PJM Power Providers Group v. FERC ( 2023 )


Menu:
  •                               PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    Nos. 21-3068, 21-3205 & 21-3243
    ____________
    PJM POWER PROVIDERS GROUP,
    Petitioner in No. 21-3068
    v.
    FEDERAL ENERGY REGULATORY COMMISSION
    ___________________________
    ELECTRICAL POWER SUPPLY ASSOCIATION,
    Petitioner in No. 21-3205
    v.
    FEDERAL ENERGY REGULATORY COMMISSION
    ___________________________
    PENNSYLVANIA PUBLIC UTILITY COMMISSION;
    PUBLIC UTILITIES COMMISSION OF OHIO,
    Petitioner in No. 21-3243
    v.
    FEDERAL ENERGY REGULATORY COMMISSION
    On Petition for Review of an Order of the
    Federal Energy Regulatory Commission
    (FERC No. ER21-2582-000)
    Argued on January 10, 2023
    Before: JORDAN, PHIPPS and ROTH, Circuit Judges
    (Opinion filed December 1, 2023)
    Elbert Lin
    Charles D. Wallace, III
    Hunton Andrews Kurth
    951 East Byrd Street
    Riverfront Plaza East Tower
    Richmond, VA 23219
    John L. Shepherd, Jr.    (ARGUED)
    Hunton Andrews Kurth
    2200 Pennsylvania Avenue, NW
    Washington, DC 20037
    Counsel for Petitioner PJM Power Providers
    Group
    2
    Paul W. Hughes
    McDermott Will & Emery
    500 N Capitol Street, NW
    Washington, DC 20001
    Counsel for Petitioner Electric Power Supply
    Association
    Kriss E. Brown             (ARGUED)
    Christian A. McDewell
    Pennsylvania Public Utility Commission
    Commonwealth Keystone Building
    400 N Street
    PO Box 3265
    Harrisburg, PA 17120
    Counsel for Petitioner Pennsylvania Public
    Utility Commission
    Thomas G. Lindgren
    Werner L. Margard, III
    Office of Attorney General of Ohio
    30 East Broad Street
    26th Floor
    Columbus, OH 43215
    Counsel for Petitioner Public Utilities
    Commission of Ohio
    3
    Jeffrey W. Mayes
    Monitoring Analytics
    2621 Van Buren Avenue
    Suite 160
    Eagleville, PA 19403
    Counsel for Intervenor Petitioner Monitoring
    Analytics LLC
    Denise C. Goulet          (ARGUED)
    McCarter & English
    1301 K Street, NW
    Suite 1000 West
    Washington, DC 20005
    Counsel for Intervenor Petitioner Office of the
    Consumers Counsel State of Ohio OCC
    Jared E. Fish             (ARGUED)
    Federal Energy Regulatory Commission
    881 1st Street, N.E.
    Washington, DC 20426
    Counsel for Respondent
    Danielle C. Fidler
    Earthjustice Legal Defense Fund
    1001 G Street, NW
    Suite 1000
    Washington, DC 20001
    Counsel for Intervenor Respondents Union of
    Concerned Scientists and Sierra Club
    4
    Peter Hopkins
    Amber L. Martin Stone
    Jeffrey A. Schwartz
    Scott H. Strauss         (ARGUED)
    Cynthia Bogorad
    Lauren L. Springett
    Spiegel & McDiarmid
    1875 Eye Street, NW
    Suite 700
    Washington, DC 20006
    Counsel for Intervenor Respondents Delaware
    Division of Public Advocate; Maryland Office
    of Peoples Counsel; New Jersey Division of
    Rate Counsel and Office of Peoples Counsel for
    the District of Columbia
    Matthew Price          (ARGUED)
    Jenner & Block
    1099 New York Avenue, NW
    Suite 900
    Washington, DC 20001
    Counsel for Intervenor Respondents
    Constellation Energy Corp and Constellation
    Energy Generation LLC
    5
    Miles H. Mitchell
    Maryland Public Service Commission
    6 St. Paul Street
    6 St. Paul Centre, 16th Floor
    Baltimore, MD 21202
    Counsel for Intervenor Respondent Maryland
    Public Service Commission
    David C. Apy
    Office of Attorney General of New Jersey
    Division of Law
    25 Market Street
    Hughes Justice Complex
    Trenton, NJ 08625
    Counsel for Intervenor Respondent New Jersey
    Board of Public Utilities
    Robert A. Weishaar, Jr.
    McNees Wallace & Nurick
    1200 G Street, NW
    Suite 800
    Washington, DC 20005
    Counsel for Intervenor Respondent PJM
    Industrial Customer Coalition
    6
    Ryan J. Collins
    Paul M. Flynn
    Wright & Talisman
    1200 G Street, NW
    Suite 600
    Washington, DC 20005
    Counsel for Intervenor respondent PJM
    Interconnection LLC
    Caroline Reiser
    Natural Resources Defense Council
    1152 15th Street, NW
    Site 300
    Washington, DC 20005
    Counsel for Intervenor Respondent Natural
    Resource Defense Council
    Casey Roberts
    Sierra Club
    1536 Wynkoop Street
    Suite 200
    Denver, CO 80202
    Megan C. Wachspress
    Sierra Club Environmental law Program
    2101 Webster Street
    13th Floor
    Oakland, CA 94612
    Counsel for Intervenor Respondent Sierra Club
    7
    Sarah A. Hunger
    Office of Attorney General of Illinois
    100 West Randolph Street
    12th Floor
    Chicago, IL 60601
    Counsel for Intervenor Respondents Illinois
    Commerce Commission and People of the State
    of Illinois
    Cynthia Bogorad
    Lauren L. Springett
    Spiegel & McDiarmid
    1875 Eye Street NW
    Suite 700
    Washington, DC 20006
    Counsel for Intervenor Respondent Buckeye
    Power, Inc.
    Adrienne E. Clair
    Thompson Coburn
    1909 K Street, NW
    Suite 600
    Washington, DC 2006
    Counsel for Intervenor Respondent Old
    Dominion Electric Cooperative; National Rural
    Electric Cooperative Association
    8
    Daniel E. Frank
    Allison Speaker
    Eversheds Sutherland
    700 Sixth Street, NW
    Suite 700
    Washington, DC 20001
    Counsel for Intervenor Respondent East
    Kentucky Power Cooperative Inc.
    Andrew D. Cordo
    Shannon E. German
    Wilson Sonsini Goodrich & Rosati
    222 Delaware Avenue
    Suite 800
    Wilmington, DE 19801
    Counsel for Intervenor Respondent Advanced
    Energy Economy
    Gerit Hull
    American Municipal Power
    1111 Schrock Road
    Suite 100
    Columbus, OH 43229
    Counsel for Intervenor Respondent American
    Municipal Power Inc.
    9
    John E. McCaffrey, III
    American Public Power Association
    2451 Crystal Drive
    Suite 1000
    Arlington, VA 22202
    Counsel for Intervenor Respondent American
    Public Power Association
    Anthony J. Corino
    PSEG Corporation
    80 Park Plaza
    Newark, NJ 07102
    Counsel for Intervenor Respondents PSEG;
    PSEG Power LLC and PSEG ER&T
    Donald R. Goodson
    Institute for Policy Integrity
    139 MacDougal Street
    Third Floor
    New York, NY 10012
    Counsel for Amicus Appellee Institute for
    Policy Integrity at New York University School
    of Law
    10
    Christopher R. Nestor
    Overstreet & Nestor
    461 Cochran Road
    P.O. Box 237
    Pittsburgh, PA 15228
    Counsel for Amicus Petitioner Pennsylvania
    Senate Republican Caucus
    Michael E. Rowan
    Office of Attorney General of Maryland
    Higher Education Div.
    200 St Paul Place
    20th Floor
    Baltimore, MD 21202
    Counsel for Amicus Respondents District of
    Columbia, State of Delaware and State of
    Maryland
    Ari Peskoe
    Harvard Electricity Law Initiative
    6 Everett Street
    Suite 4119
    Cambridge, MA 02138
    Counsel for Amicus Respondent Electricity
    Regulation Scholars
    11
    O P I N I ON
    ROTH, Circuit Judge:
    This consolidated action represents the latest salvo in a
    years-long battle over whether, and to what extent, state-
    subsidized energy resources should be subject to price
    mitigation in interstate capacity auctions. The focal point of
    the dispute is a tariff filed by PJM Interconnection, L.L.C.
    (PJM), which took effect by operation of law in 2021. 1
    Three separate petitions now ask us to exercise, for the
    first time, our authority to review this “action by inaction”
    pursuant to Section 205(g) of the Federal Power Act (FPA), 2 a
    2018 provision expressly articulating the right to review under
    these circumstances. PJM Power Providers Group (P3) and
    Electric Power Supply Association (EPSA) (collectively,
    Generators), two nonprofit associations representing energy
    generators, filed separate petitions.       Pennsylvania Public
    Utility Commission and Public Utilities Commission of Ohio
    (State Entities) jointly filed the third. 3
    1
    16 U.S.C. § 824d(g).
    2
    Id. §§ 791 et seq.
    3
    More than two dozen intervenors and amici also filed briefs.
    Intervenor Petitioners include: Monitoring Analytics LLC and
    the Ohio Office of the Consumers Counsel. Amicus for
    Petitioners is the Pennsylvania Senate Republican Caucus.
    Intervenor Respondents include:        Union of Concerned
    Scientists, Delaware Division of the Public Advocate,
    12
    The Petitioners, Federal Energy Regulatory
    Commission (FERC), and numerous intervenors and amici
    dispute the proper scope of our review pursuant to § 205(g).
    We hold that our review of FERC “action,” whether actual or
    constructive, proceeds under the same deferential standards set
    forth in the FPA and Administrative Procedure Act. 4
    Consistent with Congress’s directive in § 205(g), we further
    hold that our review properly encompasses the
    Commissioners’ mandatory statements setting forth their
    reasons for approving or denying the filing.
    Reviewing the petitions accordingly, we will deny all
    three because FERC’s acceptance of PJM’s tariff was not
    Maryland Office of Peoples Counsel, Maryland Public Service
    Commission, New Jersey Board of Public Utilities, New Jersey
    Division of Rate Counsel, Natural Resources Defense Council,
    Natural Rural Electric Cooperative, Office of Peoples Counsel
    for the District of Columbia, PJM Industrial Customer
    Coalition, PJM Interconnection LLC, Sierra Club, Illinois
    Commerce Commission, People of the State of Illinois,
    Buckeye Power Inc., Old Dominion Electric Cooperative, East
    Kentucky Power Cooperative Inc., Advanced Energy
    Economy, American Municipal Power Inc., American Public
    Power Association, PSEG, PSEG Power LLC, PSEG ER&T,
    Constellation Energy Corp, Constellation Energy Generation
    LLC, and Exelon Generation Co LLC. Amici on behalf of
    FERC include: the Institute for Policy Integrity at New York
    University School of Law, the District of Columbia, the State
    of Delaware, the State of Maryland, and Electricity Regulation
    Scholars.
    4
    
    5 U.S.C. §§ 551
     et seq.
    13
    arbitrary or capricious and was supported by substantial
    evidence in the record.
    I.     Background
    To frame the issues presented by the parties, we begin
    by reviewing the key statutory provisions governing this
    action, with a particular focus on § 205(g), the 2018
    amendment to the FPA concerning judicial review of FERC
    action by operation of law. We then turn to the factual and
    procedural context for their claims.
    A.     The Federal Power Act and Judicial Review
    FERC is the independent agency to which Congress, in
    the FPA, granted exclusive jurisdiction to ensure “rates
    charged by public utilities for the transmission and sale of
    energy in interstate commerce, and the ‘rules and regulations
    affecting or pertaining to such rates’, [sic] are ‘just and
    reasonable.’” 5 While the FPA empowers FERC to regulate
    “all facilities for such transmission or sale of electric energy,”
    it reserves jurisdiction over “facilities used for the generation
    of electric energy” to state and local authorities. 6
    5
    New Jersey Bd. of Pub. Utils. v. FERC, 
    744 F.3d 74
    , 79 (3d
    Cir. 2014) (quoting 16 U.S.C. § 824d) (hereinafter NJBPU).
    6
    NJBPU, 
    744 F.3d at 80
     (quotations omitted) (quoting §
    824(b)(1)); FERC v. Elec. Power Supply Ass’n, 
    577 U.S. 260
    ,
    264 (2016) (noting that the FPA “authorizes [FERC] to
    regulate ‘the sale of electric energy at wholesale in interstate
    commerce,’” but “leaves to the States alone, the regulation of
    ‘any other sale’ … of electricity”).
    14
    Sections 205 and 206 of the FPA set forth the means by
    which FERC may “fulfill its statutory charge of ensuring the
    justness and reasonableness of rates.” 7 Together, they
    comprise part of “a single statutory scheme under which all
    rates are established initially by the [public utilities] . . . and all
    rates are subject to being modified by the Commission upon a
    finding that they are unlawful.” 8 Section 205 provides that
    “public utilities may change their rates unilaterally, upon 60
    days’ notice to FERC, which then reviews the changed rates to
    ensure that they are ‘just and reasonable.’” 9 “It
    is not necessary, in a filing pursuant to § 205, that FERC find
    that the previous rate was unjust or unreasonable.” 10 Rather,
    here FERC “plays ‘an essentially passive and reactive role.’” 11
    Section 206, in contrast, provides that FERC may proactively
    initiate rate changes, either on its own motion or in response to
    a complaint, if the moving party demonstrates that the existing
    rate is unjust and unreasonable and the proposed alternative is
    just and reasonable. 12 Notably, § 206 does not “give[] FERC
    the power to deny a utility the right to file changes” unilaterally
    under § 205. 13
    7
    Pub. Citizen, Inc. v. FERC, 
    839 F.3d 1165
    , 1167 (D.C. Cir.
    2016).
    8
    Atl. City Elec. Co. v. FERC, 
    295 F.3d 1
    , 10 (D.C. Cir. 2002)
    (alteration in original) (quoting United Gas Pipe Line Co. v.
    Mobile Gas Serv. Corp., 
    350 U.S. 332
    , 341 (1956)).
    9
    NJBPU, 
    744 F.3d at 94
    ; see 16 U.S.C. § 824d(d).
    10
    NJBPU, 
    744 F.3d at
    94 (citing Atl. City Elec. Co., 
    295 F.3d at
    9–10); see 16 U.S.C. § 824d(a)-(d).
    11
    NJBPU, 
    744 F.3d at 94
     (quoting Atl. City Elec. Co., 
    295 F.3d at
    9–10).
    12
    16 U.S.C. § 824e(a).
    13
    Atl. City Elec. Co., 
    295 F.3d at 10
    .
    15
    Our jurisdiction to review FERC orders arises under the
    FPA and Administrative Procedure Act. 14 Specifically, the
    FPA provides that a party aggrieved by a FERC order must first
    seek rehearing by the Commission, which may grant or deny
    rehearing, abrogate or modify its order without rehearing, or
    constructively deny rehearing by failing to act within thirty
    days. 15 Within sixty days of the Commission’s order on the
    application for rehearing, an aggrieved party may seek review
    of “order[s] issued by the Commission” in the courts of
    appeals. 16 The FPA provides that we “shall have jurisdiction,
    which upon the filing of the record with it shall be exclusive,
    to affirm, modify, or set aside such order in whole or in part.” 17
    Finally, the FPA makes clear that, absent orders to the contrary,
    neither the filing of an application for rehearing before the
    Commission nor the start of proceedings before the court of
    appeals shall “operate as a stay of the Commission’s order.” 18
    The question of what constitutes a reviewable
    Commission order is central to this dispute. FERC’s enabling
    statute establishes that “[a]ctions of the Commission shall be
    determined by a majority vote of the members present.” 19
    While FERC comprises five commissioners, a quorum requires
    14
    See 16 U.S.C. § 825l(b); 
    5 U.S.C. § 702
     (waiving sovereign
    immunity for claims for relief “other than money damages”);
    
    28 U.S.C. § 1331
    .
    15
    16 U.S.C. § 825l(a).
    16
    Id. § 825l(b)
    17
    Id. (“The finding of the Commission as to the facts, if
    supported by substantial evidence, shall be conclusive.”).
    18
    Id. § 825l(c).
    19
    
    42 U.S.C. § 7171
    (e).
    16
    just three, making it possible for four commissioners to
    deadlock two-to-two. 20 In Public Citizen, Inc. v. FERC, the
    Court of Appeals for the D.C. Circuit considered whether
    judicial review was available for a § 205 rate filing that took
    effect after the four sitting Commissioners deadlocked and
    failed to act within sixty days. 21 The court determined that it
    lacked jurisdiction. 22 With regard to the FPA, the court held
    that the secretarial notice issued by the Commission to
    “describ[e] the effects of the deadlock are not reviewable
    orders” 23 because “FERC did not engage in collective,
    institutional action when it deadlocked.” 24 The court held that
    it also lacked jurisdiction under the APA because that statute
    only makes inaction reviewable “where the agency fails to take
    a ‘discrete’ action it is legally required to take,” 25 and the FPA
    does not “compel” FERC to act on a § 205 filing.26
    Accordingly, the court held that it lacked jurisdiction to review
    FERC inaction resulting in an order by operation of law. The
    court concluded that “[a]ny unfairness associated with this
    outcome inheres in the very text of the FPA. Accordingly, it
    lies with Congress, not this Court, to provide the remedy.” 27
    20
    Id. § 7171(b)(1), (e).
    21
    
    839 F.3d at 1170
    .
    22
    
    Id.
    23
    
    Id. at 1172
    .
    24
    
    Id. at 1170
    .
    25
    
    Id. at 1172
     (quoting Norton v. S. Utah Wilderness All., 
    542 U.S. 55
    , 62–63 (2004)).
    26
    Id. at 1174 (explaining that the FPA does “not compel FERC
    to either set the disputed rates for hearing or affirmatively
    disapprove any unjust or unreasonable rates through the
    Section 205 process”).
    27
    Id.
    17
    Congress did so in 2018. Rather than compelling FERC
    to act on a § 205 filing, Congress added a provision to clarify
    how agency inaction should be construed to permit judicial
    review. The new provision, § 205(g), 28 stated that if FERC
    “permits the 60-day period . . . to expire without issuing an
    order accepting or denying the change because the
    Commissioners are divided two against two as to the
    lawfulness of the change . . . or if the Commission lacks a
    quorum” then:
    (A) the failure to issue an order accepting or
    denying the change by the Commission
    shall be considered to be an order issued by
    the Commission accepting the change for
    purposes of section 825l(a) of this title [FPA
    § 313(a)]; and
    (B) each Commissioner shall add to the record
    of the Commission a written statement
    explaining the views of the Commissioner
    with respect to the change. 29
    Section 205(g) further established that if “a person seeks a
    rehearing . . . and the Commission fails to act on the merits of
    the rehearing request” within 30 days because the deadlock
    continues, “such person may appeal under section 825l(b)
    [FPA § 313(b)].” 30
    28
    16 U.S.C. § 824d(g).
    29
    Id. (emphasis added).
    30
    Id. § 824d(g)(2).
    18
    B.     Factual and Procedural Context
    “Since the FPA’s passage, electricity has increasingly
    become a competitive interstate business, and FERC’s role has
    evolved accordingly.” 31 Today, “[i]ndependent power plants
    now abound, and almost all electricity flows not through ‘the
    local power networks of the past,’ but instead through an
    interconnected ‘grid’ of near-nationwide scope.” 32 To ensure
    the reliable transmission of electricity from independent
    generators to “load serving entities” (LSEs)—the
    organizations that deliver electricity to retail consumers—
    FERC has empowered nonprofit entities, including Regional
    Transmission Organizations (RTOs), to manage segments of
    the grid. 33 RTOs constitute “public utilities” under the FPA,
    subject to FERC’s regulation. 34
    Intervenor PJM is one such RTO, managing a system
    that serves approximately fifty million consumers in thirteen
    mid-Atlantic and Midwestern states and the District of
    Columbia. 35 Like other RTOs, PJM fulfills important
    functions that include ensuring the grid maintains sufficient
    electrical supply to meet demand during peak periods. 36 To
    accomplish this, PJM manages a capacity market that
    31
    Elec. Power Supply Ass’n, 577 U.S. at 267.
    32
    Id. (quoting New York v. FERC, 
    535 U.S. 1
    , 7 (2002)).
    33
    Hughes v. Talen Energy Mktg., LLC, 
    578 U.S. 150
    , 155
    (2016).
    34
    NJBPU, 
    744 F.3d at 82
    .
    35
    PJM Br. 3; see Hughes, 578 U.S. at 155.
    36
    NJBPU, 
    744 F.3d at 82
    .
    19
    essentially “pay[s] participants for a promise to produce
    electricity when called by PJM to do so.” 37
    In 2006, the Commission found the existing capacity
    market was unjust and unreasonable because it maintained
    insufficient capacity to keep the system reliable. 38 To remedy
    this, FERC issued an order accepting a negotiated settlement
    among power providers, utility companies, and state and local
    authorities, which provided for the adoption of the Reliability
    Pricing Model. 39 This model works essentially as follows:
    PJM predicts electricity demand
    three years ahead of time, and
    assigns a share of that demand to
    each participating LSE. Owners of
    capacity to produce electricity in
    three years’ time bid to sell that
    capacity to PJM at proposed rates.
    PJM accepts bids, beginning with
    the lowest proposed rate, until it
    has purchased enough capacity to
    satisfy projected demand. . . . [A]ll
    accepted capacity sellers receive
    the highest accepted rate, which is
    called the “clearing price.” LSEs
    37
    PJM Br. 4 (citing NJBPU, 
    744 F.3d at 82
     (explaining that
    the capacity market ensures that “there are enough . . .
    generators connected to the transmission grid for the system to
    function at peak load.”)).
    38
    See PJM Interconnection, L.L.C., 
    135 FERC ¶ 61,022
     (2011)
    (hereinafter 2011 Order) at ¶ 4.
    39
    NJBPU, 
    744 F.3d at 79
    ; see PJM Interconnection, L.L.C.,
    
    117 FERC ¶ 61,331
     (hereinafter 2006 Settlement Order).
    20
    then must purchase from PJM, at
    the clearing price, enough
    electricity to satisfy their PJM-
    assigned share of overall projected
    demand. 40
    Besides allowing LSEs to satisfy their obligations to
    provide a share of projected demand, this forward-looking
    capacity auction serves another purpose, at least in theory:
    sending market signals to suppliers to incentivize resource
    development. 41 “A high clearing price in the capacity auction
    encourages new generators to enter the market, increasing
    supply and thereby lowering the [future] clearing price . . .
    [while] a low clearing price discourages new entry and
    encourages retirement of existing high-cost generators.” 42
    Because some participants both buy and sell capacity in
    the auction, the auctions are theoretically vulnerable to
    manipulation by exercise of monopsony power. 43 That is, net-
    buyers—those who buy more capacity than they sell—could
    artificially depress prices by selling capacity below its true
    cost, skewing the market signals produced by the auction. 44
    
    40 Hughes, 578
     U.S. at 155–56; see PPL Energyplus, LLC v.
    Solomon, 
    766 F.3d 241
    , 251 (3d Cir. 2014); NJBPU, 
    744 F.3d at
    83–84. Technically, PJM operates multiple capacity
    auctions. The one at issue in this appeal, and described here,
    is the Base Residual Auction.
    
    41 Hughes, 578
     U.S. at 155–56; see NJBPU, 
    744 F.3d at 84
    .
    
    42 Hughes, 578
     U.S. at 155–56; see NJBPU, 
    744 F.3d at 84
    .
    43
    NJBPU, 
    744 F.3d at 85
    .
    44
    See FERC Br. 14–15; PJM Br. 6; NJBPU, 
    744 F.3d at
    88–
    89.
    21
    “[T]o address the concern that some market participants might
    have an incentive to depress market clearing prices by offering
    supply at less than a competitive level,” the 2006 Settlement
    Order approved the implementation of the Minimum Offer
    Price Rule (MOPR). 45
    The MOPR established in the 2006 Settlement Order
    (2006 MOPR) was designed to detect bids suppressed through
    monopsony power. An offer that failed a multilevel screening
    process would be “mitigated,” or administratively raised to a
    competitive level. 46 The 2006 MOPR applied only to new
    market entrants, excluding nuclear, coal, and hydroelectric
    resources as well as state-mandated resources. 47 In approving
    this mechanism, FERC concluded that the MOPR was a
    “reasonable method of assuring that net buyers do not exercise
    monopsony power by seeking to lower prices through self
    supply.” 48 Moreover, FERC determined that the MOPR’s
    exception for “reliability projects built under state mandate is
    reasonable because it enables states to meet their
    responsibilities to ensure local reliability.” 49
    Within a few years, consistent with that responsibility,
    New Jersey and Maryland launched initiatives to develop new
    generation resources to address reliability and capacity
    45
    2011 Order at ¶ 6 (citing 2006 Settlement Order at ¶ 103).
    46
    NJBPU, 
    744 F.3d at 85
    .
    47
    
    Id. at 86
     (explaining that state-mandated resources consisted
    of “any planned resource being developed in response to a state
    regulatory or legislative mandate to resolve a projected
    capacity shortfall”).
    48
    2006 Settlement Order at ¶ 104; see NJBPU, 
    744 F.3d at 85
    .
    49
    2006 Settlement Order at ¶ 104.
    22
    concerns in their states. 50 Both initiatives required new
    generation resources to sell capacity in the PJM markets, and
    both intended to offer the capacity a price below cost to ensure
    the new resources would clear. 51
    P3, who is also one of the Petitioners in this action,
    responded by filing a § 206 complaint with FERC, calling for
    an end to the state-mandated resources exception in addition to
    other modifications. 52 PJM then filed a revised tariff pursuant
    to § 205, which FERC approved in 2011 with some alterations
    (2011 Order). The 2011 MOPR eliminated the state-mandated
    resources exemption, “declin[ing] to accord states an
    opportunity to justify their initiatives on policy grounds,
    instead . . . requiring them to submit cost-based offers like other
    entrants or suffer the consequences of mitigation.” 53 At the
    same time, the new MOPR added exemptions for wind and
    solar resources, with the result that after 2011, only natural gas
    facilities were subject to mitigation. 54
    Several parties petitioned this Court for review of the
    2011 Orders, which we denied in 2014. 55 With respect to
    50
    NJBPU, 
    744 F.3d at 87
    .
    51
    
    Id.
    52
    
    Id.
    53
    
    Id. at 91
     (“FERC . . . conclud[ed] that the exemption needed
    to be eliminated due to ‘mounting evidence of risk from what
    was previously only a theoretical weakness in the MOPR
    rules,’ namely, that state-subsidized resources would suppress
    auction prices.”).
    54
    
    Id. at 106
    .
    55
    
    Id. at 112
    . During the pendency of this Court’s decision in
    NJBPU, aspects of the 2011 tariff not relevant to the instant
    23
    FERC’s elimination of the state-mandated resources
    exemption on the grounds that they would suppress auction
    prices, we observed that while “it could easily be argued that
    this danger was foreseeable in 2006 when the MOPR was first
    approved, FERC has adequately advanced a rationale for its
    about-face . . . . As such, it cannot be said that FERC acted
    without substantial evidence.” 56
    In 2016, power suppliers filed a § 206 complaint with
    FERC, challenging the MOPR’s exclusive application to new
    market entrants. They argued that such a limitation was unjust
    and unreasonable because it “allowed below-cost offers from
    existing resources under newly-enacted state subsidy programs
    to unjustly displace non-subsidized resources.” 57 A three-year
    process culminated with FERC’s two-to-one vote in December
    2019, ordering PJM to extend the MOPR to mitigate offers
    from “both new and existing resources” and any resource either
    receiving or eligible to receive a state subsidy (2019 MOPR). 58
    The goal, FERC said, of this dramatic expansion was to
    “protect PJM’s capacity market from the price-suppressive
    effects of resources receiving out-of-market support by
    ensuring that such resources are not able to offer below a
    competitive price.” 59 The sole opposing Commissioner issued
    a dissent, arguing, among other things, that while “the MOPR
    once targeted efforts to exercise market power on behalf of
    matter were amended in a compromise approved by FERC
    order in 2013. See id. at 93–94.
    56
    Id. at 102.
    57
    P3 Br. 15; see Calpine Corp. v. PJM Interconnection, L.L.C.,
    
    169 FERC ¶ 61,239
     (hereinafter 2019 Order).
    58
    2019 Order at ¶¶ 1–2, 5; see EPSA Br. 8; FERC Br. 18–19.
    59
    2019 Order ¶ 5.
    24
    load and directly reduce the capacity market price, it now
    targets state resource decisionmaking, and particularly state
    efforts to address the externalities of electricity generation.” 60
    The 2019 MOPR prompted swift opposition. 61 Dozens
    of parties sought to overturn the 2019 MOPR, including
    “consumer advocate groups, state public utility agencies,
    electric cooperatives [and] generators, clean energy
    organizations, and environmental groups.” 62 These appeals
    were consolidated in the Seventh Circuit and remain in
    abeyance pending this action. 63
    On July 30, 2021, PJM made another § 205 filing,
    setting forth a revised MOPR (2021 MOPR) to replace the
    expansive one it set forth in 2019. PJM acknowledged that,
    over the previous three years, state investments in renewable
    and nuclear resources had proliferated, in part because of
    states’ unabated and legitimate interest in “address[ing]
    externalities that are not accounted for in PJM’s wholesale
    markets.” 64 By “pricing out resources from the capacity
    market” and failing to account for those resources when
    committing capacity, PJM stated, the 2019 MOPR was
    distorting market signals by “incentiv[izing] resources to be
    built that are not needed to maintain reliability” in light of those
    investments. 65 Moreover, the 2019 MOPR was incenting
    60
    2019 Order (Glick, dissenting), ¶ 16.
    61
    FERC Br. 20.
    62
    FERC Br. 20.
    63
    FERC Br. 20–21; see Ill. Commerce Comm’n v. FERC, Nos.
    20-1645, et al. (7th Cir.).
    64
    JA0178.
    65
    JA0178, 181.
    25
    market participants to exit the capacity market to “meet their
    policy and business objectives,” 66 a shift that threatened to
    “exacerbate[]the very price suppression issue [that the 2019
    MOPR] seeks to mitigate.” 67 The result for consumers, PJM
    concluded, would be that those in states providing subsidies
    would “pay[] twice, i.e., for both the excluded resources and
    the resource committed through the auction because the
    excluded resource did not clear” while those in other states
    would see “a capacity cost increase, when . . . the auction
    commits a resource that had a higher Sell Offer than the
    excluded resource’s original offer.” 68 PJM concluded:
    [W]hile state policies favoring certain
    generation resources may ultimately cause a
    reduction in capacity clearing prices, such an
    outcome “should not be interpreted as a
    harmful secondary impact of one state’s
    policies on other states. Rather, the reduction in
    prices is a natural consequence of the PJM
    market appropriately reflecting state policies
    and consumer preferences for certain types of
    resources. Such state subsidies only lower total
    costs for consumers in other states.” 69
    PJM explained that the 2021 MOPR would return to “its
    original purpose by focusing on prohibiting and mitigating the
    exercise of buyer-side market power.” 70 The 2021 “focused”
    MOPR would “generally accommodate both state policies
    66
    JA0182.
    67
    JA0185.
    68
    JA0179–80.
    69
    JA0180.
    70
    JA0171.
    26
    regarding generation resource mix and the long-standing
    business models of public power entities,” 71 while nonetheless
    barring state action, such as those that New Jersey and
    Maryland had pursued in 2011, that would “directly interfere
    with the auction clearing outcomes.” 72 To this end, the 2021
    MOPR would mitigate offers in just two situations: “(1) where
    a capacity resource has the ability and incentive to exercise
    buyer-side market power, and (2) where a capacity resource
    receives state subsidies under a state program that is likely
    preempted by the Federal Power Act.” 73
    When the 2021 MOPR was filed, FERC had four sitting
    commissioners. The commissioners deadlocked two-to-two
    on the new tariff, failing to issue an order accepting or denying
    the change within sixty days. On September 29, 2021, the
    Commission issued a secretarial notice stating that the new
    2021 MOPR was in effect by operation of law. Consistent with
    § 205(g)(1)(B), two commissioners (including the chair) filed
    a Joint Statement articulating their reasons for supporting the
    new tariff, while the other commissioners filed separate
    statements explaining their opposition.
    All rehearing requests were denied without an order on
    November 29, 2021. This petition followed.
    II.    Standing
    An organization suing on its members’ behalf must
    establish associational standing, demonstrating that “(1) at
    71
    JA0194.
    72
    JA0190.
    73
    JA0173; see FERC Br. 22; PJM Br. 23.
    27
    least one of its members would have standing to sue in his or
    her own right; (2) ‘the interests it seeks to protect are germane
    to the organization’s purpose’; and (3) ‘neither the claim
    asserted nor the relief requested requires the participation of
    [its] individual members.’” 74 To meet the first element of
    associational standing, the organization must establish the
    three familiar components that form “the irreducible
    constitutional minimum of standing”:                injury-in-fact,
    causation, and redressability. 75
    The Petitioners have met their burden. FERC observes
    that the Generators do not articulate any injuries in their
    opening briefs. 76      Nevertheless, the Joint Appendix
    incorporates records from the Generators’ protest before FERC
    that demonstrate that their members suffered economic losses
    as a result of the 2021 MOPR. An affidavit attached to P3’s
    reply brief elaborates on these harms. 77 We find that the
    74
    See Sierra Club v. FERC, 
    827 F.3d 59
    , 65 (D.C. Cir. 2016);
    see also Belmont Mun. Light Dep’t v. FERC, 
    38 F.4th 173
    , 185
    (D.C. Cir. 2022) (“Where there are multiple plaintiffs who
    assert overlapping arguments, at least one petitioner must have
    standing to seek each form of relief requested in the petitions
    for review.” (citing Nat’l Ass’n of Regul. Util. Commissioners
    v. FERC, 
    964 F.3d 1177
    , 1184 (D.C. Cir. 2020))).
    75
    Lujan v. Defs. of Wildlife, 
    504 U.S. 555
    , 560 (1992); see
    Friends of the Earth, Inc. v. Laidlaw Env’t Servs. (TOC), Inc.,
    
    528 U.S. 167
    , 180–81 (2000); Kansas Corp. Comm’n v. FERC,
    
    881 F.3d 924
    , 929 (D.C. Cir. 2018) (quoting Sierra Club v.
    EPA, 
    292 F.3d 895
    , 899–900 (D.C. Cir. 2002) (citations
    omitted)).
    76
    FERC Br. 35.
    77
    P3 Reply Br. 3, Attachment A (Decl. Glen Thomas).
    28
    Generators have met their burden to articulate a concrete and
    particularized injury, and that the cause of their injuries is
    traceable to FERC’s approval, by operation of law, of the 2021
    MOPR. 78 We also hold that the State Entities have met their
    burden to establish a cognizable injury, having demonstrated
    that they “represent the interests of the states in protecting their
    citizens and electric ratepayers in the traditional government
    field of utility regulation.” 79
    FERC also argues that the Petitioners failed to establish
    that their purported injuries are redressable in this action.
    Specifically, FERC argues that even if we were to vacate the
    order by operation of law that allowed the 2021 MOPR to go
    into effect, the 2021 MOPR would remain in effect until a new
    tariff could be established upon remand. 80 We disagree.
    Contrary to FERC’s assertion, “[v]acating or rescinding
    invalidly promulgated regulations has the effect of reinstating
    prior regulations.” 81 While these potentially “disruptive
    78
    See Belmont Mun. Light Dep’t, 38 F.4th at 185.
    79
    Id. at 186 (citing Maryland People’s Counsel v. FERC, 
    760 F.2d 318
    , 321 (D.C. Cir. 1985)); see State Entities Reply Br.
    5–6.
    80
    FERC Br. 39.
    81
    Abington Mem’l Hosp. v. Heckler, 
    750 F.2d 242
    , 244 (3d
    Cir. 1984); Prometheus Radio Project v. F.C.C. (Prometheus
    I), 
    652 F.3d 431
    , 453 n.25 (3d Cir. 2011) (“Because we vacate
    the NBCO rule in the 2008 Order, the rule in existence prior to
    that order will remain in effect until the FCC promulgates new
    cross-ownership regulations.”); see Council Tree Commc’ns,
    Inc. v. F.C.C., 
    619 F.3d 235
    , 258 (3d Cir. 2010) (“vacating [an
    FCC] rule will mean that” the prior rule “will once again”
    govern the regulated activity); Paulsen v. Daniels, 
    413 F.3d 999
    , 1008 (9th Cir. 2005) (“The effect of invalidating an
    29
    consequences”82 may militate toward less drastic solutions, 83
    such a remedy is nonetheless within the scope of our statutory
    authority.
    III.   Standard of Review
    At the threshold, the parties dispute the applicable
    standard and scope of judicial review upon a petition
    proceeding under § 205(g).
    agency rule is to reinstate the rule previously in force.”); Action
    on Smoking and Health v. CAB, 
    713 F.2d 795
    , 797 (D.C. Cir.
    1983) (per curiam) (“To ‘vacate,’ as the parties should well
    know, means ‘to annul; to cancel or rescind; to declare, to
    make, or to render, void; to defeat; to deprive of force; to make
    of no authority or validity; to set aside.’ . . . . [T]he judgment
    of this court had the effect of reinstating the rules previously in
    force.”).
    82
    Ameren Servs. Co. v. FERC, 
    880 F.3d 571
    , 584 (D.C. Cir.
    2018) (quoting Black Oak Energy, LLC v. FERC, 
    725 F.3d 230
    , 244 (D.C. Cir. 2013)); see Prometheus Radio Project v.
    Fed. Commc’ns Comm’n (Prometheus II), 
    824 F.3d 33
    , 52 (3d
    Cir. 2016).
    83
    See, e.g., Black Oak Energy, 
    725 F.3d at 244
     (“Although we
    remand, we do so without vacating . . . [after performing the
    disruption analysis] we deem it better to preserve the status quo
    as FERC reconsiders”); Ameren Servs. Co., 880 F.3d at 584
    (vacating because “we are troubled by the prospect of allowing
    the orders to continue”); see Belmont Mun. Light Dep’t v.
    FERC, 
    38 F.4th 173
    , 187–88 (D.C. Cir. 2022) (determining
    that a FERC order is severable and vacating only one
    component).
    30
    We review FERC orders under § 313(b) of the FPA and
    § 10(e) of the APA. 84 The FPA directs that FERC’s factual
    findings, “if supported by substantial evidence, shall be
    conclusive.” 85 Substantial evidence exists where the
    administrative record contains “more than a scintilla, but . . .
    something less than a preponderance of the evidence.” 86 Under
    the APA, we must “hold unlawful and set aside” agency action
    that is deficient for reasons including that it is “arbitrary,
    capricious, an abuse of discretion, or otherwise not in
    accordance with law,” or “in excess of statutory jurisdiction,
    authority, or limitations, or short of statutory right.” 87 In short,
    we affirm FERC orders as long as the administrative record
    shows the Commission “examined the relevant data and
    84
    16 U.S.C. § 825l(b); 
    5 U.S.C. § 706
    (2).
    85
    16 U.S.C. § 825l(b).
    86
    NJBPU, 
    744 F. 3d at 94
     (quoting La. PSC v. FERC, 
    522 F.3d 378
    , 395 (D.C. Cir. 2008)); accord Mars Home for Youth v.
    NLRB, 
    666 F.3d 850
    , 853 (3d Cir. 2011) (“Substantial
    evidence is more than a mere scintilla. It means such relevant
    evidence as a reasonable mind might accept as adequate to
    support a conclusion.” (citations and quotations omitted)). See
    also NJBPU, 
    744 F.3d at 94
     (“The question we must answer ...
    is not whether record evidence supports [petitioner]’s version
    of events, but whether it supports FERC’s.” (quoting Fla. Mun.
    Power Agency v. FERC, 
    315 F.3d 362
    , 368 (D.C. Cir. 2003))).
    87
    
    5 U.S.C. § 706
    (2); see City of Newark v. FERC, 
    763 F.2d 533
    , 545 (3d Cir. 1985) (court must determine “whether a
    rational basis exists for [FERC’s] conclusion, whether there
    has been an abuse of discretion, or . . . whether the
    Commission’s order is arbitrary or capricious or not in
    accordance with the purpose of the [FPA].”).
    31
    articulated a rational connection between the facts found and
    the choice made.” 88
    FERC urges, and we agree, that § 205(g) did not alter
    these familiar standards. 89 Rather, the provision clarified the
    universe of action subject to our review. Prior to its enactment,
    the plain text of the FPA did not convey Congress’s intent to
    allow our review of rate filings enacted by operation of law
    pursuant to § 205(d). Congress addressed this deficiency with
    § 205(g), which unambiguously instructed that we construe
    FERC’s inaction as an affirmative order “for the purposes of §
    [313](a).” 90 Notably, Congress here referred to the very
    provision setting forth a party’s right to seek the Commission’s
    rehearing of an order by majority vote, which in turn provides
    the basis for judicial review. 91 Indeed, § 205(g) specifies that
    88
    NJBPU, 
    744 F.3d at 94
     (quoting Sacramento Mun. Util. Dist.
    v. FERC, 
    616 F.3d 520
    , 528 (D.C. Cir. 2010)); see also
    Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1 of
    Snohomish Cnty., 
    554 U.S. 527
    , 532 (2008) (“The statutory
    requirement that rates be ‘just and reasonable’ is obviously
    incapable of precise judicial definition, and we afford great
    deference to the Commission in its rate decisions.”); N. Penn.
    Gas Co. v. FERC, 
    707 F.2d 763
    , 766 (3d Cir. 1983) (FERC’s
    exercise of its expertise carries “a presumption of validity”).
    89
    See FERC Br. 34–35, 49. While we generally defer to an
    agency’s reasonable interpretation of ambiguity in a statute it
    administers “through application of its expertise,” no deference
    doctrine controls the scope of a court’s jurisdiction. See
    Allegheny Def. Project v. FERC, 
    964 F.3d 1
    , 11 (D.C. Cir.
    2020).
    90
    § 205(g) (emphasis added); see 16 U.S.C. § 825l(a).
    91
    See 16 U.S.C. § 825l(b) (“Any party to a proceeding under
    this chapter aggrieved by an order issued by the Commission
    32
    if the “Commission fails to act on the merits of the rehearing
    request” within 30 days because the deadlock continues, “such
    person may appeal under § [313](b).” 92 Thus, by reference, the
    standard of review set forth in the FPA 93 applies to FERC
    orders issued by operation of law pursuant to § 205(d). 94
    We reject the State Entities’ argument that we must
    review “on a de novo basis, whether the tariff change is just
    and reasonable as a predicate to deciding whether [FERC’s]
    discretion to approve was properly exercised.” 95 This reading
    contradicts the well-settled administrative law principle,
    reflected in both the FPA and APA, that “‘a court is not to
    substitute its judgment for that of the agency.’” 96 Moreover,
    the sole authority cited by the State Entities to support its
    reading concerns an inapposite statute (the Indian Gaming
    Regulatory Act or IGRA), which at least one sister court has
    rejected as an appropriate analog for the FPA because the
    IGRA requires agency action while the FPA gives the agency
    discretion to act. 97
    in such proceeding may obtain a review of such order in the
    United States court of appeals . . . .”).
    92
    Id. § 824d(g)(2); see id. § 825l(b).
    93
    See id. § 825l(b).
    94
    § 205(g).
    95
    State Entities Br. 21–22 (citing Amador County, Cal. v.
    Salazar, 
    640 F.3d 373
    , 375 (D.C. Cir. 2011)).
    96
    Motor Veh. Mfrs. Ass’n of U.S., Inc. v. State Farm Mut. Auto.
    Ins. Co., 
    463 U.S. 29
    , 43 (1983).
    97
    Compare State Entities Br. 22, with Public Citizen, 
    839 F.3d at 1173
     (“Section 205(a)’s statement concerning the
    unlawfulness of unjust and unreasonable rates does not rise to
    an inexorable command like that found in IGRA”).
    33
    To carry out Congress’s directive to construe FERC
    inaction as an affirmative order, we must next determine what
    constitutes evidence of the agency’s reasoning for the purposes
    of § 205(g). 98 The Generators insist that nothing does, arguing
    that a deadlocked Commission can produce “no institutional
    findings of fact or conclusions of law to which this Court might
    defer.” 99 While they acknowledge Congress’s mandate in §
    205(g)(1)(B) that the members of a deadlocked Commission
    must enter their reasoning into the record, they argue that these
    statements are unattributable to the agency and are intended
    only to “facilitate compromises” and promote transparency and
    good government. 100 Because any order arising by operation
    of law would, by the Generators’ logic, lack any agency
    rationale, they conclude that any petition for rehearing
    pursuant to § 205(g) must “inevitably” 101 lead us to find such
    an order arbitrary and capricious. 102
    98
    See Sprint Nextel Corp. v. F.C.C., 
    508 F.3d 1129
    , 1132 (D.C.
    Cir. 2007) (“When the Commission failed to [act] within the
    statutory period, Congress’s decision—not the agency’s—took
    effect.”).
    99
    P3 Br. 29, 34–36 (“[a]ctions of the Commission shall be
    determined by a majority vote of the members present” (citing
    
    42 U.S.C. § 7171
    (e)); accord EPSA Br. 18, 21, 23; State
    Entities Br. 29–30 (citing Public Citizen, 
    839 F.3d at 1169
    ).
    100
    P3 Br. 36–37; see EPSA Br. 18, 23, 27 (quoting F.C.C. v.
    Prometheus Radio Project (Prometheus III), 
    141 S. Ct. 1150
    ,
    1158 (2021)); see State Entities Br. 29.
    101
    EPSA Br. 19–20; P3 Br. 33–35.
    102
    The Generators also wrongly contend that because orders
    by operation of law are necessarily arbitrary and capricious,
    they must be set aside. See P3 Br. 29, 35 (“[J]udicial review of
    34
    The Generators’ argument is inconsistent with our
    responsibility to avoid interpreting statutory provisions in ways
    that “render statutory language a nullity and leave entire
    operative clauses with ‘no job to do.’” 103 Congress established
    in § 205(d), and underscored in § 205(g), that a tariff may
    change by operation of law, 104 consistent with the principle that
    deadlocked FERC proceedings would inevitably end in
    vacatur.” (emphasis added)); EPSA Br. 15 n. 3 (incorporating
    by reference P3’s arguments concerning vacatur); EPSA Br.
    16, 25, 43. But vacatur is never a foregone conclusion. First,
    the plain text of the FPA authorizes us not only to vacate, but
    also to modify an improper order. 16 U.S.C. § 825l(b).
    Second, to determine the appropriateness of vacatur, we
    conduct a fact-sensitive analysis accounting for “the gravity of
    the orders’ flaws, and the ‘disruptive consequences’ that may
    result.” Ameren Servs. Co., 880 F.3d at 584 (quoting Black
    Oak Energy, LLC, 
    725 F.3d at 244
    ; see Prometheus II, 824
    F.3d at 52; Belmont Mun. Light Dep’t, 38 F.4th at 187–88
    (determining that a FERC order is severable and vacating only
    one component). We further observe that while vacatur is the
    Generators’ preferred remedy here, to adopt their theory
    globally risks hampering the claims of future litigants seeking
    redress by modification, and not vacatur. Accordingly, we
    reject the Generators’ reading.
    103
    Allegheny, 964 F.3d at 15 (quoting Doe v. Chao, 
    540 U.S. 614
    , 623 (2004)).
    104
    § 824d(d) (“No change shall be made by any public utility
    in any such rate, . . . rule, regulation, or contract relating
    thereto, except after sixty days’ notice to the Commission and
    to the public.” (emphasis added)); § 824d(g) (“With respect to
    a change described in subsection (d), if the Commission
    permits the 60-day period established therein to expire without
    35
    the “power to initiate rate changes rests with the utility and
    cannot be appropriated by FERC in the absence of a finding
    that the existing rate was unlawful.” 105 The Generators’ theory
    would flip § 205(d)’s protective intent on its head, enabling any
    aggrieved party to invalidate any rate change by operation of
    law simply by virtue of requesting judicial review—a process
    the Generators’ theory reduces to a mechanical exercise with
    only one possible outcome. This cannot be right. If Congress’s
    purpose were indeed to strip utilities of the protections afforded
    by § 205(d), or to otherwise invalidate orders by operation of
    law, it would have amended that portion of the statute
    accordingly, not created a cumbersome workaround via §
    205(g).
    Moreover, the Generators’ reading would sap §
    205(g)(1)(B) of purpose. It is a “fundamental canon
    of statutory construction that the words of a statute must be
    read in their context and with a view to their place in the overall
    statutory scheme.” 106 Here, § 205(g)(1)(B) appears as part of
    an enumerated list of provisions concerning aggrieved parties’
    right to seek rehearing and judicial review of a change arising
    from agency inaction. It makes little sense to argue, as P3 does,
    that Congress’s purpose in requiring the Commissioners to add
    statements explaining their reasoning to the administrative
    record could have been to “facilitate compromises” and
    issuing an order accepting or denying the change . . . the failure
    . . . shall be considered to be an order issued by the Commission
    accepting the change for purposes of” judicial review
    (emphasis added)).
    105
    Atl. City Elec. Co., 
    295 F.3d at 10
    .
    106
    King v. Burwell, 
    576 U.S. 473
    , 492 (2015) (quoting Util. Air
    Reg. Grp. V. EPA., 
    573 U.S. 302
    , 320 (2014)).
    36
    promote transparency and good government only. 107 The right
    to judicial review accrues after a party has been aggrieved by
    a change, and therefore after the time for compromise has
    passed. 108
    We agree with FERC that Congress intended “the
    Commissioners’ statements [to] play an integral role in the
    Court’s review.” 109 Here, the statements of the deadlocked
    Commissioners do more than record each person’s individual
    rationale for affirming or rejecting the rate filing. Collectively,
    they illuminate the agency’s reasons for inaction, which
    Congress has instructed us to construe as an affirmative
    order. 110 Because FERC must accept a § 205 rate filing absent
    “a finding that the existing rate was unlawful,” 111 our thorough
    consideration of the entire record must ensure that the
    107
    P3 Br. 37.
    108
    Notably, in neither of § 205(g)’s two enumerated clauses
    did Congress qualify “change” with any adjective (e.g.,
    “proposed” or “potential”) to indicate that such change was
    pending, and not already in effect. Rather, the text plainly
    refers to the change in tariff effected by the agency’s inaction,
    pursuant to § 205(d).
    109
    FERC Br. 4.
    110
    P3 repeatedly asks us to vacate the September 29, 2021
    Notice, treating that document as if it were a FERC order. P3
    confuses the nature of that instrument, which does not itself
    constitute reviewable FERC action but rather memorialized the
    results, already in effect, of the Commission’s inaction.
    111
    Atl. City Elec. Co., 
    295 F.3d at 10
    ; see Public Citizen, 
    839 F.3d at 1174
     (noting the FPA does “not compel FERC to either
    set the disputed rates for hearing or affirmatively disapprove
    any unjust or unreasonable rates through the Section 205
    process.”).
    37
    Commissioners who did not find the 2021 MOPR unlawful
    engaged in “decisionmaking [that was] reasoned, principled,
    and based upon the record.” 112
    While unusual, such a reading has precedent. In the
    Federal Election Commission Act, Congress similarly
    incorporated language making clear that a party aggrieved “by
    a failure of the Commission to act” may seek administrative
    appeal and judicial review. 113 As the D.C. Circuit Court of
    Appeals explained in Public Citizen, when the Federal Election
    Commission deadlocks over whether to exercise its discretion
    to act, “[t]o make judicial review a meaningful exercise,’ [the
    court must] treat the statements of the Commissioners voting
    to dismiss the complaint as the administrative record.” 114 The
    court in Public Citizen declined to follow this approach
    because, at the time, the FPA did not contain “a similar
    congressional indication” about how to construe agency
    deadlock. 115 With § 205(g), Congress filled that gap. 116
    112
    W. Res., Inc. v. FERC, 
    9 F.3d 1568
    , 1572 (D.C. Cir. 1993)
    (quoting Columbia Gas Transmission Corp. v. FERC, 
    628 F.2d 578
    , 593 (D.C. Cir. 1979)); see Fed. Election Comm’n v.
    Nat’l Republican Senatorial Comm., 
    966 F.2d 1471
    , 1476
    (D.C. Cir. 1992) (these commissioners “constitute a
    controlling group for purposes of the decision[ and] their
    rationale necessarily states the agency’s reasons for acting as it
    did.”).
    113
    
    52 U.S.C. § 30109
    (a)(8)(A).
    114
    Public Citizen, 
    839 F.3d at
    1170 (citing Fed. Election
    Comm’n, 
    966 F.2d at 1476
    ); see Common Cause v. Fed.
    Election Comm’n., 
    842 F.2d 436
    , 450 (D.C. Cir. 1988).
    115
    Public Citizen, 
    839 F.3d at 1171
    .
    116
    For this reason, P3 errs by relying on Public Citizen, which
    turned on the absence of such an indication, for the proposition
    38
    We disagree that § 205(g) contradicts the Commission’s
    enabling statute as codified at 
    42 U.S.C. § 7171
    (e), which
    states that “[a]ctions of the Commission shall be determined by
    a majority vote of the members present.” 117 Section 205(g)
    concerns only how agency inaction should be construed for the
    limited purposes of rehearing and review but does not
    illuminate what constitutes agency action per se. 118 Even if §
    205(g) did contradict § 7171(e), traditional rules of statutory
    interpretation counsel that “[s]pecific terms prevail over the
    general in the same or another statute which otherwise might
    be controlling.” 119       Here, Congress identified narrow
    circumstances under which to construe inaction, in a particular
    way, for a specific purpose. 120
    that FERC inaction cannot be construed as action for the
    purposes of judicial review.
    117
    P3 Br. 29, 34–36 (citing 
    42 U.S.C. § 7171
    (e) (“[a]ctions of
    the Commission shall be determined by a majority vote of the
    members present”); accord EPSA Br. 18, 21, 23; State Entities
    Br. 29–30 (citing Public Citizen, 
    839 F.3d at 1169
    ).
    118
    See 
    42 U.S.C. §7171
    (e).
    119
    Superior Oil Co. v. Andrus, 
    656 F.2d 33
    , 36 (3d Cir. 1981))
    (quoting Fourco Glass Co. v. Transmirra Corp., 
    353 U.S. 222
    ,
    228–29 (1957)).
    120
    We have no “grave constitutional concern” that a single
    Commissioner’s views could stand for all when a rate filing
    takes effect because the Commission has deadlocked. EPSA
    Br. 27. Under the terms of the statute, this circumstance would
    always result in two Commissioners’ views controlling—the
    same number that would constitute an unobjectionable
    majority among a quorum of three Commissioners.
    Nevertheless, we do not decide today whether a constitutional
    39
    For the foregoing reasons, we hold first that where a
    quorum of FERC Commissioners deadlocks two-to-two on a §
    205 rate filing, our review of the resulting order must adhere to
    the same standard that would govern our review of an order
    approved by a FERC majority. 121 Second, we hold that our
    review properly encompasses the entire record, including the
    four Commissioners’ § 205(g)(1)(B) statements.
    IV.    Merits
    We now reach the substance of the parties’ dispute.
    Construing the agency’s deadlocked vote on the 2021 MOPR
    as an affirmative order consistent with § 205(g), and
    considering the Commissioners’ recorded statements, we
    conclude that the rationale set forth in the Joint Statement for
    approving the 2021 MOPR was neither arbitrary nor capricious
    and was supported by substantial evidence in the record. We
    are not persuaded otherwise by the arguments set forth in the
    other Commissioners’ statements. Accordingly, we will deny
    the Generators’ petitions on the merits. 122
    concern might arise when a rate filing goes into effect in the
    absence of a quorum, in which case the “views of a single
    Commissioner [could] . . . gain the force of law.” EPSA Br.
    27, 28 (citing Seila Law LLC v. Consumer Fin. Prot. Bureau,
    
    140 S. Ct. 2183
    , 2201 (2020)).
    121
    NJBPU, 
    744 F.3d at
    94 (citing Sacramento Mun. Util.
    Dist., 
    616 F.3d at 528
    ).
    122
    P3 suggests that FERC’s order by operation of law pursuant
    to § 205 was facially improper because it overturned a tariff
    ordered by FERC under § 206, professing to be “unaware of
    any authority that permits a public utility to change rates
    40
    In reviewing FERC’s orders, we consider only “whether
    a rational basis exists for a conclusion, whether there has been
    an abuse of discretion, or . . . whether the Commission’s order
    is arbitrary or capricious or not in accordance with the purpose
    of the [FPA].” 123 “[B]ecause issues of rate design . . . involve
    policy judgments that lie at the core of the regulatory mission,
    our review of whether a particular rate design is just and
    imposed on that utility by FERC under FPA section 206.” P3
    Br. 31, 33 (“[T]he Notice must be vacated because it disregards
    the text and structure of the FPA by elevating a mere filing
    under section 205 above FERC orders under section 206.”).
    The State Entities similarly suggest the existence of a “higher
    Section 206 standard,” State Entities Br. 28, insisting that as a
    per se matter, “FERC cannot overturn its prior precedent
    through inaction,” State Entities Br. 28. Both parties are
    incorrect. It is well-settled that “[n]othing in section 206
    sanctions denying petitioners their right to unilaterally file rate
    and term changes.” Atl. City Elec. Co., 
    295 F.3d at 10
    (collecting cases). Indeed, “courts have repeatedly held that
    FERC has no power to force public utilities to file particular
    rates unless it first finds the existing filed rates unlawful . . . .
    Nor may FERC prohibit public utilities from filing changes in
    the first instance.” 
    Id.
     As intervenors for the respondent note,
    P3’s interpretation would erode the careful balance that
    Congress has achieved in the statute by “gradually
    eliminat[ing] the utility’s rights under Section 205 . . . to set
    the rates it will charge prospective customers, and change them
    at will, subject to review by the Commission.” Respondent-
    Intervenors Br. 29 (quoting Atl. City Elec. Co., 
    295 F.3d at 10
    )
    (cleaned up). Accordingly, we reject P3’s suggestion that a §
    205 filing cannot displace a tariff set by § 206.
    123
    City of Newark, 763 F.2d at 545.
    41
    reasonable is highly deferential.” 124 The MOPR dispute
    concerns precisely such a judgment: How best to protect the
    integrity of the capacity market, in view of the diverse and
    legitimate interests of its myriad stakeholders and the
    innumerable factors that influence price.
    FERC has approved various approaches to this
    conundrum since 2006. We have previously observed that
    “FERC is permitted to weigh the danger of price suppression
    against the counter-danger of over-mitigation, and determine
    where it wishes to strike the balance.” 125 Here, the 2021
    MOPR reflected a shift away from the regime embraced in the
    2019 MOPR, at least arguably toward the purpose of
    “address[ing] the concern that some market participants might
    have an incentive to depress market clearing prices by offering
    supply at less than a competitive level.” 126
    Such shifts are permissible. An agency may alter its
    “view of what is in the public interest.” 127 The fact that
    contrary agency precedent exists “gives us no more power than
    usual to question the Commission’s substantive
    determinations.” 128 The agency need not establish that “the
    124
    Md. Pub. Serv. Comm’n v. FERC, 
    632 F.3d 1283
    , 1286
    (D.C. Cir. 2011).
    125
    NJBPU, 
    744 F.3d at 109
    .
    126
    2011 Order at ¶ 6 (citing 2006 Settlement Order at ¶ 103).
    127
    Motor Vehicle Mfrs. Ass’n of United States, Inc. v. State
    Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 57 (1983)
    (quoting Greater Bos. Television Corp. v. F.C.C., 
    444 F.2d 841
    , 852 (D.C. Cir. 1970)); see NJPBU, 
    744 F.3d at 100
    .
    128
    NJPBU, 
    744 F.3d at 100
     (quoting Nat’l Cable &
    Telecomms. Ass’n v. F.C.C., 
    567 F.3d 659
    , 669 (D.C. Cir.
    2009)); see also Elec. Consumers Res. Council v. FERC, 407
    42
    reasons for the new policy are better than the reasons for the
    old one; it suffices that the new policy is permissible under the
    statute, that there are good reasons for it, and that the
    agency believes it to be better.” 129
    We hold that FERC met these criteria in constructively
    approving the 2021 MOPR. The eighty-six-page Joint
    Statement acknowledged that the 2021 MOPR reflects a
    change in policy and identified reasons for finding the change
    just and reasonable. 130        Specifically, the authoring
    F.3d 1232, 1239 (D.C. Cir. 2005) (stating that a court’s
    deference to FERC on complex rate market design “is based
    on the understanding that the Commission will monitor its
    experiment and review it accordingly”).
    129
    F.C.C. v. Fox Television Stations, Inc., 
    556 U.S. 502
    , 515
    (2009).
    130
    The two commissioners who concluded the 2021 MOPR
    was not just and reasonable issued separate statements
    articulating their views.            While non-identical, the
    commissioners reached the same core conclusion: The 2021
    MOPR did not meet the just and reasonable standard because
    it was anti-competitive. See JA0129 (Christie Statement)
    (“[T]he PJM MOPR Proposal, now in effect by operation of
    law, forfeits any remaining credibility to the claim that the PJM
    capacity market is based on actual competition or is run for the
    benefit of consumers”); JA0169 (Danly Statement) (“PJM’s
    proposal eliminating all mitigation of the price-suppressive
    effects of state subsidies is irredeemably inconsistent with FPA
    section 205’s requirement that proposed rates must be just and
    reasonable.”). As discussed herein, these policy concerns are
    addressed in the Joint Statement, along with the authoring
    commissioners’ reasons for not adopting them, reasons which
    43
    Commissioners asserted that a more narrowly targeted MOPR
    would benefit “investors and consumers alike” by “more
    accurately reflect[ing] the facts and realities on the ground,”131
    while “provid[ing] a sufficient opportunity for resources to
    recover their costs.” 132 The Joint Statement noted that its
    policy might result in lower prices on the capacity market than
    under the expanded 2019 MOPR but concluded that such a
    result is “just and reasonable because the market will reflect
    supply and demand fundamentals,” 133 which include state
    policies alongside federal policies, “[s]iting policies, tax rules,
    and labor regulations,” among others. 134 According to the
    Joint Statement, the 2019 MOPR allowed for an “artificially
    inflated price [that] will falsely signal that new entry is needed
    or that existing resources should forestall retirement,” with
    potentially “detrimental effects on PJM’s energy and ancillary
    services markets.” 135
    The Joint Statement identified specific changed
    circumstances to support these conclusions, including a
    proliferation of state policies to shape the resource mix that had
    occurred over the prior three years, largely to “address
    externalities that are neither accounted for nor compensated in
    are neither arbitrary nor capricious and are based on substantial
    evidence in the record. Because it may not, our conclusion in
    this regard does not derive from our own policy preferences.
    Rather, it accepts and reflects our role here as circumscribed
    by statute and precedent.
    131
    JA0060 ¶ 44.
    132
    JA0060 ¶ 45.
    133
    JA0067 ¶ 55.
    134
    JA0068 ¶¶ 56, 57.
    135
    JA0067 ¶ 54.
    44
    PJM’s wholesale markets.” 136 The Joint Statement noted that
    “[s]tates are playing a more active role in shaping the resource
    mix—including both entry and exit—than they were at the time
    the Commission issued previous orders addressing the scope
    and purpose of PJM’s MOPR.” 137 Policies passed since 2018
    alone could together “support the entry of more than 44,000
    MW of capacity into PJM’s capacity market over the next”
    fifteen years, the Joint Statement noted. 138 The authoring
    Commissioners observed that failing to account for the
    contributions of these resources to capacity could cost
    consumers a total of $3.4 billion by 2030. 139
    The Joint Statement also analyzed the results of the first
    base residual auction held under the 2019 MOPR. The
    authoring Commissioners noted that a generating station
    benefitting from one state’s zero-emission credit failed to clear,
    and that “capacity prices likely increased by over $10/MW-
    day, or an additional $90 million in the ComEd zone, as a
    result”—harms that “can be expected to increase significantly
    as states continue to support resources that will not benefit
    from the [2019] MOPR’s” exclusions. 140 The Joint Statement
    also pointed to evidence that “several states have considered
    136
    JA0057 ¶ 36.
    137
    JA0070 ¶ 59.
    138
    JA0084 ¶ 80.
    139
    JA0064 ¶ 50. See Constellation Energy Commodities Grp.,
    Inc. v. FERC, 
    457 F.3d 14
    , 24 (D.C. Cir. 2006) (“[I]t is within
    the scope of the agency’s expertise to make . . . a prediction
    about the market it regulates, and a reasonable prediction
    deserves our deference notwithstanding that there might also
    be another reasonable view.”) (cleaned up).
    140
    JA0066 ¶ 52.
    45
    abandoning the capacity market altogether rather than have the
    resources needed to meet their public policy goals be subjected
    to mitigation,” an outcome that would threaten the purpose and
    structure of the market itself. 141
    Petitioner EPSA contends that the Joint Statement failed
    to address the validity of any potential reliance interests,
    arguing the “parties demonstrated that investors have sunk
    many billions of dollars into constructing new power plants
    and maintaining existing ones, all in reliance on the existence
    of PJM market mechanisms that ensure a competitive
    marketplace, rather than a marketplace skewed by the
    participation of un-economic resources.” 142 But an agency not
    “writing on a blank slate” is required only to “assess whether
    there were reliance interests, determine whether they were
    significant, and weigh any such interests against competing
    policy concerns.” 143 Here, the Commissioners considered
    “arguments that the Expanded [2019] MOPR must be
    preserved because investors relied on it” but determined these
    did not “tilt the balance” against their articulated policy
    concerns, in light of the fact that the 2019 MOPR had been in
    place for a relatively short period during which it was “well-
    publicized” that “PJM was exploring the possibility of
    replacing the Expanded MOPR.” 144 As we concluded in 2014,
    responding to similar arguments, “we are not unsympathetic to
    [investor’s] arguments that they reasonably relied” on the
    terms of the prior MOPR, but nevertheless “find no fault with
    141
    JA0070 ¶ 58.
    142
    EPSA Br. 30.
    143
    Dep’t of Homeland Sec. v. Regents of the Univ. of
    California, 
    140 S. Ct. 1891
    , 1915 (2020).
    144
    JA0071 ¶ 61.
    46
    FERC’s ability to, and reasons for” constructively approving
    the new one. 145
    P3 challenges various technical provisions of the 2021
    MOPR, devised by PJM to accomplish its twin policy
    objectives of mitigating offers resulting from the exercise of
    buy-side market power and conditioned state support. From
    these objections, 146 P3 concludes that because PJM’s proposed
    mechanism fails to ensure adequately that “neither buyer nor
    seller have market power, ‘the prevailing price in the
    marketplace cannot be the final measure of “just and
    reasonable” rates mandated by the Act.’” 147
    145
    NJBPU, 
    744 F.3d at 100
    .
    146
    P3 generally alleges that both prongs are “unjust,
    unreasonable, and unduly discriminatory,” without articulating
    precisely how. With respect to the Buyer Side Market Power
    and Conditioned State Support provisions, including that (1)
    PJM’s proposed self-certification process is insufficiently
    robust, (2) that its requirement that sellers self-certify their
    intent is “easily evaded” and runs counter to prior policy
    approved by FERC; (3) the tests required upon review by the
    PJM and/or Independent Market Monitor are evadable and rely
    on concepts rejected, with FERC approval, in earlier MOPRs;
    and (4) the test is insufficiently transparent and affords too
    much discretion to PJM and the Independent Market Monitor.
    See P3 Br. 51–54. With respect to the provisions related to
    Conditioned State Support, P3 argues that these are “riddled
    with practical defects,” improperly exempts existing policies,
    and only mitigates state actions are already unlawful under the
    Supreme Court’s decision in Hughes v. Talen Energy Mktg,
    LLC, 
    578 U.S. 150
     (2016). P3 Br. 49–50.
    147
    P3 Br. 47 (quoting FPC v. Texaco Inc., 
    417 U.S. 380
    , 397
    47
    We disagree. “The statutory requirement that rates be
    ‘just and reasonable’ is obviously incapable of precise judicial
    definition,” 148 and “FERC’s authority to determine whether
    wholesale rates are ‘just and reasonable’ is exclusive.” 149 We
    “properly defer[] to policy determinations invoking the
    Commission’s expertise in evaluating complex market
    conditions.” 150 Although “courts have never given regulators
    carte blanche,” 151 our review is “limited to ensuring that the
    Commission has made a principled and reasoned decision
    supported by the evidentiary record.” 152 Here, the Joint
    Statement responds to both the technical and policy criticisms
    levelled by P3, concluding that the mechanisms proposed by
    PJM were sufficient to mitigate anti-competitive offers while
    “appropriately balanc[ing] the risk of under- and over-
    (1974)); see P3 Br. 47–48 (stating that the new rules “do
    virtually nothing to prevent the exercise of state-sponsored
    market power. Instead, they establish an opaque and toothless
    process of exclusions and exceptions that ‘is even worse than
    having no MOPR at all.’”) (quoting Comm’r Christie
    Statement, JA0125–26 ¶ 3).
    148
    Morgan Stanley Cap. Grp. Inc. v. Pub. Util. Dist. No. 1 of
    Snohomish Cnty., Wash., 
    554 U.S. 527
    , 532 (2008).
    149
    California ex rel. Lockyer v. FERC, 
    383 F.3d 1006
    , 1011
    (9th Cir. 2004) (quoting Miss. Power & Light Co. v.
    Mississippi, 
    487 U.S. 354
    , 371 (1988)).
    150
    Tenn. Gas Pipeline Co. v. FERC, 
    400 F.3d 23
    , 27 (D.C. Cir.
    2005).
    151
    Emera Maine v. FERC, 
    854 F.3d 9
    , 22 (D.C. Cir. 2017)
    (quoting Elec. Consumers Res. Council v. FERC, 
    747 F.2d 1511
    , 1514 (D.C. Cir. 1984)).
    152
    
    Id.
     (quoting S. Cal. Edison Co. v. FERC, 
    717 F.3d 177
    , 181
    (D.C. Cir. 2013)).
    48
    mitigation.” 153 We cannot conclude on this record that the
    Commission’s constructive acceptance of PJM’s § 205 filing
    as just and reasonable was arbitrary or capricious.
    Finally, we reject P3’s argument that the 2021 MOPR
    “unlawfully discriminates against competitive power
    suppliers,” as compared to state-sponsored resources, by
    “reduc[ing] market prices below just and reasonable levels.” 154
    As discussed above in depth, the Joint Statement set forth an
    adequate rationale for permitting PJM to implement a less
    expansive MOPR. 155 Moreover, as FERC argues, the FPA
    153
    JA0096 ¶¶ 103, 105–06); see generally JA0100 ¶¶ 85–163.
    154
    P3 Br. 39.
    155
    Judge Roth also disagrees with the Generators’ contention
    that the 2021 MOPR is unlawfully discriminatory because it
    allows states to “‘impose [their] own policy choice on
    neighboring States’ or otherwise intrude upon the ‘autonomy
    of [other] States within their respective spheres.’” P3 Br. 42–
    43 (quoting BMW of N. Am. v. Gore, 
    517 U.S. 559
    , 571 (1996))
    (quotations omitted); EPSA Br. 34–47. Rather, Judge Roth
    would conclude, consistent with New Jersey Board of Public
    Utilities v. FERC, “what FERC has actually done here is permit
    states to develop whatever capacity resources they wish, and to
    use those resources to any extent that they wish, while
    approving rules that prevent the state’s choices from adversely
    affecting wholesale capacity rates.” NJBPU, 
    744 F.3d at 98
    ;
    accord Hughes, 578 U.S. at 166 (“Nothing in this opinion
    should be read to foreclose . . . States from encouraging
    production of new or clean generation through measures
    ‘untethered to a generator’s wholesale market participation.’”);
    see Energy & Env’t Legal Inst. v. Epel, 
    793 F.3d 1169
    , 1173
    (10th Cir. 2015) (rejecting a dormant Commerce Clause
    49
    unambiguously authorizes the agency to take state policies into
    account to the extent that such policies affect its statutorily
    prescribed area of focus: the justness and reasonableness of
    wholesale rates.
    V.    Conclusion
    For the forgoing reasons, we conclude that FERC’s
    constructive acceptance of the 2021 MOPR was neither
    arbitrary nor capricious and was supported by substantial
    evidence in the record. We will accordingly deny the petitions
    for review.
    challenge to a state’s renewable energy mandate). Judge Roth
    particularly disapproves of EPSA’s assertion, citing no
    relevant authority, that “FERC must therefore play the role of
    federal referee for state intrusions into other States’
    jurisdiction,” EPSA Br. 42.
    50
    

Document Info

Docket Number: 21-3068

Filed Date: 12/1/2023

Precedential Status: Precedential

Modified Date: 12/1/2023