denial of a motion for summary judgment. Id. at
    1295. We expressly noted Asbestos School Litigation was
    "dramatically different" from Communication Workers
    because in Communication Workers, our refusal to subject
    the denial of the summary judgment motion to mandamus
    review merely required AT&T to go to trial, while in
    Asbestos School Litigation, a refusal to grant mandamus
    review "would subject [petitioner] to a continuing
    impairment of its First Amendment freedoms." Id.
    23
    Nevertheless, despite our narrow scope of review under
    mandamus, and despite the interlocutory nature of the
    district court's judicial estoppel ruling, we conclude that it
    is both appropriate and necessary that we address the
    propriety of the district court's judicial estoppel ruling now
    because that issue is an intrinsic component of the
    question that is properly before us on the mandamus
    petition. See Schlagenhauf v. Holder, 
    379 U.S. 104
    , 110
    (1964). In Schlagenhauf, the Court approved the use of
    mandamus to decide the "basic, undecided" question of
    whether a district court could order the mental and
    physical examination of a defendant under Fed. R. Civ. P.
    35(a). At the time of that decision, Rule 35(a) provided as
    follows:
    In an action in which the mental or physical condition
    of a party is in controversy, the court in which the
    action is pending may order him to submit to a
    physical or mental examination by a physician. The
    order may be made only on motion for good cause and
    upon notice to the party to be examined and to all
    other parties and shall specify the time, place, manner,
    conditions, and scope of the examination and the
    person or persons by whom it is to be made.
    Id. at 106.
    Schlagenhauf was the driver of a bus and was named as
    one of a number of defendants in a diversity personal injury
    action in which passengers sought damages for injuries
    they sustained when the bus collided with the rear of a
    tractor-trailer. Upon a motion of the plaintiffs, the district
    court ordered Schlagenhauf to submit to mental and
    physical examinations. Schlagenhauf applied to the court of
    appeals for a writ of mandamus against the district court
    judge, seeking to have the order set aside. The court of
    appeals held that its mandamus power allowed it to decide
    whether a district court had the power to order a defendant
    to submit to a mental and physical examination. Id. In
    addition, the court of appeals examined the "in controversy"
    requirement of Rule 35 and determined it adversely to
    Schlagenhauf. However, the court held that it did not have
    the power to determine the "good cause" requirement of
    Rule 35, because it believed that it was not appropriate to
    24
    review that question on a petition for mandamus. Id.
    Therefore, the court of appeals declined to issue the writ of
    mandamus.
    The Supreme Court concluded that the court of appeals
    could exercise mandamus review over the question of
    whether "good cause" had been shown for the examination
    though that question was not ordinarily within the scope of
    mandamus review. Id. at 111. The Court held that the
    "good cause" question was proper for mandamus review at
    that time because it was part of a case brought before the
    Court "on a substantial allegation of usurpation of power in
    ordering any examination of a defendant," and, therefore,
    should have been decided by the appellate court. Id. In
    short, the Court found that "the Court of Appeals had
    power to determine all of the issues presented by the
    petition for mandamus." Id. Indeed, the Court found that
    the court of appeals should have determined the"good
    cause" issue in order, not only to settle "new and important
    problems," but also "so as to avoid piecemeal litigation." Id.
    Although Schlagenhauf is not "on all fours" with the
    circumstances before us, it is instructive. Here, the district
    court's judicial estoppel holding is so tethered to its
    disregard of our mandate that we can not remedy the latter
    without addressing the former. See 16 CHARLES ALAN WRIGHT,
    ARTHUR R. MILLER & EDWARD H. COOPER, FEDERAL PRACTICE AND
    PROCEDURE S 3934 (2d ed. 1996). As we discuss below, our
    mandate left no room for judicial estoppel as applied by the
    district court on remand. Accordingly, failure to address the
    propriety of the district court's judicial estoppel rationale
    would reduce the mandate we issued in Chambers I to a
    nullity and jumble this "cube" yet again with another turn
    in the wrong direction. Moreover, since the judicial estoppel
    issue would undoubtedly come before us after Count Two is
    resolved, we face the prospect that we will have these same
    parties before us for a third time, arguing an issue that is
    implicit in the mandamus petition now before us. See
    Schlagenhauf, 379 U.S. at 110 (special circumstances can
    extend mandamus power in order to avoid piecemeal
    litigation and resolve "new and important problems").
    25
    Accordingly, we will review the district court's judicial
    estoppel decision.12
    B.
    Judicial estoppel, sometimes called the doctrine
    against the assertion of inconsistent positions, is a
    judge-made doctrine that seeks to prevent a litigant
    from asserting a position inconsistent with one that she
    has previously asserted in the same or in a previous
    proceeding. It is not intended to eliminate all
    inconsistencies, however slight or inadvertent; rather, it
    is designed to prevent litigants from playing fast and
    loose with the courts.
    Ryan Operations, G.P. v. Santiam-Midwest Lumber Co., 
    81 F.3d 355
    , 358 (3d Cir. 1996) (citations and internal
    quotations omitted).13 The party asserting the estoppel is
    not required to demonstrate detrimental reliance upon the
    prior representation. 
    Id. at 360
    . In addition, the party to be
    estopped need not have benefited from its earlier position.
    
    Id. at 361
    . However, the doctrine will not apply where
    inconsistent positions are asserted in good faith or through
    inadvertence.
    Asserting inconsistent positions does not trigger the
    application of judicial estoppel unless intentional self-
    contradiction is used as a means of obtaining unfair
    advantage. Thus, the doctrine of judicial estoppel does
    _________________________________________________________________
    12. Our review of the district court's grant of summary judgment is
    plenary. Mark v. Borough of Hatboro, 
    51 F.3d 1137
    , 1141 (3d Cir.), cert.
    denied, ___ U.S. ___, 
    116 S. Ct. 165
     (1995). We note that our standard
    of review here does not contravene the general policy that mandamus is
    not the appropriate jurisdictional method to review a district court
    decision based on the exercise of discretion. United States v. Christian,
    
    660 F.2d 892
    , 896 (3d Cir. 1981).
    13. In Ryan Operations, G.P., one member of the panel noted that there
    is, apparently, a question as to whether state judicial estoppel law or
    federal judicial estoppel law applies in a diversity action. Here, the
    magistrate judge's Report and Recommendation recites that the New
    Jersey and the federal judicial estoppel rules are consistent. December
    11, 1996 Report and Recommendation, at 5 n.4. Neither Chambers nor
    PCUA disputes that ruling. 
    81 F.3d at
    359 n.2.
    26
    not apply when the prior position was taken because of
    a good faith mistake rather than as part of a scheme to
    mislead the court. An inconsistent argument sufficient
    to invoke judicial estoppel must be attributable to
    intentional wrongdoing.
    
    Id. at 362
     (citations and internal quotations omitted). The
    reason for so limiting the doctrine is straightforward. The
    doctrine is intended for those who "act with the intent to
    play fast and loose with the courts." 
    Id. at 365
    .
    Here, the magistrate judge wrote:
    To avoid dismissal or transfer of this matter, Chambers
    represented to the Court that it was not seeking
    interpretation of Commissioner Dewling's 1987
    certification of the Short-Term Agreement and
    contingent approval of the Long-Term Agreement in a
    manner that would obstruct the NJDEPE from
    determining where Passaic County's solid waste should
    go in the 1992-2002 period. Count One of the
    Amended Complaint asks exactly that. Chambers
    should be held bound by its representations, and the
    Court should dismiss Count One of the Amended
    Complaint.
    December 11, 1996 Report and Recommendation at 8.
    There are two problems with the magistrate judge's
    conclusion. First, on the purely technical and procedural
    level, there are no findings that Chambers intentionally
    misrepresented its position so as to "play fast and lose with
    the court." For that reason alone, grant of summary
    judgment to PCUA was improper unless we assume that
    such findings are implicit in the court's ruling. However,
    under the facts sub judice, such a finding would be clearly
    erroneous because, as we will discuss, it is not supported
    by the record. Second, and more importantly, Chambers'
    position is in response to, and totally consistent with, our
    mandate in Chambers I.
    The dispute over the "inconsistent" positions can be
    traced to a motion filed by PCUA in 1992 by which PCUA
    sought to dismiss Chambers' first complaint. PCUA argued,
    inter alia, that Chambers' failure to join NJDEPE as an
    indispensable party under Fed.R.Civ.P. 19 was fatal to its
    27
    claim. Chambers responded that NJDEPE was not an
    indispensable party because Chambers was not seeking the
    rejection or modification of any NJDEPE decision nor was
    Chambers seeking to affect NJDEPE's interest in the
    administration of its solid waste management planning
    system. The district court agreed with Chambers, found
    that NJDEPE was not an indispensable party, and
    dismissed PCUA's motion.
    PCUA argues that Chambers once again assured the
    magistrate judge that it was not trying to second-guess
    NJDEPE or asking the court to interfere with NJDEPE's
    regulatory jurisdiction when Chambers filed its complaint
    seeking injunctive relief based upon PCUA's alleged
    anticipatory breach. PCUA argues that Count One of the
    amended complaint, filed after remand, specifically asked
    the court to interpret the Dewling Certification and, by so
    doing, asked the district court to interfere with NJDEPE's
    regulatory function. The district court agreed and dismissed
    Count One.
    However, Count One does not implicate NJDEPE's
    regulatory authority. The relevant portion of Count One of
    the amended complaint provides as follows:
    42. The Chambers Contract was a valid, binding
    contract when executed.
    43. As executed, the Chambers contract obligated
    PCUA to deliver all Passaic County solid waste to the
    Chambers landfills for the final ten years of the
    Contract in the event no incinerator was constructed.
    44. No incinerator was constructed.
    45. The Dewling Certification amounted to a partial
    approval of the Chambers Contract, such that
    Chambers was designated as the exclusive out-of-state
    disposal facility for Passaic County solid waste during
    the final ten years of the Contract, and could only be
    replaced by a suitable in-state disposal facility.
    46. The parties expressly and/or impliedly assented to
    Commissioner Dewling's modifications.
    47. As modified by the Dewling Certification together
    with the parties' express and/or implied assent, the
    28
    Chambers Contract obligated PCUA to utilize
    Chambers as the exclusive out-of-state disposal facility
    for Passaic County solid waste for the final ten years of
    the Contract.
    48. Furthermore, as modified by the Dewling
    Certification together with the parties' express and/or
    implied assent, the Chambers contract obligated PCUA
    to refrain from entering into any substitute disposal
    contracts with any facility located outside of New
    Jersey.
    49. In breach of these contractual obligations, PCUA
    entered into a substitute disposal contract with
    Empire, pursuant to which PCUA agreed to dispose of
    Passaic County solid waste at a landfill facility located
    in Taylor, Pennsylvania, for a period of time
    commencing December 1, 1993 through and beyond
    2002, the final year of the Chambers Contract.
    50. Starting in and around December 1, 1993, PCUA
    began performing under the Empire Contract, and
    accordingly ceased disposing of Passaic County solid
    waste at the Chambers landfills as required by the
    Chambers Contract.
    51. PCUA continues to perform under the Empire
    Contract, and upon information and belief, has no
    intention of performing under any of the obligations set
    forth under the Chambers Contract.
    52. These actions constitute a complete breach of the
    Chambers Contract, in that they have resulted in and
    continue to result in a complete abrogation of PCUA's
    duty to Chambers to dispose all Passaic County solid
    waste at the Chambers landfills until the year 2002,
    unless and until PCUA identifies a suitable in-state
    facility as directed by the Dewling Certification.
    53. PCUA's breach of the Chambers Contract has
    caused and continues to cause significant economic
    harm to Chambers, including lost profits from the
    Chambers Contract, as well as lost profits associated
    with contracts with other entities that Chambers has
    foregone in the reasonable belief that PCUA intended
    29
    on utilizing the substantial airspace set aside for
    Passaic County solid waste for the final ten years of the
    Chambers Contract.
    Petitioner's App. at 10-12.
    Thus, the essence of the averments is that the Dewling
    Certification required PCUA to identify an in-state disposal
    facility by 1992 and it approved Chambers as a contingent
    alternative in the event PCUA failed to identify an in-state
    facility. The complaint avers that PCUA was obligated to
    use Chambers as its exclusive out-of-state disposal site.
    Accordingly, Chambers asserts that PCUA breached its
    contract when it entered into a contract with Empire for
    out-of-state waste disposal.
    This theory of recovery simply does not interfere with
    NJDEPE's regulatory functions. Chambers is not asking for
    specific performance of its contract with PCUA and it is not
    asking that the district court declare the PCUA-Empire
    contract void or voidable. Chambers succinctly states:
    "Chambers seeks contract damages against PCUA for
    bringing about [the] substitution" of Empire for Chambers.
    Petitioner's Br. at 27. There is no inconsistency in
    Chambers' pre-remand and post-remand positions.
    Moreover, we stated as much in Chambers I. There, we
    pointed out that even though the parties to this contract
    apparently understood that it was subject to the approval
    of NJDEPE, neither party saw fit to specify their rights and
    obligations if the required approval was never obtained. We
    stated the following after noting the conditional nature of
    Commissioner Dewling's Certification:
    Chambers first contends that DEP's contingent
    approval of the plan made them the exclusive out-of-
    state disposal facility for Passaic County waste, subject
    only to the development of in-state alternatives. . . .
    Conversely, the Authority maintains that DEP's
    contingent approval of the plan amendment permitted
    it to replace Chambers with any waste disposal
    alternatives.
    Chambers I, 
    62 F.3d at 585
    . We then observed that the
    district court considered "the DEP's contingent plan
    30
    approval sufficient to justify enforcing the Chambers
    contract in the absence of DEP approval of some other
    plan." 
    Id. at 586
    . However, we faulted the district court for
    not resolving the effect of the 1987 Dewling Certification
    upon the Long Term Agreement between Chambers and
    PCUA.
    The court, however, did not resolve specifically whether
    DEP's original approval in 1987 made Chambers the
    exclusive out-of-state waste disposal company for
    Passaic County waste after December 1, 1992, should
    PCUA fail to develop in-state waste disposal facilities.
    Nor did it address whether the Authority could seek a
    DEP order authorizing it to use an alternative out-of-
    state waste disposal facility without violating it contract
    with Chambers.
    
    Id.
     We then remanded with the specific instructions set
    forth above. In doing so we specifically allowed Chambers
    "the privilege to . . . amend its complaint to enable it to
    present the case in its current status." Id ., at 589. We had
    hoped that doing so would result in the proper adjudication
    of this dispute. However, what has followed has only
    confused the matter further. Chambers exercised the
    privilege extended in our mandate and amended its
    complaint. In doing so it did nothing more than attempt to
    have the district court resolve the saga of this continuing
    contract dispute by ruling on the effect that the 1987
    Dewling Certification had on the Long Term Agreement.
    However, rather than comply with the mandate and rule
    upon the issues Chambers raised in the amended
    complaint, the district court interpreted Chambers'
    amendments as playing "fast and lose" with the court and
    applied the doctrine of judicial estoppel. That was clearly
    error.
    We take no position on the merits of the claim Chambers
    raises in Count One of its amended complaint. Count One
    merely requires the district court to determine the parties'
    understanding of the impact of the Dewling Certification on
    the Long Term Agreement. That is precisely what we had
    ordered in issuing our mandate, and it is precisely what the
    district court would have done had it complied with that
    mandate.
    31
    V.
    Accordingly, we will grant Chambers' petition for a writ of
    mandamus, vacate the district court's order granting
    summary judgment to PCUA on Count One of Chambers'
    amended complaint; and we will remand the case once
    again, for further proceedings consistent with this opinion.
    32
    Stapleton, Circuit Judge, concurring:
    I agree with the court that the district court's disposition
    of Count One of the Amended Complaint is inconsistent
    with the prior mandate of this court and that the record
    does not support a finding that Chambers has "played fast
    and loose" with the court. Ryand Operations, G.P. v.
    Santiam-Midwest Lumber Co., 
    81 F.3d 355
    , 358 (3d
    Cir.1996). I join the opinion of the court to the extent it is
    not inconsistent with the views expressed in my prior
    concurring opinion. Chambers Development Company, Inc.
    v. Passaic County Utilities Authorities, 
    62 F.3d 582
    , 589 (3d
    Cir. 1995).
    A True Copy:
    Teste:
    Clerk of the United States Court of Appeals
    for the Third Circuit
    33
    

Document Info

Docket Number: 97-3145

Filed Date: 5/22/1998

Precedential Status: Precedential

Modified Date: 10/13/2015

Authorities (30)

National Ass'n for the Advancement of Colored People v. ... , 102 S. Ct. 3409 ( 1982 )

smith-francis-h-administrator-of-the-estate-of-smith-ethel-e , 869 F.2d 194 ( 1989 )

in-re-asbestos-school-litigation-pfizer-inc-v-the-honorable-james-t , 46 F.3d 1284 ( 1994 )

chambers-development-company-inc-conemaugh-township-somerset-county , 62 F.3d 582 ( 1995 )

jules-lusardi-walter-n-hill-james-marr-jr-john-f-weiss-arthur , 855 F.2d 1062 ( 1988 )

citibank-na-as-indenture-trustee-of-the-lehigh-harbor-terminal-railway , 580 F.2d 82 ( 1978 )

United States v. Hon. Judge Almeric L. Christian , 660 F.2d 892 ( 1981 )

mci-telecommunications-corporation-v-teleconcepts-incorporated , 71 F.3d 1086 ( 1995 )

larry-a-martin-v-united-states-of-america-victor-fernandez-also-known , 96 F.3d 853 ( 1996 )

ryan-operations-gp-a-virginia-general-partnership-and-nvr-lp-a , 81 F.3d 355 ( 1996 )

matthew-a-delgrosso-james-p-blair-lester-ware-jimmie-mines-jr-joe , 903 F.2d 234 ( 1990 )

antonio-cipollone-individually-and-as-the-of-the-estate-of-rose-d , 822 F.2d 335 ( 1987 )

beatrice-finberg-indiv-and-on-behalf-of-all-others-similarly-situated , 658 F.2d 93 ( 1981 )

Kerr v. United States Dist. Court for Northern Dist. of Cal. , 96 S. Ct. 2119 ( 1976 )

john-d-mark-v-borough-of-hatboro-thomas-e-mcmackin-charles-j-acker , 51 F.3d 1137 ( 1995 )

Earl A. Humphreys, M.D. v. Drug Enforcement Administration , 105 F.3d 112 ( 1996 )

glenmede-trust-company-pepper-hamilton-scheetz-v-b-ray-thompson-jr , 56 F.3d 476 ( 1995 )

Edwin A. Walker v. Columbia Broadcasting System, Inc. , 443 F.2d 33 ( 1971 )

communication-workers-of-america-afl-cio-district-13-communication , 932 F.2d 199 ( 1991 )

in-re-ford-motor-company-susan-i-kelly-administratrix-and-personal , 110 F.3d 954 ( 1997 )

View All Authorities »