Adorers of the Blood of Chris v. Transcontinental Gas Pipe Line ( 2022 )


Menu:
  •                                         PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    _____________
    No. 21-2898
    _____________
    ADORERS OF THE BLOOD OF CHRIST UNITED
    STATES PROVINCE,
    n/k/a Adorers of the Blood of Christ, United States Region,
    Successor by Merger to Adorers of the Blood of Christ,
    Province of Columbia, PA, Inc. formerly known as
    Saint Joseph Convent Motherhouse of the Adorers of the
    Blood of Christ,
    Columbia, Pennsylvania, Inc. formerly known as Saint
    Joseph's Convent,
    Mother House of Sister Adorers of the Most Precious
    Blood, Columbia, PA
    also known as Sisters Adorers of the Most Precious Blood,
    St. Joseph Convent, Columbia, PA;
    SISTER SARA DWYER;
    SISTER MARIA HUGHES;
    SISTER DANI BROUGHT;
    SISTER MARY ALAN WURTH;
    SISTER THERESE MARIE SMITH,
    Appellants
    v.
    TRANSCONTINENTAL GAS PIPE LINE CO LLC
    _____________________________________
    On Appeal from the United States District Court
    for the Eastern District of Pennsylvania
    (District Court No.: 5-20-cv-05627)
    District Judge: Honorable Jeffrey L. Schmehl
    _____________________________________
    Argued
    September 15, 2022
    (Filed: November 8, 2022)
    Before: KRAUSE, BIBAS, and RENDELL, Circuit Judges.
    J. Dwight Yoder [Argued]
    Sheila V. O’Rourke
    Gibbel, Kraybill & Hess
    2933 Lititz Pike
    P.O. Box 5349
    Lancaster, PA 17606
    Counsel for Appellants
    Elizabeth U. Witmer [Argued]
    Saul Ewing Arnstein & Lehr
    1200 Liberty Ridge Drive
    Suite 200
    Wayne, PA 19087
    Patrick F. Nugent
    Sean T. O’Neill
    Shane P. Simon
    Saul Ewing Arnstein & Lehr
    2
    1500 Market Street
    Centre Square West, 38th Floor
    Philadelphia, PA 19102
    Counsel for Appellee
    _________
    OPINION OF THE COURT
    _________
    RENDELL, Circuit Judge.
    This is the second attempt by the Adorers of the Blood
    of Christ (“Adorers”), a religious group opposed to the
    extraction, transportation, and use of fossil fuels, to challenge
    the route, construction, and operation of an interstate gas
    pipeline on their property as violative of their rights under the
    Religious Freedom and Restoration Act (“RFRA”). Their first
    attempt sought an injunction before the pipeline was
    constructed; this attempt seeks money damages after its
    completion. In both cases, the District Court dismissed the
    complaint on the ground that the Adorers’ failure to present
    their claims to the Federal Energy Regulatory Commission
    (“FERC”) at any time during the years-long administrative
    proceedings, which ultimately authorized the pipeline,
    foreclosed their claim under the Natural Gas Act’s (“NGA”)
    exclusive-review framework. We affirmed the District Court’s
    order in the first action, Adorers of the Blood of Christ v. FERC
    (Adorers I), 
    897 F.3d 187
     (3d Cir. 2018), and will do so in this
    case as well.
    3
    I.
    As we explained in connection with the Adorers’ first
    case, under the NGA, FERC has the sole authority to issue a
    “certificate of public convenience and necessity,” which
    permits private gas pipeline developers to build, operate, and
    maintain new interstate gas pipelines.               15 U.S.C.
    § 717f(c)(1)(A). To determine whether to issue such a
    certificate, FERC must consider the public’s input, and, to that
    end, it must provide reasonable notice to various parties who
    would be affected by the pipeline and provide those parties
    with an opportunity to be heard. Id. § 717f(c)(1)(B). “If FERC
    ultimately issues the certificate following the requisite hearing,
    any aggrieved person may seek judicial review of its
    decision—either in the Court of Appeals for the District of
    Columbia Circuit or the circuit wherein the natural gas
    company is located or has its principal place of business.”
    Adorers I, 897 F.3d at 189 (citing 15 U.S.C. § 717r(b)). Before
    petitioning an appropriate court of appeals for review of a
    FERC order, however, the aggrieved party must first seek
    rehearing before FERC. 15 U.S.C. § 717r(a). Failure to seek
    rehearing before FERC bars the aggrieved party from later
    obtaining judicial review. Id.
    II.
    The Adorers collectively comprise an order of Roman
    Catholic nuns whose deeply-held religious beliefs require them
    “to protect, preserve, and treasure the land that” they own and
    “to protect and preserve Earth.” App. at 18 ¶ 1. They own
    property in Lancaster County, Pennsylvania, and use and
    maintain that property in accordance with their religious
    4
    beliefs, including for agricultural purposes. Among other
    things, the Adorers believe the extraction, transportation, and
    use of fossil fuels accelerates global warming and climate
    change and, thus, defiles God’s creation. Any use of their
    property to facilitate the extraction, transportation, and use of
    fossil fuels, violates their religious beliefs and practices. So,
    in 2014, when Transcontinental Gas Pipe Line Company
    (“Transco”) notified the Adorers that it was in the early stages
    of designing a new 183-mile long, 42-inch diameter interstate
    gas pipeline, known as the “Central Penn Line South,” part of
    the “Atlantic Sunrise Pipeline,” to transport 1.7 million
    dekatherms of gas through their property each day, the Adorers
    explained to Transco’s right-of-way agent that this would
    violate their religious beliefs and that they would not entertain
    any offer by Transco to purchase a right-of-way through their
    property. Nearly a year later, Transco filed a formal
    application with FERC to obtain a certificate of public
    convenience and necessity. See 15 U.S.C. § 717f(c).
    FERC then proceeded to publish numerous notices,
    over the course of more than thirty months, as part of the
    pipeline approval process and as required under the NGA and
    FERC regulations. It mailed letters about the project to
    thousands of parties, solicited comments from the public, and
    hosted four initial open meetings to discuss, among other
    things, the proposed route of the pipeline and the effect of the
    pipeline’s construction and operation on various stakeholders.
    Adorers I, 897 F.3d at 191-92. Although FERC received
    hundreds of written comments and heard scores of comments
    and objections from interested parties at its initial meetings, the
    Adorers neither provided comments to FERC nor did they
    attend any of those meetings. Id.
    5
    Even when FERC contacted the Adorers directly, they
    remained silent. On October 22, 2015, FERC delivered a letter
    to the Adorers describing various pipeline routes under
    consideration, including routes that would directly impact their
    property, and invited them to participate in the environmental
    review process where the Adorers could comment on the
    project and request modifications or accommodations,
    including the rerouting of the pipeline.1 Id. The Adorers,
    however, did not respond to the letter, did not participate in the
    process, and did not otherwise formally oppose the project as
    it remained under review before FERC. Id.
    On February 3, 2017, after receiving still further written
    comments and oral comments from hundreds of speakers at
    environmental review hearings, and after Transco altered the
    pipeline’s route at least 132 times in response to public
    comment—in total changing the original proposed route by
    about fifty percent—FERC issued a certificate to Transco
    authorizing it to build, operate, and maintain the pipeline.
    Transcon. Gas Pipe Line Co., 
    158 FERC ¶ 61,125
    , 
    2017 WL 496024
    , ¶ 151 (Feb. 3, 2017). The certificate also authorized
    1
    Indeed, some property owners obtained meaningful relief
    because of their participation in this process. In response to
    property owner concerns, FERC attached certain conditions to
    the issuance of any certificate to Transco including, for
    example, that Transco agree to “compensate [organic farm]
    landowners” if their organic farm certifications were impacted
    by the pipeline, Transcon. Gas Pipe Line Co., 
    158 FERC ¶ 61,125
    , 
    2017 WL 496024
    , ¶ 101, (Feb. 3, 2017), and that
    Transco agree to provide “monetary compensation to the
    occupants of affected noise sensitive areas in the project area,”
    id. ¶ 167.
    6
    Transco, as provided under the NGA, to use eminent domain
    to take rights-of-way from any property owners unwilling to
    sell a right-of-way to Transco voluntarily. Id. ¶ 67; see 15
    U.S.C. § 717f(h) (providing that “[w]hen any holder of a
    certificate of public convenience and necessity cannot acquire
    by contract, or is unable to agree with the owner of property to
    the compensation to be paid for, the necessary right-of-way to
    construct, operate, and maintain a pipe line . . . it may acquire
    the same by the exercise of the right of eminent domain”).
    While the final pipeline route avoided some properties because
    of fruitful discussion among the property owners, FERC, and
    Transco during the certification process, the final pipeline
    route, not surprisingly, wended through the Adorers’ property.
    On April 14, 2017, Transco filed a complaint in federal
    court under Federal Rule of Civil Procedure 71.1 (setting forth
    the procedure for condemning real property by eminent
    domain) and § 717f(h) of the NGA seeking an order of
    condemnation to permit it to take title to rights-of-way in the
    Adorers’ property necessary to build and operate the pipeline.
    Despite service, the Adorers failed to answer or otherwise
    respond to the complaint until after Transco filed a motion for
    default judgment and sought an emergency order from the
    District Court authorizing it to take immediate possession of
    the rights-of-way.
    Ultimately, the District Court granted default judgment
    to Transco regarding its substantive entitlement to the rights-
    of-way but deferred a decision on Plaintiff’s request for
    possession until after an evidentiary hearing.2
    2
    The District Court later granted full possession of the right-
    of-way to Transco and awarded “just compensation” to the
    7
    One week after the District Court granted default
    judgment to Transco and just three days before the District
    Court’s evidentiary hearing, the Adorers filed a separate suit in
    the U.S. District Court for the Eastern District of Pennsylvania
    claiming for the first time in any official filing, that FERC, and
    Transco—who was later added as a defendant—violated their
    rights under RFRA. They urged that under RFRA, they had
    the right to raise a claim or defense for “appropriate relief.”
    See 42 U.S.C. § 2000bb-1(c) (“A person whose religious
    exercise has been burdened in violation of this section may
    assert that violation as a claim or defense in a judicial
    proceeding and obtain appropriate relief against a
    government.”). And they contended that this gave them the
    right to institute an action in federal court rather than proceed
    Adorers but rejected their claim for additional damages, which
    the Adorers claimed arose from the same purported violation
    of RFRA at issue in this case. The District Court explained
    that not only was the Adorers’ RFRA claim irrelevant to the
    question of the fair market value of the right-of-way, but also
    that it was a counterclaim for compensatory damages beyond
    the ken of condemnation proceedings under Fed. R. Civ. P.
    71.1. Under Fed. R. Civ. P. 71.1, the District Court noted, “[a]
    defendant waives all objections and defenses not stated in its
    answer. No other pleading or motion asserting an additional
    objection or defense is allowed” and “Courts have repeatedly
    upheld Rule 71.1’s limitation on additional pleadings such as
    counterclaims.” App. at 523 (internal quotation marks
    omitted) (quoting Fed. R. Civ. P. 71.1(e)(3)). As the Adorers
    failed to answer the condemnation complaint and their claim
    for additional damages was not cognizable under Fed. R. Civ.
    P. 71.1, the District Court rejected the claim. The Adorers did
    not appeal that ruling.
    8
    before FERC. The Adorers sought an injunction permanently
    enjoining Transco from completing its project.
    Transco moved to dismiss the Adorers’ complaint for
    lack of subject matter jurisdiction and the District Court
    granted the motion. The District Court concluded that “RFRA
    did not allow the Adorers to circumvent the specific procedure
    prescribed by [Congress under] the NGA for challenging a
    FERC order” and “[b]ecause the Adorers had failed to seek
    FERC rehearing . . . it was foreclosed from hearing their
    claims.” Adorers I, 897 F.3d at 193. Adorers appealed and we
    affirmed the District Court’s order. Id. at 198.
    In so doing, we rejected the Adorers’ contention that
    RFRA somehow gave them the statutory right to assert their
    claim in federal district court rather than before FERC. We
    reasoned that the NGA’s “exhaustion provision . . . makes clear
    Congress’ intent to confer exclusive jurisdiction to the NGA
    by a highly reticulated statute nullifying any procedural
    alternatives an aggrieved party may otherwise have.” Id. at
    195. We continued,
    Indeed, the NGA is the exclusive
    remedy for matters relating to the
    construction of interstate natural
    gas pipelines.      It forms the
    paradigm by which FERC operates
    in matters related to interstate
    natural gas pipelines. By failing to
    avail themselves of the protections
    thereunder, the Adorers have
    foreclosed judicial review of their
    substantive RFRA claims.
    9
    Id.
    We also rejected the Adorers’ “claim that, even if they
    had indulged the administrative process, they could not have
    asserted their rights under RFRA within the NGA because they
    would have had ‘to have anticipated a possible RFRA violation
    and affirmatively acted to become a party to a private third
    party’s administrative application.’” Id. at 197. In rejecting
    this claim, we observed that “FERC may hear any claim raised
    before it—even potential violations of federal law.” Id. And
    if FERC incorrectly adjudicated such a claim, the aggrieved
    claimant “has the opportunity for direct appeal before a federal
    court of appeals.” Id. Had the Adorers “participated in the
    administrative process, FERC may have denied or modified the
    conditions of Transco’s certificate . . . . [and] [u]nder these
    circumstances, the Adorers would have, at the very least, had
    the opportunity to seek the [injunctive] relief they so desire.”
    Id. at 198.
    Soon after the pipeline was completed and put into
    service, the Adorers filed a new complaint in the District Court.
    Although, as the District Court noted, this new complaint
    “[wa]s nearly identical to the previous action filed by the
    Adorers for [an] alleged RFRA violation[]” the Adorers made
    three changes. App. at 7. First, the Adorers named only
    Transco as a defendant. Second, rather than seek injunctive
    relief as they unsuccessfully attempted to in Adorers I, they
    sought money damages for the RFRA violation. App. at 41 ¶
    129. Third, the Adorers alleged, somewhat differently from
    their position in Adorers I, that the source of the substantial
    burden on their religious exercise arose not from “FERC’s
    decision to force the Adorers to use land they own to
    accommodate a fossil fuel pipeline,” Compl. at 9 ¶ 45, Adorers
    10
    I, No. 5:17-cv-03163-JLS (E.D. Pa. July 14, 2017), ECF No. 1
    (emphasis added), but instead, from “Transco’s action in
    placing the Pipeline in to [sic] service using the Adorers’ land,”
    App. at 37 ¶ 111 (emphasis added), thus, suggesting that their
    claim was not ripe until this occurred.3
    Transco again moved to dismiss this new complaint for
    lack of subject matter jurisdiction and the District Court again
    granted the motion. The District Court, applying our holding
    in Adorers I, concluded that given Adorers’ admission that
    “they not only failed to apply for a rehearing before FERC but
    failed to present their RFRA claims in any manner to the
    FERC, and ultimately [failed] to [appeal their claim to] the
    appropriate Court of Appeals . . . . the Adorers . . . foreclosed
    judicial review of their substantive RFRA claims.” App. 9, 10
    (citation omitted). The District Court rejected the Adorers’
    argument that “because they are seeking monetary damages . .
    . as opposed to the injunctive relief they sought in Adorers I . .
    . and that money damages are not available through FERC’s
    administrative process, this Court has subject matter
    jurisdiction.” App. at 10.
    The Adorers filed this timely appeal.
    3
    Compare Compl. at 2 ¶ 1, Adorers I, No. 5:17-cv-03163-JLS
    (E.D. Pa. July 14, 2017), ECF No. 1 (“FERC’s action in issuing
    the FERC Order approving and authorizing Transco to forcibly
    take and use land owned by the Adorers . . . will, if allowed to
    proceed, substantially burden the Adorers’ exercise of their
    deeply held religious beliefs”) with App. 33 ¶ 80 (“[T]here was
    no burden placed on the Adorers’ religious exercise at the time
    the FERC Order was issued.”).
    11
    III.4
    A.
    As we did in Adorers I, we find the Supreme Court’s
    opinion in City of Tacoma v. Taxpayers of Tacoma to provide
    the controlling principle in this case, 
    357 U.S. 320
     (1958).
    There, the City of Tacoma was to construct a power plant on
    the Cowlitz River under a license issued by the Federal Power
    Commission (“FPC”). 
    Id. at 324
    . The building of the project
    required the City to take land used as a fish hatchery and owned
    by the State of Washington. 
    Id. at 325
    . Unlike the situation in
    this case, the State there did object and unsuccessfully opposed
    the grant of the license by the FPC. 
    Id. at 325-26
    . The State
    later moved successfully in the Superior Court of Washington
    for an order enjoining the City from proceeding to construct
    the project or sell any of its revenue bonds, an order which was
    then ultimately appealed and affirmed by the Supreme Court
    of Washington. 
    Id. at 331-32
    .
    The United States Supreme Court granted certiorari and
    reversed. It noted:
    This statute is written in simple
    words of plain meaning and leaves
    no room to doubt the congressional
    purpose and intent. It can hardly
    4
    We have jurisdiction under 
    28 U.S.C. § 1291
    . We review
    threshold matters of justiciability de novo. See In re Horizon
    Healthcare Servs. Inc. Data Breach Litig., 
    846 F.3d 625
    , 632
    (3d Cir. 2017); Hartig Drug Co. v. Senju Pharm. Co., 
    836 F.3d 261
    , 267-68, 267 n.8 (3d Cir. 2016).
    12
    be doubted that Congress, acting
    within its constitutional powers,
    may prescribe the procedures and
    conditions under which, and the
    courts in which, judicial review of
    administrative orders may be had.
    So acting, Congress in § 313(b)
    prescribed the specific, complete
    and exclusive mode for judicial
    review of the Commission’s
    orders. It there provided that any
    party      aggrieved     by      the
    Commission’s order may have
    judicial review, upon all issues
    raised before the Commission in
    the motion for rehearing, by the
    Court of Appeals which ‘shall
    have exclusive jurisdiction to
    affirm, modify, or set aside such
    order in whole or in part,’ and that
    ‘[t]he judgment and decree of the
    court, affirming, modifying, or
    setting aside, in whole or in part,
    any such order of the Commission,
    shall be final . . . . It thereby
    necessarily precluded de novo
    litigation between the parties of all
    issues inhering in the controversy,
    and all other modes of judicial
    review.
    Id. at 335-36 (emphasis added).
    13
    The Court then concluded that the State’s attempts to
    obtain recourse from the Washington state courts constituted
    “impermissible collateral attacks” on the approval by the FPC,
    which was reviewed and affirmed by the U.S. Court of Appeals
    for the Ninth Circuit. Id. at 341. As we observed in Adorers
    I, “the Supreme Court has long held that . . . statutory review
    scheme[s] [like that of the NGA, which channel all claims
    relating to the certification or licensing of interstate energy
    projects through an exclusive judicial review scheme], . . .
    ‘necessarily preclude[] de novo litigation between the parties
    of all issues inhering in the controversy, and all other modes of
    judicial review.’” Adorers I, 897 F.3d at 197 (quoting Tacoma,
    
    357 U.S. at 336, 341
    ) (emphasis added). The rule that any
    claim raising issues “inhering in” the certification of a new
    interstate gas pipeline must first be presented to FERC—or else
    forfeited—also applies to claims that “could and should have
    been” raised during the certification process. Tacoma, 
    357 U.S. at 339
    . In commenting on this principle, the Tenth Circuit
    has remarked that it “would be hard pressed to formulate a
    doctrine with a more expansive scope.” Williams Nat. Gas Co.
    v. City of Okla. City, 
    890 F.2d 255
    , 262 (10th Cir. 1989).
    The well-established doctrine of “impermissible
    collateral attack” has been invoked by many of our sister courts
    of appeals to bar suits brought by persons aggrieved by the
    certification, construction, or operation of new interstate
    energy projects. See, e.g., Bohon v. FERC, 
    37 F.4th 663
    , 666
    (D.C. Cir. 2022) (concluding that “[t]he Natural Gas Act’s
    review scheme precluded district-court jurisdiction over the
    Bohons’ collateral attack on the FERC order”); Otwell v. Ala.
    Power Co., 
    747 F.3d 1275
    , 1279 (11th Cir. 2014) (concluding
    that various property owners’ state tort claims regarding the
    water levels in a lake were barred as “impermissible collateral
    14
    attack[s]” on a FERC license to a hydroelectric dam company
    that permitted the company to change the water levels in the
    lake); Am. Energy Corp. v. Rockies Exp. Pipeline LLC, 
    622 F.3d 602
    , 605 (6th Cir. 2010) (concluding that a coal
    company’s various claims were barred as impermissible
    collateral attacks on a FERC certificate and explaining that
    “[e]xclusive means exclusive, and the Natural Gas Act
    nowhere permits an aggrieved party otherwise to pursue
    collateral review of a FERC certificate in state court or federal
    district court”); see also Simmons v. Sabine River Auth. La.,
    
    732 F.3d 469
    , 477 (5th Cir. 2013) (not applying Tacoma but
    otherwise concluding that a property owner’s state negligence
    claim for damages caused by floods resulting from the opening
    of a hydroelectric dam was an improper “attempt to force
    changes to a FERC-issued license”).
    The Eleventh Circuit’s opinion in Otwell is particularly
    instructive. 
    747 F.3d 1275
    . Alabama Power operated a
    hydroelectric dam on a lake for decades, under a license from
    the FPC. Id. at 1277. As the license approached its expiration,
    the utility sought to renew the license on new terms. Id. at
    1278. Contrary to its long-existing practice, the utility sought
    to lower the water level in the lake and release water at various
    times of the year to cool a downstream power plant. Id. The
    Smith Lake Improvement and Stakeholders Association
    (“SLISA”), comprised of some of the landowners from around
    the lake, intervened in the FERC proceedings and opposed the
    renewal. Id. It requested that the utility maintain higher water
    levels in the lake and minimize the release of water
    downstream. Id. FERC rejected SLISA’s requests and granted
    the utility a license to operate at the lower water level, which it
    then did. Id.
    15
    Some members of SLISA then filed a putative class
    action in state court against the utility, later removed to federal
    district court, claiming that its lowering of the water in the lake
    caused tortious injury to their property. Id. To remedy their
    injuries, the plaintiffs sought “monetary damages, a
    declaratory judgment[,] . . . and an injunction requiring [the
    utility] to construct cooling towers at [the downstream power
    plant].” Id. at 1279. The district court granted summary
    judgment to the utility concluding that the plaintiffs’ claims
    “were an impermissible collateral attack on the FERC’s . . .
    relicensing order.” Id. at 1279. The Eleventh Circuit agreed.
    Id. at 1277.
    Relying on the principle articulated in Tacoma, the
    Eleventh Circuit wrote that “Appellants cannot escape
    [Congress’ exclusive review scheme] by arguing that they are
    pursuing different claims and different relief than the parties
    before the FERC.” Id. at 1281 (citing Tacoma, 
    357 U.S. at 336
    ). “[T]heir . . . claims are inescapably intertwined with a
    review of the FERC’s final decision.” Id. at 1282 (emphasis
    added) (citations omitted).        “The review entailed by
    Appellants’ claims is statutorily dedicated to the court of
    appeals.” Id.
    The Court further concluded that the landowners were
    barred from advancing their state tort claims against the utility
    even though they were not themselves intervenors in the
    relicensing proceedings. The Court explained,
    [w]e do not read [the exclusive
    jurisdiction scheme] as allowing
    any person or entity that was not a
    party to the FERC proceedings to
    16
    collaterally challenge the final
    order resulting from those
    proceedings. Instead, we read [it]
    as limiting the persons who may
    seek judicial review of an order of
    the FERC to those parties who
    participated    in    the     FERC
    proceedings. Thus, non-parties to
    the proceedings before the FERC
    may not contest the agency’s final
    decision in an alternative forum by
    bringing challenges that are
    inescapably intertwined with a
    review of the agency’s final
    determination.
    Id. at 1282 (emphasis added) (internal citations omitted). This
    reading, the court continued, “prevents the [exclusive
    jurisdiction] provision from being rendered nugatory.” Id.
    Indeed, to read the provision in any other way would allow,
    any person or entity with an
    interest in the proceedings before
    the FERC [to] evade the . . .
    exclusive judicial review provision
    by simply choosing not to
    participate in the proceedings, or
    by creating a corporate entity to
    champion its interests before the
    agency.      Then, following an
    adverse order, the non-participants
    could      obtain    a    collateral
    redetermination of the identical
    17
    issues considered and rejected in
    the FERC’s final order because
    those persons were not parties to
    the proceedings.         Such a
    construction of the statute would
    do violence to Congress’s
    deliberately crafted administrative
    scheme.
    Id. at 1282-83 (emphasis added). In the Eleventh Circuit’s
    view, whether a party’s claim is an impermissible collateral
    attack upon a FERC order centers on whether the adjudication
    of the claim would require the court to review any issues
    “inescapably intertwined” with the earlier FERC certification
    process. Id. at 1282.
    The Eleventh Circuit thus added another way of
    determining whether the later proceeding involved issues that
    “inhered in” the certification process and constituted an
    impermissible collateral attack on a FERC decision. It looked
    to whether the later claim raised issues “inescapably
    intertwined” with the FERC certification process. This tracks
    the approaches of other courts of appeals.
    The D.C. Circuit in Bohon, for example, focused on
    whether the plaintiff’s claims were “anchored in [the] pipeline
    proceedings” and, if successful, would “directly imperil[] a
    specific certificate that FERC granted.” 37 F.4th at 666. And
    the Sixth Circuit in Am. Energy Corp. focused on whether the
    “heart of th[e] claim[]” was bound up in the operation of the
    pipeline, which was authorized by FERC’s certificate. 
    622 F.3d at 605
    . No matter the specific language employed by our
    various sister courts of appeals to describe the analysis, in
    18
    answering the question of whether a claim is an impermissible
    collateral attack, they each focus their attention not on the
    plaintiffs’ characterization of their claim but rather on whether
    the claim “could and should have” been presented to FERC
    because the claims raise “issues inhering in the controversy.”
    Tacoma, 
    357 U.S. at 336, 339
    .
    The Adorers urge that the Supreme Court’s recent
    opinion in PennEast Pipeline Co. v. New Jersey, supports their
    position that theirs is not a collateral attack. 
    141 S. Ct. 2244
    (2021). We disagree.
    There, as in Tacoma, the recipient of a certificate of
    public convenience and necessity sought to exercise its
    eminent domain power against state lands. Id. at 2253. The
    State of New Jersey, however, opposed the condemnation
    proceedings on sovereign immunity grounds. Id. It lost before
    the district court, but we reversed because we did not think that
    15 U.S.C. § 717f(h) clearly delegated the federal government’s
    power to pierce states’ sovereign immunity along with its
    eminent domain power. Id. at 2253–54. The Supreme Court
    granted certiorari and, before reaching the merits of the
    dispute, held that New Jersey had not launched a collateral
    attack on the FERC order granting PennEast’s certificate. Id.
    at 2254. The Court explained that this case was unlike
    Tacoma, because
    New Jersey does not seek to
    modify FERC’s order; it asserts a
    defense against the condemnation
    proceedings initiated by PennEast.
    To determine whether the District
    Court correctly rejected New
    19
    Jersey’s defense, the Third Circuit
    needed to decide whether
    § 717f(h) grants natural gas
    companies the right to bring
    condemnation suits against States.
    Its conclusion that § 717f(h) does
    not authorize such suits did not
    “modify” or “set aside” FERC’s
    order, which neither purports to
    grant PennEast the right to file a
    condemnation suit against States
    nor addresses whether § 717f(h)
    grants that right.
    Id. Even though the state asserted a counterclaim that would
    have the effect of negating the route that FERC had set up via
    the regulatory process, it was not a collateral attack because
    asserting the sovereign immunity defense is not the same as
    “arguing that a licensee could not exercise the rights granted to
    it by the license itself.” Id. (emphasis added). Our
    determination as to whether the NGA delegated the federal
    power to pierce states’ sovereign immunity did not touch the
    FERC order at all. See id.
    The Adorers urge that Tacoma is distinguishable and
    PennEast is the better analogue here because the “appropriate
    relief” that is due to them under RFRA is monetary damages,
    42 U.S.C. § 2000bb-1(c), and granting those does not modify
    or set aside Transco’s certificate. We disagree. The fact
    remains that their allegation that the presence and operation of
    the pipeline on their property violated their rights under RFRA
    is the essence of both lawsuits. This could and should have
    been contested before FERC during the certification
    20
    proceedings where such issues were to be resolved.5 The
    appropriate court of appeals could then have reviewed and
    remedied any insufficiency in FERC’s resolution of the
    Adorers’ claim. But, again, having failed to avail themselves
    of the exclusive review scheme established by Congress under
    the NGA for adjudicating such claims, the Adorers’ claim is
    now barred as an impermissible collateral attack.
    The Tenth Circuit’s analysis in Save the Colorado v.
    Spellmon, --- F.4th ----, No. 21-1155, 
    2022 WL 4588319
     (10th
    Cir. Sept. 30, 2022) leads us to the same result. There, the court
    let the opponents of plans to raise a local dam and expand the
    reservoir behind it sue in the district court, but the basis for
    their lawsuit was completely distinguishable from the
    Adorers’. The at-issue agency approvals did not come from
    FERC, but from the Army Corps of Engineers and the United
    States Fish and Wildlife Service. Save the Colorado, 
    2022 WL 4588319
    , at *2, *7. After analyzing the underlying statutory
    5
    Indeed, the more “appropriate relief,” as the District Court
    noted, was presumably a rerouting of the pipeline around their
    property. App. at 11. The thrust of RFRA is the prevention or
    elimination of a violation, not simply the compensation for
    spiritual harms after the fact by an award of money. See Little
    Sisters of the Poor Saints Peter & Paul Home v. Pennsylvania,
    
    140 S. Ct. 2367
    , 2395 (2020) (Alito, J., concurring) (emphasis
    added) (citation omitted) (explaining that “[o]nce it [is]
    apparent that [the Government’s action] [runs] afoul of RFRA,
    the Government [i]s required to eliminate the violation. RFRA
    does not specify the precise manner in which a violation must
    be remedied; it simply instructs the Government to avoid
    ‘substantially burden[ing]’ the ‘exercise of religion’—i.e., to
    eliminate the violation.”).
    21
    claims that the plaintiffs had brought and determining whether
    each underlying issue inhered in the controversy per Tacoma,
    
    id.
     at *7–12, the Tenth Circuit concluded that even though “the
    municipality needed a discharge permit to raise the dam and
    expand the reservoir—matters subject to [FERC’s] licensing
    decision,” because the NGA did not govern the licenses
    granted by the Corps or Service and FERC could not hear
    challenges to those licenses, the plaintiffs’ “claims did not
    attack the merits of [FERC’s] approval of an amended license,”
    id. at *14. Therefore, this was not a collateral attack. Id. at *5,
    14.
    The Tenth Circuit noted that this conclusion was
    consistent with Adorers I, because the breadth of FERC’s
    authority was not an issue in that case. Id. at *9. Here, there
    is no question that FERC can adjudicate RFRA claims, see
    Snoqualmie Indian Tribe v. FERC, 
    545 F.3d 1207
    , 1213 (9th
    Cir. 2008) (noting that FERC had evaluated the tribe’s RFRA
    claim before relicensing a hydroelectric project), and the
    Adorers do not attack any license that Transco has received
    from any other agency, so Save the Colorado does not advance
    the Adorers’ cause.
    B.
    In this case, we conclude the Adorers’ RFRA claim is
    an impermissible collateral attack on the FERC certificate
    because the claim could and should have been raised before
    FERC. Their RFRA claim raises issues inhering in the
    controversy, namely the route, construction, and operation of
    the pipeline through the Adorers’ property. The Adorers allege
    that “Transco’s action in placing the Pipeline in to [sic] service
    using the Adorers’ land caused a substantial burden to the
    22
    religious exercise of the Adorers in violation of RFRA.” App.
    at 37 ¶ 111 (emphasis added). They also allege that it was
    Transco’s “use [of their] private property . . . to install and
    operate a natural gas pipeline that . . . “damage[d] . . . the
    Adorers.” App. at 39 ¶ 117. These allegations make plain that
    their RFRA claim is “anchored in [the] pipeline.” Bohon, 37
    F.4th at 666. It is “inescapably intertwined” with the pipeline’s
    route, construction, and operation. Otwell, 747 F.3d at 1282.
    And the “heart of th[e] claim[]” challenges the operation of the
    pipeline, which was authorized after extensive, public
    proceedings before FERC as required by the NGA and FERC
    regulations. Am. Energy Corp., 
    622 F.3d at 605
    .
    The consequences of a hypothetical victory for the
    Adorers betray the collateral nature of their RFRA damages
    suit. Were the Adorers to succeed on their RFRA claim,
    moreover, a damages award could conceivably affect, among
    other things, the price of gas flowing to Transco’s customers,
    the gas flow rate, and the general fiscal and economic impact
    of operating the pipeline. Such a result would no doubt
    impermissibly, “directly imperil[]” the FERC certificate and
    would otherwise undermine the certification procedure
    Congress created in enacting the NGA. Bohon, 37 F.4th at
    666. Furthermore, it would cause potential contractors to think
    twice before embarking on a costly project only to later face
    claims for damages caused by the pipeline. Thus, the Adorers’
    claim is, like the plaintiffs’ claims in Tacoma, Otwell,
    Williams, Bohon, and Am. Energy, an impermissible collateral
    attack.
    23
    C.
    We cannot conclude without addressing three specific
    contentions pressed by the Adorers in their briefs and at oral
    argument. First, they urge that because FERC cannot award
    money damages, this suit was properly brought in District
    Court.6 But this argument makes little sense. Had they
    proceeded with an objection before FERC, and convinced the
    Commission of a violation, no doubt the Commission would
    have provided relief—by rerouting the pipeline or otherwise
    attaching some condition upon the permit as it did in countless
    other instances—and if it did not, the Adorers would have had
    recourse to an appeal to an appropriate court of appeals. If their
    claim was valid, they would have suffered no harm. Moreover,
    any claim for damages would not have been cognizable as no
    damage had yet occurred. Whether FERC can or cannot award
    damages is irrelevant.
    Second, the Adorers essentially repeat the argument
    they made in Adorers I, that their claim was not ripe at the time
    FERC issued the certificate, but rather, the claim began to
    accrue only once Transco “plac[ed] the Pipeline in to [sic]
    service,” App. at 37 ¶ 111, thereby, placing a burden upon their
    religious exercise. In addition to the reason we previously
    rejected this claim,7 we note that were we to adopt the Adorers’
    suggestion that they were under no obligation to present their
    RFRA claim to FERC because the claim was not ripe, the court
    would effectively exempt all claims against a new pipeline’s
    construction and operation from the NGA’s review scheme.
    Such a rule would entirely upend Congress’s intent.
    6
    Appellants’ Br. at 40-47.
    7
    See above Section II.
    24
    Third, the Adorers urge that because Transco knew of
    their objection to the pipeline and neither it nor FERC brought
    them into the administrative proceeding to resolve it, they
    should somehow be permitted to proceed in federal court. But
    this turns the administrative process on its head. It is not up to
    the pipeline contractor or FERC to seek out potential objectors
    at its peril. To the contrary, objectors who sit on their hands
    and do not raise their concerns in the administrative process do
    so at their peril. To permit a party to reserve a claim, the
    success of which would directly imperil a FERC decision to
    certify an interstate pipeline, by remaining silent during the
    FERC proceedings only to raise the claim in de novo litigation
    in a different forum of its own choosing would contravene
    Congress’ decision to channel all such claims through the
    NGA’s exclusive review framework. Such a result would also
    contravene the Supreme Court’s long-standing precedent in
    Tacoma.
    IV.
    For these reasons, we will affirm the District Court’s
    order granting Transco’s motion to dismiss.
    25