Port Hamilton Refining and Transportation LLLP v. EPA ( 2023 )


Menu:
  •                                        PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    _______________________
    No. 23-1094
    _______________________
    PORT HAMILTON REFINING AND TRANSPORTATION,
    LLLP,
    Petitioner
    v.
    U.S. ENVIRONMENTAL PROTECTION AGENCY
    _______________________
    On Petition for Review from a Decision of the
    Environmental Protection Agency
    __________________________
    Argued May 24, 2023
    Before: RESTREPO, McKEE, and SMITH, Circuit Judges
    (Filed: November 22, 2023)
    Andrew C. Simpson [ARGUED]
    Andrew C. Simpson Law Offices
    2191 Church Street, Suite 5
    Christiansted, VI 00820
    Counsel for Petitioner Port Hamilton Refining and
    Transportation LLLP
    Todd S. Kim
    Heather E. Gange [ARGUED]
    United States Department of Justice
    Environment & Natural Resources Division
    P.O. Box 7611
    Ben Franklin Station
    Washington, DC 20044
    Counsel for Respondent United States Environmental
    Protection Agency
    Michael R. Harris [ARGUED]
    Rajeev Venkat
    Vermont Law School
    164 Chelsea Street
    South Royalton, VT 05068
    Counsel for Amici-respondent Sierra Club, St Croix
    Environmental Association, Center for Biological
    Diversity
    __________________________
    OPINION OF THE COURT
    __________________________
    2
    SMITH, Circuit Judge.
    Petitioner Port Hamilton Refining and Transportation,
    LLLP (Port Hamilton or the company) purchased an existing
    petroleum refinery located on St. Croix (Refinery) at a
    bankruptcy auction in December 2021. Port Hamilton hoped to
    resume operations at the Refinery, which had for decades
    served as the backbone of St. Croix’s local economy until it
    ceased operations in 2012. But in November 2022, the
    Environmental Protection Agency (EPA or the agency)
    notified Port Hamilton by letter that it would need a Prevention
    of Significant Deterioration (PSD) permit before the Refinery
    could resume operations.
    The PSD permitting program is one tool among many
    provided in the Clean Air Act (CAA) that seeks to curb
    excessive air pollution. To obtain a PSD permit, a facility must
    not contribute to the violation of applicable air quality
    standards and must implement the “best available control
    technology” to limit air pollution. 
    42 U.S.C. §§ 7475
    (a),
    7479(3). As is evident from the permit’s title, the PSD is a
    preventative measure. It applies to newly constructed
    stationary sources of air pollution and sources that undergo
    emissions-altering modifications. 
    Id.
     §§ 7475(a), 7479(2)(C),
    7411(a)(4).
    Since the PSD program’s inception, EPA has developed
    its own understanding of what constitutes a newly constructed
    facility. Under EPA’s so-called “Reactivation Policy” (Policy),
    an existing facility is “new” if EPA concludes that it had
    previously been “shut down” and restarted. Matter of Monroe
    3
    Electric Generating Plant, Petition No. 6-99-2, at 7–8
    (June 11, 1999). According to EPA, a shutdown facility must
    obtain a PSD permit upon restart. Id. But if the EPA determines
    that the facility had only been “idled,” then it need not obtain
    a permit. Id.
    As relevant here, EPA issued two determinations as to
    the Refinery’s status under the Reactivation Policy. In 2018,
    EPA notified the Refinery’s prior owner that it need not obtain
    a PSD permit because the Refinery had been only “idled” since
    it last operated in 2012. Then in 2022, EPA reversed course
    and notified Port Hamilton that the agency considered the
    Refinery to have been “shut down” and accordingly would
    need to approve a PSD permit before operations could be
    resumed.
    Port Hamilton petitions this Court for review of
    EPA’s 2022 decision. The company contends that the
    Reactivation Policy as applied to the Refinery exceeds EPA’s
    statutory authority and that even if the policy is valid, EPA
    acted arbitrarily and capriciously. We agree that EPA has
    exceeded its statutory authority under the CAA. Accordingly,
    we will grant the petition and vacate EPA’s decision.
    I.    Statutory and Regulatory Background
    A. Clean Air Act
    Congress enacted the Clean Air Act of 1963 primarily
    to provide federal funding for research on air pollution and to
    encourage states to develop air pollution control programs.
    Clean Air Act of 1963, 
    Pub. L. 88-206, 77
     Stat. 393; United
    4
    States v. EME Homer City Generation, L.P., 
    727 F.3d 274
    , 278
    (3d Cir. 2013). The CAA preceded creation of EPA and left to
    the states much of the authority to regulate air pollution.
    The Clean Air Act Amendments of 1970 marked the
    beginning of a major shift in both the balance and breadth of
    federal regulation over air quality. The CAA, as amended,
    directed the newly created EPA to set “national ambient air
    quality standards,” or “NAAQS.” 
    42 U.S.C. §§ 7408
    –7409;
    Utility Air Reg. Grp. v. EPA, 
    573 U.S. 302
    , 308 (2014). The
    NAAQS set the maximum allowable levels of certain
    pollutants that, in EPA’s view, would protect public health.
    See 
    42 U.S.C. § 7409
    . The states were then required to submit
    “state implementation plans” that detailed how they planned to
    implement and enforce the NAAQS for each pollutant. 
    42 U.S.C. § 7410
    ; Utility Air, 573 U.S. at 308. The statute vests
    authority in EPA to approve or disapprove each state’s
    implementation plan. 
    42 U.S.C. § 7410
    ; Train v. Nat. Res. Def.
    Council, Inc., 
    421 U.S. 60
    , 64–65 (1975); Gen. Motors Corp.
    v. United States, 
    496 U.S. 530
    , 532–33 (1990).
    In 1977, Congress further amended the CAA to enact
    the New Source Review (NSR) program. The NSR program
    aimed to combat air pollution proactively by requiring new
    stationary sources of air pollution to meet certain requirements
    prior to the commencement of their construction. See 
    42 U.S.C. § 7475
     (titled “Preconstruction requirements”); 
    id.
    § 7502(c)(5) (requiring permits for “the construction and
    operation” of certain facilities). The program requires each
    new stationary source of air pollution to obtain one of two
    types of permits from the EPA depending on whether the
    5
    geographic area is in “attainment” of each NAAQS.1 Utility
    Air, 572 U.S. at 308–09.
    The first type of permit is what is at issue in this case—
    the PSD permit—and applies to certain stationary sources of
    air pollution to be built in designated “attainment” areas. Id. To
    obtain a PSD permit, the proposed source must not cause or
    contribute to the violation of applicable air quality standards
    and must implement the “best available control technology”
    for each NAAQS pollutant. 
    42 U.S.C. § 7475
    (a)(3)–(4); Utility
    Air, 573 U.S. at 309. The stationary sources subject to PSD
    permitting are major emitting facilities “constructed” after
    August 7, 1977 (the date the New Source Review program
    went into effect). 
    42 U.S.C. § 7475
    (a). The CAA defines
    “construction” as “includ[ing] modification.” 
    Id.
     § 7479(2)(C).
    “Modification” is “any physical change in, or change in the
    method of operation of, a stationary source which increases the
    amount of any air pollutant emitted by such source or which
    results in the emission of any air pollutant not previously
    emitted.” Id. § 7411(a)(4). In sum, the CAA provides that a
    major emitting facility must obtain a PSD permit if it is
    constructed or “modified” in an attainment area after 1977.
    The second permitting program, the Nonattainment
    New Source Review (NNSR) program, applies to stationary
    1
    The CAA requires each state to designate “all areas . . . in the
    State” as “nonattainment,” “attainment,” or “unclassifiable”
    for each of the NAAQS. 
    42 U.S.C. § 7407
    (d). “Attainment”
    means that the area has reached appropriate levels of the
    regulated air pollutant.
    6
    sources built in areas with air quality that does not meet the
    NAAQS, known as “nonattainment areas.” Gen. Motors, 
    496 U.S. at 534
    . To obtain a NNSR permit, the applicant must
    ensure that the proposed source “compl[ies] with the lowest
    achievable emission rate,” arrange for “offsetting emissions
    reductions” such that the new source will not increase regional
    emissions, and meet other stringent requirements. 
    42 U.S.C. § 7503
    ; Chevron, U.S.A., Inc. v. Nat. Res. Def. Council,
    Inc., 
    467 U.S. 837
    , 840 (1984); New York v. EPA, 
    413 F.3d 3
    ,
    13 (D.C. Cir. 2005).
    B. EPA’s Reactivation Policy
    Consistent with the CAA, EPA’s implementing
    regulations provide that the PSD program applies to any “new
    major stationary source or [] major modification.” 
    40 C.F.R. § 52.21
    (a)(2)(iii) (emphasis added). In a series of individual
    PSD permitting decisions, EPA formulated what it later called
    its “Reactivation Policy.” See Matter of Monroe, Petition
    No. 6-99-2. That policy purports to interpret the meaning of the
    word “new” in its regulations and addresses whether an
    existing but out-of-operation facility needs a PSD permit
    before restarting. Under the Policy, an existing facility is
    considered “new” (and thus in need of a PSD permit) if EPA
    determines that it had been “permanently shutdown” when it
    previously ceased operations. 
    Id. at 8
    . But if the facility had
    only been “idled,” then the existing facility is not “new.” 
    Id. 7, 10
    . To determine whether a facility had been permanently shut
    down, EPA looks to the following six factors:
    (1) “the amount of time the facility has been out of
    operation,”
    7
    (2) “the reason for the shutdown,”
    (3) “statements by the owner or operator regarding
    intent,”
    (4) “cost and time required to reactivate the facility,”
    (5) “status of permits,” and
    (6) “ongoing maintenance and inspections that have
    been conducted during shutdown.”
    
    Id.
     at 8–9. This determination requires a fact-intensive inquiry.
    EPA has explained that “[n]o single factor is likely to be
    conclusive in the Agency’s assessment of these factors, and the
    final determination will often involve a judgment as to whether
    the owner’s or operator’s actions at the facility during
    shutdown support or refute any express statements regarding
    the owner’s or operator’s intentions.” 
    Id. at 9
    . The scope of
    EPA’s authority under this policy is at the heart of what Port
    Hamilton challenges in the petition before this Court.
    II.    Factual Background
    The Refinery’s first owner built it in the late 1960s
    pursuant to an agreement with the Government of the Virgin
    Islands (GVI) and the GVI’s Port Authority. That first owner,
    HOVENSA, LLC (Hovensa), operated the Refinery
    until 2012, when it announced plans to close the facility after
    significant financial losses. The GVI, recognizing the
    Refinery’s “economic importance to the Virgin Islands,”
    intervened by urging Hovensa to find a buyer for the Refinery.
    8
    A 36 & n.30.2 Although the Refinery remained out of use since
    Hovensa’s 2012 announcement, Hovensa worked with GVI in
    attempts to sell the Refinery. Hovensa eventually entered
    bankruptcy in 2015, and the Refinery passed to the bankruptcy
    estate.
    Limetree Bay Terminals, LLC (Limetree) purchased the
    Refinery from the bankruptcy estate in 2016 and planned to
    restart the Refinery’s operations. In 2018, Limetree sent EPA
    a letter asking whether EPA would consider the Refinery a new
    source under its Reactivation Policy if Limetree resumed
    operations. EPA agreed with Limetree that the Refinery would
    not be a new source. EPA explained that, based on the
    Reactivation Policy’s six factors, the Refinery had only been
    “idled”—as opposed to “shut down”—since Hovensa ceased
    operations in 2012. A 71. That meant the Refinery did not
    qualify as a “new” facility requiring a PSD permit.3 EPA
    further noted that although it had applied its Reactivation
    Policy to address Limetree’s questions, the agency “intend[ed]
    2
    Both parties filed appendices in this appeal. We refer to the
    appendices filed by Port Hamilton and EPA as “A” and “SA,”
    respectively.
    3
    EPA’s 2018 letter also noted that it was not providing a “final
    determination” as to the applicability of the PSD program
    because Limetree had not submitted “emissions information
    and other specifics regarding [its] planned projects.” A 77. This
    statement appears to refer to the second basis for a PSD permit:
    if the facility is modified in a way that alters its emissions
    levels. See 
    42 U.S.C. §§ 7475
    (a), 7479(2)(C), 7411(a)(4).
    Neither party contends that the Refinery had been modified.
    9
    to reconsider the policy in the near future.” A 71 n.2. In
    particular, EPA expressed concern that it had not grounded the
    Reactivation Policy in “any specific regulatory provisions of
    the NSR program to support its position of ‘reactivation.’” 
    Id.
    Later that year, Limetree applied for a Plantwide
    Applicability Limit (PAL) permit. The PAL permit is not at
    issue in this appeal, but it is relevant insofar as it sheds light on
    EPA’s own misgivings concerning the Reactivation Policy. In
    response to public comments addressing Limetree’s PAL
    application, the agency reiterated its earlier view that it
    “intended to reconsider the Reactivation Policy.” SA 209. EPA
    explained:
    [T]he Agency has determined it is not
    appropriate to continue applying the
    Reactivation Policy because the policy was not
    well-grounded in the NSR regulations, and it is
    not supported by the current NSR regulations. In
    addition, the Reactivation Policy is difficult to
    follow and can produce inconsistent results
    based on subjective judgments about how to
    weigh the various factors against each other.
    
    Id.
    Over the next three years, Limetree made substantial
    financial investments in the Refinery so that it was up and
    running by February 2021. But the Refinery quickly ran into
    trouble. On February 4, 2021, a mixture of oil and water
    10
    emitted from a flare at the Refinery.4 Limetree promptly
    received calls from local residents who complained that oil
    droplets had rained upon their homes, cars, and vegetable
    gardens, and in some cases had compromised water cisterns.
    Then, for five consecutive days in April 2021, the
    Refinery emitted hydrogen sulfide and sulfur dioxide at levels
    that exceeded emissions standards. Those emissions resulted in
    the shutdown of in-person learning at three St. Croix schools.
    In May, the Refinery again emitted excessive sulfur dioxide,
    prompting the closure of the same three schools. One week
    later, the Refinery experienced another flaring incident in
    which droplets of oil rained on a nearby neighborhood.
    Soon thereafter, Limetree advised EPA that it would
    cease oil production for an unspecified period of time. Two
    days later, the agency issued an emergency order under
    Section 303 of the CAA, 
    42 U.S.C. § 7603
    , requiring Limetree
    to immediately cease all operations at the Refinery.
    In July 2021, just two months later, Limetree filed for
    bankruptcy and the Refinery was put up for sale a second time.
    In September 2021, EPA signaled that despite its earlier
    comments, it planned to continue applying the Reactivation
    Policy. It published a notice in the bankruptcy reading room
    advising that “[a] prospective purchaser may also be required
    to obtain a Prevention of Significant Deterioration (‘PSD’)
    permit under the Clean Air Act to restart the refinery.” SA 199.
    The notice explained that “EPA has required PSD permits for
    4
    A flare is a structure used to burn off excess refinery-
    generated gases.
    11
    restarting long-dormant facilities that qualify as major
    stationary sources because this action can qualify as either the
    construction of a new source or a major modification of an
    existing one.” 
    Id.
    In December 2021, Port Hamilton submitted questions
    to the U.S. Department of Justice and EPA about the permits it
    would need to operate the Refinery. Later that month, and
    before it received a response from DOJ and EPA, Port
    Hamilton purchased the Refinery from Limetree’s bankruptcy
    estate. The agency responded to Port Hamilton’s inquiry,
    advising in March of 2022, that based on the information it
    had, there were “strong indicators” that Port Hamilton would
    need a PSD permit to start up the Refinery. SA 248.
    EPA issued its final determination as to PSD permitting
    for the Refinery in November 2022 (Final Determination
    Letter). Although EPA’s application of the Reactivation Policy
    in 2018 led it to conclude that the Refinery had been “idled”
    since 2012, its 2022 Determination Letter informed Port
    Hamilton that it considered the Refinery to actually have been
    “shut down” since Hovensa ceased operations in 2012. A 23.
    The agency noted that it arrived at its 2022 decision after
    considering a more developed record than it had reviewed
    in 2018.
    Port Hamilton timely petitioned this Court for review of
    the Final Determination Letter. Port Hamilton contends that
    EPA’s application of the Reactivation Policy exceeds its
    statutory authority because the CAA applies the PSD program
    only to newly constructed facilities and modifications. Because
    the Refinery meets neither of those criteria, Port Hamilton
    12
    argues, the agency exceeded its statutory authority by requiring
    the company to obtain a PSD permit for the Refinery.
    Alternatively, Port Hamilton argues that even if the
    Reactivation Policy is valid, EPA acted arbitrarily and
    capriciously by reaching two opposing conclusions in 2018
    and 2022.
    III.   Analysis5
    Port Hamilton contends that EPA has exceeded its
    authority under the Clean Air Act. We agree. The Clean Air
    Act unambiguously limits the PSD program’s application to
    newly constructed or modified facilities. The Refinery is not
    new and has not undergone a “modification” as the Act defines
    that term. The EPA therefore exceeded its authority by
    requiring Port Hamilton to obtain a PSD permit for the
    Refinery.
    We begin and end our analysis with the unambiguous
    text of the CAA.6 Section 7475(a) provides that “[n]o major
    5
    We have jurisdiction to review EPA’s Final Determination
    Letter because it is a “final action” within the meaning of 
    42 U.S.C. § 7607
    (b)(1).
    6
    Because the statute is clear, we need not consider whether
    Chevron or Auer deference is appropriate. Johnson v. Guzman
    Chavez, 
    141 S. Ct. 2271
    , 2291 n.9 (2021) (“Chevron deference
    does not apply where the statute is clear.”); EME Homer City
    Generation, 
    727 F.3d at
    291 n.17 (concluding that the Court
    need not “defer to the EPA’s interpretation of the PSD
    regulations . . . because such an interpretation would contradict
    the unambiguous text of § 7475(a)”).
    13
    emitting facility on which construction is commenced after
    August 7, 1977, may be constructed” in an attainment area
    without a PSD permit. 
    42 U.S.C. § 7475
    . The statute defines
    “construction” as including “modification.” 
    Id.
     § 7479(2)(C).
    The plain text here is straightforward. Reading these two
    sections together, major emitting facilities constructed or
    modified in attainment areas after 1977 are required to obtain
    a PSD permit.
    Yet EPA contends that § 7475 is ambiguous because it
    fails to address exactly what sort of construction triggers the
    need for a PSD permit. The agency argues that the phrase
    “construction is commenced” could refer to construction
    commenced at a shutdown facility in preparation for a restart.
    But EPA overlooks the second half of § 7475(a). That portion
    provides that no major emitting facility “may be constructed”
    in an attainment area if that construction is commenced
    after 1977. Id. (emphasis added). That text directly speaks to
    the question that EPA has posed. The type of construction that
    requires a PSD permit is construction commenced after 1977
    that brings a major emitting facility into existence.
    EPA next contends that the statute’s definition of
    “construction” is ambiguous. The CAA defines “construction”
    as follows: “The term ‘construction’ when used in connection
    with any source or facility, includes the modification (as
    defined in section 7411(a) of this title) of any source or
    facility.” Id. § 7479(2)(C). EPA seizes on the word “includes.”
    Because the definition only “includes” modification, EPA
    argues, the statute leaves open the possibility that there are
    other types of construction also covered by the statute.
    14
    But we have already held that § 7475 and § 7479 set out
    an exclusive definition of “construction.” In United States v.
    EME Homer City Generation, L.P., we explained that the
    CAA’s PSD permitting provisions unambiguously extended
    the PSD program to construction and modification alone, and
    not “operation” as EPA had argued. 
    727 F.3d at 284
    ; see also
    
    id. at 290
     (“In short, § 7475(a) unambiguously prohibits only
    constructing or modifying a facility without meeting PSD
    requirements.”). We also noted that the statute’s definition of
    construction “include[s]” modification, but “does not include
    ‘operation.’” Id. The same goes for EPA’s position here. The
    CAA’s definition of construction includes “modification” but
    does not include “restart after a shutdown” or language to that
    effect. As we held in EME Homer, the CAA limits the PSD
    program’s reach to only two circumstances: construction and
    modification. Id. at 284–85.
    EPA’s Reactivation Policy extends the PSD program
    beyond those limited circumstances. Under that policy,
    because EPA in 2022 determined that the Refinery had been
    “shut down,” Port Hamilton would need to obtain a PSD permit
    before it could resume its operations. This application of the
    PSD program strays from the unambiguous text of the CAA.
    The parties do not dispute that Hovensa built the Refinery
    before 1977, nor does the agency contend that Port Hamilton
    had “modified” the Refinery within the meaning of the statute.
    EPA therefore exceeded its statutory authority by requiring
    Port Hamilton to obtain a PSD permit for the Refinery. We
    15
    conclude that EPA’s Final Determination Letter must be
    vacated.7
    IV.    Conclusion
    We will grant Port Hamilton’s petition for review and
    vacate EPA’s Final Determination Letter.
    7
    Because we hold that EPA’s Reactivation Policy exceeds its
    statutory authority, we need not decide whether EPA applied
    the Reactivation Policy arbitrarily and capriciously as to Port
    Hamilton.
    16
    

Document Info

Docket Number: 23-1094

Filed Date: 11/22/2023

Precedential Status: Precedential

Modified Date: 11/22/2023