Great Amer Ins Co v. Norwin Sch Dist ( 2008 )


Menu:
  •                                                                                                                            Opinions of the United
    2008 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    9-29-2008
    Great Amer Ins Co v. Norwin Sch Dist
    Precedential or Non-Precedential: Precedential
    Docket No. 07-2441
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2008
    Recommended Citation
    "Great Amer Ins Co v. Norwin Sch Dist" (2008). 2008 Decisions. Paper 430.
    http://digitalcommons.law.villanova.edu/thirdcircuit_2008/430
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 2008 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    Case No: 07-2441
    GREAT AMERICAN INSURANCE CO.
    v.
    NORWIN SCHOOL DISTRICT
    v.
    SHOFF CONSTRUCTION AND DESIGN, INC.
    FOREMAN PROGRAM & CONSTRUCTION MANAGERS,
    INC.
    Foreman Program & Construction Managers, Inc.,
    Appellant
    On Appeal from the United States District Court
    for the Western District of Pennsylvania
    District Court No. 04-cv-01148
    District Judge: The Honorable Terrence F. McVerry
    ARGUED May 20, 2008
    Before: SMITH and NYGAARD, Circuit Judges,
    and STAFFORD, District Judge *
    (Filed: September 29, 2008)
    Amy E. Bentz, Esq. (Argued)
    James W. Bentz, Esq.
    Bentz Law Firm
    680 Washington Road
    The Washington Center Building
    Pittsburgh, PA 15228-0000
    Counsel for Great American Insurance Company
    David Raves, Esq.
    Maiello, Brungo & Maiello
    3301 McCrady Road
    One Churchill Park
    Pittsburgh, PA 15235-0000
    Counsel for Norwin School District
    Ross A. Giorgianni, Esq. (Argued)
    Metz Lewis
    11 Stanwix Street
    18th Floor
    Pittsburgh, PA 15222-0000
    Counsel for Shoff Construction and Design, Inc.
    *
    The Honorable William H. Stafford, Jr., Senior United
    States District Judge for the Northern District of Florida, sitting
    by designation.
    2
    Mark J. Gesk, Esq. (Argued)
    Wayman, Irvin and McAuley
    1624 Frick Building
    437 Grant Street
    Pittsburgh, PA 15219-0000
    Counsel for Foreman Program & Construction
    Managers, Inc.
    OPINION
    STAFFORD, District Judge.
    Third-Party Defendant, Foreman Program &
    Construction Managers, Inc. ("Foreman"), appeals from a
    judgment entered in favor of Third-Party Plaintiff, Norwin
    School District ("Norwin"), on Norwin's breach of contract
    claim against Foreman. We vacate the District Court's judgment
    and remand to the District Court with directions to enter
    judgment in Foreman's favor.
    I. FACTS
    Our trek through the factual morass from which this case
    arose begins in 2001, when Norwin undertook two public school
    construction projects. These two projects spawned, inter alia,
    four contracts and two payment bonds, namely: (1) two
    3
    construction contracts, under which Shoff Construction and
    Design, Inc. ("Shoff"), agreed to serve as the general contractor
    for the two projects, one for the construction of a new Sheridan
    Terrace Elementary School and one for renovations and
    additions to Hillcrest Intermediate School, both in North
    Huntingdon, Pennsylvania; (2) an architectural services contract,
    under which N.J. Cunzolo & Associates, Inc. ("Cunzolo"),
    agreed to serve as architect for the two projects; (3) a
    construction management services contract, under which
    Foreman agreed to perform construction management services
    for the two projects; and (4) two payment bonds,1 one on each
    project, issued by Great American Insurance Company
    ("GAIC") as surety on behalf of Shoff as principal and in favor
    of Norwin as obligee.
    A. The Norwin-Foreman Construction Management Contract
    Norwin and Foreman entered into a construction
    management contract (the "CM Contract") on August 20, 2001,
    using the American Institute of Architects ("AIA") standard
    form B801/Cma–1992, entitled "Standard Form of Agreement
    Between Owner and Construction Manager." As noted on the
    cover page of the agreement, Form B801/Cma–1992 was
    intended to be used in conjunction with the 1992 edition of AIA
    standard form B141/Cma, entitled "Standard Form of
    1
    Shoff also procured two performance bonds from
    GAIC, neither of which is at issue in this case.
    4
    Agreement Between Owner and Architect." Both forms
    incorporated by reference standard form A201/Cma–1992,
    entitled "General Conditions of the Contract for Construction"
    ("General Conditions"). The lump sum fee to be paid Foreman
    for its services under the CM Contract was $807,168.00
    ($391,408.00 for Sheridan and $415,760.00 for Hillcrest).
    The CM Contract required Foreman to act as a joint
    adviser (with Cunzolo, the architect) to Norwin throughout the
    Sheridan and Hillcrest projects. During the pre-construction
    phase of the projects, Foreman was required to assist Norwin in
    a number of tasks, including selection of the project contractors
    and preparation of the construction contracts. Once the
    construction contracts were awarded, Foreman was responsible
    for administering those contracts in cooperation with Cunzolo
    as set forth in Form A201/Cma.
    Among other things, Foreman was required to review
    Shoff's applications for progress and final payments. Based on
    Foreman's observations of the work performed and evaluations
    of Shoff's applications for payment, Foreman was required to
    certify the amounts to be paid to Shoff by Norwin. As stated in
    Article 2.3.11.3 of the CM Contract, Foreman's certification
    constituted "a representation to [Norwin] . . . that the Work
    ha[d] progressed to the point indicated and the quality of the
    Work [wa]s in accordance with the Contract Documents."
    Under Article 2.3.11.4, the issuance of a certificate of payment
    was not a representation that Foreman had "(1) reviewed
    5
    construction means, methods, techniques, sequences for
    [Shoff]'s own Work, or procedures, (2) reviewed copies of
    requisitions received from Subcontractor and material suppliers
    and other data requested by [Norwin] to substantiate [Shoff]'s
    right to payment, or (3) ascertained how or for what purpose
    [Shoff] ha[d] used money previously paid on account of the
    Contract Sum." Indeed, Article 4.7 provided that Norwin, not
    Foreman, was responsible for furnishing any services necessary
    "to ascertain how or for what purposes [Shoff] ha[d] used the
    money paid by or on behalf of [Norwin]." In other words,
    before issuing a certificate for payment, Foreman was required
    to verify the quality and quantity of Shoff's work but not the
    appropriateness of Shoff's expenditure of monies.
    B. The Norwin-Cunzolo Architectural Services Contract
    Cunzolo and Norwin entered into an architectural
    services contract (the "AS Contract") using Form B141/Cma,
    the Form intended to be used in conjunction with Foreman's CM
    Contract. Like the CM Contract, the AS Contract incorporated
    by reference the General Conditions set forth in form
    A201/Cma.
    In addition to design services, Cunzolo agreed to perform
    construction administration tasks in cooperation with Foreman.
    Among other things, Cunzolo—like Foreman—was required
    under the terms of the AS Contract to review and certify the
    amounts due to Shoff. In particular, at the time of final
    6
    completion of the projects, Cunzolo was required—under
    Article 2.6.14 of the AS Contract—to issue "a final Project
    Certificate for Payment upon compliance with the requirements
    of the Contract Documents." As stated in Article 2.6.9.1,
    Cunzolo's certification constituted "a representation to [Norwin]
    . . . that . . . the work ha[d] progressed to the point indicated and
    the quality of the Work [wa]s in accordance with the Contract
    Documents." Under Article 2.6.9.2, Cunzolo's certification was
    not a representation that Cunzolo (1) "made exhaustive or
    continuous on-site inspections to check the quality or quantity
    of the Work, (2) reviewed construction means, methods,
    techniques, sequences or procedures, (3) reviewed copies of
    requisitions received from Subcontractors and material
    suppliers, or (4) ascertained how or for what purpose [Shoff]
    ha[d] used money previously paid on account of the Contract
    Sum." Like Article 4.7 in the CM Contract, Article 4.9 in the
    AS Contract made it Norwin's responsibility to provide all
    necessary services—including auditing services—"to verify
    [Shoff's] Application for Payment or to ascertain how or for
    what purposes [Shoff] ha[d] used the money paid by or on
    behalf of [Norwin]." As was the case for Foreman, Cunzolo
    was required to verify the quality and quantity of Shoff's work
    before issuing a certificate of payment, but he was not required
    to verify the appropriateness of Shoff's expenditure of monies.
    C. The Norwin-Shoff Construction Contracts
    Norwin and Shoff entered into the Sheridan and Hillcrest
    7
    construction contracts (collectively the "Shoff Contracts") on
    February 18, 2002, and April 17, 2002, respectively, using the
    AIA standard form A101/CMa, entitled "Standard Form of
    Agreement Between Owner and Contractor." The Shoff
    Contracts specifically incorporated not only form A201/CMa,
    containing the General Conditions applicable to construction
    contracts, but also document 00800, entitled "Supplementary
    Conditions." 2 The contract price of the Sheridan project was
    $3,750,700.00; the contract price of the Hillcrest project was
    $5,422,400.00.3
    Each of the Shoff Contracts required Norwin to make
    monthly progress payments to Shoff based upon "Applications
    for Payment" submitted by Shoff to Foreman and upon
    "Certificates for Payment" issued to Norwin by Foreman and
    Cunzolo. The amounts requested in each Application for
    Payment were required to be based upon a "Schedule of Values"
    that allocated the entire contract sum among the various portions
    of the work to be done. Upon receipt of an Application for
    Payment, Foreman was required to forward the application to
    Cunzolo. If Foreman and Cunzolo were both satisfied with the
    2
    The General Conditions were effective only to the
    extent that they were not modified, voided, or deleted by the
    Supplementary Conditions.
    3
    With change orders, the final contract price for the
    Sheridan project was $3,731,574.00. For the Hillcrest project,
    the final contract price was $5,615,267.11.
    8
    amounts requested in the Application for Payment, they issued
    a Certificate for Payment—signed by each—to Norwin.
    Consistent with provisions in both the CM Contract and
    the AS Contract, the Shoff Contracts—through Article 9.4.3 of
    the General Conditions—provided that the issuance of a
    Certificate for Payment constituted "representations made
    separately by [Foreman] and [Cunzolo] to [Norwin], based on
    their individual observations at the site and the data comprising
    the Application for Payment submitted by [Shoff], that the Work
    ha[d] progressed to the point indicated and that, to the best of
    [Foreman]'s and [Cunzolo]'s knowledge, information and belief,
    quality of the Work [wa]s in accordance with the Contract
    Documents." Also consistent with the CM Contract and the AS
    Contract, Article 9.4.3 of the General Conditions provided that
    a Certificate for Payment did not constitute a representation that
    Foreman or Cunzolo
    "(1) made exhaustive or continuous on-site
    inspections to check the quality or quantity of the
    Work, (2) reviewed [Shoff's] construction means,
    methods, techniques, sequences or procedures, (3)
    reviewed copies of requisitions received from
    Subcontractors and material suppliers and other
    data requested by [Norwin] to substantiate
    [Shoff]'s right to payment, or (4) made
    examination to ascertain how or for what purpose
    [Shoff] ha[d] used money previously paid on
    9
    account of the Contract Sum."
    Until the work was fifty percent (50%) complete, Norwin
    was required under Article 5.6.1 of the Shoff Contracts to retain
    ten percent (10%) from its monthly payments as security against
    Shoff's performance. Article 5.7.1 in each of the Shoff
    Contracts provided that, upon "Substantial Completion" of the
    work, progress payments were to be modified by adding "a sum
    sufficient to increase the total payments to ninety-five percent
    (95%) of the Contract Sum, less such amounts as [Foreman]
    recommends and [Cunzolo] determines for incomplete Work
    and unsettled claims." The Sheridan contract, but not the
    Hillcrest contract, defined "Substantial Completion" to mean
    fifty percent (50%) completion. The Sheridan contract, but not
    the Hillcrest contract, further specified that retainage was to be
    reduced to five percent (5%) when the work was fifty percent
    (50%) complete.4
    Using somewhat different language, the Supplementary
    Conditions applicable to both contracts addressed the matter of
    retainage as follows:
    4
    Article 5.8 in each of the contracts provided that
    "[r]eduction or limitation of retainage, if any, shall be as follows
    . . ." In the Sheridan contract, the words "[r]educe to 5% at 50%
    of work installed" had been added after the word "follows." In
    the Hillcrest contract, no reduction or limitation of retainage was
    specified.
    10
    9.3.6: The sum or sums withheld by [Norwin]
    from [Shoff] shall be 10 percent of the amount
    due [Shoff] until 50 percent of the Contract is
    completed. When the Contract is 50 percent
    complete, one-half of the amount retained by
    [Norwin] shall be released to [Shoff], provided
    that [Cunzolo] approves the Application for
    Payment; and provided further, that [Shoff] is
    making satisfactory progress and there is no
    specific cause for greater withholding.
    9.3.7: The sum or sums withheld by [Norwin]
    from [Shoff] after the Contract is 50 percent
    completed shall not exceed 5 percent of the value
    of completed work based on monthly progress
    payment requests.
    Article 6 in the Shoff contracts provided that "[f]inal
    payment, constituting the entire unpaid balance of the Contract
    Sum, shall be made by [Norwin] to [Shoff] when (1) the
    Contract has been fully performed by [Shoff] . . . and (2) a final
    Project Certificate for Payment has been issued by [Foreman]
    and [Cunzolo]." The parties' responsibilities with regard to final
    payment were explained in greater detail in the General
    Conditions:
    9.10.1. Upon completion of the Work, [Shoff]
    shall forward to [Foreman] a written notice that
    the Work is ready for final inspection and
    acceptance and shall also forward to [Foreman] a
    final Contractor's Application for Payment. Upon
    11
    receipt, [Foreman] will forward the notice and
    Application to [Cunzolo] who will promptly make
    such inspection. When [Cunzolo], based on the
    recommendation of [Foreman], finds the Work
    acceptable under the Contract Documents and the
    Contract fully performed, [Foreman] and
    [Cunzolo] will promptly issue a final Certificate
    for Payment stating that to the best of their
    knowledge, information and belief, and on the
    basis of their observations and inspections, the
    Work has been completed in accordance with
    terms and conditions of the Contract Documents
    and that the entire balance found to be due [Shoff]
    and noted in said final Certificate is due and
    payable.
    The General Conditions further provided that the final
    Certificate for Payment constituted a "representation that
    conditions listed in Subparagraph 9.10.2 as precedent to the
    Contractor's being entitled to final payment have been fulfilled."
    Subparagraph 9.10.2 of the General Conditions provided that
    "[n]either final payment nor any remaining retained percentages
    shall become due" until Shoff submitted to Cunzolo through
    Foreman certain documents, including, inter alia, (1) "an
    affidavit that payrolls, bills for materials and equipment, and
    other indebtedness connected with the Work for which [Norwin]
    or [Norwin]'s property might be responsible or encumbered . .
    . ha[d] been paid or other wise satisfied;" and (2) "consent of
    surety, if any, to final payment."
    C. The Payment Bonds
    12
    As required under Pennsylvania law and Article 11.4.1 of
    the Supplementary Conditions, Shoff was required to procure
    payment bonds for the two school projects, each in the amount
    of one hundred percent (100%) of the contract price. Shoff
    obtained the required payment bonds from GAIC. 5 Under
    paragraph 1 in each of the payment bonds, GAIC and Shoff
    agreed to jointly and severally bind themselves to Norwin "to
    pay for labor, materials and equipment furnished for use in the
    performance of the Construction Contract, which is incorporated
    herein by reference." Paragraph 8 in each of the two bonds
    states: "By [Shoff] furnishing and [Norwin] accepting this Bond,
    they agree that all funds earned by [Shoff] in the performance of
    the Construction Contract are dedicated to satisfy obligations of
    [Shoff] and [GAIC] under this Bond, subject to [Norwin]'s
    priority to use the funds for the completion of the work."
    To obtain the bonds, Charles and Melanie Shoff signed
    an "Agreement of Indemnity"—dated July 26, 2001—under
    which they agreed to indemnify GAIC for any losses and
    expenses arising from issuance of the bonds. In addition, on
    March 25, 2004, the Shoffs executed a loan and collateral
    security agreement, which provided, inter alia, that "as of the
    date of this agreement, there were in excess of $750,000.00 in
    accrued debts owed to the equipment, labor and materials
    suppliers relating to the [bonded] Projects," and "[the Shoffs]
    have requested financial assistance from [GAIC] to enable
    5
    The record contains copies of the two payment bonds.
    The bond on the Hillcrest project is signed; the bond on the
    Sheridan project is not.
    13
    [Shoff] to meet its financial obligations and complete its bonded
    construction projects that have not been terminated." GAIC
    obtained a mortgage on the Shoff's personal property as
    collateral security on the loan note.
    D. The Payments
    Shoff received eighteen (18) progress payments on the
    Sheridan project and seventeen (17) progress payments on the
    Hillcrest project.    For each payment, Shoff submitted
    Applications for Payment, designating both the contract sum
    earned to date and the amount of retainage—expressed both as
    a percentage and a dollar amount—to be subtracted from the
    total earned. In each case, Shoff obtained a Certificate of
    Payment from Foreman and Cunzolo and received payment from
    Norwin with the designated retainage subtracted. At the time of
    each payment, Shoff, Foreman, Cunzolo, and Norwin were all
    aware of the amounts— in terms of dollars and
    percentages—being retained from the payments due.
    On the Sheridan project, Shoff designated ten percent
    (10%) retainage on the first six of its Applications for Payment.
    On the next nine Applications for Payment, when the work was
    fifty percent (50%) or more completed, Shoff designated five
    percent (5%) retainage. On Application No. 16, when work
    completed to date totaled $3,652,547.49 (ending contract price
    was $3,731,574.00), Shoff designated retainage of two and a
    half percent (2.5%). On Application Nos. 17 and 18, Shoff
    reduced retainage to less than one percent (0.67%).
    On the Hillcrest project, Shoff designated ten percent
    14
    (10%) retainage on the first five of its Applications for Payment.
    On the next seven Applications for Payment, when the work was
    fifty percent (50%) or more complete, retainage was at or near
    five percent (4.75% to 5%). On Application No. 16, when work
    completed to date was estimated at a total of $5,649,902.51
    (ending contract price was, in fact, $5,615,267.11), Shoff
    designated retainage of three and a half percent (3.5%). On
    Application No. 17, retainage was reduced to two percent (2%).
    Each time Shoff submitted an Application for Payment,
    Charles Shoff, as President of Shoff, certified as follows:
    [T]o the best of the Contractor's knowledge,
    information and belief the work covered by this
    application for Payment has been completed in
    accordance with the Contract Documents, that all
    amounts have been paid by Contractor for Work
    for which previous Certificates for Payment were
    issued and payments received from the owner,
    and that current payment shown herein is now
    due.
    Shoff's certifications were sworn and notarized. As provided in
    Article 9.4.3 of the General Conditions, Foreman had no duty to
    "ma[k]e examination to ascertain how or for what purpose
    [Shoff] ha[d] used money previously paid on account of the
    Contract Sum."
    Shoff submitted its final Applications for Payment for
    Sheridan on September 4, 2003, and for Hillcrest on November
    15
    24, 2003. Shoff requested a final payment of $24,961.17 for
    Sheridan and $78,362.65 for Hillcrest. On the Sheridan project,
    Foreman and Cunzolo both signed the final Certificate of
    Payment in the amount of $19,961.17, $5000.00 less than was
    requested. On the Hillcrest project, Foreman, but not Cunzolo,
    signed the final Certificate of Payment in the amount of
    $78,362.65.
    With its final Applications for Payment, Shoff
    transmitted affidavits—one each for the two projects—to
    Foreman, indicating that all of Shoff's debts relating to the two
    projects had been paid. Specifically, on AIA form G706,
    "Contractor's Affidavit of Payment of Debts and Claims," Shoff
    certified that "payment has been made in full and all obligations
    have otherwise been satisfied for all materials and equipment
    furnished, for all work, labor, and services performed, and for
    all known indebtedness." On the Affidavit forms were boxes for
    Shoff to check, indicating whether the "Consent of Surety to
    Final Payment" was or was not attached.6 Shoff checked neither
    box, and the Consent of Surety to Final Payment was not
    attached.
    Foreman admitted that it did not obtain the consent of
    surety before certifying Shoff's final Application for Payment on
    both projects. Foreman explained that it signed and submitted
    the Final Certificates for Payment without the consent of surety
    because (1) it had not experienced any problems with Shoff on
    6
    The G706 form provided that "[w]henever Surety is
    involved, Consent of Surety is required."
    16
    past projects, (2) Shoff's performance on the Sheridan and
    Hillcrest projects—both in terms of timeliness and quality—had
    been very good, (3) Shoff had met its obligations with regard to
    final punch list items, (4) contractors and subcontractors
    generally want to be paid promptly, (5) Norwin's board met only
    once in a 30-day period to approve and issue payments, (6)
    Foreman wanted to get the Final Certificates for Payment "in the
    works" so that those certificates could be submitted at the next
    school board meeting, and (7) Shoff had indicated that the
    surety's consent would be forthcoming.
    Unknown to Foreman, and despite certifications and
    affidavits to the contrary, Shoff failed to pay all of its debts to
    subcontractors and suppliers, resulting in liens that were not
    disclosed to Foreman, Cunzolo, or Norwin. Shoff's President,
    Charles Shoff ("Charles Shoff"), explained at trial that, while
    the payments his company received from Norwin were used to
    pay subcontractors and vendors, the jobs "lost $800,000,"
    meaning "there wasn't enough money to pay" all of the debts.
    Indeed, it appears that some of the subcontractors and suppliers
    had begun making claims against the payment bonds before
    Shoff made its final Applications for Payment, a fact that was
    communicated to neither Foreman nor Norwin.7 It was not until
    7
    GAIC's representative, Joel Beach ("Beach"), testified
    at trial that, had consent of surety been requested at the end of
    the projects, such consent would have been withheld and GAIC
    would have instead requested that final payment be sent to
    GAIC "because we have had issues on the job." Beach did not
    explain why, if GAIC knew about "issues on the job" before the
    17
    July 1, 2004—many months after Shoff submitted its final
    Applications for Payment on September 4, 2003 (Sheridan), and
    November 24, 2003 (Hillcrest)—that GAIC informed Norwin
    that it had received bond payment claims totaling nearly
    $800,000.00, roughly the same amount that Shoff said was
    "lost" on the projects.
    II. PROCEEDINGS
    A. The Claims
    Invoking the District Court's diversity jurisdiction, GAIC
    filed suit against Norwin on August 4, 2004, alleging that
    Norwin breached both of the Shoff Contracts by failing to obtain
    GAIC's consent before making final payments to Shoff.
    According to GAIC, the final payment under each of the
    contracts should have been equal to five percent (5%) of the
    contract price, the amount of retainage allegedly required at the
    time of final payment. As alleged by GAIC, "[Norwin's] failure,
    as . . . bond obligee and stakeholder, to obtain [GAIC's] consent
    prior to paying Shoff, impaired [GAIC's] security to the extent
    that the retainage was improperly paid." Under the doctrine of
    equitable subrogation, GAIC sought damages in the total
    amount of $467,342.06, an amount equal to five percent (5%) of
    the combined Sheridan and Hillcrest contract prices.
    After unsuccessfully moving to dismiss GAIC's
    job was finished, timely notice was not given to Norwin,
    Foreman, or Cunzolo.
    18
    complaint, Norwin filed a counterclaim against GAIC, alleging
    that GAIC had breached its responsibility to remedy Shoff's
    incomplete and/or defective work. Norwin also filed a third-
    party complaint against Shoff and Foreman, alleging that (1)
    Shoff had breached the Shoff Contracts by failing to pay its
    suppliers and subcontractors; (2) Shoff had breached the Shoff
    Contracts by failing to correct and complete, with the warranty
    period, incomplete and defective work; (3) Foreman had
    breached the CM Contract by failing to "produce and obtain the
    necessary documentation and certify the same with respect to
    payments to [Shoff];" and (4) Foreman was negligent in its
    provision of construction management services. Norwin
    asserted that Shoff and Foreman were either "solely liable to
    [GAIC] for any damages allegedly sustained by [GAIC]," or
    they were "jointly and severally liable with [Norwin] and/or
    liable over to [Norwin] or directly liable for contribution and/or
    indemnity." 8
    8
    As conceded at oral argument, the record does not
    support— and Norwin is not pursuing— claims of
    indemnification and contribution against Foreman. Foreman has
    not raised—and we do not consider—whether Norwin's breach
    of contract claim against Foreman states a proper claim under
    Rule 14 of the Federal Rules of Civil Procedure. See e.g.,
    American Zurich Ins. Co. v. Cooper Tire & Rubber Co., 
    512 F.3d 800
    , 805 (6th Cir. 2007) (explaining that "Rule 14(a) does
    not allow a third-party complaint to be founded on a defendant's
    independent cause of action against a third-party defendant,
    even though arising out of the same occurrence underlying
    plaintiff's claim").
    19
    After answering Norwin's third-party complaint, Foreman
    filed a cross claim against Shoff, seeking contribution and
    indemnity from Shoff. Shoff in turn filed a cross-claim against
    Foreman and a counterclaim against Norwin. For whatever
    reason, Cunzolo was left out of the fray.
    B. The GAIC-Norwin-Shoff Agreement
    On November 30, 2005, all parties—GAIC, Norwin,
    Shoff, and Foreman—filed cross-motions for summary
    judgment. Soon after, unbeknownst to both the District Court
    and Foreman, the other three parties—GAIC, Norwin, and
    Shoff—signed a settlement agreement9 (the "Settlement
    Agreement") that provided as follows:
    1. Norwin agreed not to oppose GAIC's motion
    for summary judgment on the issue of liability.
    2. Norwin agreed not to oppose GAIC's motion
    for summary judgment on the issue of damages.
    Not only did Norwin agree not to contest the
    amount requested by GAIC, namely, $467,362.06;
    but it also agreed not to assert that those damages
    should be reduced by (a) the value of any
    collateral taken by GAIC from Shoff; and (b) any
    9
    The copy of the agreement that appears in the record
    contains the signatures of GAIC's and Norwin's representatives.
    The signature line for Shoff is blank. It is undisputed, however,
    that Shoff was a party to the agreement.
    20
    monies paid to GAIC by its underwriter Seubert
    & Associates, Inc., under the Agency Agreement
    or the Surety Profit Sharing Agreement.
    3. Shoff agreed to undertake all corrective
    measures requested by Norwin.
    4. Norwin agreed to release GAIC from any
    liability to Norwin with respect to all bonds
    executed by GAIC as surety to Shoff, the
    principal, and to Norwin, the obligee, including
    all those claims that were asserted and could have
    been asserted in the litigation.
    5. Norwin agreed to retain—at no cost to
    N orw in— G A IC 's counsel after G AIC 's
    unopposed motion for summary judgment was
    granted. GAIC's counsel would then pursue
    Norwin's claims against Foreman. Norwin agreed
    that it would turn over to GAIC any amounts that
    it might obtain from Foreman through judgment
    or settlement.
    6. Norwin agreed to voluntarily dismiss its claims
    against Shoff.
    7. In the event GAIC's counsel was unable to
    obtain a judgment against Foreman on Norwin's
    behalf, GAIC agreed "to satisfy of record [GAIC's
    21
    judgment against Norwin] upon the occurrence of
    one of the following: (1) the expiration of sixty
    days after the entry of a final, non-appealable
    judgment in favor of Foreman; or (2) the
    expiration of sixty days after Foreman establishes,
    to the satisfaction of GAIC, that Foreman and its
    insurance carrier are unable to pay the amount of
    any judgment entered in favor of Norwin's claims
    against Foreman in this Litigation."          This
    provision appears to say, and the parties have
    since conceded that it means, that Norwin will not
    have to satisfy the judgment obtained by GAIC
    against Norwin.
    8. GAIC, Norwin, and Shoff agreed to cooperate
    in the litigation against Foreman.
    C. The Rulings
    On February 13, 2006, the Magistrate Judge entered a
    report and recommendation addressing the four motions for
    summary judgment that were filed on November 30, 2005. The
    Magistrate Judge did not then know about the GAIC-Norwin-
    Shoff Settlement Agreement. Noting that Norwin altogether
    failed to respond to GAIC's motion for summary judgment, the
    Magistrate Judge recommended that summary judgment be
    entered in GAIC's favor on GAIC's claims against Norwin and
    on Norwin's counterclaims against GAIC. With respect to
    Norwin's and Foreman's cross-motions for summary judgment
    (regarding Norwin's third-party claims against Foreman), the
    Magistrate Judge recommended that summary judgment be
    22
    granted in Foreman's favor on Norwin's third-party negligence
    claims and in Norwin's favor—as to liability—on Norwin's
    third-party breach of contract claims. With respect to Shoff's
    motion for summary judgment against Foreman (regarding
    Foreman's cross-claims against Shoff), the Magistrate Judge
    recommended that summary judgment be entered in Shoff's
    favor.
    The District Court adopted the Magistrate Judge's report
    and recommendation by order docketed March 20, 2006.
    Neither the District Court nor Foreman had yet been informed
    about the Settlement Agreement. Shoff later withdrew its cross-
    claim against Foreman, and Norwin and Shoff withdrew their
    claims against each other.
    By motion filed April 18, 2006, GAIC requested entry of
    judgment against Norwin in the total amount of $701,456.38,
    which amount included $467,342.06, plus "attorney's fees, costs,
    and other damages under the Public Contractor and
    Subcontractor Payment Act, 62 Pa. C.S.A. § 3931." The next
    day, Norwin filed a motion for entry of judgment against
    Foreman, arguing that Foreman was "liable over" to Norwin for
    the summary judgment granted to GAIC on March 20, 2006, a
    judgment purportedly requiring Norwin to pay $467,342.06,
    plus "attorney's fees, costs, and other damages." Norwin
    thereafter responded to GAIC's motion for entry of judgment by
    stating that it would not contest the amounts sought by GAIC,
    "so long as the Court enters Judgment in its favor and against
    Foreman in the same amount, as requested in Norwin's Motion
    for Judgment."
    23
    Foreman first learned about the GAIC-Norwin-Shoff
    Settlement Agreement at a status conference held before the
    Magistrate Judge on April 18, 2006. Foreman thereafter filed a
    counter-motion to GAIC's and Norwin's motions for entry of
    judgment, asserting that the District Court's previous order
    granting summary judgment to Norwin against Foreman should
    be vacated based on the secret Settlement Agreement. Foreman
    also moved to amend its affirmative defenses to Norwin's third-
    party claims. Specifically, Foreman sought leave to add three
    affirmative defenses, one each based on: (1) GAIC's agreement
    to forebear from executing on its judgment against Norwin,
    thereby relieving Norwin from having to pay any damages; (2)
    Norwin's failure to mitigate damages; and (3) GAIC's and
    Norwin's agreement, which purportedly released or extinguished
    Norwin's claims against Foreman.
    In a memorandum order dated June 8, 2006, the
    Magistrate Judge noted as follows:
    Great American and Norwin argue that Foreman
    is liable over to Norwin for the amount that
    Norwin owes Great American. However, the
    Court has not determined what the amount is that
    Norwin owes Great American and, even if they
    [Great American and Norwin] were to
    unequivocally agree upon an amount, such an
    agreement would not be binding upon a third
    party. Moreover, that argument appears to be
    based on an indemnity theory which, as explained
    above, is not the basis for Foreman's liability.
    24
    The Magistrate Judge accordingly dismissed Norwin's motion
    for entry of judgment as premature and deferred GAIC's motion
    for entry of judgment, stating that the motion "will be
    considered by the Court if and when Norwin unconditionally
    consents to the entry of judgment against it." The Magistrate
    Judge also denied Foreman's motion to amend its affirmative
    defenses on the ground that the proposed amendment would be
    futile. In the Magistrate Judge's words: "[B]ecause Foreman's
    liability to Norwin is based on Foreman's breaches of its
    contractual obligations and not on a theory of indemnification,
    the provisions of the Agreement would not have made any
    difference in this case." Finally, the Magistrate Judge denied
    Foreman's counter-motion to set aside the district court's March
    20 order regarding the parties' cross-motions for summary
    judgment. According to the Magistrate Judge, "the issue of
    liability has been established and all that remains to be
    determined is the amount of damages."
    On June 19, 2006, GAIC filed an amended motion for
    entry of judgment against Norwin. In its amended motion,
    GAIC requested entry of judgment in the amount of
    $467,342.06, plus prejudgment interest. After Norwin advised
    the District Court that it did not oppose the motion, the District
    Court entered an order dated September 1, 2006, directing entry
    of judgment in favor of GAIC and against Norwin "in the
    amount of $467,342.05 [sic] together with prejudgment
    interest."
    On June 20, 2006, Norwin filed an amended motion for
    entry of judgment against Foreman, this time requesting
    judgment in the amount of $467,342.06 plus interest. As he did
    25
    with Norwin's earlier motion for entry of judgment, the
    Magistrate Judge dismissed the amended motion as premature.
    Norwin thereafter filed a motion for summary judgment on
    damages, arguing that Foreman owed $467,342.05, the amount
    of the judgment already entered in GAIC's favor and against
    Norwin. On November 13, 2006, the Magistrate Judge
    recommended that Norwin's motion for summary judgment as
    to damages be denied. The Magistrate Judge wrote:
    Norwin cannot sustain this burden [of proving its
    damages] by referring to a judgment entered
    against it, with its consent, by Great American.
    Although Great American and Norwin can agree
    to Norwin's liability, such an agreement is not
    binding on third parties. Nor can Norwin succeed
    by proffering an agreement reached between other
    parties when Foreman has presented testimony
    that Norwin will not be making payments to Great
    American as a result of this agreement.
    The District Court later adopted the Magistrate Judge's report
    and recommendation and denied Norwin's motion for summary
    judgment as to damages. A jury trial on damages was scheduled
    to begin on April 16, 2007.
    As the case proceeded toward a trial on Norwin's
    damages, Norwin and Foreman filed a number of motions in
    limine. On April 5, 2007, the District Court ruled on these
    motions, ordering, among other things, that (1) neither party
    would be permitted to introduce the GAIC-Norwin-Shoff
    Settlement Agreement into evidence, the agreement being
    26
    "irrelevant to the merits of the instant dispute;" (2) Norwin
    could introduce evidence of the judgment in favor of GAIC and
    against Norwin, as well as evidence of the retainage amounts
    paid to Shoff, in order to establish its damages; (3) Foreman
    would not be permitted to argue that, because Norwin would
    never have to pay the GAIC judgment, Norwin suffered no
    damages; (4) Foreman would be permitted to introduce evidence
    to establish that Norwin failed to mitigate its damages; and (5)
    Norwin would not be permitted to present evidence regarding
    Foreman's insurance coverage. In essence, the District Court
    concluded that, "[t]o put Norwin in the same position that it
    would have been had Foreman performed [the CM Contract]
    properly, the Great American judgment against Norwin must be
    satisfied." The District Court determined—in other words—that
    "the entry of judgment against Norwin is sufficient evidence of
    its damages."
    Several days before trial began, Foreman submitted an
    offer of proof regarding evidence that it wished to introduce at
    trial. On the morning of trial, the District Court addressed
    Foreman's offer of proof by ruling that Foreman could not
    introduce (1) the Settlement Agreement to show bias or
    prejudice on the part of "any witnesses who are employees,
    agents, or representatives of the signatories to the said
    settlement agreement;" (2) evidence that Norwin's damages were
    caused by Shoff's alleged misrepresentations; (3) evidence that
    Norwin caused its own damages by failing to abide by the
    provisions of the Shoff Contracts; (4) evidence that Norwin
    breached its CM Contract with Foreman by assigning rights
    under that contract to Great American; and (5) the deposition
    testimony of Superintendent Boylan, indicating that Norwin
    27
    expected that "not one dime of school district money would be
    used toward payment of the judgment [in favor of GAIC]." At
    the same time, the District Court granted Norwin's motion in
    limine to exclude all evidence (1) that Shoff breached its
    contract with Norwin and/or committed fraud; (2) that Norwin
    failed to mitigate its damages by not pursuing claims against
    Shoff; (3) that Norwin failed to mitigate its damages by not
    contesting the amount of damages claimed by GAIC; and (4)
    that GAIC had a potential, but speculative, right of recovery
    against Shoff through a security interest granted to GAIC by
    Charles and Melanie Shoff.
    During trial, over Foreman's objection, the District Court
    took judicial notice of the uncontested judgment entered against
    Norwin in the amount of $467,342.05. Norwin's business
    manager testified that the amount of the judgment was equal to
    the amount of the retainage (5%) that was improperly released
    to Shoff. Other than introducing the certified payment
    applications documenting the release of the five percent (5%)
    retainage, Norwin presented no other evidence of its damages.
    Indeed, when instructing the jury, the District Court stated: "The
    Court has taken judicial notice of the judgment in favor of Great
    American Insurance Company against Norwin School District.
    Therefore, Norwin School District need not produce any other
    formal proof of the existence or amount of its damages." Not
    surprisingly, the jury returned a verdict in favor of Norwin and
    against Foreman in the amount of $467,347.05, plus six percent
    28
    (6%) interest from July 1, 2004.10 On April 19, 2007, consistent
    with the jury's verdict, the District Court entered judgment in
    favor of Norwin in the amount of $467,347.05, plus six percent
    (6%) interest from July 1, 2004. This timely appeal followed.11
    III. DISCUSSION
    In its notice of appeal filed May 10, 2007, Foreman
    stated that it was appealing from (1) the judgment entered on the
    jury's verdict; (2) the ruling on summary judgment docketed
    March 20, 2006, granting summary judgment in favor of GAIC
    against Norwin, in favor of Norwin against Foreman (as to
    liability), and in favor of Shoff against Foreman; 12 (3) the order
    docketed September 1, 2006, entering judgment in favor of
    GAIC and against Norwin in the amount of $467,342.05; and
    (4) the order docketed April 5, 2007, on motions in limine.
    10
    The jury awarded $467,347.05, which is five dollars
    more than the figure used in the September 1 judgment.
    Apparently, no one complained about the jury's error.
    11
    The district court exercised jurisdiction pursuant to 28
    U.S.C. §§ 1332(a) and 1367. Appellate jurisdiction exists under
    28 U.S.C. § 1291.
    12
    Although Foreman appealed from the order granting
    Shoff's motion for summary judgment against Foreman,
    Foreman has abandoned its appeal against Shoff. Foreman not
    only failed to address the Shoff ruling in its appellate brief, but
    it also advised this Court at oral argument that it was not
    pursuing its appeal against Shoff.
    29
    Because this is a diversity case, we apply the substantive law of
    Pennsylvania. Erie R.R. Co. v. Tompkins, 
    304 U.S. 64
    , 78-80
    (1938).
    A. Contract Interpretation
    The Pennsylvania Supreme Court summarized
    Pennsylvania law as it relates to contract interpretation in
    Murphy v. Duquesne University, 
    777 A.2d 418
    (Pa. 2001).
    The fundamental rule in interpreting the
    meaning of a contract is to ascertain and give
    effect to the intent of the contracting parties.
    The intent of the parties to a written agreement
    is to be regarded as being embodied in the
    writing itself. The whole instrument must be
    taken together in arriving at contractual intent.
    Courts do not assume that a contract's language
    was chosen carelessly, nor do they assume that
    the parties were ignorant of the meaning of the
    language they employed. When a writing is
    clear and unequivocal, its meaning must be
    determined by its contents alone.
    Only where a contract's language is
    ambiguous may extrinsic or parol evidence be
    considered to determine the intent of the parties.
    A contract contains an ambiguity if it is
    reasonably susceptible of different constructions
    and capable of being understood in more than
    one sense. This question, however, is not
    30
    resolved in a vacuum. Instead, contractual
    terms are ambiguous if they are subject to more
    than one reasonable interpretation when applied
    to a particular set of facts. In the absence of an
    ambiguity, the plain meaning of the agreement
    will be enforced. The meaning of an
    unambiguous written instrument presents a
    question of law for resolution by the court.
    
    Id. at 429-30
    (internal quotation marks and citations omitted).
    We exercise plenary review over questions of contract
    interpretation. Local Union No. 1992 v. Okonite Co., 
    189 F.3d 339
    , 341 (3d Cir. 1999).
    1. Reduction of Retainage
    An issue central to this case is whether GAIC's consent
    was required before retainage fell below five percent (5%) of
    the combined final prices of the two projects. The contracts
    provided that GAIC's consent was required before "final
    payment." Norwin and GAIC contend that the contracts
    required Norwin to retain a full five percent (5%) of the total
    contract prices until the time of final payment, at which time
    GAIC's consent was purportedly required.13 Foreman argues
    13
    It bears noting that all four of the parties to the various
    construction contracts—Shoff, Cunzolo, Foreman, and
    Norwin—participated in the decision to gradually reduce the
    retainage below five percent (5%).               Shoff submitted
    Applications for Payment with the reduced retainage amounts
    31
    otherwise. The District Court never addressed the issue,
    assuming, instead, that an amount equal to five percent (5%) of
    the total contract prices was a proper measure of what the final
    payment should have been.
    We begin with the Hillcrest contracts. The relevant
    language in the Shoff Contract–Hillcrest ("Hillcrest Contract")
    provided as follows:
    5.6 Subject to the provisions of the Contract
    Documents [namely, the Shoff Contract plus the
    General and Supplementary Conditions], the
    amount of each progress payment shall be
    computed as follows:
    5.6.1. Take that portion of the Contract Sum
    properly allocable to completed Work as
    determined by multiplying the percentage
    completion of each portion of the Work by the
    share of the total Contract Sum allocated to that
    portion of the Work in the Schedule of Value, less
    retainage of ten percent (10%). . . .
    5.6.2 Add that portion of the Contract Sum
    properly allocable to materials and equipment
    delivered and suitably stored at the site for
    listed; Foreman and Cunzolo both certified the Applications for
    Payment with the reduced retainage amounts; and Norwin paid
    Shoff amounts that clearly reflected the reduced retainage.
    32
    subsequent incorporation in the completed
    construction . . . , less retainage of ten percent
    (10%).
    ....
    Article 5.6 of the Hillcrest Contract thus set the amount of
    retainage applicable to progress payments at ten percent (10%).
    As provided in Article 5.7 of the Hillcrest Contract, the
    amount of retainage was subject to modification:
    5.7 The progress payment amount determined in
    accordance with Paragraph 5.6 shall be further
    modified under the following circumstances:
    5.7.1 Add, upon Substantial Completion of the
    Work, a sum sufficient to increase the total
    payments to ninety-five percent (95%) of the
    Contract Work, less such amounts as the
    Construction Manager recommends and the
    Architect determines for incomplete Work and
    unsettled claims.
    While it appears that Article 5.7.1 required the eventual release
    of one-half of the amounts previously retained, i.e., one-half of
    the ten percent (10%) retainage, the timing of the release was
    left unclear because the Hillcrest Contract failed to define the
    phrase "Substantial Completion of the Work."
    Article 5.8 of the Hillcrest Contract provided that "[i]f it
    33
    is intended, prior to Substantial Completion of the entire Work,
    to reduce or limit the retainage resulting from the percentages
    inserted in Subparagraphs 5.6.1. and 5.6.2 above, and this is not
    explained elsewhere in the Contract Documents, insert here
    provisions for such reduction or limitation." Because no
    percentage was inserted in Article 5.8 of the Hillcrest Contract,
    we look "elsewhere in the Contract Documents" for guidance.
    Indeed, in the Supplementary Conditions, retainage was
    specifically addressed as follows:
    9.3.6: The sum or sums withheld by [Norwin]
    from [Shoff] shall be 10 percent of the amount
    due [Shoff] until 50 percent of the Contract is
    completed. When the Contract is 50 percent
    complete, one-half of the amount retained by
    [Norwin] shall be released to [Shoff], provided
    that [Cunzolo] approves the Application for
    Payment; and provided further, that [Shoff] is
    making satisfactory progress and there is no
    specific cause for greater withholding.
    9.3.7: The sum or sums withheld by [Norwin]
    from [Shoff] after the Contract is 50 percent
    completed shall not exceed 5 percent of the value
    of completed work based on monthly progress
    payment requests.
    The first sentence in Article 9.3.6 made very clear that
    ten percent (10%) retainage was required until the project was
    fifty percent (50%) complete. The words "shall be 10 percent"
    were unequivocal. The second sentence in Article 9.3.6
    34
    provided that, when the project was fifty percent (50%)
    complete, and with certain provisos, one-half of the amounts
    previously retained "shall be released."        Such release
    presumably served to increase the total payments to Shoff to
    ninety-five percent (95%) of the then-completed work, leaving
    Norwin with five percent (5%) retainage at the fifty percent
    (50%) completion mark.
    In addressing the sums to be withheld after the work was
    fifty percent (50%) complete, Article 9.3.7 did not use the "shall
    be" language that was used in Article 9.3.6. Instead, Article
    9.3.7 provided that retainage "shall not exceed 5 percent" after
    the project was fifty percent (50%) complete. While the words
    "shall be 10 percent" drew a bright line, permitting no variation
    in the amount of retainage before the work was fifty percent
    (50%) complete, the words "shall not exceed 5 percent" left
    room for a range of retainage values—capped at five percent
    (5%)—after the work was fifty percent (50%) complete.
    The Supplementary Conditions were expressly
    incorporated into, and constituted a vital part of, the Hillcrest
    Contract. Like the General Conditions, the Supplementary
    Conditions supplied details that were not contained in the
    Hillcrest Contract itself. With respect to retainage, the detail
    provided by the Supplementary Conditions was not inconsistent
    with any other provision in the Hillcrest Contract. We must,
    accordingly, give effect to the retainage provision contained in
    the Supplementary Conditions. As noted above, that provision
    stated that "[t]he sum or sums withheld by [Norwin] from
    [Shoff] after the Contract is 50 percent completed shall not
    exceed 5 percent of the value of completed work." We cannot
    35
    assume that the language used in the retainage provision was
    chosen carelessly; we cannot ignore the difference in meaning
    between the words "shall not exceed" and the words "shall be;"
    and we cannot distort the unambiguous meaning of the words
    "shall not exceed." Applying—as we must—the rules of
    contract interpretation, we conclude that the Hillcrest Contract
    did not require five percent (5%) retainage at the time of final
    payment.14 Thus, after the projects were more than fifty percent
    (50%) complete, Foreman and Cunzolo were permitted to certify
    payments with less than five percent (5%) retainage, and Norwin
    was permitted to make payments to Shoff with less than five
    percent (5%) retainage, all without the consent of surety.
    We are not persuaded otherwise by the arguments of
    Norwin and GAIC. According to Norwin and GAIC:
    By stating that sums withheld "shall not exceed 5
    percent," Paragraph 9.3.7 is consistent with
    Paragraph 9.3.6 of the General [sic] Conditions
    and the payment provisions in the contracts
    themselves which directed that first 10% and then
    14
    Our conclusion is buttressed by Article 9.10.2 of the
    General Conditions, which addresses the conditions precedent
    to final payment as follows: "Neither final payment nor any
    remaining retained percentage shall become due until the
    Contractor submits to the Architect through the Construction
    Manager" certain documents. The phrase "any remaining
    retained percentage" suggests that the percentage of retainage at
    the time of final payment could vary.
    36
    5% shall be retained. In no way did Paragraph
    9.3.7 overrule the clear directive that retainage
    shall be 5%.
    In fact, there was no "clear directive" in the Hillcrest Contract
    that retainage "shall be 5%" at the time of final payment.
    Indeed, the only directive concerning a reduction in retainage
    appeared in Article 9.3.7 of the Supplementary Conditions, and
    that directive did not specify that retainage "shall be" five
    percent (5%) until the project was complete.
    Nor are we persuaded by Norwin's and GAIC's
    suggestion that the words "shall not exceed" should be construed
    to mean "shall be." The use of different language to address the
    same or similar issue—namely, retainage—strongly implies that
    a different meaning was intended. In fact, it would have been
    quite easy to draft the requirements for retainage, both above
    and below the fifty percent (50%) completion mark, using the
    same "shall be" language. The same language was not used,
    however; and we must assume that the choice of different words
    was deliberate. See, e.g, Penncro Assocs., Inc. v. Sprint
    Spectrum, L.P., 
    499 F.3d 1151
    , 1156-57 (10th Cir. 2007) (noting
    that, "[w]hen a contract uses different language in proximate
    and similar provisions, we commonly understand the provisions
    to illuminate one another and assume that the parties' use of
    different language was intended to convey different meanings");
    Taracorp, Inc. v. NL Industries, Inc., 
    73 F.3d 738
    , 744 (7th Cir.
    1996) (noting that "when parties to the same contract use such
    different language to address parallel issues . . ., it is reasonable
    to infer that they intend this language to mean different things");
    see also Commonwealth v. Berryman, 
    649 A.2d 961
    , 969 (Pa.
    37
    Super. Ct. 1994) (recognizing the rule that, when different
    language is used in parallel provisions of a statute, the
    provisions are intended to mean different things). In plain
    terms, by using the words "shall not exceed" instead of "shall
    be," Article 9.3.7 of the Supplementary Conditions set a ceiling
    on the monies to be retained during the second half of the
    project; it did not "direct" that retainage be five percent (5%) at
    the time of final payment.
    We are also unconvinced by Norwin's and GAIC's
    protection-of-the-surety argument. According to Norwin and
    GAIC, the only reasonable construction of the contract
    documents is a construction that affords meaningful security and
    protection to the surety—and that purportedly means requiring
    five percent (5%) retainage at the time of final payment.15 As
    15
    We note that a surety is not necessarily without
    protection when a construction contract makes retainage
    permissive rather than obligatory. A surety, for example, can
    protect itself by issuing a notice to the obligee that the contractor
    is in default and/or that claims have been made against the
    surety. Such notice places the obligee in the role of a
    stakeholder, with a duty to protect the surety by withholding
    payments to the contractor. See, e.g., American Ins. Co. v.
    United States, 
    62 Fed. Cl. 151
    , 155 (2004) (noting that, under
    the doctrine of equitable subrogation, "notice [by the surety] that
    the contractor is in default and that the surety is invoking its
    rights to the remaining contract proceeds converts the [obligee]
    to a stakeholder with duties to the surety," allowing the surety to
    sue the obligee for recovery of contract funds owed but not yet
    38
    the case law makes clear, however, the Court may not rewrite
    the contracts to provide protections that the contracts did not
    themselves provide. See, e.g., Meeting House Lane, Ltd. v.
    Melso, 
    628 A.2d 854
    , 857 (Pa. Super. Ct. 1993) (noting that "the
    parties have the right to make their own contract, and it is not
    the function of a court to rewrite it or to give it a construction in
    conflict with the accepted and plain meaning of the language
    used").
    Norwin and GAIC cite three cases in support of their
    argument that Norwin "had no discretion" to reduce retainage
    below five percent (5%) prior to final payment. Prairie State
    Nat'l Bank of Chicago v. United States, 
    164 U.S. 227
    (1896);
    Nat'l Sur. Corp. v. United States, 
    118 F.3d 1542
    (Fed. Cir.
    1997); Transamerica Premier Ins. Co. v. United States, 32 Fed.
    Cl. 308 (1994). None of the cited cases involved the issues
    and/or the contract terms that are before this Court. In Prairie
    State National 
    Bank, 164 U.S. at 230-40
    , the Supreme Court
    considered the relative priorities of parties competing for
    retainage held by the government under a construction contract.
    In National Surety 
    Corp., 118 F.3d at 1545
    , the Federal Circuit
    held that, by improperly releasing retainage in violation of clear
    contractual terms, the government incurred liability to the
    surety. In Transamerica Premier Insurance 
    Co., 32 Fed. Cl. at 313-16
    , the Court of Federal Claims held that the government
    was liable to the surety for payments that the government
    wrongly issued to the contractor after the government was put
    on notice regarding the contractor's financial inability to
    complete the contract. To be sure, in each of these cases, the
    courts recognized, as a general proposition, that contract
    retainage serves to protect not only the obligee but also the
    paid). If, as GAIC's representative testified, GAIC knew before
    the projects were completed that there were "issues on the job,"
    GAIC could have protected itself by notifying Norwin.
    39
    surety. None of these cases, however, supports Norwin's and
    GAIC's assertion that, under the terms of the Contract
    Documents at issue here, Norwin was required to retain five
    percent (5%) of the contract price until the time of final
    payment.
    The Sheridan Contract differed from the Hillcrest
    Contract in one important respect: namely, the words "[r]educe
    to 5% at 50% of work installed" were inserted in Article 5.8 of
    the Sheridan Contract to explain any "[r]eduction or limitation
    of retainage." In contrast, no provision for reduction or
    limitation of retainage was inserted in Article 5.8 of the Hillcrest
    Contract. We must decide whether the added insertion in the
    Sheridan Contract leads to a different conclusion regarding the
    amount of retainage that was required at the time of final
    payment.
    In construing the Sheridan Contract, we must consider
    the entirety of the contract documents, including the
    Supplementary Conditions; and we must read the contractual
    provisions to avoid ambiguities if possible. Masters v. Celina
    Mut. Ins. Co., 
    224 A.2d 774
    , 115 (Pa. Super. Ct. 1966). We
    must also keep in mind that specific provisions ordinarily
    control more general provisions. In re Alloy Mfg. Co.
    Employees Trust, 
    192 A.2d 394
    , 396 (Pa. 1963).
    Here, the words inserted in Article 5.8 of the Sheridan
    Contract—"[r]educe to 5% at 50% of work installed"—must be
    read in conjunction with the more detailed retainage provisions
    contained in the Articles 9.3.6 and 9.3.7 of the Supplementary
    Conditions. By themselves, the words "[r]educe to 5% at 50%
    of work installed" were ambiguous. For example, those words
    could have meant that any limitation—or ceiling—on retainage
    was reduced to five percent (5%) at the fifty percent (50%)
    completion mark, or those words could have meant that
    40
    retainage was reduced to, and would remain at, five percent
    (5%) at and after the fifty percent (50%) completion mark. Any
    ambiguity was eliminated, however, if the words were
    considered in conformity with the more detailed Supplementary
    Conditions. The Supplementary Conditions provided that, while
    retainage was to be reduced to five percent (5%) when work was
    fifty percent (50%) complete, retainage was thereafter to be
    capped at five percent (5%). If the words "[r]educe to 5% at
    50% of work installed" were construed to mean that retainage
    was limited to, or could not exceed, five percent (5%) after the
    project was fifty percent (50%) complete, the words would be
    consistent with the clear provisions contained in Articles 9.3.6.
    and 9.3.7. So construed, the insertion did nothing more than
    provide, in broad terms, what the Supplementary Conditions
    provided more explicitly.
    In sum, we find that the Supplementary
    Conditions—specifically Articles 9.3.6 and 9.3.7—controlled
    the matter of retainage on both the Sheridan and the Hillcrest
    projects. Because the Supplementary Conditions did nothing
    more than place a five percent (5%) ceiling on retainage once
    the projects were fifty percent (50%) complete, we
    conclude—as to both projects—that five percent (5%) retainage
    was not required at the time of final payment, that GAIC's
    consent was not required before retainage could be reduced to
    amounts less than five percent (5%), and that Foreman,
    accordingly, did not breach its contract with Norwin by failing
    to obtain GAIC's consent before certifying Shoff's progress
    payment applications reflecting retainage of less than five
    percent (5%).
    2. Consent of Surety
    Article 9.10.2 of the General Conditions provided that
    "[n]either final payment nor any remaining retained percentage
    41
    shall become due until the Contractor submits to the Architect
    through the Construction Manager . . . consent of surety, if any,
    to final payment." Foreman now argues—as it argued before the
    district court—that the Contract Documents required Shoff to
    submit the consent of surety if, and only if, the surety reserved
    such right in the bond documents. In this case, the bond
    documents were silent as to any consent-of-surety requirement.16
    In support of its argument, Foreman cites Exchange
    National Bank of Chicago v. United States Fidelity & Guaranty
    Co., No. 81C7119, 
    1985 WL 2123
    , *1 (N.D. Ill. July 25, 1985).
    In that case, the court construed a contract provision stating that
    "[n]either the final payment nor the remaining retained
    percentage shall become due until the Contractor submits to the
    Architect . . . consent of the surety, if any, to final payment." 
    Id. The court
    concluded that the contract provision itself did not
    require the surety's consent to final payment. Instead, the court
    determined that the words "if any" in the phrase "consent of
    surety, if any, to final payment" indicated that a consent-of-
    surety requirement must be found elsewhere, perhaps in the
    bond documents. 
    Id. We know
    of no other court that has followed the decision
    in Exchange National Bank. Nor are we persuaded to follow the
    decision ourselves. Indeed, we conclude that the words "if any"
    in the phrase "consent of surety, if any, to final payment" were
    meant to qualify the word "surety," meaning that, if and when a
    surety was involved, the surety's consent to final payment was
    16
    The record establishes that Foreman's project
    managers were well aware that the surety's consent was needed
    as part of the close-out documentation.
    42
    required.17 Here, a surety—GAIC—was involved, and GAIC's
    consent to final payment was required. See Capital Indemnity
    Corp. v. Price Municipal Corp., No. 2:99cv0141, 
    2002 WL 818064
    (D. Utah April 25, 2002) (assuming, without discussion,
    that the surety's consent to final payment was required when the
    contract provided that "final Application for Payment shall be
    accompanied . . . by . . . consent of the surety, if any, to final
    payment").
    3. Final Payment
    Because the Shoff Contracts required the consent of
    surety to "final payment," we must consider the meaning of the
    words "final payment." Unfortunately, the contract documents
    provided no clear definition of those words. Article 6 of the
    Shoff Contracts provided that final payment constituted "the
    entire unpaid balance of the Contract Sum." Article 9.10.1 of
    the General Conditions provided that the final Certificate of
    Payment should state "the entire balance found to be due the
    Contractor." Article 9.10.2 of the General Conditions provided
    that "[n]either final payment nor any remaining retained
    percentage shall become due until . . . consent of surety, if any,
    to final payment" was obtained. In essence, the contract
    documents allowed "final payment" to mean whatever the final
    Certificate of Payment said it was.
    Foreman contends that, as to the Hillcrest project, "final
    payment" was $78,362.65, the amount requested by Shoff on the
    17
    We note that AIA Form G706, entitled "Contractor's
    Affidavit of Payment of Debts and Claims," stated that
    "[w]henever Surety is involved, Consent of Surety is required."
    Although AIA Form G706 was used in this case, the form was
    not incorporated into the Contract Documents and was,
    therefore, not binding on Foreman.
    43
    Final Application for Payment. That amount equaled the
    difference between the final contract price ($5,615,267.11) and
    the total amounts previously paid ($5,536,904.46). Shoff's Final
    Application for Payment was certified by Foreman and paid by
    Norwin on December 16, 2003. The check issued by Norwin on
    that date was marked "FINAL." We agree with Foreman that
    "final payment" on the Hillcrest project was $78,362.65.
    As to the Sheridan project, Foreman argues that no "final
    payment" was ever made. In support of its argument, Foreman
    points to the $5,000.00 that was "retained" from Shoff's final
    Application for Payment. Indeed, Shoff requested a final
    payment of $24,961.17, the difference between the final contract
    price ($3,731,574.000 and the total amounts previously paid
    ($3,706,612.83). While Foreman certified the amount requested
    by Shoff, Norwin paid Shoff only $19,961.17 (by check dated
    November 26, 2003). According to Foreman, Norwin withheld
    the $5,000.00 for uncompleted work. The record is otherwise
    silent about what alerted Norwin to the need to withhold a
    portion of the certified amount.
    That Norwin withheld $5,000.00 from the amount
    requested by Shoff in its final Application for Payment does not
    change the fact that the final Certificate of Payment reflected a
    "final payment" of $24,961.17, the remainder of what was owed
    under the Sheridan Contract. Foreman certified final payment
    in the amount of $24,961.17, and—under the Contract
    Documents—that certification constituted a representation that
    the consent of surety had been obtained. Thus, for purposes of
    the consent-of-surety requirement on the Sheridan project, "final
    payment" was $24,961.17.
    B. Breach
    Foreman contends that the District Court erred in
    44
    entering summary judgment in Norwin's favor on the issue of
    Foreman's liability for breach of contract. The Magistrate Judge
    recommended that Norwin's motion for summary judgment be
    granted on the basis that there were "no genuine issues of
    material fact that Foreman failed to provide close-out
    documents, including the Consent of Surety." The District
    Court adopted the Magistrate Judge's recommendation regarding
    Foreman's liability for breach of contract. Because breach of a
    contract is essentially a question of contract interpretation, our
    review is plenary. St. John Mortgage Co. v. United States
    Fidelity and Guar. Co., 
    897 F.2d 1266
    , 1268 (3d Cir. 1990).
    Foreman admits that it failed to obtain GAIC's consent
    before it certified Shoff's final Applications for Payment. Under
    Articles 9.10.1 and 9.10.2 of the General Conditions, Foreman
    was required to obtain GAIC's consent as a condition precedent
    to final payment to Shoff. By issuing final Certificates of
    Payment without such consent, Foreman clearly breached the
    terms of the contract documents.
    Foreman contends that, because Norwin itself breached
    the terms of the contracts, Norwin should not be permitted to
    demand Foreman's strict adherence to the contractual terms.
    Foreman refers specifically to Norwin's act of issuing final
    payment to Shoff on the Hillcrest project without first obtaining
    Cunzolo's certification. The Magistrate Judge rejected this
    argument, stating, without explanation, that "Great American's
    damages were not the result of Norwin's failure to obtain
    Cunzolo's certification for the Final Payment Application on the
    Hillcrest project." The Magistrate Judge did not mention that,
    as to the final Certificate of Payment, the contract documents
    treated Cunzolo and Foreman alike; both were required to
    certify that all conditions precedent to final payment—which
    included having the consent of surety—had been fulfilled.
    45
    In practice, Cunzolo apparently did not review the close-
    out documentation before reviewing and certifying Shoff's final
    Applications for Payment.          According to Hank Tkacik
    ("Tkacik"), the Cunzolo representative responsible for signing
    the various Applications for Payment, Foreman did not forward
    the close-out documentation to Cunzolo because of its volume.
    Thus, Tkacik's review of the final Applications for Payment did
    not include verification that all of the close-out documentation
    had been submitted. The procedure used on both projects was
    as follows: (1) Foreman would review the Applications for
    Payment, certify payment, then send the certified Applications
    for Payment to Norwin; (2) upon receipt of the certified
    Applications for Payment, Norwin would notify Tkacik, who
    would go to Norwin's offices to sign the Applications; and (3)
    Norwin would then issue payment to Shoff. Tkacik had no
    recollection about why he failed to sign the final Application for
    Payment on the Hillcrest project. He stated that, consistent with
    his certification on the Sheridan project, he would have signed
    the final Application for Payment on Hillcrest because Shoff's
    work had progressed to a point entitling it to final payment.
    We are unconvinced that the District Court erred in
    rejecting Foreman's attempt to excuse its breach by pointing to
    Norwin's failure to obtain Cunzolo's signature before issuing
    final payment on the Hillcrest project. Norwin, Cunzolo, and
    Foreman all apparently acquiesced in a procedure that resulted
    in Foreman's being the only party that, in fact, reviewed the
    close-out documentation. Foreman cannot now complain about
    a procedure that it endorsed.
    C. Damages
    Foreman challenges a number of the District Court's
    evidentiary rulings with respect to damages. This Court
    generally reviews evidentiary decisions for abuse of discretion;
    46
    however, to the extent an evidentiary decision involves a legal
    component, this court's review is plenary. Inter Med. Supplies,
    Ltd. v. EBI Med. Systems, Inc., 
    181 F.3d 446
    , 464 (3d Cir.
    1999). An erroneous evidentiary ruling will be considered
    harmless if "it is highly probable that the district court's [ruling]
    did not affect [the party's] substantial rights." Becker v. ARCO
    Chem. Co., 
    207 F.3d 176
    , 179 (3d Cir. 2000).
    Among other things, Foreman challenges the District
    Court's motion-in-limine ruling that entry of judgment against
    Norwin in GAIC's first-party action was admissible in Norwin's
    third-party action as evidence of damages caused by Foreman.
    At trial, consistent with its ruling in limine, the District Court
    took judicial notice of the uncontested judgment against Norwin
    in the amount of $467,342.05, then instructed the jury as
    follows: "The Court has taken judicial notice of the judgment in
    favor of Great American Insurance Company against Norwin
    School District. Therefore, Norwin School District need not
    produce any other formal proof of the existence or amount of its
    damages."
    We note initially that Foreman was not a party to the
    uncontested judgment against Norwin. Accordingly, the
    judgment was not binding on Foreman. The Magistrate Judge
    correctly explained what the District Court failed to recognize:
    "Norwin cannot sustain th[e] burden [of proving its damages] by
    referring to a judgment entered against it, with its consent, by
    Great American. Although Great American and Norwin can
    agree to Norwin's liability, such an agreement is not binding on
    third parties."
    Furthermore, the amount of the judgment was the
    unchallenged product of GAIC's and Norwin's behind-the-
    scenes Settlement Agreement. Norwin agreed not to oppose
    GAIC's motion for summary judgment in the amount of
    47
    $467,362.06; in return, GAIC agreed not to seek satisfaction of
    the judgment from Norwin unless Norwin first obtained a
    judgment and received payment from Foreman. From Norwin's
    perspective, it mattered little, if at all, what amount was plugged
    into an uncontested judgment that required no payment from
    Norwin's pockets.
    Indeed, knowing that it would never have to pay the
    judgment, Norwin had little incentive to challenge the amount
    of damages sought by GAIC. That amount, moreover, was
    subject to at least one meritorious defense that Norwin never
    raised. Norwin could have challenged, for example, GAIC's
    erroneous interpretation of the contract language. As we have
    already explained, the contract documents did not require
    GAIC's consent before retainage was reduced to amounts less
    than five percent of the total contract prices. GAIC's consent
    was required before "final payment;" and—for consent-of-surety
    purposes—"final payment" was $78,362.65 on the Hillcrest
    project and $24,961.17 on the Sheridan project. The combined
    total of improperly released payments was thus
    $103,323.82, not $467,362.06.18 Norwin was certainly free to
    18
    There may have been other meritorious defenses as
    well. For example, GAIC's actual damages would be less than
    $103,323.82 if the evidence revealed that GAIC was not
    prejudiced by the unauthorized release of final payments to
    Shoff. In National Security Corp., the court explained that, if
    the unauthorized payments "were expended for the purposes of
    the contract so that the extent of the surety's subsequent
    performance was reduced thereby, any injury to the surety would
    to that extent be mitigated." 
    Id. at 1548
    (concluding that a
    surety seeking money damages for an obligee's improper release
    of funds must establish prejudice); Ramada Devel. Co. v. United
    States Fidelity & Guar. Co., 
    626 F.2d 517
    , 521 (6th Cir. 1980)
    48
    agree to an inflated judgment, but that inflated judgment was not
    an appropriate—or relevant—measure of damages caused by
    Foreman.19 Clearly, the District Court abused its discretion in
    admitting GAIC's uncontested judgment as evidence of damages
    caused by Foreman.
    Not only did the District Court admit, over Foreman's
    objection, the uncontested judgment as the sole evidence of
    Norwin's damages; it also denied Foreman's request to introduce
    evidence to challenge that judgment. By doing so, the District
    Court, in effect, directed a verdict against Foreman in an amount
    (noting that a compensated surety is not entitled to pro tanto
    discharge following improperly released retainage unless the
    surety experiences some injury, loss or prejudice). Here,
    Charles Shoff stated during his deposition that the payments his
    company received from Norwin were used to pay subcontractors
    and vendors.      Shoff also stated that the projects lost
    approximately $800,000—roughly the amount GAIC had to pay
    on the bonds. Such deposition testimony tends to demonstrate
    that GAIC's bond payments were the result of project losses and
    not the result of Norwin's improper release of the final
    payments.
    19
    While we agree that the $467,362.05 judgment was an
    improper measure of damages for purposes of Norwin's suit
    against Foreman, we reject Foreman's argument that the District
    Court erred in entering the $467,342.05 judgment in GAIC's
    first-party action against Norwin. We cannot fault the District
    Court for entering summary judgment against Norwin when
    Norwin raised no opposition to the motion and, indeed,
    expressly advised the District Court that it did not oppose entry
    of the $467,342.05 judgment. Norwin picked its own poison in
    that regard.
    49
    that not only was unsupported by the contract language but
    may also have been unsupported by the facts.
    In particular, Foreman wanted to introduce evidence to
    prove that, in fact, Norwin suffered no damages at all and that
    Norwin received the benefit of its bargain at no more than the
    contract price. See Ferrer v. Trustees of Univ. of Pennsylvania,
    
    825 A.2d 591
    , 609 (Pa. 2002) (explaining that damages for
    breach of contract are typically measured by the non-breaching
    party's expectation interest, the interest—that is—in having the
    benefit of its bargain by being put in as good a position as it
    would have been in had the contract not been breached). In
    rejecting Foreman's request to introduce the Settlement
    Agreement as evidence that Norwin would never have to pay a
    dime to GAIC, the District Court concluded that "it is not
    necessary for Norwin to actually pay the judgment to suffer
    'actual damages' or to maintain its damages claim against
    Foreman." The District Court based its conclusion on two
    Pennsylvania cases, Ammon v. McCloskey, 
    655 A.2d 549
    (Pa.
    Super. Ct. 1995), and Gray v. Nationwide Mutual Insurance Co.,
    
    223 A.2d 8
    (1966), both of which involved assignees who
    stepped into the shoes of assignors to bring suit against third
    parties who caused damage—in tort—to the assignors in
    amounts determined by juries in contested proceedings. No
    such circumstances exist in this case.20
    In Gray, the plaintiff brought suit against an insured for
    20
    We note that, among other differences, there was no
    assignment of Norwin's breach-of-contract claim to GAIC. As
    stated by the District Court in its order on motions in limine:
    "There is no assignment provision in the settlement agreement
    and there is no evidence of record that any such assignment
    [from Norwin to GAIC] took place."
    50
    personal injuries resulting from an automobile accident. The
    insurance company undertook the defense and a jury verdict in
    excess of the policy limits was returned in the plaintiff's favor.
    After the insurance company paid the policy limits, the plaintiff
    demanded the unpaid balance of the judgment from the insured.
    The insured then assigned to the plaintiff his right to assert a bad
    faith claim against the insurer. The assignment agreement
    provided that, regardless of the outcome of a bad faith action,
    any obligation of the insured to the plaintiff would be satisfied.
    The plaintiff, as assignee, then brought suit against the insurer.
    After the trial court dismissed the assignee's bad faith claim
    against the insurer, the plaintiff appealed.
    When the Gray case reached the Supreme Court of
    Pennsylvania, the first issue addressed was whether the insured
    was required to pay the balance due on the judgment as a
    prerequisite to a bad faith action against the insurer. In deciding
    that no such actual payment was required, the supreme court
    explained that, among other things, adoption of a non-payment
    rule would
    prevent[] an insurer from benefiting from the
    impecuniousness of an insured who has a
    meritorious claim but cannot first pay the
    judgment imposed upon him. . . . Were payment
    the rule, an insurer with an insolvent insured
    could unreasonably refuse to settle, for, at worst,
    it would only be liable for the amount specified by
    the policy. To permit this would be to impair the
    usefulness of insurance for the poor man.
    
    Id. at 10
    (internal quotation marks and citation omitted). The
    supreme court also noted that "such [non-payment] view
    recognizes that the fact of entry of the judgment itself against
    the insured constitutes a real damage to him because of the
    51
    potential harm to his credit rating." 
    Id. In Ammon,
    a passenger who was injured in an automobile
    accident sued the driver of the vehicle. The driver's lawyer
    failed to raise a meritorious defense at trial, and a substantial
    judgment—on a jury verdict—was entered against the driver in
    favor of the passenger. The driver fired his lawyer, then
    retained new counsel who negotiated a settlement between the
    driver and the passenger. In exchange for the passenger's
    promise not to execute the judgment against the driver, the
    driver assigned to the passenger the driver's claim for legal
    malpractice against the driver's former lawyer. Relying on
    Gray, the Ammon court held that actual payment of the
    judgment by the driver was not a prerequisite to the assignee's
    legal malpractice claim against the lawyer. The court explained:
    "The lawyer occupies no less a fiduciary relationship to the
    client than an insurer occupies with respect to its insured, and
    the judgment entered against a client constitutes no less a real
    damage than the entry of a judgment against an insured." 
    Id. at 553.
    We are unpersuaded that the non-payment view adopted
    in Gray (and followed in Ammon) applies in this case. In Gray,
    the defendant in the original action (the insured) suffered a
    litigated judgment, the amount of which resulted, in part, from
    the alleged tortious conduct of the defendant in the second
    action (the insurance company that defended the original
    action). The insured satisfied the judgment by assigning to the
    plaintiff the insured's right of action against the insurance
    company. Fashioning a rule to fit the circumstances, the
    Supreme Court of Pennsylvania would not permit the insurance
    company to raise as a defense in the second action the insured's
    non-payment of the judgment because, to do so, would reward
    the insurance company whose tortious conduct contributed to
    52
    the harm suffered by the insured. The circumstances in Ammon
    were similar. In contrast, the original defendant in this
    case—Norwin—agreed to entry of an uncontested judgment, all
    the while knowing that it would never have to pay the judgment
    from its own pockets.          The defendant in the second
    action—Foreman—did not participate in or have any knowledge
    of the agreement that resulted in the uncontested judgment. The
    Gray rule simply does not fit the circumstances here, and the
    District Court's reliance on those cases was misplaced.
    In its breach of contract action against Foreman, Norwin
    was required to prove that it did not get the benefit of its
    bargain. Foreman was entitled to defend by showing otherwise.
    That Norwin had no obligation to pay GAIC any monies for the
    two school projects was relevant to the issue of Norwin's
    damages, and Foreman should have been permitted to introduce
    evidence to that effect. The District Court abused its discretion
    by ruling to the contrary.
    In its motion for summary judgment, Norwin argued to
    the District Court that the "[d]amage incurred by the School
    District is the amount that it is required to pay twice resulting
    from Foreman's failure to obtain consents of surety."21 In fact,
    the record is devoid of evidence that Norwin has been, or ever
    21
    Norwin's "pay-twice" argument was first advanced to
    the District Court before the Settlement Agreement was
    executed. The District Court entered summary judgment months
    after the Settlement Agreement was executed, without being
    informed that, pursuant to the terms of the Settlement
    Agreement, Norwin would never have to pay any monies twice.
    At oral argument, this panel pointed out that, by failing to
    inform the District Court about the changed circumstances,
    Norwin caused the District Court to enter summary judgment
    based, in part, on misrepresentations.
    53
    will be, under an obligation to pay any amounts twice for its
    school projects. At oral argument before this panel, Norwin's
    counsel was asked to explain what damages Norwin suffered.
    Counsel did not reiterate the "pay twice" argument. She,
    instead, responded by saying that there was a judgment against
    Norwin that could affect the school's credit rating.22 She gave
    no other explanation for Norwin's damages.
    When a District Court has abused its discretion in
    admitting, or not admitting, evidence, and has affected a party's
    substantial rights in doing so, we ordinarily remand the case to
    the District Court for further proceedings. Here, we see no need
    for remand. To succeed on its breach-of-contract claim against
    Foreman, Norwin was required to prove that it was damaged,
    that it did not receive the benefit of its bargain. We have said
    that Norwin cannot rely on GAIC's uncontested judgment to
    prove that it was damaged by Foreman. For the same reasons,
    the effect—if any—of that judgment on Norwin's credit rating
    also cannot be attributed to Foreman. In addition, the record
    establishes that Norwin has not paid, and will not be required to
    pay, anything to GAIC. The record is otherwise devoid of
    evidence that Norwin did not get exactly what it bargained
    for—two completed school projects at the contract price.23
    22
    Norwin's counsel did not mention that the judgment
    against Norwin will be satisfied—without Norwin's having to
    pay one dime—once Norwin's action against Foreman is
    resolved. The effect, if any, on the school's credit rating will be
    brief.
    23
    We note, moreover, that even though Norwin failed to
    complain about defective and non-conforming work within the
    one-year post-completion maintenance bond period, Shoff
    nevertheless made the needed repairs—at no cost to Norwin—as
    the Settlement Agreement required.
    54
    Because the record establishes that Norwin suffered no damages
    as a result of Foreman's breach, we think a remand would be
    fruitless.
    IV. CONCLUSION
    The facts in this case are singular, the case history
    bizarre. Briefly, Foreman breached its contract with Norwin by
    certifying final payment on two construction projects without
    obtaining the consent of surety. Such breach left Norwin
    exposed to potential damages. The issue of Norwin's damages
    was tried before a jury, but the District Court's evidentiary
    rulings precluded a fair trial for Foreman. Consequently, the
    results of that trial—both the District Court's judgment on
    damages as well as the jury's verdict upon which the damages
    judgment was based—cannot stand. The record, moreover,
    contains no evidence to establish that Norwin was, in fact,
    damaged by Foreman's breach. Accordingly, we will vacate the
    jury's verdict and the District Court's judgment and will remand
    to the District Court with directions to enter judgment in
    Foreman's favor.
    NYGAARD, Circuit Judge, dissenting
    Because the majority’s conclusion collides with the plain
    language of the contract, I must dissent. I shall be brief:
    In ruling that Norwin did not have any actual damages,
    the majority relies heavily upon a settlement agreement between
    Norwin and Great American that was properly excluded in an
    evidentiary ruling by the District Court because it was not
    relevant to the matter between Norwin and Foreman. Moreover,
    Great American’s conditional forbearance of its judgment
    55
    against Norwin did not negate Norwin’s obligation to satisfy the
    judgment. The result reached by the majority now allows
    Foreman to escape the consequences of its breach, leaving either
    Norwin or Great American to suffer the damages.
    Moreover, the majority posits that, even if damages had
    been awarded, the amount of damages could not exceed the
    “final payment” made by Norwin to the contractor. I think the
    majority misinterprets the language of the contract. The contract
    required Foreman to obtain the consent of Great American
    before releasing the final payment and retainage. The majority
    misinterprets the contract to conclude that Great American’s
    authority was limited to signing off only on the final payment.
    In so doing, the majority misapprehends an important factual
    basis for the damages.
    Because, in my view, the majority has erred and the
    District Court was correct, I must respectfully dissent.
    56