HSM Constr Ser v. MDC Sys Inc , 239 F. App'x 748 ( 2007 )


Menu:
  •                                                                                                                            Opinions of the United
    2007 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    7-16-2007
    HSM Constr Ser v. MDC Sys Inc
    Precedential or Non-Precedential: Non-Precedential
    Docket No. 06-2584
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2007
    Recommended Citation
    "HSM Constr Ser v. MDC Sys Inc" (2007). 2007 Decisions. Paper 762.
    http://digitalcommons.law.villanova.edu/thirdcircuit_2007/762
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 2007 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    NOT PRECEDENTIAL
    UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT
    No. 06-2584
    HSM CONSTRUCTION SERVICES, INC.;
    HSM MANAGEMENT SERVICES, INC.,
    Appellants
    v.
    MDC SYSTEMS, INC.
    On Appeal from the United States District Court
    for the Eastern District of Pennsylvania
    (D.C. No. 05-cv-05983)
    District Judge: Honorable Ronald L. Buckwalter
    Submitted Under Third Circuit LAR 34.1(a)
    July 9, 2007
    Before: SLOVITER, HARDIMAN, and ROTH, Circuit Judges
    (Filed July 16, 2007 )
    OPINION
    SLOVITER, Circuit Judge.
    Appellants HSM Construction Services, Inc. (“Construction”) and HSM
    Management Services, Inc. (“Management”) (jointly referred to as “HSM” unless
    otherwise noted) appeal from the District Court’s order confirming an arbitration award in
    favor of the appellee, MDC Systems, Inc. HSM argues that the Arbitration Panel
    manifestly disregarded the law and was evidently partial to MDC Systems, Inc.1
    I.
    Because the parties are familiar with the facts, we adopt the factual scenario as
    stated by the District Court in its opinion:
    The present case stems from a lawsuit regarding the construction of
    the Rosewood Care Center of St. Charles, Illinois, in which Construction
    was a named defendant. To aid in its defense of that lawsuit, Construction
    hired MDC Systems, Inc. (“MDC”) to prepare expert engineering reports.
    By a letter dated July 18, 2002, MDC drafted a Proposal of Expert
    Consulting Services. Throughout the Proposal, MDC refers to the other
    party to the contract as “HSM” and does not specify whether it is referring
    to “HSM Management” or “HSM Construction.” By a letter dated July 19,
    2002, printed on “HSM Management Services, Inc.” letter head, “HSM”
    provided supplementary terms and conditions. The fax also included the
    signature page of the Proposal, which was signed by General Counsel for
    “HSM.” Afterwards, HSM Management Services, Inc. paid the initial
    retainer and made two subsequent partial payments to MDC.
    Construction and Management argue[d] that MDC prepared an
    unusable expert disclosure report. As a result, MDC was not paid for the
    1
    The District Court had diversity jurisdiction over this action
    pursuant to 
    28 U.S.C. § 1332
    . This court has jurisdiction over the
    appeal pursuant to 
    9 U.S.C. § 16
    (a)(1)(D) and 
    28 U.S.C. § 1291
    .
    2
    balance due under the contract. MDC then submitted a Demand for
    Arbitration to the American Arbitration Association (“AAA”) seeking relief
    of $80,662.53 in unpaid fees from only “HSM Management Services, Inc.”
    Construction was not named as a party on MDC’s initial Demand.
    On March 16, 2004, the arbitration Panel conducted a preliminary
    hearing conference call. Management argued that it was not a party to the
    contract in question. The Panel later amended the caption from “HSM
    Management, Inc.” to “HSM, Inc., HSM Management, Inc., and HSM
    Construction Services, Inc.”
    HSM Constr. Serv., Inc. v. MDC Sys., Inc., 
    2006 WL 1030229
    , at *1 (E.D.Pa. Apr. 13,
    2006).
    At the conclusion of the arbitration, the panel issued a decision in favor of MDC
    and held Construction and Management jointly and severally liable for $86,969. HSM
    raises two issues in its appeal. It argues first, that “the District Court err[ed] in
    determining that the arbitration panel did not manifestly disregard the law by finding
    Management liable to MDC where Management was not a party to the agreement
    between Construction and MDC[.]” Appellants’ Br. at 3. Second, it argues that the
    District Court erred in determining that the arbitration panel was not evidently partial to
    MDC.
    II.
    A.
    We consider first which law applies. HSM argued in the District Court that the
    3
    Federal Arbitration Act (“FAA”) applies, whereas MDC argued that the Delaware
    Uniform Arbitration Act (“DUAA”) applies. The District Court decided that “the
    provisions of the FAA and the DUAA that are applicable in this case, the ‘evidently
    partial’ standard and the ‘manifest disregard of the law’ standard, are identical” and
    therefore it declined to decide which law applies because the result would be the same.
    
    2006 WL 1030229
    , at *2. We agree with the District Court in this respect.
    This court reviews a district court’s denial of a motion to vacate a commercial
    arbitration award de novo. Dluhos v. Strasberg, 
    321 F.3d 365
    , 369 (3d Cir. 2003). In
    reviewing a district court’s order confirming an arbitration award, this court reviews the
    district court’s factual findings for clear error and exercises plenary review over the
    district court’s determination on questions of law. See China Minmetals Materials Imp.
    & Exp. Co., Ltd. v. Chi Mei Corp., 
    334 F.3d 274
    , 278-79 (3d Cir. 2003) (citing First
    Options of Chicago, Inc. v. Kaplan, 
    514 U.S. 938
    , 947-48 (1995)); Kaplan v. First
    Options of Chicago, Inc., 
    19 F.3d 1503
    , 1509 (3d Cir. 1994), aff’d, 
    514 U.S. 938
     (1995).
    B.
    HSM contends that Management was never a party to the agreement with MDC
    (the “Agreement”) because it neither signed the Agreement nor was a party to the
    underlying lawsuit concerning the construction of the Rosewood Care Center. Because
    the issue as to whether Management was a party to the arbitration agreement is an issue of
    4
    arbitrability, the court must make an independent determination. See First Options, 
    514 U.S. at 943-45
    .
    The parties’ objective manifestations control in deciding whether they formed a
    contract by mutual assent. Management’s outward words and acts indicate that it is a
    party to the Agreement. First, the signature page of MDC’s Proposal and the July 19,
    2002 letter from “HSM” to MDC (the “Letter”) were both signed by Dennis McCubbin,
    the General Counsel of Management and Construction, on behalf of “HSM.” Although
    neither MDC nor McCubbin explicitly specified whether “HSM” referred to Management
    or Construction, both the Letter and its fax cover sheet were on Management’s letter
    head. “HSM Management Services, Inc.,” as it appears on both the letter head and fax
    cover page, is the only full name on those documents that is consistent with the
    abbreviation of “HSM.” This leads to the conclusion that the “HSM” referred to in the
    Letter as a party must be “HSM Management Services, Inc.”
    Second, Management is the entity that paid MDC’s fees for its service. The
    checks payable to MDC for its service were all under Management’s name. Indeed, it
    paid the initial retainer and the two subsequent partial payments. Although Management
    contends that it paid the check on behalf of Construction, there was no outward indication
    of such subjective and undisclosed intention. From the objective acts of Management, it
    was Management who signed the Agreement and performed the obligation to pay under
    5
    the Agreement. Thus, Management is a party to the Agreement.
    Management argues that it never was a party to the underlying Rosewood Care
    Center lawsuit, and therefore it could not be a party to the Agreement, which retained
    MDC to provide expert services for the underlying proceeding. However, Management
    had an interest in the proceeding, because it possessed one of the claims for which
    Construction sought indemnification in the Rosewood Care Center lawsuit. Moreover,
    whether Management is a party to the underlying lawsuit is not directly related to the
    question as to which entity is the party to the Agreement. The objective manifestation by
    Management was sufficient to indicate its assent to be a party to the Agreement.
    Management also argues that MDC’s president “knew MDC was dealing with
    Construction, not Management.” Appellants’ Br. at 16. It notes that MDC’s president, in
    response to questioning at the arbitration hearing, appears to have agreed that references
    to “HSM” in the expert report were specifically meant to indicate “HSM Construction
    Services, Inc.” because “they were the party to the contract, so it would only be proper to
    do that.” App. at 41.
    MDC does not fully respond to the foregoing argument. Although these
    statements show that MDC knew that it was providing services to Construction, they do
    not lead to the conclusion that MDC knew it was not also signing the Agreement with
    Management.
    The contract between the parties was the subject of a broad arbitration clause
    6
    covering “all” disputes arising from the transaction. App. at 50. We conclude that
    Management’s outward manifestations were clear enough to find its objective intention to
    be a party and accordingly hold that it is bound by the arbitration award.
    C.
    We turn then to the second issue, HSM’s argument that “the District Court erred in
    determining that the arbitration panel was not evidently partial to MDC where MDC
    informed the arbitration panel in writing that Construction and Management ‘ha[ve] not
    paid the AAA-required fees or deposits,’” Appellants’ Br. at 3, and the panel was made
    aware that HSM “were not paying [their] share of the arbitration fees” in the conference
    after the first day of the hearing. App. at 82. This issue arose from a letter sent by MDC
    to the Arbitration Panel on July 12, 2004, stating, in part, “HSM has not paid the AAA-
    required fees or deposits, nor has it requested in forma pauperis relief[.]” App. at 78.
    Originally, the arbitration was to be for a single day, but the panel believed a second day
    would be required. HSM argues that because the salary of the arbitrators “originate[s]”
    from the arbitration fees, the Panel has a financial interest “in the outcome of the
    arbitration,” and thus created, at the very least “an appearance of impropriety.”
    Appellants’ Br. at 21.
    MDC responds that during the conference after the first day of the arbitration
    hearing, no party (MDC, AAA or the Arbitration Panel) other than HSM itself could have
    known that HSM planned to refuse to pay its share of fees. Therefore, even if the Panel
    7
    did know of HSM’s intention, HSM has not proven that it was MDC who told the
    arbitrators so. MDC also argues that if evident partiality may be found based on the fact
    that an arbitration panel knows a party refused to pay arbitration fees, it would be easy for
    parties to get rid of an arbitration award simply by voluntarily telling the panel that it did
    not pay arbitration fees. The District Court refused to find evident partiality of the
    Arbitration Panel, because HSM failed to prove that the July 12, 2004 letter of MDC
    actually reached the Panel, and failed to submit any additional evidence of bias.
    The courts have not clearly articulated the standard to be applied in interpreting
    section 10 of the Federal Arbitration Act which provides that courts may vacate an
    arbitration award if an arbitrator shows “evident partiality.” 
    9 U.S.C. §10
    (a)(2). On one
    hand, the Supreme Court has stated that evident partiality is shown when arbitrators fail to
    disclose “any dealings that might create an impression of possible bias.” Commonwealth
    Coatings Corp. v. Cont’l Cas. Co., 
    393 U.S. 145
    , 149 (1968). The arbitrators “not only
    must be unbiased but also must avoid even the appearance of bias.” 
    Id. at 150
    . On the
    other hand, this court has appeared to adopt what we refer to as a “reasonably construed”
    bias standard, which finds evident partiality only when “a reasonable person would have
    to conclude that the arbitrator was partial to [one] party to the arbitration.” Kaplan, 
    19 F.3d at
    1523 n.30 (quoting Apperson v. Fleet Carrier Corp., 
    879 F.2d 1344
    , 1358 (6th Cir.
    1989)). The reasonably construed bias standard requires proof of circumstances
    “powerfully suggestive of bias.” 
    Id.
     (quoting Merit Ins. Co. v. Leatherby Ins. Co., 714
    
    8 F.2d 673
    , 681-82 (7th Cir. 1983)).
    The First, Second, Fourth, Sixth, Seventh, Ninth and Eleventh Circuits have
    adopted the reasonably construed bias standard, albeit not under that name. See Morelite
    Const. Corp. v. N.Y. City Dist. Council Carpenters Benefit Funds, 
    748 F.2d 79
    , 84 (2d
    Cir. 1984) (evident partiality will be found where “a reasonable person would have to
    conclude that an arbitrator was partial to one party to the arbitration”); JCI Commc’ns,
    Inc. v. Int’l Bhd. of Elec. Workers, Local 103, 
    324 F.3d 42
    , 51 (1st Cir. 2003) (same);
    ANR Coal Co., Inc. v. Cogentrix of N.C., Inc., 
    173 F.3d 493
    , 500-01 (4th Cir. 1999)
    (same); Apperson, 
    879 F.2d at 1358
     (same); see also Gianelli Money Purchase Plan and
    Trust v. ADM Investor Servs., Inc., 
    146 F.3d 1309
    , 1312 (11th Cir. 1998); Toyota of
    Berkeley v. Auto. Salesman’s Union, Local 1095, 
    834 F.2d 751
    , 756 (9th Cir. 1987) (“the
    party alleging bias must establish facts that create a reasonable impression of partiality”)
    (internal citation and quotation marks omitted); Merit Ins. Co., 714 F.2d at 681.
    We need not decide the standard of bias in this case because HSM has failed to
    show evident partiality of the arbitrators even under the more generous standard of
    “appearance of bias.” The District Court found that it was unclear whether MDC’s letter
    actually reached the Panel members. Without clear error, we will not reverse a factual
    finding of the District Court. The District Court also held that there is “no additional
    evidence of bias.” 
    2006 WL 1030299
    , at *3. We agree. Although HSM has stated that
    9
    the Arbitration Panel learned that HSM was planning not to pay arbitration fees in the
    conference after the hearing, it is no more than a conclusory assertion. The only evidence
    in the record regarding this allegation is the affidavit of HSM’s General Counsel,
    McCubbin, who stated, “[o]n February 2, 2005, the arbitrators were aware that
    [Construction and Management] were not paying a share of the arbitration fees.” App. at
    82. No other evidence is cited to support McCubbin’s allegation or to prove that it was
    MDC who informed the Panel of HSM’s intention to avoid arbitration fees.
    Even if HSM had proven that the Arbitration Panel was aware of HSM’s intention
    not to pay the arbitration fee, such awareness itself is not sufficient to show that the
    arbitrators had a financial interest in the outcome of the arbitration. Rule 54 of the
    AAA’s Commercial Rules of Arbitration provides that the AAA may suspend or
    terminate the hearing or proceeding if arbitration fees are not paid on time. The fact that
    the arbitration proceeded suggests that the fees were paid, no matter which party actually
    paid them. HSM conceded that if it did not pay the arbitration fees, MDC “would have to
    pay the fees for both parties in order for the arbitration to proceed.” App. at 82.
    Therefore, the Panel did not have any financial interest in the outcome of the arbitration,
    because the fees would have been paid as long as the proceeding continued.
    In conclusion, HSM has failed to prove that MDC’s July 12, 2004 letter actually
    reached the Arbitration Panel, and it has not provided any additional evidence showing
    bias of the arbitrators. Even under the generous standard of “appearance of bias,” we
    10
    conclude that HSM has failed to raise any genuine issue of bias.
    III.
    For the reasons set forth, we will affirm the District Court’s order confirming the
    arbitration award.
    11