Siegfried Construct v. Gulf Insurance Co ( 2000 )


Menu:
  • UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    SIEGFRIED CONSTRUCTION,
    INCORPORATED,
    Plaintiff-Appellant,
    v.
    GULF INSURANCE COMPANY,
    Defendant-Appellee,
    and
    No. 98-2808
    JENNIFER BUILDERS, INCORPORATED, t/a
    Jennifer Drywall, Incorporated,
    Defendant.
    ASSOCIATED BUILDERS AND
    CONTRACTORS OF VIRGINIA,
    INCORPORATED; THE SURETY
    ASSOCIATION OF AMERICA; AMERICAN
    INSURANCE ASSOCIATION,
    Amici Curiae.
    Appeal from the United States District Court
    for the Eastern District of Virginia, at Alexandria.
    Albert V. Bryan, Jr., Senior District Judge.
    (CA-98-555-A)
    Argued: October 28, 1999
    Decided: February 2, 2000
    Before WIDENER, WILKINS, and TRAXLER, Circuit Judges.
    _________________________________________________________________
    Reversed and remanded by unpublished per curiam opinion.
    _________________________________________________________________
    COUNSEL
    ARGUED: Mark Peyser Friedlander, Jr., FRIEDLANDER &
    FRIEDLANDER, P.C., McLean, Virginia, for Appellant. Erica
    Swecker Beardsley, WATT, TIEDER, HOFFAR & FITZGERALD,
    L.L.P., McLean, Virginia, for Appellee. ON BRIEF: Maurice
    Baskin, David C. Mancini, Charles W. Durant, VENABLE, BAET-
    JER & HOWARD, L.L.P., McLean, Virginia, for Amicus Curiae
    Associated Builders. Martha L. Perkins, AMERICAN INSURANCE
    ASSOCIATION, Washington, D.C.; Edward G. Gallagher, WICK-
    WIRE GAVIN, P.C., Vienna, Virginia, for Amicus Curiae Surety
    Association.
    _________________________________________________________________
    Unpublished opinions are not binding precedent in this circuit. See
    Local Rule 36(c).
    _________________________________________________________________
    OPINION
    PER CURIAM:
    Siegfried Construction, Inc. ("Siegfried" or"SC") appeals from the
    district court's grant of judgment as a matter of law for Gulf Insur-
    ance Company ("Gulf"), the surety on behalf of Siegfried's subcon-
    tractor, Jennifer Builders, Inc. ("Jennifer"). The district court
    concluded that (1) Siegfried did not declare Jennifer to be in default,
    and (2) Siegfried did not provide Gulf with reasonable notice that
    Siegfried was arranging for the correction and completion of Jenni-
    fer's work. Based upon these findings, the district court determined
    as a matter of law that Siegfried had not met the requirements of the
    performance bond. We reverse and remand.
    I.
    Siegfried was the general contractor for the construction of a Sleep
    Inn Hotel in Rockville, Maryland. In this capacity, Siegfried hired
    numerous subcontractors to perform portions of the work. Siegfried
    2
    engaged Jennifer to install dry wall and door frames, hang valances,
    and complete some trim and finishing work. The subcontract required
    Jennifer to obtain a performance bond, which Gulf issued shortly after
    Jennifer began work on the hotel.1
    _________________________________________________________________
    1 The performance bond, which incorporated the subcontract by refer-
    ence, in pertinent part provides:
    NOW, THEREFORE, THE CONDITION OF THIS OBLI-
    GATION is such that, if Principal shall promptly and faithfully
    perform said subcontract, then this obligation shall be null and
    void; otherwise to remain in full force and effect.
    Whenever Principal shall be, and be declared by Obligee to be
    in default under the subcontract, the Obligee having performed
    Obligee's obligations thereunder:
    1. Surety may promptly remedy the default subject to the
    provisions of paragraph 3 herein, or;
    2. Obligee, after reasonable notice to Surety may, or Surety
    upon demand of Obligee may, arrange for the perfor-
    mance of Principals' obligation under the subcontract sub-
    ject to the provisions of paragraph 3 herein;
    3. The balance of the subcontract price, as defined below,
    shall be credited against the reasonable cost of completing
    performance of the subcontract. If completed by the Obli-
    gee, and the reasonable cost exceeds the balance of the
    subcontract price, the Surety shall pay to the Obligee such
    excess, but in no event shall the aggregate liability of the
    Surety exceed the amount of this bond. If the Surety
    arranges completion or remedies the default, that portion
    of the balance of the subcontract price as may be required
    to complete the subcontract or remedy the default and to
    reimburse the Surety for its outlays shall be paid to the
    Surety at the times and in the manner as said sums would
    have been payable to Principal had there been no default
    under the subcontract. The term "balance of subcontract
    price," as used in this paragraph, shall mean the total
    amount payable by Obligee to Principal under the subcon-
    tract and amendments thereto, less the amounts heretofore
    properly paid by Obligee under the subcontract.
    J.A. 17.
    3
    The Sleep Inn construction, however, did not proceed smoothly.
    The hotel was originally scheduled to be completed by August 9,
    1997, but was not finished until September 19, 1997. In many cases
    the delays were caused by various subcontractors, including Jennifer.
    During the course of the construction, Siegfried repeatedly com-
    plained to Jennifer about the quality of work and the laborers pro-
    vided. Specifically, Siegfried remonstrated that the metal door frames
    installed by Jennifer were crooked, dry wall was hung in the wrong
    sequences causing delays, piece workers hanging drywall had no des-
    ignated foreman, only four to eight dry wall workers were on the job
    when more were needed to remain on schedule, dry wall was improp-
    erly fitted around electrical and plumbing boxes, and in many areas
    dry wall was improperly placed so that it bulged.
    On July 14, 1997, Siegfried sent Jennifer a "Formal Notice of Ter-
    mination for Failure to Perform." J.A. 183. The letter, in accordance
    with the subcontract,2 gave Jennifer "three (3) days formal notifica-
    tion of [Siegfried's] intention to terminate your subcontract agreement
    _________________________________________________________________
    2 Article X of the subcontract provided that:
    If, in the opinion of SC, Subcontractor shall at any time (1)
    refuse or fail to provide sufficient properly skilled workmen or
    materials of the proper quality, (2) fail in any respect to prose-
    cute the work according to the current schedule, (3) cause, by
    any action or omission, the stoppage or delay of or interference
    with the work of SC or of any other builder or subcontractor, . . .
    or (8) by any other action, indicate an unwillingness or inability
    to perform, or continue performing, hereunder then, after serving
    three days' written notice, unless the condition(s) specified in
    such notice shall have been eliminated within such three days,
    SC may, at its option (i) without voiding the other provisions of
    this Subcontract and without notice to Subcontractor's sureties,
    if any, take such steps as are necessary in SC's reasonable dis-
    cretion, to overcome the condition(s), in which case the Subcon-
    tractor shall be liable to SC for the full cost thereof, (ii) terminate
    the Subcontract for default, or (iii) seek specific performance of
    Subcontractor's obligations hereunder, it being agreed by Sub-
    contractor that specific performance may be necessary to avoid
    irreparable harm to SC and/or Owner. . . .
    J.A. 170.
    4
    for default, unless acceptable corrections are effected by July 17,
    1997." J.A. 183. The letter then set forth a number of grievances
    regarding Jennifer's workers and demanded that Jennifer take correc-
    tive action. On July 15, Siegfried sent a corrected termination letter
    to Jennifer further detailing problems with Jennifer's work and
    demanding prompt correction. Jennifer responded by making some
    changes, but Siegfried soon found that the original problems reoccur-
    red.
    On July 22, Siegfried sent a "Second Notice of Termination for
    Failure to Perform." J.A. 188. The second notice informed Jennifer
    that "Siegfried Construction intends, at its discretion, to terminate
    your subcontract agreement or to supplement your work forces in
    order to complete your work and the project on time." J.A. 188. The
    letter stated that Jennifer had failed to remedy the problems outlined
    in previous letters and set forth a schedule for the completion of Jen-
    nifer's work.
    On July 26, Siegfried sent a "Follow-up to Second Notice of Ter-
    mination for Failure to Perform." J.A. 190. Siegfried averred that
    "progress has not been maintained on certain key work activities and
    necessitates that [Siegfried] supplement your manpower with person-
    nel capable of performing with acceptable quality of workmanship."
    J.A. 190. The supplementation was in accordance with Article X of
    the subcontract agreement. The letter contained a revised schedule for
    the completion of Jennifer's work and provided that Siegfried would
    notify Gulf of the problems unless Jennifer could show marked
    improvement.
    Not satisfied with Jennifer's progress, Siegfried sent Gulf a "Notice
    of Claim" on July 28 in which Siegfried announced that it would "al-
    most certainly submit a claim for reimbursement of costs associated
    with completing and correcting work performed by Jennifer." J.A.
    197. By this communication, Siegfried also informed Gulf of the sup-
    plementation of Jennifer's workforce and Siegfried enclosed copies of
    the letters sent to Jennifer which threatened termination.
    Gulf forwarded Siegfried's communication to COP, Inc. ("COP"),
    Gulf's investigator. On August 5, COP informed Siegfried that it had
    been retained "to investigate claims against[Jennifer's] bond." J.A.
    5
    198. COP acknowledged receipt of the letters Siegfried had sent to
    Jennifer and promised to contact Siegfried at the end of the investiga-
    tion.
    Shortly thereafter, Siegfried discussed the claim with COP in a
    telephone conversation. Siegfried presented evidence that it told COP
    that it "needed some help" either from Gulf or Jennifer to complete
    the work on the hotel. J.A. 107. Siegfried did not hear from COP or
    Gulf while construction proceeded, and there is some dispute con-
    cerning Jennifer's abandonment of the job. However, all parties agree
    that Siegfried never terminated Jennifer.
    In January 1998, Siegfried submitted a claim on Jennifer's bond
    which Gulf refused to pay. Siegfried then brought suit in Virginia
    state court against Jennifer for breach of contract and against Gulf on
    the bond. The defendants removed the case to federal court, where a
    non-jury trial was held. At the conclusion of Siegfried's case, the
    court heard motions for judgment as a matter of law from Jennifer and
    Gulf. The court denied the former's motion, but granted the latter's.
    In ruling in Gulf's favor, the district court found that the July 28,
    1997 letter to Gulf was not a proper declaration of default nor reason-
    able notice that Siegfried was arranging for the performance of Jenni-
    fer's contractual obligation. The case proceeded no further because
    Siegfried and Jennifer then stipulated to the amount of damages and
    the court entered judgment for Siegfried against Jennifer. Siegfried
    now appeals the court's grant of Gulf's motion for judgment as a mat-
    ter of law.
    II.
    For a grant of judgment as a matter of law pursuant to Federal Rule
    of Civil Procedure 52(c), we review the district court's legal conclu-
    sions de novo, see Freeman v. Case Corp., 
    118 F.3d 1011
    , 1014 (4th
    Cir. 1997), cert. denied, 
    118 S. Ct. 739
     (1998), and its findings of fact
    for clear error, see Carter v. Ball, 
    33 F.3d 450
    , 457 (4th Cir. 1994).
    Judgment as a matter of law is appropriate when, without weighing
    the credibility of witnesses, there can be but one reasonable conclu-
    sion as to the correct judgment. See Anderson v. Liberty Lobby, Inc.,
    
    477 U.S. 242
    , 250 (1986). If, however, evidence viewed in a light
    most favorable to the nonmovant indicates that more than one conclu-
    6
    sion is plausible, judgment as a matter of law is improper. 
    Id.
     at 250-
    51. Because the appeal from the district court is before us in diversity,
    see 
    28 U.S.C.A. § 1332
     (West 1993 & Supp. 1998), we are bound by
    the substantive law of Virginia, see 
    28 U.S.C.A. § 1652
     (West 1994);
    Erie R.R. Co. v. Tompkins, 
    304 U.S. 64
    , 78 (1938), and the parties
    agree that Virginia law is controlling.
    A.
    Siegfried first challenges the district court's determination that
    Siegfried never declared Jennifer to be in default. A performance
    bond is simply a contract and thus we turn to Virginia's principles of
    contract interpretation to guide the resolution of this issue. The
    court's task is to enforce contracts as written, not to unilaterally alter
    the parties' obligations. See D.C. McClain, Inc. v. Arlington County,
    
    452 S.E.2d 659
    , 662 (Va. 1995). In Virginia, surety bonds are liber-
    ally construed, see Fidelity & Deposit Co. v. A.J. Bailey, 
    133 S.E. 797
    , 797 (Va. 1926), and "[s]ureties for hire" are required to "abide
    by their contracts and pay everything which by fair intendment can
    be charged against them." C.S. Luck & Sons, Inc. v. Boatwright, 
    162 S.E. 53
    , 54 (Va. 1932).
    Under the performance bond, Gulf is liable for Jennifer's breach of
    contract if two conditions occur: (1) Jennifer is in default, and (2)
    Siegfried declares Jennifer to be in default. Siegfried argues that it
    declared Jennifer in default by virtue of the four notices of termina-
    tion and the July 28, 1997 notice of claim sent to Gulf.
    1.
    To determine whether there was a proper declaration of default, we
    must first define a "default," a term that neither the bond nor the sub-
    contract specifically explicate. In general, a default is defined as "the
    omission or failure to perform a legal or contractual duty." Black's
    Law Dictionary 417 (6th ed. 1990). According to the Virginia
    Supreme Court, a "building contractor defaults in the performance of
    his contract if he furnishes defective materials or workmanship."
    Clevert v. Jeff W. Soden, Inc., 
    400 S.E.2d 181
    , 183 (Va. 1991). Stated
    another way, "a builder's breach in the performance of his contract,
    i.e., a defective performance, also would be a ``default' in that con-
    7
    tract." 
    Id.
     The subcontract before us, though not specifically defining
    default, describes a "failure to perform" as follows: failure to provide
    skilled workers and quality materials; failure to complete work on
    time, causing delays for Siegfried or other subcontractors; or any
    other action indicating an inability or unwillingness to perform.
    "When contract terms are clear and unambiguous, the words used by
    the parties must be given their plain and ordinary meanings."
    Gordonsville Energy v. Virginia Elec. & Power Co. , 
    512 S.E.2d 811
    ,
    817 (Va. 1999).
    Siegfried's uncontradicted evidence indicates that the workers Jen-
    nifer provided were too few and without adequate supervision, that
    workmanship was substandard, and that Jennifer's deficiencies were
    causing delays in construction. Viewing this series of failings in a
    light most favorable to Siegfried, Jennifer's failure to perform was
    defective, material, and "defeat[ed] an essential purpose of the con-
    tract." Horton v. Horton, 
    487 S.E.2d 200
    , 204 (Va. 1997); see also
    RW Power Partners v. Virginia Elec. & Power Co., 
    899 F. Supp. 1490
    , 1496 (E.D. Va. 1995) (stating that under Virginia law a mate-
    rial breach deprives the party of an expected benefit and "goes to the
    root of the contract") (internal quotation marks omitted). As the provi-
    sions of the subcontract and the performance bond must be read
    together, see New Amsterdam Cas. Co. v. Moretrench Corp., 
    35 S.E.2d 74
    , 77 (Va. 1945), we conclude that the evidence presented
    during Siegfried's case in chief demonstrates that Jennifer was in
    default.
    2.
    Turning next to the second condition of the bond, the declaration
    of default, the district judge concluded as a matter of law that Sieg-
    fried never declared Jennifer to be in default. We disagree.
    We are aware that the evidence in this case is not complete; and
    in passing on a challenge to a judgment as a matter of law, we must
    view the evidence in a light most favorable to Siegfried. In so doing,
    we find that Siegfried's evidence was sufficient to establish that it
    declared Jennifer in default. In communications to Jennifer and Gulf,
    Siegfried outlined the problems with Jennifer's laborers, their work,
    and the resulting delays. Siegfried repeatedly threatened Jennifer with
    8
    formal termination for default if changes were not implemented.3
    These communications could reasonably be interpreted as pronounce-
    ments that Jennifer was not fulfilling its fundamental contractual obli-
    gations and that a claim for payment under the bond would be
    forthcoming. Thus, Siegfried presented sufficient evidence that it
    complied with the bond's condition that Jennifer be declared in
    default.
    In support of the district court's ruling, Gulf avers that Siegfried's
    statement that it would "almost certainly submit a claim for reim-
    bursement" was equivocal and cannot be interpreted as a declaration
    of default. J.A. 197. However, under the bond, Siegfried could collect
    from Gulf only if the reasonable cost of completion exceeded the bal-
    ance of the subcontract. Thus, Siegfried could not have known the
    amount of its claim, if any, until it completed the work originally
    assigned to Jennifer. Under the terms of the bond, Siegfried could not
    have made a more definite statement regarding the specific amount of
    the likely claim.
    Gulf further argues that Siegfried had to actually terminate Jennifer
    to declare default. Though other courts have required obligees to ter-
    minate a subcontractor to invoke a surety's obligations, see L & A
    Contracting Co. v. Southern Concrete Servs., Inc., 
    17 F.3d 106
    , 111
    (5th Cir. 1994); Balfour Beatty Constr., Inc. v. Colonial Ornamental
    Iron Works, Inc., 
    986 F. Supp. 82
    , 85-86 (D. Conn. 1997), Virginia
    law does not counsel this result. Had the parties intended that Sieg-
    fried actually terminate Jennifer before making a claim on the bond,
    "such a provision would surely, in clear language, have been inserted
    in the bond." Phoenix Ins. Co. v. Lester Bros., Inc., 
    127 S.E.2d 432
    ,
    436 (Va. 1962). Were the court to read such a requirement into the
    bond, we would be drafting rather than enforcing the bond as written.
    See D.C. McClain, Inc., 452 S.E.2d at 662 (stating that courts must
    enforce contracts as written).
    Moreover, equating termination with default could effect a major
    change in the construction industry in Virginia. When the general
    _________________________________________________________________
    3 Though Siegfried did not initially copy Gulf on the four notices of ter-
    mination sent to Jennifer, Gulf did receive these letters when Siegfried
    submitted the July 28, 1997 notice of claim to Gulf.
    9
    contractor notices deficiencies in a subcontractor's work, generally all
    parties benefit if the subcontractor remains on the job. This common
    practice keeps the subcontractor working and permits the correction
    of problems and mistakes. The actual termination of a subcontractor
    is disruptive to the entire construction process because it adds to
    delays and expenses as new subcontractors must be found and
    retained, often at higher rates because of the premium paid for avail-
    ability.
    Similarly, Gulf contends that its involvement in the construction of
    the Sleep Inn -- absent Jennifer's termination-- could have resulted
    in Jennifer bringing a suit for tortious interference with contractual
    relations.4 We find this to be an unlikely result. Considering that Sieg-
    fried arranged for the correction and completion of Jennifer's work,
    it is unclear how Gulf would have been faced with a suit for tortious
    interference had it simply paid the claim. Likewise, Gulf's exercise
    of other options under the bond, such as arranging for the completion
    of Jennifer's work, could not have been the cause of a breach of the
    subcontract or Jennifer's termination. Jennifer's failure to perform
    prior to the declaration of default would be considered the cause of
    a breach or termination. Even assuming Gulf's fear has some merit,
    the danger arises from the wording of Gulf's own bond. If Gulf
    believes termination is necessary to avoid a tortious interference suit,
    the better course would be to add this requirement to its performance
    bond. As the bond currently reads, the obligee is simply required to
    declare default, not terminate the principal.
    Furthermore, Gulf's assertion that termination was a necessary
    component of a declaration of default is inconsistent with Gulf's con-
    duct. In response to Siegfried's notice of claim, Gulf's investigator
    promised to contact Siegfried after it reviewed the claim. If termina-
    _________________________________________________________________
    4 The elements of tortious interference with contractual relations are as
    follows: "``(1) the existence of a valid contractual relationship or business
    expectancy; (2) knowledge of the relationship or expectancy on the part
    of the interferor; (3) intentional interference inducing or causing a breach
    or termination of the relationship or expectancy; and (4) resultant dam-
    age to the party whose relationship or expectancy has been disrupted.'"
    Century-21 v. Elder, 
    391 S.E.2d 296
    , 298-99 (Va. 1990) (quoting Chaves
    v. Johnson, 
    335 S.E.2d 97
    , 102 (Va. 1985)).
    10
    tion of Jennifer was the determining factor triggering Gulf's responsi-
    bilities under the bond, then Siegfried could reasonably have expected
    Gulf to say so immediately. Instead, Gulf's hiring of COP to investi-
    gate the matter and COP's initial response could easily have con-
    vinced Siegfried that payment or assistance would be forthcoming. In
    fact, Siegfried told COP that Siegfried needed help from Gulf or Jen-
    nifer to complete the work. In the face of this pronouncement, COP,
    Gulf's representative, voiced no impediment to Gulf's involvement.
    In sum, we conclude that Siegfried presented adequate evidence to
    find that it declared Jennifer in default. In so holding, we reject Gulf's
    argument that termination must precede a declaration of default.
    B.
    Siegfried next challenges the district court's conclusion that Gulf
    was denied its options under the bond because Siegfried neglected to
    provide reasonable notice that it was arranging for the correction and
    completion of Jennifer's work. Once Siegfried declared Jennifer in
    default, there were three options under the performance bond: (1)
    Gulf could remedy the default, (2) Gulf, upon Siegfried's demand,
    could arrange for the performance of Jennifer's obligation, or (3)
    Siegfried, after reasonable notice, could arrange for the performance
    of Jennifer's obligation. Though not defined in the bond, reasonable
    notice is generally described as notice conveying the requisite infor-
    mation and permitting time for response. Cf. Mullane v. Central Han-
    over Bank & Trust Co., 
    339 U.S. 306
    , 314 (1950) (defining
    reasonable notice in the context of due process). Siegfried contends
    that its July 28, 1997 letter to Gulf and accompanying documents con-
    stituted reasonable notice that it was arranging for the performance of
    Jennifer's contractual duties. The first paragraph of the letter
    informed Gulf that Siegfried planned to submit a claim for payment
    under the bond. The second paragraph informed Gulf that Jennifer's
    "failure to perform has necessitated that the Obligee supplement the
    Principal's work resources to correct unacceptable work and to assist
    in completing the Principal's work so as to mitigate delays." J.A. 197.
    On August 5, 1997, Siegfried received a letter from COP, Gulf's
    investigator, acknowledging receipt of the notice of claim, and prom-
    ising to investigate all claims against Jennifer's bond. Apparently,
    Siegfried then telephoned COP and explained that it needed help to
    11
    complete Jennifer's work on the Sleep Inn. Siegfried had no further
    communications with COP, and Gulf did not object to Siegfried
    arranging for the completion and correction of Jennifer's work.
    We disagree with the district court that Siegfried's communications
    cannot be interpreted as providing Gulf with reasonable notice or giv-
    ing Gulf an opportunity to hire a replacement for Jennifer. Virginia
    courts have not been overly strict in interpreting the notice require-
    ments of construction bonds. See Southwood Builders, Inc. v. Peerless
    Ins. Co., 
    366 S.E.2d 104
    , 106-07 (Va. 1988) (stating that the princi-
    ples of strict construction do not apply in favor of sureties for hire);
    see also American Surety Co. of New York v. Zoby, 
    130 S.E.2d 587
    (Va. 1963). And the evidence presented -- viewed in a light most
    favorable to Siegfried -- indicates that Siegfried's July 28 letter con-
    veyed the requisite information under the bond. Siegfried explained
    to Gulf that as a result of Jennifer's substandard workmanship and
    insufficient number of workers, Siegfried was augmenting Jennifer's
    workforce and thus arranging for the performance of Jennifer's con-
    tractual duties. Moreover, Siegfried presented evidence that during
    the telephone conversation with Gulf's investigator it asked for help
    in completing Jennifer's work. In light of this request for assistance
    and considering that the project was not completed until the middle
    of September, Gulf had time to respond and exercise its options under
    the bond.
    Gulf attempts to buttress the district court's holding by pointing out
    that Siegfried had been supplementing Jennifer's workforce long
    before the July 28 letter. While this fact is relevant to the amount of
    damages claimed against Gulf, it has no bearing on whether notice
    was given. In sum, the evidence produced at trial, which we construe
    in a light most favorable to Siegfried, indicates that Gulf received rea-
    sonable notice that Siegfried was arranging for the performance of
    Jennifer's obligation.
    III.
    For the foregoing reasons, we conclude that the district court erred
    in awarding Gulf judgment as a matter of law. The judgment of the
    district court is reversed and this matter is remanded for further pro-
    ceedings consistent with this opinion.
    REVERSED AND REMANDED
    12