United States Ex Rel. E & H Steel Corp. v. C. Pyramid Enterprises, Inc. , 509 F.3d 184 ( 2007 )


Menu:
  •                                                                                                                            Opinions of the United
    2007 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    11-27-2007
    E&H Steel Corp v. C Pyramid Entr Inc
    Precedential or Non-Precedential: Precedential
    Docket No. 06-4209
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2007
    Recommended Citation
    "E&H Steel Corp v. C Pyramid Entr Inc" (2007). 2007 Decisions. Paper 152.
    http://digitalcommons.law.villanova.edu/thirdcircuit_2007/152
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 2007 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    No. 06-4209
    UNITED STATES OF AMERICA FOR THE USE
    AND BENEFIT OF E & H STEEL CORPORATION
    vs.
    C. PYRAMID ENTERPRISES, INC.;
    FIDELITY & DEPOSIT COMPANY OF MARYLAND;
    and ZURICH AMERICAN INSURANCE COMPANY,
    E & H Steel Corporation, Appellant
    ____________
    ON APPEAL FROM THE UNITED STATES DISTRICT
    COURT FOR THE DISTRICT OF NEW JERSEY
    (D.C. Civ. No. 04-cv-02519)
    District Judge: Honorable Robert B. Kugler
    ____________
    Argued September 18, 2007
    Before: SLOVITER, SMITH and WEIS, Circuit Judges.
    Filed: November 27, 2007
    ____________
    David W. Mockbee, Esquire (ARGUED)
    Mary Elizabeth Hall, Esquire
    MOCKBEE HALL & DRAKE, P.A.
    Lamar Life Building, Suite 1000
    317 E. Capitol Street
    Jackson, Mississippi 39201
    Sandhya M. Feltes, Esquire
    Kaplin, Stewart, Meloff, Reiter & Stein
    910 Harvest Drive
    P.O. Box 3037
    Blue Bell, PA 19422
    Attorneys for Appellant
    Paul W. Norris, Esquire (ARGUED)
    Lewis J. Pepperman, Esquire
    STARK & STARK
    A Professional Corporation
    P.O. Box 5315
    Princeton, New Jersey 08543
    Attorneys for Appellees
    ____________
    OPINION
    WEIS, Circuit Judge.
    2
    In this Miller Act case, we decide that a firm acted as a
    subcontractor when it supplied fabricated steel to the prime
    contractor that then used the material to construct the framework
    for a large Air Force facility. The subcontractor defaulted in
    payments due the company that it hired to fabricate the steel and
    deliver it to the construction site. The District Court denied
    recovery to the steel fabricator in this suit against the prime
    contractor and its sureties. We will reverse and remand for
    entry of judgment in favor of the steel company.
    In September 2002, C. Pyramid Enterprises, Inc. was
    awarded a contract by the United States Army Corps of
    Engineers to design and build a large C-17 Maintenance Hangar
    and Shops facility at the McGuire Air Force Base in New
    Jersey. The original contract price was $24,119,450.00.
    Pyramid issued a standard form “purchase order” to
    Havens Design-Build to provide custom fabricated structural
    steel for the building’s framework at a cost of $2,230,000.00.
    The agreement provided that Havens was also to arrange for the
    preparation of shop drawings and erection drawings, design the
    connectors for the steel, and perform some “design assist
    engineering” that primarily involved material substitution.
    Havens in turn contracted with E & H Steel Company to
    fabricate the steel and deliver it to the construction site. E & H
    delivered 50 trailers of fabricated steel between November 13,
    2003 and April 16, 2004.1 Pyramid erected the steel framework
    1
    E & H asserts that the shipments contained 5,379 major
    pieces of structural steel, which included seven long-span jumbo
    3
    for the building and did most of the remaining construction
    itself, including the electrical, mechanical, site utilities,
    plumbing, and concrete work.
    In accordance with the Miller Act, 40 U.S.C. §
    3131(b)(2), Pyramid issued a payment bond in favor of “all
    persons having a direct relationship with [Pyramid] or a
    subcontractor of [Pyramid] for furnishing labor, material or both
    in the prosecution of the work provided for in the contract.”
    Defendants Fidelity & Deposit Company of Maryland and
    Zurich American Insurance Company acted as sureties on the
    bond.
    Although it had been paid by Pyramid during the
    construction process, Havens filed for bankruptcy owing E & H
    $565,125.40 for the delivered steel. E & H brought suit against
    Pyramid and its sureties, asserting entitlement to reimbursement
    from the payment bond. After a bench trial, the District Court
    found in favor of defendants.
    The Court correctly determined that because of a
    statutory limitation E & H’s right to recover on the bond hinged
    on whether Havens was a “subcontractor” under § 3133(b)(2) of
    the Miller Act. However, case law did not provide a uniform
    rule for determining whether a company such as Havens, which
    acted as a middleman between a general contractor and a
    supplier of materials or services, was a “subcontractor.” In
    roof trusses 203 feet in length and five steel members that
    weighed between 19,000 and 20,000 pounds. Pyramid does not
    dispute this assertion.
    4
    resolving that issue, the Court considered a number of factors,
    including the nature of the material or service supplied, the cost
    of the material or service in relation to the total contract price,
    the payment terms and exchange of information, and the overall
    relationship between the contractor and the middleman.
    The District Court concluded that Havens furnished
    standard work customarily performed by steel fabricators, a role
    similar to that of a supplier of pre-cut wooden beams for
    residential construction. Havens supplied material from non-
    inventory stock and Pyramid used the steel to erect the
    building’s substantial frame. Although Havens’ work on the
    project comprised 7.8% of the total contract price, the District
    Court noted that Havens did not post a bond or provide
    insurance or payroll data to Pyramid. Finally, the District Court
    observed that Pyramid and Havens did not have a prior
    relationship.
    After evaluating these details, the District Court held that
    Havens was a material supplier and not a “subcontractor” under
    the Miller Act. Therefore, E & H was not entitled to recover on
    the bond.
    E & H timely appealed. We have jurisdiction under 28
    U.S.C. § 1291 and under the Miller Act, 40 U.S.C. §
    3133(b)(3)(B).
    I.
    Congress recognized that sovereign immunity left
    suppliers of labor or materials for federal construction projects
    5
    without the protection of the mechanics’ liens normally
    available in private industry. See Dep’t of Army v. Blue Fox,
    Inc., 
    525 U.S. 255
    , 264-65 (1999). To provide some protection
    for suppliers, Congress enacted the Heard Act2 and later
    replaced it with the Miller Act, found in its current version at 40
    U.S.C. § 3131, et seq. Id.3
    The Miller Act requires every contractor on a federal
    government contract exceeding $100,000 to provide “[a]
    payment bond with a surety . . . for the protection of all persons
    supplying labor and material in carrying out the work provided
    for in the contract.” 40 U.S.C. § 3131(b)(2). In pertinent part,
    § 3133(b)(1) provides that “[e]very person that has furnished
    labor or material . . . and that has not been paid in full within 90
    days after the day on which the person did or performed the last
    2
    Act of August 13, 1894, ch. 280, 28 Stat. 278, as
    amended by Act of February 24, 1905, ch. 778, 33 Stat. 811.
    3
    See also United States ex rel. Daniel H. Hill v.
    American Sur. Co., 
    200 U.S. 197
    , 202 (1906) (The Heard Act
    as amended “shows the consistent purpose of Congress to
    protect those who furnish labor or material in the prosecution of
    public work.”); Fanderlik-Locke Co. v. United States ex rel.
    Morgan, 
    285 F.2d 939
    , 942 (10th Cir. 1960) (“The purpose of
    the Miller Act is to provide security for those who furnish labor
    and material in the performance of government contracts . . . .
    The benefits of the Act are not intended for the prime contractor
    who is required by the Act to furnish a bond to effectuate its
    provisions.” (internal citations omitted)).
    6
    of the labor or furnished or supplied the material . . . may bring
    a civil action on the payment bond.” 40 U.S.C. § 3133(b)(1).
    However, § 3133(b)(2) limits the scope of those
    protected. It states:
    “A person having a direct contractual
    relationship with a subcontractor but no
    contractual relationship, express or implied, with
    the contractor furnishing the payment bond may
    bring a civil action on the payment bond on
    giving written notice to the contractor within 90
    days from the date on which the person did or
    performed the last of the labor or furnished or
    supplied the last of the material for which the
    claim is made.”
    40 U.S.C. § 3133(b)(2).
    Because the statute does not define the term
    “subcontractor,” the Supreme Court has been called upon to
    explain the meaning of the term. In Clifford F. MacEvoy Co. v.
    United States ex rel. Calvin Tompkins Co., 
    322 U.S. 102
    (1944),
    the Court recognized that the Miller Act “is highly remedial in
    nature. It is entitled to a liberal construction and application in
    order properly to effectuate the Congressional intent to protect
    those whose labor and materials go into public projects.” 
    Id. at 107.
    Nevertheless, the Court observed that it must also give
    effect to Congress’ intent to limit liability under the Act through
    7
    the restrictions in § 3133(b)(2). 
    Id. at 107-08.
    In the Court’s
    view, Congress used the term “subcontractor” in the technical
    sense to apply to “one who performs for and takes from the
    prime contractor a specific part of the labor or materials
    requirements of the original contract, thus excluding ordinary
    laborers and materialmen.” 
    Id. at 109.4
    The Court pointed out that its conclusion was supported
    by practical considerations in that it was unlikely that Congress
    intended to impose liability on the general contractor for labor
    and materials provided by those beyond the “relatively few
    subcontractors who perform part of the original contract” and
    are well known to the prime contractor. 
    Id. at 110.
    In a later
    case, the Court also made clear that Congress “intended the
    scope of protection of a payment bond to extend no further than
    4
    Thus, although a kingdom may be lost for lack of a
    nail, a vendor who supplied a box of nails is unlikely to be
    protected by the Miller Act.
    “For want of a nail the shoe was lost. For want of
    a shoe the horse was lost. For want of a horse the
    rider was lost. For want of a rider the battle was
    lost. For want of a battle the kingdom was lost.
    And all for the want of a horseshoe nail.”
    A version of this rhyme of apparent English origin first appeared
    in written form in John Gower’s Confessio Amantis, dated
    approximately 1390. Benjamin Franklin included a version in
    his Poor Richard’s Almanack.
    8
    to sub-subcontractors.” J.W. Bateson Co. v. United States ex
    rel. Bd. of Trustees, 
    434 U.S. 586
    , 591 (1978).
    The Supreme Court further explained its definition of a
    “subcontractor” under the Miller Act in F. D. Rich Co. v. United
    States ex rel. Indus. Lumber Co., 
    417 U.S. 116
    (1974). F. D.
    Rich, the prime contractor for a federal housing project, awarded
    two contracts to Cerpac Company, one for the installation of
    custom mill work and another to provide standard sheets of
    plywood. 
    Id. at 119.
    Cerpac had a close relationship with F. D.
    Rich and had worked with it on other projects. 
    Id. at 118.
    Cerpac placed an order for the plywood with Industrial Lumber,
    a broker, which purchased the plywood from its own suppliers.
    
    Id. at 119.
    After Cerpac fell behind in its payments for the
    wood, Industrial Lumber filed a claim under the Miller Act. 
    Id. at 120.
    The Court concluded that under MacEvoy the test for
    determining whether one is a subcontractor hinges on “the
    substantiality and importance of his relationship with the prime
    contractor.” 
    Id. at 123.
    The Court noted that Cerpac, in
    addition to its role as a plywood supplier, had a contract “to
    select, modify, detail and install all custom millwork . . . [and]
    in effect, took over a substantial part of the prime contract
    itself.” 
    Id. at 124.
    Finding that the close relationship and prior
    dealings between Cerpac and F. D. Rich was determinative, the
    Court concluded that Cerpac acted as a “subcontractor” when it
    supplied the plywood and Industrial was entitled to recover. 
    Id. The F.
    D. Rich Court explained that the ability of a prime
    contractor to protect itself by requiring a middleman to post a
    9
    bond is an indication that he is a “subcontractor.” 
    Id. Generally, when
    a subcontractor is required to provide a bond
    the premiums will cause him to increase his bid. See Note,
    Mechanics’ Liens and Surety Bonds in the Building Trades, 68
    Yale L.J. 138, 171 (1958) (“[W]here bonding is conventional,
    premiums constitute a construction expense which is reflected
    in every contractor's bid. The owner who accepts a bid may be
    expected to pass the premium costs on to the ultimate users of
    the particular project.”). Thus, a prime contractor may decide
    to forego requiring a bond from a subcontractor to obtain a
    lower bid. The Court’s statement appears to recognize that it is
    equitable for a prime contractor to bear the risk of loss when he
    does not require the subcontractor to secure a bond or make
    other arrangements for the security of its suppliers.
    To summarize, MacEvoy and F. D. Rich established
    broad criteria under which “subcontractor” status applies to one
    who performs a specific part of the original contract and has a
    substantial and important relationship with the prime contractor.
    Because of the variety of circumstances that arise in
    government construction projects, the general standards of
    MacEvoy and F. D. Rich are not always easy to apply. In the
    many cases that have applied MacEvoy and F. D. Rich, lower
    courts have created inconsistent tests for defining
    “subcontractor” status and have compiled laundry lists of
    elements to consider. The District Court here cited opinions of
    various appellate courts in describing circumstances it
    considered relevant:
    10
    “Some of the factors to consider include: (1) the
    nature of the material or service supplied by the
    alleged subcontractor to the prime contractor, see
    F. D. Rich, 
    417 U.S. 116
    (1974); United States ex
    rel. Consol. Pipe & Supply Co. v.
    Morrison-Knudsen Co., 
    687 F.2d 129
    (6th Cir.
    1982); Miller Equip. Co. v. Colonial Steel & Iron
    Co., 
    383 F.2d 669
    (4th Cir. 1967); United States
    ex rel. Wellman Eng’g Co. v. MSI Corp., 
    350 F.2d 285
    (2d Cir. 1965); (2) the financial
    magnitude of the goods or services provided in
    relation to the total federal contract, see
    Morrison-Knudsen, 
    687 F.2d 129
    ; Miller, 
    383 F.2d 669
    ; (3) the payment terms and exchange of
    information between the prime contractor and
    alleged subcontractor, see MSI Corp., 
    350 F.2d 285
    ; and (4) the overall relationship between the
    prime contractor and the alleged subcontractor,
    see F. D. Rich, 
    417 U.S. 116
    ; Morrison-Knudsen,
    
    687 F.2d 129
    .”
    United States ex rel. E & H Steel Corp. v. C. Pyramid
    Enterprises, Inc., 
    2006 WL 2570849
    , *6 (D.N.J. Sept. 1, 2006)
    (some internal citations omitted).
    The District Court also noted that, as part of these
    inquiries, courts have also considered
    “(1) whether the goods produced came from
    inventory or whether they had to be
    custom-manufactured, (2) whether they were
    11
    complex in nature, (3) whether they constituted a
    significant and integral portion of the overall
    project, (4) whether the items provided were
    generally available on the market, (5) whether the
    subcontractor performed work on-site, (6)
    whether the alleged subcontractor had design or
    installation responsibility for the items or services
    it provided, and (7) whether the alleged
    subcontractor had ultimate responsibility for a
    portion of the work under the government
    contract.”
    
    Id. (citations omitted).
    Although a survey of factors can be helpful in applying
    the standards in MacEvoy and F. D. Rich, the opinions
    interpreting those two cases often evolve into a process of
    “color matching” the various precedents rather than focusing on
    the purpose of the Act, the relationship between the parties, and
    the middleman’s role in the project. See, e.g., United States ex
    rel. Conveyor Rental & Sales Co. v. Aetna Cas. & Sur. Co., 
    981 F.2d 448
    , 452-55 (9th Cir. 1992).
    Many of the opinions emphasize the nature of the
    materials supplied while overlooking the fact that the Supreme
    Court held that a firm that provided plywood sheets that were
    not unique or customized was a “subcontractor” in F. D. Rich.
    See F. D. 
    Rich, 417 U.S. at 119
    . The Miller Act does not make
    distinctions based on characteristics such as whether the
    material supplied was customized or unique. Thus, for example,
    the oft-cited pre-F. D. Rich case of Aetna Cas. & Sur. Co. v.
    12
    United States ex rel. Gibson Steel Co., 
    382 F.2d 615
    (5th Cir.
    1967), inappropriately emphasized the simplicity of the
    prefabricated steel supplied to the contractor. 
    Id. at 618
    (concluding that “[t]he most important factor is the nature of the
    items . . . supplied” and that “the variety and relative simplicity
    of the items supplied weigh heavily against finding” that the
    supplier was a subcontractor).
    Similarly, in another pre-F. D. Rich case, United States
    ex rel. Bryant v. Lembke Constr. Co., 
    370 F.2d 293
    (10th Cir.
    1966), the Court was impressed by the simplicity of materials
    supplied when denying subcontractor status to a company that
    supplied concrete to the prime contractor. 
    Id. at 295-96.
    Although furnishing customized or complex material may
    in some cases be a helpful indication of the strength of the
    supplier’s relationship with the prime contractor, it does not
    follow that the absence of such characteristics in the material
    supplied establishes a lack of “subcontractor” status. The
    holding in F. D. Rich shows that a person who furnishes very
    basic materials can be a “subcontractor,” thus allowing his
    suppliers to recover on the payment bond.
    In Morrison-Knudsen, the Court of Appeals correctly
    focused more on the substantiality of the relationship between
    the prime contractor and alleged subcontractor when it was
    presented with circumstances somewhat similar to those before
    
    us. 687 F.2d at 135-36
    . The Court concluded that a fabricator
    that supplied large amounts of pipe, some of which required a
    special lining and coating, was a “subcontractor.” 
    Id. at 134.
    The Court observed that, although the fabricator did not install
    13
    the pipe or participate in the project design, it supplied 40% of
    the pipe for the facility, submitted shop drawings for approval
    of the prime contractor, and had representatives at the job site to
    help interpret the drawings and check the material for damage
    when it arrived. 
    Id. at 135.
    The Court of Appeals also stated that the prime
    contractor’s ability to procure a bond from the middlemen was
    “a significant and probative consideration.” 
    Id. Considering all
    these circumstances, the Court concluded that the evidence
    established the substantial relationship necessary to designate
    the fabricator as a “subcontractor.” 
    Id. at 136.
    The Morrison-Knudsen Court gave little consideration to
    the fact that the contractual instrument was “styled a ‘purchase
    order.’” 
    Id. at 134.
    We agree that the label that the parties apply
    to the relationship between the contractor and the middleman is
    not determinative of “subcontractor” status. The designation of
    the agreement as a “purchase order” rather than a “subcontract,”
    therefore, or the failure to designate a supplier as a
    “subcontractor,” is entitled to little weight.
    Rather than attempting to reconcile the often inconsistent
    case law and laundry lists of factors, we prefer to focus our
    analysis on the formulas provided by the Supreme Court, vague
    as they are, by following their rationale.
    We begin with the premise that the Miller Act is to be
    interpreted liberally to protect persons who supply labor or
    materials for government construction projects. That protection
    is restricted to parties who are no more distant from the prime
    14
    contractor than sub-subcontractors. J.W. Bateson 
    Co., 434 U.S. at 591
    . “Subcontractor” status may extend to those who supply
    necessary material, as well as to those who incorporate items
    into the structure.
    Neither the Miller Act nor the Supreme Court make a
    distinction between those who supply complex or simple
    material, nor do they differentiate between projects involving
    simple and complicated structures. The Court’s definition of a
    “subcontractor” is “one who performs for and takes from the
    prime contractor a specific part of the labor or materials required
    by the original contract.” 
    MacEvoy, 322 U.S. at 109
    . A
    “subcontractor” must have a substantial and important
    relationship with the prime contractor. F. D. 
    Rich, 417 U.S. at 123
    . The prime contractor’s ability to require the posting of a
    bond is also an indication of where the risk of financial loss
    should fall. 
    Id. at 123-24;
    MacEvoy, 322 U.S. at 110
    .
    II.
    The issue here is whether Havens qualifies as a
    “subcontractor” under this approach. We conclude that it does.
    Havens’ task was to supply a specific and crucial part of
    the materials required by the original contract to construct the
    steel framework. It arranged for the fabrication and delivery to
    the site of a substantial amount of structural steel necessary for
    the skeleton of the hangar building. Havens also prepared shop
    drawings and erection drawings, designed the connectors, and
    performed some “design-assist engineering.”
    15
    The relationship with the prime contractor was a
    substantial and important one. The work and material Havens
    supplied for the framework required Pyramid to exercise
    substantial attention and oversight. The shop drawings were
    submitted to Pyramid for approval and the parties communicated
    about the connectors design and design-assist work.
    Although Pyramid did most of the construction work
    itself, the steel that Havens supplied had to be carefully
    manufactured so that Pyramid could efficiently erect the
    framework. Delivery of the steel to the site had to be arranged
    to comply with Pyramid’s construction schedule. The
    importance of this coordination became clear when, in Havens’
    bankruptcy proceeding, Pyramid made a claim against Havens
    for costs incurred because of delays in delivery of the steel.
    Further, it does not appear that, for this project, a large
    number of subcontracts were awarded and none were as large as
    that with Havens. Finally, Pyramid likely could have requested
    a bond, although the record does not disclose whether Havens
    could have qualified for one.
    The District Court, in denying recovery, analogized the
    supplying of pre-fabricated steel beams to providing pre-cut
    wood beams for residential construction. As noted above, in F.
    D. Rich the Supreme Court decided that a firm that furnished
    standard sheets of plywood was a “subcontractor.” A supplier
    of pre-cut wooden beams could qualify as well. Moreover, the
    fact that Havens’ contract amounted to 7.8% of the total project
    costs is not a weighty reason to deny recovery, especially since
    Pyramid did most of the construction itself.
    16
    We conclude, therefore, that Havens was a
    “subcontractor.” Because it had a contract with Havens, E & H
    is entitled to recover under the Miller Act bond. Accordingly,
    the judgment of the District Court will be reversed and the case
    will be remanded for entry of a judgment in favor of E & H
    Steel Company.
    17