T-Mobile Northeast LLC v. Loudoun County Board of Supervisors , 748 F.3d 185 ( 2014 )


Menu:
  •                                PUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 12-2396
    T-MOBILE NORTHEAST LLC,
    Plaintiff - Appellee,
    v.
    THE LOUDOUN COUNTY BOARD OF SUPERVISORS,
    Defendant - Appellant.
    No. 12-2397
    T-MOBILE NORTHEAST LLC,
    Plaintiff - Appellant,
    v.
    THE LOUDOUN COUNTY BOARD OF SUPERVISORS,
    Defendant - Appellee.
    Appeals from the United States District Court for the Eastern
    District of Virginia, at Alexandria. Gerald Bruce Lee, District
    Judge. (1:11-cv-01201-GBL-JFA)
    Argued:   December 12, 2013                 Decided:   April 3, 2014
    Before NIEMEYER, AGEE, and WYNN, Circuit Judges.
    Affirmed by published opinion. Judge Niemeyer wrote the opinion
    for the court except as to Part IV.C.1 in part and Part IV.C.2,
    in which Judge Agee concurred except as to Part IV.C.1 in part
    and Part IV.C.2. Judge Niemeyer wrote a separate opinion as to
    Part IV.C.1 in part and Part IV.C.2.         Judge Agee wrote a
    separate opinion concurring in part.        Judge Wynn wrote a
    separate opinion concurring in part and dissenting in part.
    ARGUED:   Thomas David Stoner, GREEHAN, TAVES, PANDAK & STONER,
    PLLC, Chantilly, Virginia, for Appellant/Cross-Appellee. Thomas
    Scott Thompson, DAVIS WRIGHT TREMAINE, LLP, Washington, D.C.,
    for Appellee/Cross-Appellant.    ON BRIEF:    J. Patrick Taves,
    Michael W.S. Lockaby, GREEHAN, TAVES, PANDAK & STONER, PLLC,
    Chantilly, Virginia; John R. Roberts, County Attorney, Ronald J.
    Brown, Deputy County Attorney, LOUDOUN COUNTY ATTORNEY’S OFFICE,
    Leesburg, Virginia, for Appellant/Cross-Appellee.      Daniel P.
    Reing, DAVIS WRIGHT TREMAINE, LLP, Washington, D.C., for
    Appellee/Cross-Appellant.
    2
    NIEMEYER, Circuit Judge, for the court except as to Part IV.C.1
    in part and Part IV.C.2:
    In October 2011, the Loudoun County (Virginia) Board of
    Supervisors denied the applications of T-Mobile Northeast LLC
    for permits to build two telecommunication towers in Loudoun
    County -- one disguised as a bell tower, to be located on the
    property of a church in Sterling (in the eastern part of the
    county), and one disguised as a silo on a farm in Lovettsville
    (in the northern part of the county).              T-Mobile commenced this
    action under the Telecommunications Act of 1996, challenging the
    Board’s decisions.
    On cross-motions for summary judgment, the district court
    concluded       that    the    Board    improperly       denied        T-Mobile’s
    application for the silo tower in Lovettsville because the Board
    relied on the environmental effects of radio frequency emissions
    -- a statutorily prohibited basis for regulation.                     Even though
    the Board had given other valid reasons for its decision, the
    court   issued    an   injunction   requiring     the   Board    to    issue    the
    necessary permits for the site, concluding that if it remanded
    the case, the valid reasons would only become a subterfuge for
    the invalid environmental reason.           The district court affirmed
    the   Board’s    decision     denying   permits   for   the     bell    tower    in
    Sterling because (1) substantial evidence supported the Board’s
    decision; (2) a denial of the permits would not have the effect
    3
    of prohibiting T-Mobile from providing personal wireless service
    to its customers; and (3) the decision was not based on the
    environmental effects of radio frequency emissions.
    On appeal, the Board contends that the illegal reason it
    gave for denying the application for the silo tower represented
    the views of only one member of the Board and was not binding on
    the Board.       Moreover, it argues, it gave other valid reasons
    sufficient to justify denial of T-Mobile’s application for the
    silo tower.      On its cross-appeal, T-Mobile contends that neither
    of the Board’s denials were supported by substantial evidence
    and, with respect to the bell tower, that the Board’s decision
    denied it the ability to fill significant gaps in its wireless
    coverage and therefore effectively prohibited it from providing
    personal wireless service, in violation of the Act.                 It also
    contends that the Board relied on radio frequency emissions to
    deny the bell tower application, although not expressly.
    For   the    reasons   given   herein,     we   affirm   the   district
    court’s rulings as to both of the Board’s decisions.
    I
    T-Mobile’s     business   includes   the    provision    of    personal
    wireless service, along with other telecommunications services,
    in the Washington metropolitan area, including Loudoun County.
    Its wireless network, like other wireless networks, operates by
    4
    transmitting           radio          signals    to        and    from     antennas         mounted         on
    towers,      poles,         buildings,          or    other       structures.              In    order      to
    provide          reliable         service,       it        must     have        multiple         antennas
    arranged in a grid by which to overlap coverage.                                       While T-Mobile
    currently         has       56     wireless          telecommunications                facilities           in
    Loudoun          County,         it     determined,             based     upon       its        engineers’
    analyses, that it still had substantial gaps in coverage in the
    areas       at    issue      here.         To        address       the     deficiency,            T-Mobile
    identified            two    locations          at    which        it    sought        to       build      new
    wireless          telecommunication              facilities:                   (1)     the        property
    surrounding the Christ Our Savior Lutheran Church on Jefferson
    Drive in Sterling, Virginia (the “Bell Tower Site”) and (2) the
    area    surrounding              the     Stephens          family        farm    in     Lovettsville,
    Virginia (the “Silo Site”).                      After making arrangements with both
    the     Stephens            family       and     the           Church     for     construction             of
    facilities on their properties, T-Mobile submitted applications
    to    the    Loudoun         County       Board           of    Supervisors          for    permits        to
    construct monopole antennas at the sites -- one disguised as a
    silo and the other as a bell tower.
    In order to build on the sites, T-Mobile was required to
    secure from Loudoun County:                          (1) a “commission permit,” which
    issues      initially            from    the    County           Planning       Commission           and   is
    reviewed         by    the    Board       for    final          approval,       and    (2)       a   zoning
    “special         exception,”            which        is        granted    by     the       Board.           In
    5
    evaluating both types of applications, the Planning Commission
    and       the    Board      consider     the    location       and    character    of   the
    proposed structure to determine whether it is in accord with the
    Loudoun County Comprehensive Plan (the “Comprehensive Plan” or
    the “Plan”).           Since 1996, the Comprehensive Plan has included a
    “strategic land use plan for telecommunications facilities” that
    favors          the    construction       of        such    facilities      on     existing
    structures and requires compatibility with other land uses.                             The
    plan requires that proposals for facilities include siting and
    design elements that “mitigate negative impacts” and satisfy a
    number of aesthetic criteria.                   Also, the county’s zoning rules
    require that such facilities be “compatible with development in
    the       vicinity       with   regard    to    the        setting,    color,    lighting,
    topography, materials, and architecture.”                            The plan’s overall
    goal is to ensure that telecommunications facilities “blend with
    the background.”
    The Silo Site application
    T-Mobile’s Silo Site application proposed a monopole hidden
    in    a    125-foot-high        farm     silo   that       T-Mobile    would     construct.
    When the Planning Commission voiced concerns about the height of
    the silo, T-Mobile revised its proposal to reduce the height to
    100   feet.           The   Planning     Commission         then   issued   a    commission
    permit and recommended approval of the facility, finding that
    6
    the design was in conformity with the Comprehensive Plan.                       After
    T-Mobile     submitted   the    Planning         Commission’s      decision    to   the
    Board, the Board held a public hearing in July 2011 on both the
    commission permit and the special exception.                       County residents
    present spoke mostly in opposition to the proposal, mentioning
    concerns about the silo’s aesthetics and the antenna’s emission
    of   radio    waves.       In       response      to   the   continuing       comments
    regarding     aesthetics       at    the    Board      meeting,     T-Mobile     again
    revised its proposal, reducing the proposed height of the silo
    to 90 feet.
    The Board conducted a business meeting on October 17, 2011,
    to vote on the Silo Site application.                     During the meeting, the
    Board members (Supervisors) discussed reasons for rejecting the
    application, including aesthetic concerns and the availability
    of other potential sites.             Supervisor Miller also requested, in
    response to the numerous comments of citizens, that the Board
    include the “negative environmental impact” from radio frequency
    emissions    as   a   reason    in    the       pending   motion    for   denying   T-
    Mobile’s application.          The Board accepted Miller’s suggestion to
    amend the pending motion and then voted 7 to 2 to carry the
    motion.      As required by the Telecommunications Act, the Board
    issued a written notice of its decision.                     It gave four reasons
    for denying the special exception:                 (1) the proposed design did
    not mitigate the silo’s significant structural presence, thus
    7
    creating      “an   unnecessary        visual    impact       on   surrounding
    properties”; (2) the proposed silo height of 90 feet did not
    “blend with the . . . surrounding area”; (3) a denial of the
    application     would   not    “have    the   effect   of    prohibiting   the
    provision of personal wireless services in this area”; and (4)
    the facility would have a “negative environmental impact.”                 And
    it gave two reasons for denying the commission permit:                (1) the
    project was not consistent with the strategic land use plan; and
    (2) other preferred locations were available to T-Mobile.
    The Bell Tower Site application
    T-Mobile’s     original    application     for    a    telecommunications
    facility on the Church property included a proposal to construct
    an 80-foot flagpole that would house the antenna.                    When the
    Planning Commission rejected that proposal, T-Mobile amended it
    to propose instead an 80-foot bell tower to house the antenna.
    During the ensuing review process, T-Mobile made a number of
    additional changes in design, such as varying the color scheme
    of the structure to better blend with the background.                 It also
    offered alternative designs, such as a steeple or tree pole.
    After a lengthy give-and-take process, the Planning Commission
    issued the commission permit and recommended approval of the
    facility.
    8
    The Board held its public hearing on the Bell Tower Site
    application on September 12, 2011, and citizens raised a number
    of concerns with the project, primarily aesthetic, referring to
    the proposed facility’s visual impact.                      As with the Silo Site,
    some citizens also raised concerns over the possible negative
    health impacts of radio frequency emissions.
    The Board conducted a business meeting on the Bell Tower
    Site   application    on    October       4,      2011,    and,       following      a    brief
    discussion, voted to reject it.                   The Board’s written notice of
    decision gave as reasons that the proposed facility (1) was not
    at a preferred location; (2) was not on an existing structure;
    (3) was in a residential area; and (4) did not mitigate the
    impact on adjacent residential uses.                     The Board did not refer to
    the citizens’ concerns over radio frequency emissions and gave
    no   indication    that     it    relied       on   such       concerns      to    deny    the
    application.
    Following   the     Board’s       rejection        of    its    applications,         T-
    Mobile    commenced        this        action,      alleging          that     the        Board
    overstepped       several        limitations         imposed          on     it    by      the
    Telecommunications Act of 1996.                   With respect to the Silo Site,
    T-Mobile alleged that the Board’s denial was not supported by
    substantial    evidence          and    was       made     on    the       basis     of    the
    environmental effects of radio frequency emissions.                                And with
    respect to the Bell Tower Site, it alleged that the Board’s
    9
    rejection was not supported by substantial evidence, caused an
    effective prohibition of service, and was made on the basis of
    radio frequency emissions.
    On       the   parties’    cross-motions            for    summary   judgment,       the
    district court entered judgment in favor of T-Mobile on the Silo
    Site,     concluding       that       although       the       Board’s    rejection       was
    supported by substantial evidence, the Board improperly relied
    on the environmental effects of radio frequency emissions.                                The
    court entered an injunction directing the Board to issue the
    necessary permits to T-Mobile for construction of the Silo Site
    tower.        And,    as   to   the    Bell    Tower       Site,    the   court     entered
    judgment in favor of the Board, rejecting each of T-Mobile’s
    arguments.           T-Mobile   Northeast          LLC    v.    Loudoun   Cnty.     Bd.    of
    Supervisors, 
    903 F. Supp. 2d 385
     (E.D. Va. 2012).
    From the district court’s judgment dated July 20, 2012, the
    Board filed an appeal challenging the court’s decision on the
    Silo Site, and T-Mobile filed a cross-appeal challenging the
    court’s affirmance of the Board’s decision on the Bell Tower
    Site, as well as its conclusion that the Board’s decision on the
    Silo Site was supported by substantial evidence.
    II
    The    Telecommunications         Act       of     1996    was    enacted     “[t]o
    promote competition and reduce regulation in order to secure
    10
    lower    prices          and     higher        quality          services     for          American
    telecommunication consumers and encourage the rapid deployment
    of new telecommunications technologies.”                           Pub. L. No. 104-104,
    
    110 Stat. 56
    , 56 (1996).                    As part of the Act, Congress divided
    authority over personal wireless service facilities, preserving
    generally      to    state       and        local    governments         their    traditional
    zoning        control          over     the         placement,       construction,                 and
    modification        of     such       facilities          while,    at     the    same         time,
    limiting state and local governments’ ability “to frustrate the
    Act’s national purpose of facilitating the growth of wireless
    telecommunications.”              360° Commc’ns Co. of Charlottesville v.
    Bd. of Supervisors of Albemarle Cnty., 
    211 F.3d 79
    , 86 (4th Cir.
    2000); see also City of Rancho Palos Verdes v. Abrams, 
    544 U.S. 113
    ,    115    (2005)      (noting      that        the   Act    “reduc[ed]       .       .    .   the
    impediments imposed by local governments upon the installation
    of    facilities         for    wireless       communications,           such     as          antenna
    towers”).       Specifically, the Act provides that in regulating the
    siting and construction of wireless facilities, a state or local
    government       (1)       may        not     “unreasonably         discriminate                among
    providers”; (2) may not effectively prohibit “the provision of
    personal wireless services”; (3) must act on a request to place,
    construct, or modify such facilities “within a reasonable period
    of time”; (4) must render its decisions “in writing” and with
    the    support      of    “substantial         evidence         contained    in       a       written
    11
    record”; and (5) may not regulate the placement, construction or
    modification          of     such     facilities         “on     the    basis      of    the
    environmental effects of radio frequency emissions to the extent
    that    such     facilities          comply       with    the    [FCC’s]      regulations
    concerning such emissions.”                  
    47 U.S.C. § 332
    (c)(7)(B).                  State
    and local governments must comply with each of these provisions
    when regulating wireless facilities.
    The    Act     provides      that    anyone       “adversely     affected”       by    a
    final decision of a state or local government under § 332(c)(7)
    may commence an action “in any court of competent jurisdiction,”
    which must hear and decide the action “on an expedited basis.”
    
    47 U.S.C. § 332
    (c)(7)(B)(v).             When       such   action     challenges
    whether the state or local government’s decision was supported
    by    “substantial         evidence,”       see    
    id.
        §    332(c)(7)(B)(iii),         the
    court defers to the state or local government, upholding its
    decision if it has “substantial support in the record as a whole
    even    if     [the    court]       might     have    decided        differently    as       an
    original matter.”             New Cingular Wireless PCS, LLC v. Fairfax
    Cnty. Bd. of Supervisors, 
    674 F.3d 270
    , 274 (4th Cir. 2012)
    (quoting AT&T Wireless PCS, Inc. v. City Council of Va. Beach,
    
    155 F.3d 423
    ,    430    (4th    Cir.    1998)      (internal      quotation       marks
    omitted)); see also AT&T Wireless PCS, Inc. v. Winston-Salem
    Zoning Bd. of Adjustment, 
    172 F.3d 307
    , 314 (4th Cir. 1999).                                 On
    the other hand, if the action alleges that the state or local
    12
    government violated any of the other statutory limitations on
    its regulatory authority, the court decides the issue de novo.
    See   
    47 U.S.C. § 332
    (c)(7)(B)(v);             see   also    Second       Generation
    Props., L.P. v. Town of Pelham, 
    313 F.3d 620
    , 629 (1st Cir.
    2002)      (“Unlike       the      substantial         evidence     issue,       the    issue      of
    whether [a board] has prohibited or effectively prohibited the
    provision       of   wireless        services          is   determined      de    novo       by   the
    district        court”);       VoiceStream        Minneapolis,           Inc.    v.    St.    Croix
    Cnty., 
    342 F.3d 818
    , 833 n.6 (7th Cir. 2003) (applying same
    standard).
    With these principles in hand, we turn to the issues raised
    by the parties on appeal.
    III
    The Board contends on appeal that the district court erred
    in    ordering       it       to   grant   T-Mobile           permits     to     construct        the
    facility at the Silo Site in Lovettsville on the basis that the
    Board illegally relied on the environmental effects of radio
    frequency emissions.                 See 
    47 U.S.C. § 332
    (c)(7)(B)(iv).                            The
    Board argues that this reason, albeit illegal, was given by only
    one Board member and therefore was “not binding on the Board as
    a whole.”         The Board also argues that even if this reason were
    binding on it, its decision to deny the application was also
    based      on    valid        reasons      that        were    sufficient        to    deny       the
    13
    application,     and   that      therefore    the    court’s    injunction       was
    simply punishment for the inclusion of an illegal reason.
    At    its   October   17,    2011   meeting,     the   Board     rejected    T-
    Mobile’s    application     for    the    Silo   Site,      citing    the   silo’s
    “significant      structural       presence”        and     related     aesthetic
    complaints.      At the suggestion of Supervisor Miller, the Board
    also included as a reason for rejection the antenna’s “negative
    environmental impact.”           As Supervisor Miller explained, “We've
    had speaker after speaker come in here and talk to us about
    their concerns of being exposed to radiation from an evolving,
    dynamic technology.”          With particular relevance to the issue
    before us, in proposing his amendment, Supervisor Miller told
    the Board that it was made “notwithstanding the prohibition on
    what I’m going to propose [i]n the Telecommunications Act of
    1996.”
    Although the district court concluded that the aesthetic
    reasons the Board gave for denying T-Mobile’s application were
    supported by substantial evidence, it also concluded that the
    Board nonetheless impermissibly relied, “at least in part,” on
    the environmental effects of radio frequency emissions.                          The
    court noted that Supervisor Miller
    even commented that the Board and other local
    governing bodies deny wireless facility applications
    on the prohibited basis of environmental impact but
    cite permissible reasons as subterfuge for their true
    concerns.   Despite Supervisor Miller’s admission to
    14
    violating federal law, the Board finally adopted his
    proposed amendment by a 7-to-2 vote.
    Loudoun Cnty., 903 F. Supp. 2d at 409 (citation omitted).                               The
    court refused to rule that the valid reasons given by the Board
    to deny T-Mobile’s application should allow it to overlook the
    invalid    reason     because      the     Board’s     decision       to     include    the
    illegal reason was deliberate, and any remand to allow the Board
    to   reform    its   reasons       would    only      contribute       to    the   Board’s
    subterfuge:
    The evidence before the Court urges the conclusion
    that a remand would result in the Board simply
    justifying denial of the Stephens Silo application by
    citing the same permissible reasons listed in the
    written decision challenged in this action. The Court
    is not satisfied that this decision would be valid
    under the Telecommunications Act, particularly in
    light of Supervisor Miller’s comment that the Board
    falsely   cites   lawful  reasons   as    pretexts   for
    unlawfully denying permit applications and the Board’s
    silent approval of Supervisor Miller’s proposal.       A
    remand would simply invite the Board to violate the §
    332(c)(7)(B) again while concealing its violation with
    false    justifications    for    denying     T-Mobile’s
    application.
    Loudoun    Cnty.,    903     F.    Supp.   2d    at    412.      In    support     of   its
    holding,      the    court    also       noted     that   the      record      contained
    substantial     evidence      to    support      approval     of      the    application,
    pointing to the County Planning Commission’s recommendation that
    the Board approve the proposed facility based on its staff’s
    finding that “the interior location and stealth design of the
    proposed    facility       were    in    conformance      with     the      Comprehensive
    15
    Plan     and    sensitive        to   the    surrounding         rural   agricultural
    landscape.”       Id. at 411 (internal quotation marks omitted).
    Based on our review of the record, we conclude that the
    district court correctly held that the Board’s basis for its
    decision       violated    the    prohibition          against    regulating      on    the
    basis of radio frequency emissions.
    First, the record shows that Supervisor Miller’s comments
    during    the    Board     meeting    were       not    isolated,   either       from   the
    evidence before the Board or from the Board’s own views.                                The
    record shows that discussions of health concerns were prevalent
    throughout the several hearings.                   On July 11, 2011, the Board
    questioned a representative of T-Mobile about the transmission
    wattage of the antenna at the Silo Site and whether the signal
    would    be    “optimized”       in   such    a   way    that    would   increase       the
    radiation       exposure    level.          At    the    same    hearing,    a    citizen
    testified that her two boys and “other children . . . [would] be
    affected by the electromagnetic radiation.”                         And in light of
    these comments about “health and safety,” a T-Mobile employee
    offered to address the safety concerns of the citizens.
    Again     at   a   September     21,       2011    hearing   to   discuss        the
    application, Supervisor York stated:
    But I do have a question because I hear we are
    concerned about the radio waves and the possibility of
    health issues, which I don’t even think we have the
    ability to consider under FCC rules.       But having
    give[n] that, now I am hearing the limit to three
    16
    users [on the proposed monopole].      Are there more
    radio wave impacts for health issues with each user on
    a tower?   In other words, if you limit to one, is it
    different than if you have five users on a tower or is
    it the same no matter what?
    A T-Mobile representative responded that there would be some
    increase in radio frequency emissions with an increase in the
    number of telecommunications providers using the tower but that
    the increase would not present a health risk.
    Finally, at the October 17, 2011 Board meeting, Supervisor
    Miller successfully requested that radio frequency emissions be
    given as a reason for denying the permits.   As he explained:
    We’ve had speaker after speaker come in here and talk
    to us about their concerns of being exposed to
    radiation from an evolving, dynamic technology.
    *     *     *
    Unless these applications are going to be reviewed and
    voted on by the Congress of the United States, they
    have done the opposite of occupy the field by
    depriving the level of government that does have to
    review and vote on these applications the right to
    consider something that our direct constituents have
    asked us to look at.      Governments at our level all
    over the country do the same thing when they decide
    that’s   the  reason   to   turn   down one   of  these
    applications: They lie. They give a reason that’s on
    the legal list when that’s not what’s on their mind.
    I want this decided in a court of law that will be
    asked the question, Do we have the right to look at
    something that Congress closed its eyes to 15 years
    ago and in the context of an evolving technology where
    frequencies change, power levels change, radiation
    patterns change, and studies have been made available
    since the decision was made that there are risks to
    being exposed this close.
    17
    When    Supervisor            Miller    made      a     motion     to    include        the   health
    effects       of    radiation          as     a       reason     for     denying        T-Mobile’s
    application, the Board added the reason to the motion to deny
    the application and voted 7 to 2 to carry the motion.                                            The
    written       denial      given    by       the     Board      specifically         included     the
    health risk reason.
    Based       on    this    record,       it      is   thus   indisputable           that   the
    Board    as    a    whole       regulated         on    the    basis     of    radio     frequency
    emissions, a prohibited basis under the Act.                                   See 
    47 U.S.C. § 332
    (c)(7)(B)(iv).               This explicit statutory prohibition against
    regulating         the    placement,          construction,             and    modification      of
    wireless facilities “on the basis of the environmental effects
    of radio frequency emissions” is a limitation imposed by the Act
    on the Board’s authority.                   And the fact that the Board relied on
    valid    reasons         to    support      its       decision     does       not   immunize     its
    violation of a statutory limitation.                             As noted by the Supreme
    Court,    each          subsection       in       §     332(c)(7)(B)          is    a    “specific
    limitation[] on the traditional authority of state and local
    governments         to        regulate       the        placement,        construction,          and
    modification of [wireless] facilities.”                             City of Ranchos Palos
    Verdes, 
    544 U.S. at 115
     (2005).                         We thus conclude that the fact
    that the Board gave valid reasons for its decision, which by
    themselves would be sufficient, does not immunize it from its
    violation of the statutory limitation.
    18
    We    also    agree      with    the        district     court       that   in   the
    circumstances presented -- where radio frequency emissions were
    a genuine and substantial concern of the Board and where the
    County Planning Commission, when considering factors other than
    radio frequency emissions, found the Silo Site application in
    compliance      with    the    existing           criteria    for     evaluating       such
    applications -- the matter should not be remanded to the Board.
    The district court properly interpreted the record in concluding
    that while the Board would, on remand, omit its concerns over
    radiation when giving reasons for denial of the application, the
    radiation    concerns       would     nonetheless          persist    as   part   of   the
    decisionmaking         process.         To        reject     the     district     court’s
    conclusions in the circumstances presented in this case would
    mock Congress’s prohibition against the use of radio frequency
    emissions as a basis for regulating wireless facilities when
    those emissions were in compliance with FCC regulations.                           See 
    47 U.S.C. § 332
    (c)(7)(B)(iv).
    The Board devotes a substantial portion of its brief on
    appeal to noting that it gave legitimate reasons for denying T-
    Mobile’s Planning Commission permit and that only its denial of
    the   special      exception      included        improper     environmental       health
    concerns.     It thus argues that the environmental reasons had no
    effect on the ultimate decision because T-Mobile would have been
    ineligible to obtain a special exception without first obtaining
    19
    a commission permit.            Yet the Board did not reject the special
    exception on the basis that T-Mobile was ineligible for one.
    While the Board’s technical description of its procedure
    may be accurate, the district court correctly concluded that the
    Board denied T-Mobile’s application in one regulatory action.
    It conducted its hearings on both the permit and the special
    exception simultaneously, receiving the comments of citizens in
    connection with both; it addressed one motion when articulating
    the reasons for denying T-Mobile’s application; and it issued
    one decision for both, even though it did, in its written notice
    of that decision, separate the reasons for denying the permit
    and the special exception.               That formality, however, did not
    change       the   fact   that    the    Board      was       regulating    T-Mobile’s
    placement of the antenna at the Silo Site on the basis of the
    environmental effects of radio frequency emissions.
    The    Telecommunications        Act      does   not     limit   particularized
    local    procedural       mechanisms;       it    limits      all   local   regulatory
    authority, providing that “[n]o State or local government . . .
    may regulate the placement, construction, and modification of
    personal       wireless    service      facilities         on    the    basis   of    the
    environmental effects of radio frequency emissions,” by whatever
    means.       
    47 U.S.C. § 332
    (c)(7)(B)(iv) (emphasis added).                     Thus, in
    this    case,      regardless    of   the     mechanism         employed,   the      Board
    regulated the placement of T-Mobile’s proposed facility based on
    20
    radio frequency emissions, and its argument assigning reasons to
    one mechanism for denial and not the other does not justify its
    violation of the limitation.
    Because we affirm the district court’s injunction directing
    the Board to grant the necessary permits for the Silo Site, we
    need      not    address      T-Mobile’s      arguments     challenging        the
    sufficiency of the other evidence given by the Board for its
    rejection of T-Mobile’s application.
    IV
    On its cross-appeal, T-Mobile contends that the district
    court erred in affirming the Board’s denial of its application
    to construct a wireless facility at the Bell Tower Site.                        It
    argues    (1)    that   the    Board’s    decision   was    not    supported    by
    substantial        evidence,       as     required     by     
    47 U.S.C. § 332
    (c)(7)(B)(iii); (2) that the decision effectively prohibited
    T-Mobile    from   providing       its   customers   with   personal   wireless
    service, in violation of § 332(c)(7)(B)(i)(II); and (3) that the
    decision was made “on the basis of the environmental effects of
    radio frequency emissions,” in violation of § 332(c)(7)(B)(iv).
    Before    we    address    these    arguments,   however,     we   address     the
    Board’s    contention      that    T-Mobile    did   not    have   Article     III
    standing to challenge in court the Board’s decision on the Bell
    Tower Site.
    21
    A
    The Board’s standing argument is based on its contention
    that T-Mobile did not have any property interest in the Bell
    Tower Site to vindicate.            See Warth v. Seldin, 
    422 U.S. 490
    , 498
    (1975) (holding that to have Article III standing, the plaintiff
    must have “a personal stake in the outcome of the controversy”);
    see also Friends of Earth, Inc. v. Laidlaw Envtl. Servs. (TOC),
    Inc., 
    528 U.S. 167
    , 180-81 (2000) (noting that standing requires
    a plaintiff to have suffered an injury that “will be redressed
    by a favorable decision”).                The Board’s position rests on the
    fact that T-Mobile’s original written agreement with the Church
    covered the placement of a flagpole on its property, which the
    Planning Commission rejected, and that the Church and T-Mobile
    never modified the agreement to give T-Mobile a right to place a
    bell tower on the property, as ultimately proposed.                        The Board
    argues that even if the court were to find that the Board’s
    decision denying the Bell Tower application was unlawful and
    subsequently were to grant T-Mobile injunctive relief, T-Mobile
    would    still   not    be   able    to    build     its    facility     without   the
    consent of the Church.              Accordingly, the Board concludes, the
    court had no ability to redress T-Mobile’s injuries, as required
    for standing.
    The   Board’s   argument,         however,    is    based   on    an   overly
    restrictive      view   of   the     interests       that    T-Mobile     sought    to
    22
    vindicate in court.            While the written agreement with the Church
    did indeed anticipate an antenna disguised as a flagpole, it
    also anticipated revisions to the plan.                             Moreover, the Church
    agreed     to   cooperate        with   T-Mobile        in    the    development           of    any
    revised     plan    and    did    so    throughout           the    application          process.
    When     T-Mobile      first      proposed    a     bell       tower,          in   lieu       of   a
    flagpole,       a   representative           of    the        Church       sent      an        email
    indicating      that      they    “like[d]        the    idea       of     a    bell      tower.”
    Similarly,      when      further       refinements           of     the       proposal         were
    forwarded to the Church, the representative indicated that “it
    looks good to us.”          Representatives of the Church also attended
    Planning Commission meetings in support of T-Mobile’s Bell Tower
    Site application, and the officially designated representative
    of the Church, who had conducted the negotiations with T-Mobile,
    later submitted an affidavit stating that “the current design of
    the proposed wireless facility, which the Church has approved,
    is   a    freestanding      structure        with       the    appearance           of     a    bell
    tower.”     (Emphasis added).
    T-Mobile expended substantial time and money in pursuing
    the Bell Tower Site application, and it certainly would not have
    done so if it had any reason to believe that it could not have
    benefited from the effort.              We conclude that it had a sufficient
    interest in the Bell Tower Site and in the outcome of its permit
    23
    application process to give it standing to challenge in court
    the Board’s denial of its application.
    B
    On the merits of T-Mobile’s challenge of the Board’s Bell
    Tower decision, T-Mobile argues first that the Board did not
    have substantial evidence in the record to support its decision,
    thus violating § 332(c)(7)(B)(iii).                 We disagree.
    The record contains the testimony of numerous citizens in
    the community, as well as citizen petitions and emails, stating
    their strong opposition to the construction of the Bell Tower
    facility.     The residents noted that the tower would be out of
    proportion    with    the    surrounding        natural      environment;    that    it
    would    diminish    the    value    of     their     properties;    and    that    the
    machinery used to support the operation of the tower, such as
    generators,    would       introduce      unwanted     noise.       These    concerns
    constituted a legitimate basis for the Board’s denial of the
    application.        See New Cingular Wireless, 
    674 F.3d at 274
     (“[A]
    proposed    telecommunication            facility’s    negative     impact    on    the
    neighborhood    may       support    a    finding     of   substantial      evidence”
    (internal quotation marks omitted)); City Council of Virginia
    Beach, 
    155 F.3d at 427
     (upholding rejection based on “preserving
    the     character    of     the     neighborhood       and     avoiding     aesthetic
    blight”).
    24
    T-Mobile       contends,       however,         that        these       aesthetic
    considerations were not legitimate in this case because existing
    zoning at the site already authorized the Church to construct a
    bell tower for its own use up to a height of 74 feet.                          It argues
    that because the county’s zoning rules would accept the visual
    impact   of    a    similar   bell    tower      without      a    telecommunications
    antenna within it, it was not legitimate to reject T-Mobile’s
    bell tower based on visual impact.                But the fact that the Church
    would not need a special exception to construct a similar bell
    tower without a telecommunications facility in it does not imply
    that   citizens      may   not     have   legitimate       objections      to       such    a
    tower.       Moreover, T-Mobile fails to recognize that any zoning
    decision reflects a balance between the benefit provided by the
    facility      and   the    aesthetic      harm    caused,         and   thus    a    local
    government might be willing to tolerate what is aesthetically
    displeasing for one type of use but not for another.
    The    district     court    did   not    err   in     concluding       that       the
    Board’s aesthetic reasons had “substantial support in the record
    as a whole.”        New Cingular Wireless, 
    674 F.3d at 275
    .
    C
    1
    T-Mobile next argues that the Board’s denial of its Bell
    Tower Site application had the effect of prohibiting it from
    providing      personal       wireless     service,         in     violation         of     §
    25
    332(c)(7)(B)(i)(II)                  (“The        regulation          of        the        placement,
    construction,         and        modification            of    personal         wireless     service
    facilities by any State or local government . . . shall not
    prohibit      or     have    the         effect     of   prohibiting        the       provision     of
    personal wireless services”).                          The district court rejected T-
    Mobile’s argument because T-Mobile failed to carry its burden of
    showing       “an      effective               absence        of    coverage,”         failed        to
    demonstrate a “lack of reasonable alternative sites,” and failed
    to    show    that    further            efforts       for    alternative        sites      would   be
    “fruitless.”
    To     show    that       a       local    government        regulation        or    decision
    “prohibit[s]”         service             or     has     “the      effect       of    prohibiting”
    service,      the     telecommunications                 provider     may       demonstrate     that
    the    regulation           calls          for    the        rejection      of       all    wireless
    facilities -- i.e., that “a local governing body has a general
    policy       that    effectively            guarantees         rejection        of    all    wireless
    facility applications.”                    T-Mobile Northeast LLC v. Fairfax Cnty.
    Bd. of Supervisors, 
    672 F.3d 259
    , 266 (4th Cir. 2012).                                        Or, if
    the local government rejects a facility at a single site, the
    telecommunications provider may demonstrate that the rejection
    was    “tantamount          to       a    general      prohibition         of    service.”          
    Id.
    (internal quotation marks omitted).                             To make that showing, the
    telecommunications provider must demonstrate (1) that there is
    an “effective absence of coverage” in the area surrounding the
    26
    proposed facility, and (2) that there is a “lack of reasonable
    alternative         sites         to     provide        coverage”        or     that        “further
    reasonable efforts to gain approval for alternative facilities
    would be ‘fruitless.’”                   
    Id.
     at 268 (citing Albemarle Cnty., 211
    F.3d at 87-88).              This burden is “substantial and is particularly
    heavy      when     .    .    .    the      [telecommunications           provider]          already
    provides some level of wireless service to the area.”                                  Id.
    The “effective absence of coverage” does not mean a total
    absence; it may mean coverage containing significant gaps.                                         See
    Albemarle Cnty., 211 F.3d at 87-88.                            This cannot, however, be
    defined       metrically           by       simply      looking      at        the     geographic
    percentage of coverage or the percentage of dropped calls.                                          It
    is    a    contextual        term      that    must     take     into     consideration            the
    purposes       of   the      Telecommunications            Act    itself.            See    City    of
    Rancho Palos Verdes, 
    544 U.S. at 115
    .                          The        Telecommunications
    Act       announces       that      among      its      purposes        are     the        goals    of
    “promot[ing]            competition”;         “secur[ing]        .   .    .    higher        quality
    services        for       American           telecommunications               consumers”;          and
    “encourag[ing]           the      rapid     deployment      of    new     telecommunications
    technologies.”            Pub. Law. No. 104-104, 
    110 Stat. 56
    , 56 (1996).
    We    should      therefore        not      read    §   332(c)(7)        to    frustrate       these
    goals.       See City of Rancho Palos Verdes, 
    544 U.S. at 115
    .                                 While
    §     332(c)(7)(A)             preserves           state    and      local           authorities’
    traditional         authority          to    regulate      the    design        and    siting       of
    27
    wireless facilities, the express limitations of § 332(c)(7)(B)
    promote      the    purposes        of     securing         higher     quality       wireless
    services      and   encouraging          new    technology.           See    also     City    of
    Rancho Palos Verdes, 
    544 U.S. at 115
    .
    The   technology        of   10    years       ago   may   have      only    supported
    wireless service that had substantial gaps in coverage and high
    dropped      call     rates.        But    the       technology      of     today    supports
    increased wireless coverage with reduced rates of dropped calls.
    On this trajectory, the technology of tomorrow may support 100%
    coverage with no dropped calls, and the focus may instead be on
    subtler      issues    about    the       nature      and   strength        of    signals    for
    particular uses.           The Telecommunications Act clearly intends to
    encourage this technological development and, to that end, to
    protect such development from interference from state and local
    governments         when    approving           the     design       and         location     of
    facilities.         This is manifested in § 332(c)(7)(B).                            Thus, in
    construing          the     level          of        service         protected         by      §
    332(c)(7)(B)(i)(II),           we    must       take    a   contextual           approach    and
    cannot rely on any specific formula.                          See Fairfax Cnty., 672
    F.3d   at    267    (observing       that       “reviewing     courts       should     not    be
    constrained by any specific formulation, but should conduct a
    fact-based analysis of the record, as contemplated by the Act”).
    28
    2
    Even though we affirm the Board’s decision on the ground
    that     T-Mobile      failed    to    show        that     there       was     a    lack       of
    alternative sites from which to provide coverage or that further
    efforts to gain approval for alternative facilities would be
    fruitless -- as we explain below -- we nonetheless also address
    T-Mobile’s effort to establish an effective absence of coverage
    at the Bell Tower Site.           This issue is one that was at the core
    of the parties’ arguments and, even with our affirmance on the
    basis of the alternative-sites issue, the issue of effective
    coverage      remains    open     as     T-Mobile         makes    efforts          to    pursue
    facilities      at    alternative      sites       in     the    same    area       and    again
    attempts to demonstrate an effective absence of coverage.
    In   this    case,    T-Mobile    provided         evidence      that       it    had    a
    dropped call rate of 1.82% in the area of the Bell Tower Site
    and an access failure rate of 2.8% in buildings within that
    area.        The district court, noting that “[t]he Fourth Circuit
    Court    of    Appeals    has    not   directly           resolved      the   question          of
    precisely what minimum level of wireless service is adequate
    under subparagraph B(i)(II),” relied primarily on these dropped-
    call rates in holding that T-Mobile failed to meet its burden of
    demonstrating a question of fact as to its absence of coverage.
    But    providing      coverage   may     be       more    than    simply      ensuring      low
    dropped-call         rates.      T-Mobile          also     provided       evidence         from
    29
    “advanced computer propagation modeling” and “actual drive test
    data”    of    what   its    expert     called    a   “significant    gap”       in    in-
    building coverage in the area of the Bell Tower Site, an area
    consisting of “approximately 1.4 square miles,” in which there
    are “approximately 10,536 residents.”                 Its expert testified that
    this level of signal strength effectively prohibited it from
    providing       “acceptable”       personal      wireless      service    inside        of
    buildings.        The expert witness testified that consumers demand
    to be able to reliably make and maintain wireless calls, and in
    some cases, to access wireless data service, within their homes
    and     offices    and      that   if    T-Mobile     lacks     sufficient       signal
    strength to reliably provide service in buildings, it is not,
    from a consumer’s perspective, providing service.
    In     contrast,     the    Board’s       expert   conducted       a    separate
    computer      propagation      modeling      study,    using    different       methods
    than T-Mobile, and found fewer gaps in service than T-Mobile
    did.     We are not in a position to assess the relative merits of
    those studies here, but the Board’s expert acknowledged that “if
    you accept T-Mobile’s definition of reliable and if you accept
    their methodology at arriving at their definitions of signal
    strength threshold, then . . . there are areas around . . . the
    Church site, that do not have reliable in-building service at
    some locations at some time.”                When asked directly whether she
    disagreed      with   T-Mobile’s        conclusion     that    it   was       unable   to
    30
    provide reliable in-building service around the Church site, the
    Board’s     expert   witness   responded,      “I     think       that    is    an    open
    question.”
    We conclude that this evidence is sufficient to create at
    least a factual question about the effective absence of coverage
    at the Bell Tower Site and therefore that the district court
    should not have resolved that question against T-Mobile as a
    matter of law.        See Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248, 255 (1986).
    3
    As we have already indicated, T-Mobile failed to satisfy
    the second prong for showing an effective absence of coverage at
    a particular site -- that is, it failed to show that there was a
    lack   of   reasonable    alternative        sites    from        which    to     provide
    coverage or that “further reasonable efforts to gain approval
    for alternative facilities would have been fruitless.”                          Fairfax
    Cnty., 672 F.3d at 266.
    T-Mobile claimed that any alternative sites were inadequate
    because they were not of sufficient height.                        But it conceded
    that   constructing     multiple   antennas      at    reduced         heights       would
    “provide     some    improvement   of    coverage       .     .    .     within      their
    respective areas.”        The Board’s expert witness went further and
    identified     numerous    other   sites       capable        of       providing      the
    enhancement of service desired by T-Mobile, including both new
    31
    and existing structures.               And she asserted that antennas at a
    combination of two sites -- one to the northeast of the Bell
    Tower Site and another to the southwest of the Site -- would
    provide better service than one alone at the Bell Tower Site.
    While       T-Mobile    did     dispute        the    efficacy       of    many       of    the
    alternative         sites   separately,         it     failed      to     show       that   the
    alternative         sites     would,      in     the       aggregate,          not     provide
    sufficient coverage.
    The district court also determined that T-Mobile failed to
    show     that    attempting      to     place        its    wireless       facilities       at
    alternative sites would have been “fruitless.”                          We agree.
    The    Board    identified       alternative          sites      that     “would     not
    require the construction of free-standing monopoles or towers,
    but     would    require       the    collocation           of    T-Mobile’s          wireless
    facilities on existing buildings, a preferred location under the
    County’s Telecom Plan.”              Based on our review of the record, we
    do not believe that the district court erred in its finding that
    “T-Mobile [had] cite[d] no provision in the Zoning Ordinance or
    Comprehensive        Plan     suggesting       that    any       efforts    to       collocate
    wireless facilities on the existing structures . . . would be
    ‘fruitless.’”         T-Mobile, 903 F. Supp. 2d at 402.
    We    thus    conclude    that     on    this       record,      T-Mobile      did   not
    carry its substantial burden of demonstrating that alternative
    sites were not available to remedy the deficiency in coverage
    32
    that it had identified.                 Accordingly, we affirm the district
    court’s conclusion that the Board’s denial of the application
    for the Bell Tower Site did not cause an effective prohibition
    of service in the area.
    D
    Finally, T-Mobile contends that the Board made its decision
    regarding     the     Bell     Tower    Site       in   part    on   the   basis    of    the
    environmental effects of radio frequency emissions, in violation
    of § 332(c)(7)(B)(iv).               It argues that the “overwhelming focus
    of the public comment both explicitly and indirectly centered on
    the   fears     of    radio    frequency       emissions”        and   that   “the    Board
    denied    the        Bell    Tower     Site        based   on     residents’       concerns
    regarding the health effects of RF emissions, while concealing
    that reason behind the veil of ‘visual impact.’”
    The record shows that citizens did voice objections to the
    Bell Tower Site on the basis of health concerns.                              But the Act
    does not prohibit citizens from expressing such concerns; it
    prohibits the Board’s acting on them.                          See T-Mobile Northeast
    LLC v. City Council of Newport News, 
    674 F.3d 380
    , 390 (4th Cir.
    2012).    Moreover, the record also shows that citizens objected
    for   other     reasons,       all     of   which       were    legally    valid.        They
    worried about reductions in the value of their properties; they
    pointed       out       that     other         local       communities         prohibited
    33
    telecommunications           towers       in       residential       areas;       and     they
    articulated specific aesthetic complaints.
    While the record does indicate that one Board member voiced
    concerns      about        environmental            health      effects        during      the
    application        process,       there     is      no    evidence      that     the     Board
    discussed including health effects as a reason for denying T-
    Mobile’s application.              Nor did the Board’s written order refer
    to radio frequency emissions as a reason for its decision.                                 At
    bottom, unlike the evidence presented in connection with the
    Silo Site, there is simply no evidence to indicate that the
    Board    relied      on    radio     frequency           emissions    in   reaching        its
    decision on the Bell Tower Site, and T-Mobile’s argument can
    only be speculation.             Accordingly, we reject it.
    V
    In sum, we conclude that the Board’s decision to deny T-
    Mobile’s      Bell        Tower     Site       application        was      supported        by
    substantial evidence; did not have the effect of prohibiting the
    provision     of      personal          wireless      services       in    view     of    the
    possibility of other alternatives; and was not made on the basis
    of health concerns about radio frequency emissions.                               And as to
    the Silo Site, we conclude that while the aesthetic concerns
    that    the   Board       gave    for    denying      T-Mobile’s      application         were
    supported     by    substantial          evidence,        its   decision    to    base     the
    34
    denial    of   T-Mobile’s     application       on    improper    environmental
    concerns about radio frequency emissions was prohibited by the
    Act.      A    remand   would   not      eliminate     those     concerns   from
    consideration of T-Mobile’s application.
    Accordingly,     the   judgment     of   the    district     court   with
    respect to both Sites is
    AFFIRMED.
    35
    AGEE, Circuit Judge, concurring:
    I     agree     that      we   should          affirm     the     district     court’s
    judgment.       However, I write separately to underscore that we
    need   not     and    do    not     reach    and       decide    one     particular      issue:
    whether the district court correctly determined the effective-
    absence-of-coverage issue.
    To    affirm     the       district       court’s        judgment    on     T-Mobile’s
    effective-prohibition claim, it is enough for us to say that
    there were reasonable alternative sites and efforts to secure
    permits for those sites would not have been fruitless.                               By going
    further, we “stray into the practice of advisory opinion-making,
    solving      questions       that     do    not       actually    require    answering       in
    order to resolve the matters before [us].”                               Karsten v. Kaiser
    Found. Health Plan of Mid-Atl. States, 
    36 F.3d 8
    , 11 (4th Cir.
    1994).        Yet    “the     oldest       and    most    consistent        thread    in   the
    federal law of justiciability is that the federal courts will
    not give advisory opinions.”                     Flast v. Cohen, 
    392 U.S. 83
    , 96
    (1968) (quotation marks omitted).
    Respectfully,          then,    I    do    not    join     Part    IV.C.2    of    Judge
    Niemeyer’s opinion or the portion of Part IV.C.1 of his opinion
    that       addresses       the    effective-absence-of-coverage                  issue.      I
    36
    conclude   that   these   sections   –-   which   are   not   part   of   the
    opinion of the Court -- offer an advisory opinion. *
    *
    Even if those portions were part of the opinion of the
    Court, they would still be nothing more than non-binding dicta.
    See Pittston Co. v. United States, 
    199 F.3d 694
    , 703 (4th Cir.
    1999) (“Dictum is [a] statement in a judicial opinion that could
    have been deleted without seriously impairing the analytical
    foundations of the holding -- that, being peripheral, may not
    have received the full and careful consideration of the court
    that uttered it.” (quotation marks omitted)).
    37
    WYNN, Circuit Judge, concurring in part and dissenting in part:
    While I otherwise agree with the majority opinion, I cannot
    agree with Part III or with the portion of Part IV.C.1 that
    discusses        the   “effective         absence          of    coverage”       aspect      of    a
    telecommunications provider’s burden.                             As noted on the cover
    page of the opinion, Part IV.C.2 does not constitute the opinion
    of   this    court.            The   discussion            in     Part    IV.C.1          regarding
    effective absence of coverage is, therefore, dicta because we do
    not decide whether T-Mobile established an effective absence of
    coverage.          Put    differently,          because          we    affirm       the    Board’s
    decision on the ground that T-Mobile failed to show both a lack
    of alternative sites and that further efforts to gain approval
    of   alternative          sites      would       be        fruitless,         the     discussion
    pertaining to the effective absence of coverage in Part IV.C.1
    is   unnecessary         to    the   holding         of    this       case.      Therefore,        I
    decline to join Part IV.C.1’s dicta regarding effective absence
    of coverage.
    Regarding Part III of the majority opinion, I must dissent
    because     it    fails       to   fully   consider             the    significance         of   two
    separate     and         distinct        land        use        entitlements—the           special
    exception permit and the commission permit.                              Although the Board
    of   Supervisors         (“Board”)       improperly         denied       the     Stephens        Silo
    special     exception         permit     based       on     its       concerns      about    radio
    frequency        emissions,        the    Board       provided         distinct      and     valid
    38
    reasons    for       denying           the   Stephens     Silo     commission        permit.
    Neither the majority nor the district court has sufficiently
    explained how it is that the improper special exception denial
    somehow    taints          the    separate       and   distinct       commission      permit
    denial, which alone would have been sufficient to bar T-Mobile
    from constructing its Stephens Silo project.                            Because I would
    reverse the district court’s order that the Board grant both
    permits,       I    must    respectfully         dissent    from      Part    III    of    the
    majority opinion.
    I.
    Focusing on the facts that pertain to the Stephens Silo
    site, T-Mobile wanted to construct a wireless telecommunications
    facility on a farm in Lovettsville, Loudoun County, Virginia.
    Loudoun County’s land use regulations required two separate land
    use entitlements before construction: a “commission permit” and
    a “special exception.”
    The Board and the Planning Commission make decisions on
    whether    to      grant        such   entitlements.        In     doing     so,    they   are
    guided    by       the    policies       and   regulations       in    Loudoun      County’s
    Comprehensive            Plan    and    Zoning      Ordinance. 1       Loudoun      County’s
    1
    The State of Virginia requires “every governing body [to]
    adopt a comprehensive plan for the territory under its
    jurisdiction.” 
    Va. Code Ann. § 15.2-2223
    (A). The purpose of a
    39
    Comprehensive Plan contains a Telecommunications Facilities Plan
    (“Telecom Plan”), which explains that its overarching goal is
    “to encourage improvements in telecommunications services while
    mitigating the impacts on . . . residents, nearby land uses,
    scenic beauty, and rural heritage.”               J.A. 314.     The Telecom Plan
    is     generally        intended     to      “ensure       compatibility         of
    telecommunication facilities with nearby land uses” by requiring
    collocation of facilities whenever possible, establishing design
    criteria     and   removal     provisions,    and    creating    a    process    “by
    which an applicant can demonstrate their compliance with these
    policies.”     J.A. 314–15.
    The   Telecom    Plan   contains     specific   policies       designed    to
    mitigate the visual impact that antennas, towers, and monopoles
    have on the “historic character of the rural . . . areas.”                      J.A.
    318.     Of note here, “the County prefers locating new antennas on
    existing     towers,    monopoles    or   other     tall   structures[,]”        and
    “[w]hen existing structures cannot be used, new monopoles or
    towers    should   be   sited    within     the   right-of-way       for   overhead
    comprehensive   plan    is   to  “guid[e]  and  accomplish[]   a
    coordinated,   adjusted    and  harmonious development  of   the
    territory” to “best promote the health, safety, morals, order,
    convenience, prosperity and general welfare of the inhabitants .
    . . .” 
    Id.
     A zoning ordinance is a method of implementing the
    comprehensive plan. 
    Id.
     § 15.2-2224(B)(4).
    40
    utility      transmission            lines    where        the       visual    impact      of      an
    additional tall structure would be minimal.”                            J.A. 318.
    All    telecommunication              facilities         in    Loudoun        County     must
    meet    specified          criteria     to     demonstrate            compliance       with      the
    Comprehensive Plan.              The procedural mechanism for ensuring such
    compliance is the commission permit, which certifies that the
    proposed project is “substantially in accord with the adopted
    Comprehensive Plan.”              Loudoun Cnty., Va. Zoning Ordinance § 6-
    1101(A).      In some zoning districts, telecommunication facilities
    are permitted “by right[.]”                   But in other zoning districts, the
    Board has determined that telecommunication facilities “have the
    potential for a deleterious impact upon the health, safety, and
    welfare      of    the     public[.]”          Id.    §§       5-618(B),      6-1301.         If    a
    telecommunication              facility       is     proposed          in     such     a   zoning
    district,         the    proponent      must       obtain       a    special    exception          in
    addition to a commission permit.                     Id. § 5-618(B)(2).               Proponents
    of   projects           that   are    subject        to    a     special      exception         must
    demonstrate compliance with criteria beyond those required for a
    commission permit.              Id. § 5-618(B)(3).                  Ultimately, whether to
    grant a special exception is in the Board’s discretion.                                       Id. §
    6-1301.
    The    Stephens         Silo    site,       located       in    the    AR-1     district,
    required a special exception in addition to a commission permit.
    When the Stephens Silo proposal came before the Board on October
    41
    17, 2011, the Board voted to overturn the Planning Commission’s
    approval   of    the       commission   permit    and   to    deny   T-Mobile’s
    application     for    a   special   exception.     The      Board   articulated
    different reasons for the denials:
    Commission Permit
    1. The proposed project is not fully consistent
    with the land use policies of the Revised General Plan
    and Strategic Land [U]se Plan for Telecommunications
    Facilities   (Telecommunications   Plan).      The   1996
    Strategic   Land   Use   Plan   for    Telecommunications
    Facilities     recommends     any      new     commercial
    telecommunication antennas in the rural areas first
    locate on existing towers, buildings, or other tall
    structures within a two (2) mile radius. . . .
    2. Currently there are existing agricultural
    silos within a two (2) mile radius on which to locate
    telecommunications   antennas    which    are   preferred
    locations as outlined in the Telecommunications Plan.
    Special Exception
    1. The proposed design and siting has not
    mitigated its significant structural presence, thus
    creating an unnecessary visual impact on surrounding
    properties.
    2. The proposed silo height of 90-feet does not
    blend with the natural and built environment of the
    surrounding area. The height and appearance is not in
    keeping with the silos and other farm structures in
    the immediate vicinity.
    3. A denial does not have the effect of
    prohibiting   the   provision  of   personal   wireless
    services in this area of the County, with current
    service available from T-Mobile and others. . . .
    Supervisor Miller made a friendly amendment to include
    negative environmental impact as the fourth reason for
    denial of the SPEX 2010-0020.
    J.A. 1180–81.
    42
    II.
    Thus, the Board articulated separate and distinct reasons
    for denying each permit.             Regarding the commission permit, the
    reasons given for its denial are directly related to the rural
    location policies contained in the Telecom Plan.                    In denying
    that permit, the Board did not exercise discretion; rather, it
    made a finding that T-Mobile’s proposal failed to comply with
    the Comprehensive Plan—a prerequisite to obtaining a commission
    permit. 2     And because T-Mobile could not construct the facility
    without first obtaining both permits, the lack of a commission
    permit      would   have   been   sufficient   to   preclude   T-Mobile   from
    building its Stephens Silo project.
    The      majority     opinion     dismisses    this   nuance    regarding
    Loudoun County’s permitting procedures as a mere “formality.”
    However, I must agree with the County that T-Mobile could not
    2
    The majority opinion and the district court find it
    significant that the Board overturned the Planning Commission’s
    approval of the commission permit.          But this fact is
    unremarkable for two reasons. First, the Zoning Ordinance makes
    clear that the Board has the authority to overturn decisions of
    the Planning Commission. Loudoun Cnty., Va. Zoning Ordinance §
    6-1104.    Second, T-Mobile had justified its decision not to
    locate its facilities on nearby silos on the bases that the
    nearby property was in foreclosure and that efforts to negotiate
    with the owner were “to no avail.”    J.A. 1511.   But the Board
    knew that the property had emerged from foreclosure, and T-
    Mobile had made no attempt to negotiate with the new owners.
    Thus, T-Mobile failed to demonstrate to the Board’s satisfaction
    that it used its best efforts to comply with the Comprehensive
    Plan’s rural location policies.
    43
    construct its facility without the commission permit and that
    the   denial    of   the    special   exception     was      thus    “superfluous.”
    Appellant’s Br.at 37.          And neither the district court nor the
    majority   opinion     has    explained     how    it   is    that    the   improper
    “superfluous” denial tainted or in any way impacted the proper
    and supported commission permit denial.
    In sum, I agree with the majority opinion regarding the
    Board’s denial of the special exception.                  That denial—based on
    concerns       about       radio   frequency        emissions,         which    the
    Telecommunications Act unequivocally places beyond consideration
    by local governments—was improper.                However, I fail to see how
    that invalid denial necessarily taints the proper denial of the
    separate, distinct, and additionally required commission permit—
    especially when the district court held that the County’s denial
    of the commission permit was supported by substantial evidence. 3
    Therefore, I must respectfully dissent from that part of
    the majority opinion that affirms the district court’s order
    3
    The majority opinion and the district court express
    concerns regarding the effectiveness of remanding this matter to
    the Board.    However, such concerns are present whenever the
    Court orders relief, and nothing suggests that Loudoun County
    would flout an order of this Court.    Assuming otherwise at the
    expense of local procedures places us in the position of
    substituting our judgment for that of the local planning agency
    and “sitting as a zoning board of appeals[.]”        Pomponio v.
    Fauquier Cnty. Bd. of Supervisors, 
    21 F.3d 1319
    , 1327 (4th Cir.
    1994) (en banc) (overruled on other grounds by Quackenbush v.
    Allstate Ins. Co., 
    517 U.S. 706
     (1996)). The job of making land
    use decisions is not ours; it belongs solely to local officials.
    44
    forcing Loudoun County to grant T-Mobile a commission permit for
    the   Stephens   Silo   site.   And    because   Part   IV.C.2   does   not
    constitute the opinion of this court, I also decline to join the
    portion of Part IV.C.1 that discusses the “effective absence of
    coverage” aspect of a telecommunications provider’s burden.
    45