Great American Insurance Company v. Hinkle Contracting Corporation ( 2012 )


Menu:
  •                             UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 12-1014
    GREAT AMERICAN INSURANCE COMPANY,
    Plaintiff - Appellee,
    v.
    HINKLE   CONTRACTING  CORPORATION,      now   known     as   Hinkle
    Contracting Company, LLC,
    Defendant - Appellant.
    Appeal from the United States District Court for the Southern
    District of West Virginia, at Charleston.  Joseph R. Goodwin,
    Chief District Judge. (2:11-cv-00396)
    Argued:   October 4, 2012                 Decided:    November 28, 2012
    Before KING, KEENAN, and THACKER, Circuit Judges.
    Vacated and remanded by unpublished opinion. Judge Keenan wrote
    the opinion, in which Judge King and Judge Thacker joined.
    ARGUED: Buckner Hinkle, Jr., STITES & HARBISON, PLLC, Lexington,
    Kentucky, for Appellant.    Timothy Dale Martin, WARD, HOCKER &
    THORNTON, Louisville, Kentucky, for Appellee.   ON BRIEF: Steven
    M. Henderson, STITES & HARBISON, PLLC, Louisville, Kentucky;
    Stephen Lee Thompson, BARTH-THOMPSON, Charleston, West Virginia,
    for Appellant.    Harold F. Salsbery, FROST BROWN TODD, LLC,
    Charleston, West Virginia, for Appellee.
    Unpublished opinions are not binding precedent in this circuit.
    BARBARA MILANO KEENAN, Circuit Judge:
    This appeal concerns the scope of an arbitration clause
    contained in a written agreement between a general contractor
    and   subcontractor         (the       subcontract),         which    was     incorporated
    without      limitation     in     a    performance        bond    issued    by    a    surety
    guaranteeing         the    subcontractor’s               obligations.         After       the
    subcontractor         defaulted,          the        surety        filed    the        present
    declaratory         judgment     action        against       the    general       contractor
    seeking to avoid the surety’s obligations under the performance
    bond.        The general contractor responded by seeking a dismissal
    or    stay     of     the     declaratory           judgment       proceedings         pending
    arbitration of the parties’ dispute.
    The district court determined that the surety’s claims were
    not arbitrable, holding that the parties intended to exclude
    claims brought by the surety under the terms of the performance
    bond.         The    district          court    therefore          denied    the       general
    contractor’s motion for stay or dismissal of the proceedings
    pending arbitration.             We reverse the district court’s decision
    based   on     the    broad      scope    of        the   arbitration       clause,     which
    manifested the parties’ intent that all claims “arising from or
    relating to” the subcontract be subject to arbitration.
    2
    I.
    In     November          2009,       the       West     Virginia       Department        of
    Transportation (WVDOT) hired Hinkle Contracting Corporation, LLC
    (Hinkle) as the general contractor for construction of a portion
    of a highway in Mingo County.                   Hinkle entered into a subcontract
    with Chapman-Martin Excavation and Grading, Inc. (CME or the
    subcontractor) to perform the grading and drain work for the
    highway project.
    As     required      by       the    subcontract,            CME     obtained    both    a
    performance bond and a payment bond.                          Great American Insurance
    Company    (Great      American          or   the     surety)      issued     those    bonds,
    naming CME as principal and Hinkle as obligee.                              The performance
    bond, the only bond at issue in the present case, stated that
    Hinkle and CME had entered into the subcontract, and that the
    “subcontract      is      by       reference         made     a    part    hereof.”          The
    performance      bond     also       stated      that       if    CME   defaulted     on     its
    obligations under the subcontract, Great American was required
    to remedy CME’s default either by providing for completion of
    CME’s     work   or      by    compensating           Hinkle       financially       for     the
    reasonable       costs        of    completing         that       work.       Finally,       the
    performance bond stated that “[a]ny suit under this bond must be
    instituted” within two years from the due date of the final
    payment under the subcontract.
    3
    After obtaining the required bonds, CME began its work on
    the highway project.            In September 2010, Hinkle notified CME
    that it was in default for failing to complete certain work.
    Hinkle and CME entered into negotiations to cure the default and
    ultimately executed a “change order” to the subcontract, which
    modified     CME’s     contractual           obligations.        The     change       order
    established new deadlines for the completion of various phases
    of   CME’s     work,    and    included           provisions     for     an     award   of
    liquidated damages to Hinkle in the event that CME defaulted on
    its obligations under the change order.
    Several months later, Hinkle again declared CME in default,
    citing CME’s failure to complete its work as required by the
    subcontract      and   the     change        order.      In     March    2011,       Hinkle
    notified Great American that CME was in default and demanded
    payment from Great American under the terms of the performance
    bond.
    Great     American      filed       a   complaint     in   the     district      court
    against      Hinkle    seeking       a       declaratory      judgment        that   Great
    American was not liable under the performance bond, primarily
    because    the    change      order      materially      altered       “the     financial
    obligations under the [s]ubcontract in the event of default by
    CME.”     Great American alleged that the terms in the change order
    were not “within the reasonable contemplation of Great American”
    when it issued the performance bond.
    4
    In     an    amended       complaint,        Great    American        raised    an
    additional claim.           In that claim, Great American alleged that
    Hinkle breached the terms of its contract with WVDOT, which was
    incorporated into the subcontract, by failing to pay CME for
    work     performed        under      the    subcontract.             Great     American
    accordingly        sought    an    order   requiring        Hinkle    to    provide    an
    accounting of payments received from WVDOT and to deposit with
    the district court funds owed to CME.
    Hinkle filed a motion to dismiss or stay the proceedings
    pending arbitration, pursuant to Hinkle’s notice and demand for
    arbitration issued in July 2011.                   Hinkle asserted that because
    the     performance       bond     incorporated       the     subcontract       in    its
    entirety, including the provisions granting Hinkle an exclusive
    right    to    demand     arbitration,        Great    American      was    obliged    to
    submit its claims to arbitration.
    The language at issue in the subcontract is contained in
    Section 16, which is entitled “Dispute Resolution.”                        Included in
    this    section      is     a     provision       stating    that    “[a]ll     claims,
    disputes,      controversies        and    matters     in   question       (hereinafter
    ‘Claims’) arising out of, or relating to, this [subcontract] or
    the breach thereof . . . shall be resolved by mediation followed
    by arbitration or litigation at [Hinkle’s] sole option.”
    The district court denied Hinkle’s motion to dismiss or
    stay the proceedings pending arbitration.                     The court concluded
    5
    that although the arbitration clause states that it applies to
    all claims arising out of or relating to the subcontract, other
    language in the subcontract demonstrates the parties’ intent to
    limit   the   scope   of   arbitrable       disputes.      In   support   of   its
    conclusion, the court relied on Section 16.2(e), which details
    dispute   resolution       procedures.         That     provision   states,     in
    relevant part:
    If   a   disputed    Claim   remains   unresolved    after
    negotiation and mediation, [Hinkle] shall have the
    exclusive option either to have the dispute decided by
    a court or by arbitration . . . . [Hinkle],
    Subcontractor and Subcontractor’s surety agree that
    the   disputed   Claim    shall   be  resolved    in   the
    appropriate forum selected by [Hinkle] at its sole
    discretion.    If Subcontractor or its surety first
    commences a court action with respect to a dispute
    which [Hinkle] desires to have determined by an
    arbitration proceeding, or if Subcontractor or its
    surety first commences an arbitration proceeding which
    [Hinkle] desires to have determined by a court,
    [Hinkle] shall commence the arbitration proceeding or
    court action . . . within thirty (30) calendar days
    after receiving service of Subcontractor’s complaint
    or arbitration demand. If, at any time . . . [Hinkle]
    becomes involved in litigation or arbitration with
    another party or parties involving questions of fact
    or law common to the dispute between [Hinkle] and
    Subcontractor     to    the    extent    that   (a)     in
    Subcontractor’s absence, complete relief cannot be
    accorded   among    those   already   parties,    or   (b)
    disposition of such other action may as a practical
    matter, impair or impede [Hinkle’s] or Subcontractor’s
    ability to fully prevent its incurring multiple or
    otherwise inconsistent obligations, then Subcontractor
    and its surety may be joined by [Hinkle] in such other
    litigation or arbitration proceedings for complete
    resolution of all disputes and controversies arising
    under this [subcontract] and that upon such joinder,
    any pending action between [Hinkle] and Subcontractor
    shall be dismissed. (Emphasis added.)
    6
    The    court       also   cited       Section       16.2(f),       which      addresses       the
    procedure for appointing arbitrators and states, “Subcontractor
    and [Hinkle] shall each appoint one member of the [arbitration]
    panel,”      and    those      two    members       together      will    appoint       a   third
    member of the arbitration panel.                    (Emphasis added.)
    The    district      court      observed          that    the    language    in      these
    provisions         included     references          to    the    subcontractor        and     the
    surety in some instances, but in other instances referenced only
    the subcontractor.              Based on these inconsistencies, the court
    determined that claims brought by Great American as surety are
    subject to arbitration only when they deal with the rights and
    obligations         of    the        subcontractor.             Concluding       that       Great
    American’s present claims are not related to CME’s obligations
    under the subcontract, but constitute “unique surety claims” or
    “surety defenses” arising from obligations under the performance
    bond, the court held that Great American’s present claims are
    not subject to arbitration.                 Hinkle timely filed in this Court
    an appeal challenging the denial of its motion to dismiss or to
    compel arbitration.
    II.
    Our standard of review in this case is well established.
    We    review       de   novo    the    district          court’s       holding   that       Great
    American’s      claims      are      not   arbitrable           under   the   terms      of   the
    7
    subcontract incorporated in the performance bond.                        See Peabody
    Holding Co., LLC v. United Mine Workers of Am., Int’l. Union,
    
    665 F.3d 96
    , 101 (4th Cir. 2011).
    Hinkle      argues     that       because    the        dispute        resolution
    provisions      of    Section      16    (the    arbitration      clause)        broadly
    encompassed     all       claims   “arising      under    or    relating       to”     the
    subcontract, the district court erred in concluding that this
    language was limited by other terms of that clause.                            According
    to Hinkle, the district court should have examined the scope of
    the arbitration clause under the “significant relationship” test
    used by this Court in American Recovery Corp. v. Computerized
    Thermal Imaging, Inc., 
    96 F.3d 88
    , 93 (4th Cir. 1996).                              Hinkle
    contends that Great American’s claims are subject to arbitration
    under    this      test    because       those   claims    bear     a     significant
    relationship         to     the     subcontract,         irrespective          of      the
    “suretyship” label that Great American seeks to attach to them.
    In response, Great American argues that it did not agree to
    arbitrate disputes concerning the terms of the performance bond
    simply by incorporating the subcontract into the bond.                               Great
    American asserts that its defenses originate solely under the
    performance bond and, thus, constitute “unique” surety defenses
    that are not subject to arbitration.               As further support for its
    argument, Great American maintains that the word “[c]laims” is
    used    in   the     subcontract        solely   with    reference       to    disputes
    8
    between    CME    and      Hinkle,      or    disputes        between     CME    and     WVDOT.
    Thus, according to Great American, only claims involving those
    entities    are    subject        to    arbitration           under   the    terms      of   the
    subcontract.       Finally, Great American contends that because the
    arbitration       clause      allows         only       CME    and    Hinkle     to      choose
    arbitrators and only describes disputes arising between them,
    the parties did not manifest an intent that Great American be
    subject to arbitration of its performance bond obligations.                                  We
    disagree with Great American’s arguments.
    A.
    We    begin      by    reviewing        the    principles        guiding      a    court’s
    determination whether a particular dispute is arbitrable.                                 Under
    the Federal Arbitration Act (the FAA), 
    9 U.S.C. §§ 1-16
    , a court
    is   required      to      stay    an    action         or    proceeding        pending      the
    arbitration      of     claims     covered         by   the    terms    of   the       parties’
    written agreement.           Adkins v. Labor Ready, Inc., 
    303 F.3d 496
    ,
    500 (4th Cir. 2002) (citing 
    9 U.S.C. § 3
    ).                            Because the FAA in
    essence guarantees the enforcement of a private contract, courts
    first must consider the contract’s terms in ascertaining the
    scope of an arbitration agreement contained therein.                                   E.E.O.C.
    v. Waffle House, Inc., 
    534 U.S. 279
    , 294 (2002).
    A     party      may     compel         arbitration          under      the       FAA    by
    demonstrating: (1) a dispute between the parties; (2) a written
    agreement containing an arbitration provision that could be read
    9
    as covering the dispute; (3) the relationship of the transaction
    to    interstate        or    foreign     commerce,          as     evidenced       by    the
    agreement;      and    (4)    the    failure,        neglect,       or    refusal    of   the
    defendant to submit the dispute to arbitration.                           See Adkins, 
    303 F.3d at 500-01
    .             The issue in the present case relates to the
    second        requirement,         raising         the      question        of      contract
    interpretation         as     to    whether        Great    American’s          claims    are
    arbitrable.      See Am. Recovery, 
    96 F.3d at 92
    .
    A party will not be required to arbitrate a dispute that
    the   party     has    not    agreed     to   submit       to     arbitration.        United
    Steelworkers of Am. v. Warrior & Gulf Navigation Co., 
    363 U.S. 574
    , 582 (1960).            However, under decisions interpreting the FAA,
    courts    must        resolve      any    doubts         concerning       the    scope     of
    arbitrable issues in favor of arbitration.                         Moses H. Cone Mem’l
    Hosp.    v.    Mercury       Constr.     Corp.,      
    460 U.S. 1
    ,    24-25     (1983);
    Wachovia Bank Nat’l Ass’n v. Schmidt, 
    445 F.3d 762
    , 767 (4th
    Cir. 2006) (citation omitted).
    An issue will be classified as being outside the scope of
    an arbitration provision only when the parties have manifested
    such an intent in their written agreement.                         Peabody, 665 F.3d at
    104 (citing First Options of Chi., Inc. v. Kaplan, 
    514 U.S. 938
    ,
    944-45 (1995)).          Because sophisticated parties negotiate their
    written contracts with an understanding of this policy favoring
    arbitration,      courts        require       this       degree     of    clarity     before
    10
    determining      that    a     particular       claim    is    not     subject      to    an
    arbitration provision.            
    Id.
     (citing First Options, 
    514 U.S. at 945
    ).     Thus, when the scope of an arbitration clause remains
    “open    to   question”      regarding      the    inclusion         of     a   particular
    issue,    a   court     must     declare    that      the     issue    is       subject   to
    arbitration.      Peoples Sec. Life Ins. Co. v. Monumental Life Ins.
    Co., 
    867 F.2d 809
    , 812 (4th Cir. 1989).
    B.
    Informed by these principles, we turn to consider whether
    the   district     court       properly    concluded        that      the       arbitration
    clause excluded Great American’s claims.                      In relevant part, the
    arbitration clause states that all claims “arising out of, or
    relating to the subcontract or breach thereof . . . shall be
    resolved by mediation followed by arbitration or litigation,” at
    Hinkle’s sole option.            Courts ordinarily construe such clauses,
    which contain the phrase “arising out of or relating to” or
    similar language, as having an “expansive reach.”                         Am. Recovery,
    
    96 F.3d at
    93 (citing Prima Paint Corp. v. Flood & Conklin Mfg.
    Co., 
    388 U.S. 395
    , 398 (1967)).
    In partial limitation of this broad language in Section 16,
    the   arbitration       clause    contains      one     express      exclusion,       which
    appears in Section 16.2(g) of the subcontract.                              This express
    exclusion     states     that     “[t]he    provisions         of    this       Section   16
    [addressing Dispute Resolution] do not preclude litigation for
    11
    injunctive relief.”             (J.A. 94.)       No other types of claims are
    expressly excluded from arbitration in the arbitration clause.
    The   district       court       nonetheless      determined      that   certain
    language     in    Section      16.2(e)     relating      to    dispute    resolution
    procedures,       including      three     references      to     the   subcontractor
    without accompanying references to the surety, demonstrated the
    parties’ intent to exclude from arbitration claims unique to the
    surety.     We disagree that the absence of such references to the
    surety    manifests    a     clear      intent   to     exclude    Great   American’s
    present claims from arbitration, particularly when the surety’s
    participation in arbitration proceedings is referenced numerous
    times throughout Section 16.2(e).                  See United Steelworkers of
    Am., 
    363 U.S. at 584-85
     (in the absence of an express provision
    excluding claims, “only the most forceful evidence” of an intent
    to exclude can prevail, particularly when the arbitration clause
    is broad).
    Most notably, the first part of Section 16.2(e) states that
    Hinkle, the subcontractor, and the surety “agree” that after
    attempting to negotiate a disputed claim, Hinkle “shall have the
    exclusive option either to have the dispute decided by a court
    or by arbitration.”             That section also anticipates that either
    the   subcontractor        or    its    surety    may    commence       litigation   or
    arbitration proceedings.
    12
    In addition, contrary to Great American’s contention, the
    subcontract      does    not   employ       the    term   “claims”      solely    with
    reference to disputes between CME and Hinkle, or those between
    CME and WVDOT.        The express language of Section 16 provides that
    the term “[c]laims” includes, with exceptions not relevant here,
    “[a]ll claims, disputes, controversies and matters in question.”
    And, as stated above, the arbitration clause provides that such
    claims “arising out of, or relating to, this [subcontract] or
    the breach thereof . . . shall be resolved by mediation followed
    by arbitration or litigation at Hinkle’s sole option.”
    When read in this context, the references relied on by the
    district court demonstrate, at best, an uncertainty concerning
    the scope of arbitrable claims asserted by the surety.                           Under
    federal   policy,       this   type    of    ambiguity    generally      triggers    a
    presumption that such claims are subject to arbitration under
    the parties’ agreement.          See Moses H. Cone Mem’l Hosp., 
    460 U.S. at 24-25
    .        Thus, we turn to consider whether Great American’s
    claims    against     Hinkle    fall    within      the    broad   scope     of   the
    arbitration clause, as claims “aris[ing] under or relat[ing] to”
    the subcontract.
    Great    American     asserts      that      its   claims   bear    a   general,
    rather    than    a   significant,      relationship       to    the    subcontract,
    because those claims are “surety defenses” arising under the
    13
    bond.      We disagree with this attempt to shield the claims from
    the broad reach of the arbitration clause.
    In    American      Recovery,    we    explained      that   in   contrast     to
    narrow arbitration clauses, which only encompass claims “arising
    under” a contract, broad arbitration clauses like the present
    one     embrace    “every     dispute       between     the   parties      having     a
    significant       relationship”    to   the      contract,    regardless     of     the
    label that a party chooses to assign to a particular claim.                         
    96 F.3d at
    93 (citing J.J. Ryan & Sons v. Rhone Poulenc Textile,
    S.A., 
    863 F.2d 315
    , 321 (4th Cir. 1988)); see also Wachovia, 
    445 F.3d at 767
    ; Long v. Silver, 
    248 F.3d 309
    , 316-17 (4th Cir.
    2001).      In determining whether such a significant relationship
    exists, a court must review the factual allegations underlying
    the particular claim and evaluate the connection between those
    allegations and the contract containing the arbitration clause.
    Am. Recovery, 
    96 F.3d at 93
    .
    Great    American      alleged    in       its   primary     claim   that     its
    obligations       under    the   performance       bond   were     void,   based     on
    Hinkle’s material alteration of the subcontract by effecting the
    change order.       In support of this claim of material alteration,
    Great American asserted that: (1) the change order included a
    liquidated        damages     provision,         contrary     to     the    original
    provisions of the subcontract prohibiting such damages; and (2)
    the change order included new deadlines for CME’s completion of
    14
    work that were not contained in the original subcontract.                      We
    conclude that the allegations contained in this claim bear a
    significant relationship to the subcontract, because they are
    premised on the differences between the terms of the subcontract
    and the terms of the change order.
    Great American also alleged in its amended complaint that
    Hinkle    breached    the   terms    of    the   subcontract,       which   fully
    incorporated Hinkle’s contract with WVDOT, when Hinkle failed to
    pay CME for completed work upon Hinkle’s receipt of payment for
    that work from WVDOT.         Because this claim on its face requires
    an   examination     of   Hinkle’s   obligations     under    the    subcontract
    regarding payment to CME, we conclude that this claim also bears
    a significant relationship to the subcontract.                Accordingly, we
    conclude   that    Great    American’s     present   claims    against      Hinkle
    bear a significant relationship to the subcontract, regardless
    of the particular label that Great American assigns to them.
    See Am. Recovery, 
    96 F.3d at
    93 (citing J.J. Ryan & Sons, 863
    F.3d at 321).        Given this significant relationship between the
    claims asserted and the subcontract, we hold that those claims
    fall within the scope of the arbitration clause. *
    *
    We are not persuaded by Great American’s argument that                 the
    performance bond incorporated the subcontract only for                        the
    purpose of defining Great American’s secondary obligations,                   and
    did not bind Great American to the arbitration clause.                        The
    incorporation of the subcontract into the performance bond                    was
    (Continued)
    15
    III.
    For these reasons, we hold that the district court erred in
    denying    Hinkle’s   motion     seeking    dismissal      or    stay   of   the
    proceedings    pending   arbitration.         We   therefore       vacate     the
    district   court’s    judgment    and     remand   the    case    for   further
    proceedings   consistent   with    the     principles     expressed     in   this
    opinion.
    VACATED AND REMANDED
    not qualified or limited in any manner, and the performance bond
    lacks any language reflecting an intent by the parties to
    resolve disputes in a manner inconsistent with the terms of the
    subcontract.   Additionally, Great American’s reliance on AgGrow
    Oils, LLC v. National Fire Ins. Co. of Pittsburgh, PA, 
    242 F.3d 777
     (8th Cir. 2001), is unpersuasive, based on the dissimilar
    language in the performance bond in that case regarding
    litigation of disputes.
    16