Chemtech International, Inc. v. Chemical Injection Technologies, Inc. , 247 F. App'x 403 ( 2007 )


Menu:
  •                                                                                                                            Opinions of the United
    2007 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    9-10-2007
    Chemtech Intl Inc v. Chem Injection Tech
    Precedential or Non-Precedential: Non-Precedential
    Docket No. 06-3345
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2007
    Recommended Citation
    "Chemtech Intl Inc v. Chem Injection Tech" (2007). 2007 Decisions. Paper 455.
    http://digitalcommons.law.villanova.edu/thirdcircuit_2007/455
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 2007 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    NOT PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    No. 06-3345
    CHEMTECH INTERNATIONAL, INC.,
    Appellant,
    v.
    CHEMICAL INJECTION TECHNOLOGIES, INC.
    Appeal from the United States District Court
    for the Eastern District of Pennsylvania
    D.C. Civ. No. 05-cv-00140
    District Judge: The Honorable Robert F. Kelly
    Submitted Under Third Circuit LAR 34.1(a)
    May 24, 2007
    Before: BARRY, CHAGARES, and TASHIMA,* Circuit Judges.
    (Opinion Filed: September 10, 2007 )
    *
    Honorable A. Wallace Tashima, Senior Circuit Judge, United States Court of
    Appeals for the Ninth Circuit, sitting by designation.
    OPINION OF THE COURT
    TASHIMA, Circuit Judge:
    Appellant Chemtech International, Inc. (“Chemtech”) sued Chemical Injection
    Technologies, Inc. (“CIT”) for breach of contract. Under a contract dated November 18,
    1996, Chemtech acted as the exclusive Southeast Asia distributor of CIT’s gas
    chlorination equipment. CIT informed Chemtech on March 26, 2002, that Chemtech
    would no longer hold its status as an exclusive distributor. Chemtech learned on about
    April 16, 2003, that CIT had been dealing directly with Chemtech’s subdistributors and
    customers of CIT’s gas chlorination equipment since March 26, 2002. Finally, on about
    July 1, 2004, CIT revoked Chemtech’s distributor status as to certain products and
    revoked Chemtech’s distributor status altogether shortly thereafter. Chemtech contends
    that each of these actions constituted breach of contract. CIT successfully moved for
    dismissal of Chemtech’s amended complaint pursuant to Fed. R. Civ. P. 12(b)(6), and
    Chemtech timely appealed. We have jurisdiction under 
    28 U.S.C. § 1291
    , and we now
    affirm.
    I.        Factual and Procedural Background
    The November 1996 agreement (“Agreement”), by its terms, expired after one
    year, but it contained a renewal provision: “This agreement will be renewed at the end of
    the initial period providing that all terms and conditions have been met as stated in this
    agreement, and further providing that both parties are in accord as to projected unit sales
    2
    goals.” (App. at 36.) The first year sales goal was stated as 100 units. (Id.)
    Chemtech’s original complaint alleged only that CIT took action “in breach of the
    agreement,” and the district court dismissed the complaint with prejudice for failure to
    state a claim. On appeal, we affirmed the district court’s dismissal, but vacated the
    judgment to allow Chemtech to amend its complaint. Chemtech Int’l, Inc. v. Chem.
    Injection Techs., Inc., 170 F. App’x 805 (3d Cir. 2006). The amended complaint added
    the following allegations:
    After November 18, 1997, Plaintiff and Defendant conducted themselves as
    if “all terms and conditions [had] been met” and as if they had explicitly
    agreed “as to projected unit sales goals”.
    After November 18, 1997, Plaintiff and Defendant conducted themselves as
    if the Agreement renewed itself and continued in full force and effect for
    successive one year terms.
    (App. at 30.) The amended complaint also alleged that neither Chemtech nor CIT
    notified the other party of an intent to terminate the Agreement, and that even after receipt
    of the March 26, 2002, letter, Chemtech continued to believe that the 1996 contract
    operated to grant exclusive distributor status with respect to “other of Defendant’s
    products.” (Id. at 31.) The parties agree that the Agreement is governed by Pennsylvania
    law.
    II.    Standard of Review
    We exercise plenary review over the district court’s dismissal of a complaint under
    Rule 12(b)(6). Vallies v. Sky Bank, 
    432 F.3d 493
    , 494 (3d Cir. 2006). A Rule 12(b)(6)
    motion will be granted “‘if it appears to a certainty that no relief could be granted under
    3
    any set of facts which could be proved.’” Evancho v. Fisher, 
    423 F.3d 347
    , 351 (3d Cir.
    2005) (quoting D.P. Enters. Inc. v. Bucks County Cmty. Coll., 
    725 F.2d 943
    , 944 (3d Cir.
    1984)). We accept all factual allegations in Chemtech’s complaint as true and examine
    “whether, under any reasonable reading of the complaint, the plaintiff may be entitled to
    relief.” Del. Nation v. Pennsylvania, 
    446 F.3d 410
    , 415 (3d Cir. 2006). However, we are
    not required to credit bald assertions or legal conclusions improperly alleged in the
    complaint, and legal conclusions draped in the guise of factual allegations may not benefit
    from the presumption of truthfulness. In re Rockefeller Ctr. Props., Inc. Sec. Litig., 
    311 F.3d 198
    , 216 (3d Cir. 2002); In re Burlington Coat Factory Sec. Litig., 
    114 F.3d 1410
    ,
    1426 (3d Cir. 1997); see also Angstadt v. Midd-West Sch. Dist., 
    377 F.3d 338
    , 342 (3d
    Cir. 2004).
    III.   Analysis
    The issue on appeal is whether the additional allegations pleaded in Chemtech’s
    amended complaint sufficiently allege breach of contract. We conclude that they do not.
    To state a claim for breach of contract under Pennsylvania law, a plaintiff must
    allege “‘(1) the existence of a contract, including its essential terms, (2) a breach of a duty
    imposed by the contract[,] and (3) resultant damages.’” Ware v. Rodale Press, Inc., 
    322 F.3d 218
    , 225 (3d Cir. 2003) (quoting CoreStates Bank, N.A. v. Cutillo, 
    723 A.2d 1053
    ,
    1058 (Pa. Super. Ct. 1999)). Thus, in order to proceed with its claim that CIT breached
    its contractual duties, Chemtech must first allege that a contract in fact existed. This it
    has failed to do.
    4
    Chemtech contends that the one-year Agreement, which expired in November
    1997, continued to govern the parties’ business relationship five years later. The
    Agreement itself, however, provided that its terms would not be automatically extended.
    Rather, renewal expressly depended upon two conditions:
    (1) all terms and conditions have been met as stated in the Agreement; and
    (2) both parties are in accord as to projected unit sales goals.
    CIT thus had no contractual duty to Chemtech unless these two prerequisites were
    satisfied. Restatement (Second) of Contracts § 225 (1981) (“Performance of a duty
    subject to a condition cannot become due unless the condition occurs or its non-
    occurrence is excused”); see, e.g., Suburban Transfer Serv., Inc. v. Beech Holdings, Inc.,
    
    716 F.2d 220
    , 225 (3d Cir. 1983) (defendant had no obligations under contract because
    condition precedent was not satisfied).
    Chemtech’s amended complaint fails to allege satisfaction of either of the
    conditions precedent to renewal in 1997 or at any subsequent time. Instead, the amended
    complaint states: “After November 18, 1997, Plaintiff and Defendant conducted
    themselves as if “all terms and conditions [had] been met” and as if they had explicitly
    agreed “as to project unit sales goals.” (App. at 30.) Thus, what Chemtech contends is
    that the parties acted as if the conditions precedent to renewal were fulfilled, which is not
    the same thing as claiming that the conditions were actually satisfied. A complaint that
    alleges a breach of contract without averring compliance with conditions precedent does
    5
    not state a valid breach of contract claim.1 Cf. InfoComp, Inc. v. Electra Prods., Inc., 
    109 F.3d 902
    , 905-07 (3d Cir. 1997) (written agreement was unenforceable under
    Pennsylvania law because a condition precedent to agreement’s formation was not
    satisfied); Franklin Interiors v. Wall of Fame Mgmt. Co., 
    511 A.2d 761
    , 762 (Pa. 1986)
    (same); Jennison v. Aacher, 
    193 A.2d 769
    , 772 (Pa. Super. Ct. 1963) (if plaintiff holds
    burden to prove that condition of formation has been performed, then plaintiff must aver
    performance of condition in order to show satisfaction of contract). Moreover, aside from
    this legal conclusion couched as a factual allegation, Chemtech alleges no subsequent
    conduct that could be construed as an indication that the parties intended to waive these
    conditions of renewal. Therefore, the district court’s dismissal of Chemtech’s amended
    complaint was proper.2
    1
    Chemtech’s reliance on Fed. R. Civ. P. 9(c) is misplaced. It is true that under Rule
    9, it is sufficient to aver generally that all conditions precedent have occurred. The
    deficiency here, however, lies not in Chemtech’s failure to identify the conduct
    establishing satisfaction of the Agreement’s renewal preconditions at the requisite level of
    detail, but in the omission of any allegation that the two conditions precedent occurred at
    all.
    2
    Even assuming the Agreement was renewed in 1997, the amended complaint still
    fails to state a claim for breach of contract. Under Pennsylvania law, a sales contract that
    does not specify a definite duration is terminable at will by either party. 
    13 Pa. Cons. Stat. § 2309
    (b); Stelwagon Mfg. Co. v. Tarmac Roofing Sys., Inc., 
    63 F.3d 1267
    , 1277
    n.20 (3d Cir. 1995). Consequently, CIT would have been free to terminate the renewed
    agreement, unless the renewal occurred under circumstances demonstrating that the
    parties intended a definite period. Chemtech’s amended complaint alleges only that
    “After November 18, 1997, Plaintiff and Defendant conducted themselves as if the
    Agreement renewed itself and continued in full force and effect for successive one year
    terms.” (App. at 30.) But the complaint fails to identify any actual facts that, if proven,
    would refute the presumption of an at-will relationship and support a finding that the
    6
    For the reasons we have discussed, we will affirm the judgment.
    parties intended to renew the original Agreement for successive one-year terms through
    2002, 2003, or 2004. Consequently, the allegation is merely a legal conclusion “draped in
    the guise of” a factual allegation that we do not credit.
    7