U.S. Home Corporation v. Settlers Crossing, L.L.C. , 685 F. App'x 173 ( 2017 )


Menu:
  •                                    UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 15-1254
    U. S. HOME CORPORATION; LENNAR CORPORATION,
    Plaintiffs − Appellants,
    v.
    SETTLERS CROSSING, L.L.C.; WASHINGTON PARK ESTATES, LLC;
    BEVARD DEVELOPMENT COMPANY; STEVEN B. SANDLER; ISTAR
    FINANCIAL, INCORPORATED; DANIEL I. COLTON,
    Defendants – Appellees.
    Appeal from the United States District Court for the District of Maryland, at Greenbelt.
    Deborah K. Chasanow, Senior District Judge. (8:08−cv−01863−DKC)
    Argued: March 23, 2017                                         Decided: April 12, 2017
    Before DUNCAN, AGEE, and KEENAN, Circuit Judges.
    Affirmed by unpublished per curiam opinion.
    ARGUED: Jonathan D. Hacker, O’MELVENY & MYERS LLP, Washington, D.C., for
    Appellants. Peter D. Keisler, SIDLEY AUSTIN, LLP, Washington, D.C., for Appellees.
    ON BRIEF: Daniel M. Petrocelli, David Marroso, James M. Pearl, Los Angeles,
    California, David K. Roberts, O’MELVENY & MYERS LLP, Washington, D.C., for
    Appellants. Eric Kuwana, John Rosans, William McGonigle, KATTEN MUCHIN
    ROSENMAN LLP, Washington, D.C.; Quin M. Sorenson, Erika L. Maley, SIDLEY
    AUSTIN LLP, Washington, D.C., for Appellee iStar Financial Incorporated. Thomas R.
    Folk, REED SMITH, LLP, Falls Church, Virginia, for Appellees Settlers Crossing,
    L.L.C., Washington Park Estates, L.L.C., Bevard Development Company, Steven B.
    Sandler, and Daniel I. Colton.
    Unpublished opinions are not binding precedent in this circuit.
    2
    PER CURIAM:
    The Plaintiffs-Appellants in this case, Lennar Corporation and its subsidiary U.S.
    Home Corporation (collectively, “Lennar”), appeal the district court’s holding that
    Defendant-Appellee iStar Financial, Inc. (“iStar”) is entitled to specific performance
    under a land sales contract. For the reasons ably stated by the district court, we affirm.
    I.
    A.
    This diversity appeal involves a long-running contract dispute over the sale of
    1,250 acres of land in Prince George’s County, Maryland (“the Property”). Because the
    district court recounted the facts comprehensively, we incorporate its opinions by
    reference and recite only those facts necessary to our analysis.
    In 2005, Lennar--a homebuilder--began negotiating with Settlers Crossing, L.L.C.
    (“Seller”) 1--a land developer--to purchase the Property in order to develop it for
    residential use. That November, Lennar and Seller entered into a sales agreement under
    which Lennar would purchase the Property for $200 million, to be paid in full on
    September 30, 2006, with a $20 million deposit paid immediately. Seller turned over the
    environmental studies that had been conducted on the Property, and Lennar had access to
    the Property to inspect it from September 2005 to December 2007. Lennar learned
    1
    Defendant-Appellee Steven B. Sandler controlled Settlers Crossing, L.L.C.,
    Washington Park Estates, L.L.C., and Bevard Development Company, and we refer to
    them collectively as “Seller.”
    3
    through the studies that portions of the Property had been used as the site of a wastewater
    treatment plant, as well as for sand and gravel mining, and therefore some of the land
    could “contain heavy metals, sludge, and varying debris.” J.A. 2454. Lennar in fact
    commissioned a number of additional studies and engaged in remediation work, such as
    removal of storage tanks. There is no evidence indicating that Lennar was unable to
    conduct any analysis or test it wished to undertake during this time.
    In 2006, given a decline in the housing market, Lennar asked to renegotiate the
    contract to reduce the purchase price, from $200 million to $134 million. Seller agreed,
    on the condition that, in exchange, Lennar would guarantee specific performance under
    the contract--an important incentive because Seller was then seeking to refinance the
    Property. After extensive negotiations, the parties executed an amendment to the contract
    on May 16, 2007. Seller obtained a loan from iStar with the Property as security. Lennar
    affirmed that it had no knowledge that any of Seller’s representations were not true. The
    parties rescheduled closing for December 5, 2007.
    In late 2007, Lennar began seeking a partner to share the costs and risks of the
    project, and represented to at least one entity that independent environmental assessments
    had not identified any hazardous conditions requiring extraordinary measures or higher-
    level studies. J.A. 4778. According to the district court, after “initial efforts to find a
    partner were unsuccessful, Lennar began to investigate strategies to delay the scheduled
    settlement date, if not to avoid closing altogether.”       J.A. 4779.   Lennar’s internal
    memoranda and correspondence show it placed the Property on a so-called “Hit List,”
    reflecting Lennar’s conclusion that it needed to change its strategy in light of continuing
    4
    declines in the housing market.     Characterizing the Agreement as “not making any
    financial sense,” J.A. 1138, Lennar’s executives ordered all spending on the project
    stopped and instructed personnel to focus on creating “a way to off-load” it, J.A. 1137,
    through “alternative strategies,” J.A. 1138. This included reviewing the contract to find
    an “escape clause.” J.A. 4257.
    Seller noticed that Lennar’s work on the Property “had ground to a halt,” and
    heard from one of Lennar’s departing project managers that Lennar “was seeking to get
    out of the contract.” J.A. 4781. When Seller inquired, Lennar provided no response.
    By letter dated November 21, 2007, Lennar notified Seller that Seller had failed to
    satisfy conditions precedent to closing. Throughout the dispute and ensuing litigation,
    Lennar “resisted providing a definitive list of allegedly unsatisfied conditions.”
    J.A. 4782 n.7. Lennar missed the closing on December 5, 2007. As a result, Seller
    defaulted on the loan, and iStar foreclosed on the Property.
    On December 6, 2007, Seller then sued for declaratory relief in federal district
    court in the Eastern District of Virginia, seeking to identify which conditions precedent,
    if any, were unsatisfied so that the parties could still proceed to closing. This court
    affirmed a dismissal for lack of subject matter jurisdiction. Settlers Crossing, L.L.C. v.
    U.S. Home Corp., 383 F. App’x. 286 (4th Cir. 2010) (unpublished).
    On January 3, 2008, Lennar asked to enter the Property, identifying “a laundry list
    of issues that [it] purportedly sought to investigate--the vast majority of which had
    previously been addressed by the parties.” J.A. 4784. Lennar’s President testified that,
    5
    when it made the request, Lennar “didn’t know what [it would] find” and had “no reason
    to believe that there was anything wrong with the property.” J.A. 4785.
    Distrusting Lennar’s intentions, Seller denied access. On May 16, 2008, Lennar
    responded by serving Seller with a notice of default, citing Seller’s denial of access,
    which triggered Seller’s and iStar’s cure periods under the contract and separate consent
    agreement. On May 30, 2008, Seller served its own notice of default, arguing that
    Lennar wrongfully failed to settle. To Lennar’s consternation, the district court in the
    declaratory action granted Lennar the access it claimed it wanted, but within the cure
    period, thereby resolving any default by Seller. Instead of exercising that right, Lennar
    terminated the contract.
    B.
    Lennar filed the instant action on July 17, 2008, seeking the return of its deposit
    and claiming that Seller breached the contract by refusing Lennar’s request for access
    and--later through an amended complaint--by failing to disclose that sewage sludge had
    been deposited on the Property. Seller and iStar counterclaimed for declaratory relief and
    specific performance of Lennar’s obligation to close, as well as pre- and post-judgment
    interest at rates set by the contract.
    As relevant to this appeal, the litigation also involved two evidentiary disputes
    regarding privilege. First, Lennar claimed that Steven Engel was its attorney, and that
    documents and communications with Engel were entitled to the attorney-client privilege.
    However, Engel was not licensed to practice law. The district court therefore sanctioned
    Lennar, and ordered it to turn over Engel documents and communications wrongfully
    6
    withheld under the attorney-client privilege but allowed it to continue to withhold
    documents under the work-product doctrine if it submitted such documents for in camera
    review.   Second, the district court held that Lennar had waived the attorney-client
    privilege for documents produced to Seller by Lennar’s former law firm, Greenberg
    Traurig, because Lennar and its counsel failed to take reasonable steps to prevent or
    promptly rectify the disclosure.
    Following discovery, the parties filed cross-motions for summary judgment, which
    the district court denied. A two-week bench trial addressed two main issues: (1) whether
    Seller breached the contract when it denied Lennar access, and (2) whether Seller’s
    environmental representations were adequate under the contract. The bulk of the trial
    focused on the second issue: Lennar asserted that the Property contained elevated
    concentrations of elements that it claimed were “Hazardous Materials” under the contract
    and that these elements could only be present as a result of the application of processed
    sewage sludge, which Seller did not disclose in the environmental reports. The parties
    each offered experts on this issue.
    After trial, the district court issued a comprehensive 75-page opinion, holding that
    Lennar failed to meet its burdens at trial and that iStar--standing in the shoes of Seller--
    was entitled to specific performance. The district court found that Seller’s denial of
    access did not constitute a breach of the contract for three reasons: (1) Lennar acted in
    bad faith because it requested access solely to delay or avoid closing and, when given the
    access it claimed to want, never even exercised that right; (2) Lennar failed to satisfy the
    precondition of having insurance; and (3) any breach from the initial denial was cured
    7
    when the district court granted Lennar access to the Property in the declaratory-judgment
    action.
    As for the adequacy of Seller’s environmental representations, the district court
    held that Lennar had not demonstrated that “the source of ‘Hazardous Materials’ on the
    Property was something other than what was disclosed in the environmental reports
    provided by Seller.” J.A. 4824. The district court expressly found that neither of the two
    experts on which Lennar relied were persuasive, and that one of them was not credible.
    J.A. 4812.       By contrast, iStar’s experts “were highly credible and informative,
    overwhelmingly so” compared to Lennar’s experts. J.A. 4815 n.19. In any event, Lennar
    also failed to demonstrate that any “Hazardous Materials” were present in material
    amounts, as required by the contract.
    Following further hearings, the district court issued additional opinions and orders
    to resolve disputes Lennar raised about appropriate remedies concerning (1) specific
    performance and (2) interest. In April and July 2013, Prince George’s County passed
    certain zoning changes that affected a portion of the Property. The district court held that
    specific performance was still appropriate because the contract imposed the risk of
    zoning changes on Lennar from the date it was contractually obligated to settle: the
    contract’s specific plat density and governmental takings provisions superseded the
    contract’s boilerplate risk-of-loss provision. Moreover, the district court concluded that
    Lennar will receive the substantial benefit of its bargain when it purchases the Property,
    because the zoning changes “do not prohibit [Lennar] from pursuing its main purpose.”
    J.A. 4893 n.20. With respect to interest, the district court held that iStar was entitled to
    8
    the contractual interest rate because Lennar defaulted by wrongfully failing to settle
    under the terms of the contract.
    II.
    Lennar appeals the district court’s legal and factual findings regarding contractual
    breach, privilege assertions, award of specific performance, and interest. We review the
    district court’s factual findings for clear error and legal conclusions de novo. Roanoke
    Cement Co., L.L.C. v. Falk Corp., 
    413 F.3d 431
    , 433 (4th Cir. 2005). We see neither
    type of error here.
    The district court issued comprehensive and well-reasoned opinions addressing the
    various aspects of this dispute. Seller did not breach the contract when it denied Lennar
    access because, among other factors, the evidence reflects Lennar made its request in bad
    faith. Further, Seller’s environmental representations were adequate under the contract.
    In particular, Lennar’s “late-developing theory,” J.A. 4823, that heavy metals on the
    Property were due to sewage sludge that Seller failed to disclose lacks merit, especially
    given the district court’s express credibility determinations.       The district court’s
    resolutions of the evidentiary disputes were well reasoned and far from an abuse of
    discretion. Lennar bargained for a reduced purchase price in exchange for the obligation
    to close.      Specific performance and interest at the contractual rate are therefore
    appropriate.
    9
    III.
    Litigation in this matter has extended for nearly a decade. The district court
    handled the dispute with considerable care, and we discern no error in its meticulous
    opinions.
    AFFIRMED
    10
    

Document Info

Docket Number: 15-1254

Citation Numbers: 685 F. App'x 173

Judges: Duncan, Agee, Keenajst

Filed Date: 4/12/2017

Precedential Status: Non-Precedential

Modified Date: 10/19/2024