Milton Regional Sewer Authority v. Travelers Casualty & Surety Co. of America , 648 F. App'x 215 ( 2016 )


Menu:
  •                                                               NOT PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    ________________
    No. 14-4575
    ________________
    MILTON REGIONAL SEWER AUTHORITY,
    Appellant
    v.
    TRAVELERS CASUALTY & SURETY CO. OF AMERICA
    ________________
    On Appeal from the United States District Court
    for the Middle District of Pennsylvania
    (D.C. Civil No. 4-13-cv-02786)
    District Judge: Honorable Matthew W. Brann
    ________________
    Argued: October 29, 2015
    Before: GREENAWAY, JR., SCIRICA, and ROTH, Circuit Judges
    (Filed: April 28, 2016)
    Preston L. Davis, Esq. [ARGUED]
    Davis Davis & Kaar
    37 Arch Street
    P.O. Box 319
    Milton, PA 17847
    Counsel for Appellant
    Benjamin E. Gordon, Esq.
    Patrick R. Kingsley, I, Esq. [ARGUED]
    Karl S. Myers, Esq.
    Stradley Ronon Stevens & Young, LLP
    2005 Market Street
    Suite 2600
    Philadelphia, PA 19103
    Counsel for Appellee
    ________________
    OPINION*
    ________________
    SCIRICA, Circuit Judge
    Milton Regional Sewer Authority (“Milton”) appeals from an order of the District
    Court dismissing its complaint against Travelers Casualty and Surety Company of
    America (“Travelers”). For the reasons detailed below, we will affirm.
    I.
    Milton is a municipal authority located in Milton, Pennsylvania. On July 25, 2011,
    it entered into a construction contract with Ankiewicz Enterprises (“Ankiewicz”) for a
    public works project. The contract was secured by a performance bond issued by
    Travelers. The contract with Ankiewicz contains several provisions specifying when and
    how Milton could terminate the contract. The provision relevant to this appeal is
    commonly referred to as a right-to-cure provision. It states:
    [Ankiewicz’s] services will not be terminated if [Ankiewicz] begins within
    seven days of receipt of notice of intent to terminate to correct its failure to
    perform and proceeds diligently to cure such failure within no more than 30
    days of receipt of said notice.
    In other words, before Milton could terminate the contract, it was required to give
    *
    This disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not
    constitute binding precedent.
    2
    Ankiewicz thirty days to fix whatever problem had arisen.
    The bond likewise contains several provisions specifying when and how an
    obligation could arise for Travelers. The provision relevant to this appeal is the Owner
    Default provision, which states that no obligation for Travelers can arise if Milton
    defaults on its contract with Ankiewicz. The bond defines default as the “[f]ailure of
    [Milton] . . . to pay [Ankiewicz] as required by the Contract or to perform and complete
    or comply with the other terms thereof.” In other words, no obligation could arise for
    Travelers if Milton failed to comply with the terms of its contract with Ankiewicz,
    including the right-to-cure provision.
    After the contract and the bond were finalized, Ankiewicz began working on the
    project. Milton quickly became unsatisfied with the work being done. On February 20,
    2012, Milton sent a letter to Ankiewicz ordering it to suspend work on the project.
    Ankiewicz responded on February 24, offering to correct any failures in the work it had
    performed. On February 28, Milton rejected that offer, forbidding Ankiewicz from
    performing any more work under the contract. After a meeting between the parties,
    Milton terminated the contract without affording Ankiewicz an opportunity to fix its
    allegedly defective work.
    Following the termination of the contract, Milton hired another construction firm
    to complete the project, incurring additional costs as a result. Milton asserted a bond
    claim against Travelers for these additional costs, and after Travelers refused to pay,
    Milton filed a complaint in state court. Travelers removed the case to federal court, and
    moved to dismiss the complaint.
    3
    The District Court granted Travelers’ motion to dismiss. Its opinion included two
    separate holdings. First, the court held Milton did not follow the right-to-cure provision
    of the contract. Milton Reg’l Sewer Auth. v. Travelers Cas. & Sur. Co. of Am., No. 4:13-
    CV-2786, 
    2014 WL 5529169
    , at *3 & n.1 (M.D. Pa. Nov. 3, 2014). That holding is not
    on appeal.
    Second, the court held Milton had no valid reason under Pennsylvania law to
    violate the right-to-cure provision. Id. at *8. It acknowledged Pennsylvania allows parties
    to violate right-to-cure provisions in cases of an extreme breach. Id. at *5 (citing LJL
    Transp., Inc. v. Pilot Air Freight Corp., 
    962 A.2d 639
     (Pa. 2009)). But the court held
    Milton “failed to plead that Anki[ew]icz materially breached the contract such that the
    material breach would excuse [Milton] from complying with the contractually agreed to
    termination procedures.” Milton, 
    2014 WL 5529169
    , at *8. Because Milton failed to
    comply with the terms of the contract, Travelers’ obligation under the bond was not
    triggered, and the complaint against Travelers was dismissed with prejudice. Id. at *9.
    Following the dismissal, Milton filed this timely appeal.
    II.1
    1
    The District Court had jurisdiction under 
    28 U.S.C. § 1332
    (a)(1) and we have
    jurisdiction under 
    28 U.S.C. § 1291
    . We exercise plenary review of a district court’s
    ruling on a motion to dismiss under Federal Rule of Civil Procedure 12(b)(6). Pearson v.
    Sec’y Dep’t of Corr., 
    775 F.3d 598
    , 601 (3d Cir. 2015). “To survive a motion to dismiss,
    a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to
    relief that is plausible on its face.’” Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009) (quoting
    Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    , 570 (2007)).
    4
    Pennsylvania follows the general rule of contract law that “a material breach of a
    contract relieves the non-breaching party from any continuing duty of performance
    thereunder.” LJL Transp., 962 A.2d at 648. But this general rule gives way to a more
    specific one “if the contract includes an express provision granting the breaching party
    the opportunity to cure before the contract is terminated.” Id. Such a contract may only be
    terminated without providing an opportunity to cure “when there is a material breach of
    the contract so serious it goes directly to the heart and essence of the contract, rendering
    the breach incurable . . . .” Id. at 641. The breach must be so severe that “requiring . . .
    notice before termination . . . would be a useless gesture.” Id. at 652.
    A typical example of a breach that goes directly to the essence of a contract is
    fraud. Indeed, the only case in which the Pennsylvania Supreme Court found a breach to
    be severe enough to justify immediate termination of a contract with a right-to-cure
    provision involved fraudulent conduct by one of the contracting parties. Id. at 642-43.
    Moreover, the court’s opinion in that case relied heavily on two cases from other
    jurisdictions that likewise involved fraudulent conduct by a contracting party. See id. at
    648, 650 (citing Olin v. Central Indus., Inc., 
    576 F.2d 642
     (5th Cir. 1978), and Larken v.
    Larken City Ltd. P’ship, 
    589 N.W.2d 700
     (Iowa 1998)). The court recognized that, when
    one contracting party defrauds the other, the breach “is so fundamentally destructive, it
    understandably and inevitably causes the trust which is the bedrock foundation and
    veritable lifeblood of the parties’ contractual relationship to essentially evaporate.” LJL
    Transp., 962 A.2d at 652. Thus, there is no need to allow for a right to cure in such
    instances.
    5
    Milton’s complaint does not allege so severe a breach. Even assuming, as we
    must, the allegations in Milton’s complaint are true, and drawing all inferences in
    Milton’s favor, Milton does not allege a breach “so serious it goes directly to the heart
    and essence of the contract, rendering the breach incurable.” Id. at 641. The complaint
    does not allege that Ankiewicz defrauded or deceived Milton. Instead, it alleges various
    deficiencies in the work performed by Ankiewicz which, taken together, amount to an
    allegation that Ankiewicz performed poorly, even quite poorly. But unlike fraud, poor
    performance is not incurable. In fact, Ankiewicz demonstrated its willingness to cure its
    deficiencies if given the chance, and Milton admits another party was able to complete
    the project.
    The purpose of right-to-cure provisions is to give contractors the opportunity to
    correct unsatisfactory work before their contracts may be terminated. Were poor
    performance a justification for ignoring such provisions, their utility would be severely
    undercut. Pennsylvania contract law therefore requires a more severe breach before
    contracting parties may violate right-to-cure provisions. Because Milton’s complaint does
    not allege such a breach, the District Court correctly held it had no valid reason to violate
    the right-to-cure provision of its contract. Accordingly, Travelers’ obligation under the
    bond was not triggered, and the complaint against it was properly dismissed.
    IV.
    For the foregoing reasons, we will affirm the order of the District Court dismissing
    Milton’s complaint.
    6
    

Document Info

Docket Number: 14-4575

Citation Numbers: 648 F. App'x 215

Judges: Greenaway, Scirica, Roth

Filed Date: 4/28/2016

Precedential Status: Non-Precedential

Modified Date: 10/19/2024