Friends of Back Bay v. United States Army Corps of Engineers ( 2012 )


Menu:
  •                          PUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    FRIENDS OF BACK BAY; BACK BAY            
    RESTORATION FOUNDATION, LTD.,
    Plaintiffs-Appellants,
    v.
    UNITED STATES ARMY CORPS OF
    ENGINEERS; JOHN MCHUGH, in his
    official capacity as Secretary of
    The Army; ROBERT L. VAN
    ANTWERP, Lieutenant General, in             No. 11-1184
    his official capacity as Chief of
    Engineers and Commanding
    General of the U.S. Army Corps
    of Engineers; ANDREW W. BACKUS,
    Colonel, in his official capacity as
    District Engineer of the U.S.
    Army Corps of Engineers, Norfolk
    District,
    Defendants-Appellees.
    
    Appeal from the United States District Court
    for the Eastern District of Virginia, at Norfolk.
    Henry Coke Morgan, Jr., Senior District Judge.
    (2:10-cv-00270-HCM-TEM)
    Argued: January 25, 2012
    Decided: June 18, 2012
    Before KING, GREGORY, and FLOYD, Circuit Judges.
    2          FRIENDS OF BACK BAY v. U.S. ARMY CORPS
    Vacated and remanded by published opinion. Judge King
    wrote the opinion, in which Judge Gregory and Judge Floyd
    joined.
    COUNSEL
    ARGUED: Deborah M. Murray, SOUTHERN ENVIRON-
    MENTAL LAW CENTER, Charlottesville, Virginia, for
    Appellants. Brian C. Toth, UNITED STATES DEPART-
    MENT OF JUSTICE, Washington, D.C., for Appellees. ON
    BRIEF: Ignacia S. Moreno, Assistant Attorney General,
    Environment & Natural Resources Division, Katherine J. Bar-
    ton, UNITED STATES DEPARTMENT OF JUSTICE,
    Washington, D.C., for Appellees.
    OPINION
    KING, Circuit Judge:
    Friends of Back Bay, together with Back Bay Restoration
    Foundation, Ltd., the plaintiffs below, appeal the district
    court’s award of summary judgment to defendants United
    States Army Corps of Engineers (the "Corps"), Secretary of
    the Army John McHugh, the Commanding General of the
    Corps, Robert L. Van Antwerp, and Colonel Andrew W.
    Backus, the District Engineer for the Corps in its Norfolk Dis-
    trict. The plaintiffs’ Complaint challenged the Corps’s deci-
    sion to approve a permit under section 404 of the Clean Water
    Act ("CWA"), 
    33 U.S.C. § 1344
    , and section 10 of the Rivers
    and Harbors Act of 1899 ("RHA"), 
    33 U.S.C. § 403
    , to build
    a mooring facility and concrete boat ramp about 3,000 feet
    from the Back Bay National Wildlife Refuge (the "Refuge")
    in Virginia Beach, Virginia. As set forth below, we vacate the
    district court’s judgment and remand.
    FRIENDS OF BACK BAY v. U.S. ARMY CORPS                      3
    I.
    A.
    Proposed by developer Kenneth Douglas Wilkins, the per-
    mitted project (the "Project" or the "Wilkins Project") in a
    man-made cove off North and Shipps Bays, tributaries to
    Back Bay, would expand to 76 from 12 the number of exist-
    ing slips at the same site, the additional 64 being dedicated for
    watercraft use primarily by residents of nearby condomini-
    ums. The approved permit directly authorizes channel dredg-
    ing, as well as the excavation and relocation within the
    Project area of silt and other material. See 
    33 U.S.C. § 1344
    (a) (empowering Secretary of the Army to "issue per-
    mits . . . for the discharge of dredged or fill material into the
    navigable waters [of the United States]"). In addition, the per-
    mit provides for the construction of bulkheads, piers, mooring
    piles, and a walkway in conjunction with the slips and ramp.
    See 
    33 U.S.C. § 403
     (requiring approval of Secretary for, inter
    alia, "creation of any obstruction not affirmatively authorized
    by Congress[ ] to the navigable capacity of any of the waters
    of the United States").
    In mitigation of vegetated wetlands cleared to make way
    for the facility, the permit specifies the creation of equivalent
    wetlands nearby, and it requires the relocation there of the
    plants being displaced by the new construction. The permit
    also attaches a number of operational conditions to the com-
    pleted Project, including horsepower limitations on boat
    motors, restrictions on who may use the facility, and the
    installation of signs informing the public of the establishment
    of a no-wake zone (the "NWZ") for watercraft within the Ref-
    uge. See J.A. 232-33.1
    1
    Citations herein to "J.A. ___" refer to the contents of the Joint Appen-
    dix filed by the parties to this appeal.
    4            FRIENDS OF BACK BAY v. U.S. ARMY CORPS
    Prior to issuing the permit, the Corps solicited public com-
    ment on the underlying application; it received over 350
    responses, "the overwhelming majority of which were in
    opposition to the project." J.A. 194. The mayor of Virginia
    Beach recounted that various state and federal government
    agencies had "expended countless millions of dollars to con-
    serve Back Bay," and she expressed concern that "detrimental
    environmental impacts" would result from "greatly
    increase[d] access for jet skis and powerboats" to the ecologi-
    cally sensitive area. J.A. 152-53.
    In considerably more detail, the Gloucester, Virginia, field
    office of the United States Fish and Wildlife Service (the
    "FWS") documented the historical efforts to preserve and
    restore submerged aquatic vegetation ("SAV") in the area.
    The FWS surmised that "well documented" adverse effects of
    motorized watercraft, such as "sediment resuspension, water
    pollution, shoreline erosion, destruction of SAV and other
    wetlands, and disturbance to fish and wildlife," would
    increase if the Wilkins Project were fully realized, and pre-
    dicted that "because Back Bay is a shallow water system,
    these effects are likely to be amplified." 
    Id. at 159
    .2 The
    Regional Director of the FWS followed up with a separate
    comment, in which he maintained that the § 404 discharges
    occasioned by the Project "will have a substantial and unac-
    ceptable impact on aquatic resources of national importance,"
    and that, consequently, "the subject permit must be modified,
    conditioned, or denied." Id. at 166.
    2
    The FWS pointed out that a nearby Corps district headquartered in
    Wilmington, North Carolina, "is working with many other State and Fed-
    eral partners in a joint effort to improve the aquatic and wetlands environ-
    ments" in Back Bay and adjacent Currituck Sound (straddling Virginia
    and North Carolina), opining that "issuance of a permit for this type of
    facility . . . will open the door for additional development that is not com-
    patible with the watershed restoration goals developed by many agencies
    and partners for the Back Bay estuary." J.A. 158, 160.
    FRIENDS OF BACK BAY v. U.S. ARMY CORPS            5
    Similar sentiments were echoed by the Virginia Depart-
    ment of Game and Inland Fisheries (warning that "restoration
    efforts will face even more challenges in this unique system
    and may ultimately be rendered unsuccessful"), J.A. 168, and
    the federal Environmental Protection Agency (professing its
    belief that "the proposed project is contradictory to the envi-
    ronmental goals of several federal, state, [and] local resource
    agencies and the public interests," and thus "strongly recom-
    mends that the Corps deny the applicant’s request for per-
    mits"), id. at 165. The FWS likewise supported "denial of this
    project as proposed," id. at 161, but suggested that if the
    Corps were inclined to proceed, it should prepare an Environ-
    mental Impact Statement ("EIS") to address "impacts to Fed-
    eral trust resources . . . due to project construction and
    operation, habitat loss, and disruption/elimination of migra-
    tory pathways and feeding and resting areas." Id. at 160-61.
    An EIS is "a detailed statement" that ascertains, among
    other things, the effect of the proposed action on the environ-
    ment, including "any adverse environmental effects which
    cannot be avoided should the proposal be implemented," and
    evaluates alternatives. 
    42 U.S.C. § 4332
    (2)(C). As an integral
    underpinning of the National Environmental Protection Act
    ("NEPA"), an EIS must be devised in connection with "every
    recommendation or report on proposals for . . . major Federal
    actions significantly affecting the quality of the human envi-
    ronment." Id.; see State ex rel. Campbell v. O’Leary, 
    64 F.3d 892
    , 896 (4th Cir. 1995). To determine whether a particular
    action meets the threshold of "significantly affecting" envi-
    ronmental quality, federal agencies are required to draft an
    Environmental Assessment ("EA"), which is "a concise public
    document" designed to "provide sufficient evidence and anal-
    ysis for determining whether to prepare an [EIS] or a finding
    of no significant impact [‘FONSI’]." 
    40 C.F.R. § 1508.9
    (a)(1); see Campbell, 
    64 F.3d at 896
    .
    In its March 1, 2005 Public Notice of the permit applica-
    tion, the Corps announced its preliminary determination "that
    6            FRIENDS OF BACK BAY v. U.S. ARMY CORPS
    . . . no [EIS] will be required." J.A. 150. In light of the FWS
    comments advocating for denial or, at a minimum, urging
    preparation of an EIS, the Corps broached the concept of the
    NWZ, which it could create through designating the Project
    vicinity a Temporary Restricted Area.3 An internal memoran-
    dum dated June 16, 2006, reflected the Corps’s understanding
    that the FWS "indicated that implementation of the [NWZ]
    regulation should alleviate many of their concerns and that
    they will likely withdraw their objection to the Wilkins [Proj-
    ect] once this plan is in effect." Id. at 195.
    The NWZ went into effect that same day by virtue of a
    Local Order, for which Public Notice was subsequently pro-
    vided on June 28, 2006. Therein, the Corps recognized that
    watercraft use in and around the Refuge was "adversely
    impacting [SAV] and nesting, feeding and breeding birds as
    well as causing shoreline erosion from boat wakes." Id. at
    197. According to the Corps, the NWZ would secure "a sig-
    nificant measure of protection to the Refuge and its
    resources." Id. The Local Order expired on December 31,
    2007, after which the Corps made permanent the Restricted
    Area designation, effective May 16, 2008. The official Corps
    Memoranda issued in connection with the temporary and per-
    manent designations each provided that the NWZ
    may be enforced by any Federal Agency, State,
    3
    The Corps’s regulations explain that a "restricted area" is "[a] defined
    water area for the purpose of prohibiting or limiting public access to the
    area. Restricted areas generally provide security for Government property
    and/or protection to the public from the risks of damage or injury arising
    from the Government’s use of that area." 
    33 C.F.R. § 334.2
    (b). A "no-
    wake zone" is not specifically defined, but within the context of the per-
    manent Restricted Area designation, detailed infra, the NWZ in this case
    means that, save for certain carefully delineated exceptions, "[n]o vessel
    of any type shall operate at a speed that causes a wake while they are
    within 100 yards of the shoreline of the Back Bay National Wildlife Ref-
    uge." J.A. 211. The shoreline is deemed to commence at the "Ordinary
    High Water" mark. 
    Id.
    FRIENDS OF BACK BAY v. U.S. ARMY CORPS            7
    Local or County Law Enforcement agency, or Pri-
    vate Security Firms in the employment of the
    [Corps] or U.S. Fish and Wildlife Service so long as
    the entity undertaking enforcement action has the
    legal authority to do so under the appropriate Fed-
    eral, State, or Local laws.
    
    Id. at 192, 212
    .
    As a practical matter, however, enforcement of the NWZ
    appears to be problematic. In the course of interagency dis-
    cussions of the Project in 2006, it was revealed that the
    marine detachment of the Virginia Beach Police Department
    was "unable to routinely patrol the Back Bay due to current
    staffing constraints." J.A. 186. Responding to the continuing
    concerns expressed by the FWS, Colonel Dionysios Anninos,
    the District Commander for the Corps, conceded on Septem-
    ber 11, 2008, that "[e]nforcement will be an issue," but he was
    "hopeful" that compliance with the NWZ would be achieved
    "through education, signage, [and] public pressure." 
    Id. at 203, 223
    . Colonel Anninos insisted, however, that "the lack
    of funding necessary for a state or federal agency to fulfill
    obligations is not a sufficient reason to deny a project." 
    Id.
    By letter of October 3, 2008, the FWS Regional Office
    memorialized the agency’s ongoing discussions with the
    Corps concerning the Wilkins Project. Although the FWS
    acknowledged that "details of the measures are still to be
    worked out," its acquiescence in the Project was conditioned
    on "[a]dequate funding for the enforcement of" the NWZ,
    with further discussions to be conducted as to the proper allo-
    cation of "[r]esponsibility of enforcement and cost share
    funds." J.A. 226-27. On October 10, 2008, Colonel Anninos
    wrote to his district’s regulatory section, explaining that the
    Corps’s coordination with the FWS had addressed the latter
    agency’s concerns. See 
    id. at 229
    . That same date, the Corps
    issued the permit.
    8          FRIENDS OF BACK BAY v. U.S. ARMY CORPS
    The permit, however, neither mandates enforcement of the
    NWZ nor guarantees funding therefor. Aside from requiring
    that signage be posted, the permit specifies only that Wilkins
    "serve on and participate in a committee of local, state and
    federal agencies and community stakeholders to attempt to
    establish a funding program for enforcement of the [NWZ] in
    Back Bay." J.A. 233. The permit identifies several potential
    sources for such funding, including grants, assessments, and
    user fees, and notes that Wilkins also "may be required to
    contribute a fair and equitable portion of the funding for this
    program." 
    Id. at 234
    .
    In the final EA, issued contemporaneously with the permit,
    Colonel Anninos, on behalf of the Corps, reiterated the "con-
    sensus . . . that the currently unrestricted use of the waters in
    and around the Refuge may be having an adverse impact on
    the sensitive and unique natural resources of the . . . Refuge
    and Back Bay as a whole." J.A. 259. The Corps observed,
    however, that refusing the permit "would not solve existing
    and future problems associated with recreational boating in
    Back Bay," and insisted that "denying this proposal would
    logically necessitate the denial of all future private piers, boat
    ramps and mooring projects in Back Bay due to the potential
    for cumulative impacts." 
    Id. at 269
    . Notwithstanding that
    "there are no city or state maritime patrols within the Bay,"
    
    id. at 261
    , the Corps asserted that the NWZ "will limit and
    reduce any adverse impacts from the construction and opera-
    tion of the facility," 
    id. at 250
    . The EA culminated in a
    FONSI, thus declaring that "no [EIS] will be prepared." 
    Id. at 277
    .
    B.
    The plaintiffs filed a Complaint in the District Court for the
    District of Columbia on December 14, 2009, seeking review
    of the Corps’s decision, in accordance with § 404 of the
    CWA, to allow the dredging and subsequent discharge via
    relocation of silt and fill material, and challenging the Corps’s
    FRIENDS OF BACK BAY v. U.S. ARMY CORPS                9
    determination that issuance of the permit does not qualify
    under NEPA as a federal action "significantly affecting the
    quality of the human environment," such that an EIS must be
    prepared in advance. On the defendants’ motion, and over the
    plaintiffs’ opposition, venue was subsequently transferred to
    the Eastern District of Virginia.
    The district court exercised jurisdiction over both aspects of
    the Complaint pursuant to the general review provisions of
    the Administrative Procedure Act ("APA"). See 
    5 U.S.C. §§ 702
    , 704; Ohio Valley Envtl. Coal. v. Aracoma Coal Co.,
    
    556 F.3d 177
    , 192 (4th Cir. 2009) (instructing that "[c]laims
    challenging federal agency action under the CWA and NEPA
    are subject to judicial review under the APA"). The court
    directed the filing of the administrative record, after which the
    parties submitted cross-motions for summary judgment. Fol-
    lowing a hearing on January 28, 2011, the district court, by its
    Opinion and Order of February 9, 2011, entered judgment on
    behalf of the defendants.
    In so doing, the district court rejected the plaintiffs’ conten-
    tion that potential harm to the Refuge from boating activities
    could properly be considered a legitimate secondary effect of
    the dredging and filling authorized pursuant to the CWA. See
    Friends of Back Bay v. U.S. Army Corps of Eng’rs, No. 2:10-
    cv-0070, slip op. at 36 (E.D. Va. Feb. 9, 2011). With respect
    to the NEPA challenge, the court concluded that the Corps’s
    decision to grant the permit without preparing an EIS was
    within the agency’s broad discretion and not contrary to law.
    See id. at 30. Upon timely notice filed on February 23, 2011,
    the plaintiffs pursue this appeal.
    II.
    The APA provides that a reviewing court is bound to "hold
    unlawful and set aside agency action" for certain specified
    reasons, including whenever the challenged act is "arbitrary,
    capricious, an abuse of discretion, or otherwise not in accor-
    10         FRIENDS OF BACK BAY v. U.S. ARMY CORPS
    dance with law." 
    5 U.S.C. § 706
    (2)(A); see Ohio Valley Envtl.
    Coal. v. Aracoma Coal Co., 
    556 F.3d 177
    , 192 (4th Cir.
    2009). The foregoing statutory criteria render our oversight
    "highly deferential, with a presumption in favor of finding the
    agency action valid," yet the arbitrary-and-capricious standard
    does not "reduce judicial review to a rubber stamp of agency
    action." 
    Id.
     (citation and internal quotation marks omitted).
    To comply with NEPA, "federal agencies must take a ‘hard
    look’ at the potential environmental consequences of their
    actions." Aracoma Coal, 
    556 F.3d at 191
     (citation omitted).
    In a similar fashion, we must "engage in a ‘searching and
    careful’ inquiry of the record," so that we may "consider
    whether the agency considered the relevant factors and
    whether a clear error of judgment was made." 
    Id. at 192
    (quoting Citizens To Preserve Overton Park, Inc. v. Volpe,
    
    401 U.S. 402
    , 416 (1971)). Insofar as an agency’s decision
    may be deemed unreasonable as a matter of law, it is likely
    to have been arbitrary and capricious. See Marsh v. Oregon
    Natural Res. Council, 
    490 U.S. 360
    , 377 n.23 (1989) (noting
    courts’ adoption of "arbitrary and capricious" and "reason-
    ableness" standards under the APA, and explaining that dif-
    ference between the two "is not of great pragmatic
    consequence"). We evaluate the reasonableness of the Corps’s
    decisionmaking de novo, without deference to the district
    court’s resolution of the issue. See Hughes River Watershed
    Conservancy v. Glickman, 
    81 F.3d 437
    , 443 (4th Cir. 1996).
    III.
    A.
    1.
    The parties devoted much effort below, and have again on
    appeal, debating how to properly characterize the EA.
    According to the plaintiffs, the Corps found at the threshold
    that granting the permit would affect the environment to the
    FRIENDS OF BACK BAY v. U.S. ARMY CORPS             11
    degree necessary to trigger the need for an EIS, but that estab-
    lishment of the NWZ would ameliorate the adverse effects
    such that the net result would be no significant impact. When
    an agency relies on such a "mitigated FONSI," it may avoid
    preparing an EIS. See Ohio Valley Envtl. Coal. v. Aracoma
    Coal Co., 
    556 F.3d 177
    , 191-92 (4th Cir. 2009). In support of
    their position, the plaintiffs point out that the permit applica-
    tion caused the Corps to examine and appreciate the problems
    associated with watercraft use in Back Bay; the Project thus
    spurred the Corps’s decision to designate the Refuge as a
    Restricted Area and impose the NWZ.
    The defendants, to the contrary, maintain that because the
    NWZ was in effect for nearly two years prior to issuance of
    the EA, it constituted a "baseline" condition reflecting the
    state of the environment absent any undertaking pursuant to
    the permit. See N.C. Wildlife Fed’n v. N.C. Dep’t of Transp.,
    No. 11-2210, 
    2012 WL 1548685
     (4th Cir. May 3, 2012), at *6
    (equating baseline with "no action" EIS alternative mandated
    for consideration by 
    40 C.F.R. § 1502.14
    (d)). As such, the
    argument goes, the Corps considered from a historical per-
    spective (albeit a somewhat brief one) the issues giving rise
    to its creation of the Restricted Area and the efficacy of the
    NWZ in resolving those issues, but nonetheless concluded
    that a FONSI was appropriate.
    The parties perceive the mitigation/baseline distinction
    important in light of pertinent authorities requiring that
    assumptions underlying a mitigated FONSI be supported by
    record evidence. See, e.g., Hill v. Boy, 
    144 F.3d 1446
    , 1450-
    51 (11th Cir. 1998) (ruling Corps’s refusal to prepare EIS
    arbitrary and capricious where no evidence supported key
    mitigation assumption and no analysis conducted gauging
    effect of opposite assumption); Nat’l Audubon Soc’y v. Hoff-
    man, 
    132 F.3d 7
    , 17 (2d. Cir. 1997) (concluding that Forest
    Service arbitrarily and capriciously bypassed EIS where
    record failed to establish likely efficacy of mitigation pro-
    posal). An unjustified leap of logic or unwarranted assump-
    12           FRIENDS OF BACK BAY v. U.S. ARMY CORPS
    tion, however, can erode any pillar underpinning an agency
    action, whether constructed from the what-is or the what-
    may-be. Once the roof caves in, it offers but a smattering of
    solace to explain that only the latter were inspected and
    deemed sound.
    A material misapprehension of the baseline conditions
    existing in advance of an agency action can lay the ground-
    work for an arbitrary and capricious decision. We recently
    confronted precisely that situation in North Carolina Wildlife
    Federation, supra. There, the federal and state agencies
    charged with evaluating the construction of a proposed toll
    highway erroneously adopted the assumption that the road
    would be built in estimating the consequences resulting from
    no action being taken. In light of the obvious and fundamental
    blunder, we had no difficulty remanding the matter for recon-
    sideration, noting that "courts not infrequently find NEPA
    violations when an agency miscalculates the ‘no build’ base-
    line or when the baseline assumes the existence of a proposed
    project." N.C. Wildlife Fed’n, 
    2012 WL 1548685
    , at *6 (cita-
    tions and footnote omitted).
    Here, it cannot be disputed that the creation and continued
    existence of the NWZ is a foundational proposition upon
    which the FONSI was premised. The EA did not pretend to
    the contrary; the Corps, to its credit, did not endeavor therein
    to downplay the potential deleterious consequences if water-
    craft are suffered to freely scurry about the Refuge.4 The
    4
    The EA asserts that educating the public about the NWZ, as an integral
    part of the operational conditions incorporated within the permit and made
    an enforceable condition thereof, "will ensure that boaters from the Wil-
    kins . . . Facility will not adversely impact the ecologically sensitive Back
    Bay/North Bay area," and "will limit and reduce any adverse impacts from
    the construction and operation of the facility." J.A. 250. In summing up
    the EA, Colonel Anninos expressed the Corps’s conclusion that the permit
    conditions were of sufficient heft such that "there are no longer substantial
    adverse impacts" associated with the Project. J.A. 277. The defendants
    contend that "adverse impacts" and even "substantial adverse impacts" do
    FRIENDS OF BACK BAY v. U.S. ARMY CORPS                       13
    NWZ, however, is entirely unenforced. Indeed, as revealed at
    the hearing below on January 28, 2011, the NWZ remained
    unmarked and undisclosed to the public nearly five years after
    its initial implementation. See J.A. 63, 73-74. As the district
    court astutely remarked at the hearing, "[E]ven if people
    wanted to obey the no wake zone, I don’t know how in the
    world they could do it without it being marked." J.A. 78.
    The most that the Corps could say was that it was "hopeful"
    that the public would comply with the secret NWZ. J.A. 203,
    223. No doubt the thoughtful folks who leave cauldrons of
    candy on their front porches at Halloween hope the neighbor-
    hood trick-or-treaters will behave themselves and take only
    their fair share, but common experience has shown that those
    hopes often remain unfulfilled. While the betrayal of trust on
    All Hallows’ Eve might cost the credulous a bag or two of
    sweets, the potential cost to the Refuge in this case from the
    Corps’s hopefulness is, inarguably, considerably higher.
    Measures designed to render minimal a particular action’s
    impact upon the environment, whether proposed in mitigation
    or assumed to already exist, are more readily deemed effica-
    cious (and thus more comfortably within an agency’s broad
    prerogative to propose or assume) "when they are likely to be
    policed," Hoffman, 
    132 F.3d at
    17 (citing Abenaki Nation of
    Mississquoi v. Hughes, 
    805 F. Supp. 234
    , 239 n.9 (D. Vt.
    not necessarily rise to the level of "significant impacts" triggering an EIS,
    but any notion that unrestricted watercraft access to the Refuge would be
    of no significance under NEPA is belied both by the lack of that sort of
    analysis in the EA and by the sustained efforts of the Corps in pursuing
    and implementing the temporary Local Order and subsequent Restricted
    Area designation. The Corps undertook both courses of conduct notwith-
    standing its estimate that the 64 additional slips associated with the Wil-
    kins Project would increase traffic no more than three to six percent, see
    J.A. 257, and despite a three-day stakeout of about ten percent of the Ref-
    uge it conducted in August 2006, at the conclusion of which the Corps sur-
    mised that there is "minimal traffic on the bay during the majority of the
    boating season." J.A. 260.
    14         FRIENDS OF BACK BAY v. U.S. ARMY CORPS
    1992)). Such policing may occur prospectively by administra-
    tive enforcement through the imposition of a mandatory per-
    mit condition, as in Abenaki Nation, or it may be recognized
    as a baseline incident, enforced by a literal police presence.
    Neither is currently the case in Back Bay.
    Absent any reasonable basis to conclude that, as of October
    2008, the NWZ was being adequately enforced or its efficacy
    was otherwise assured, the concept thereof as discussed
    within the EA was a logical nullity. Being unable to divorce
    the Corps’s demonstrably incorrect assumption of an effective
    NWZ from its ultimate conclusion that no EIS need be pre-
    pared, we find ourselves constrained to invalidate the resul-
    tant FONSI as arbitrary and capricious. The judgment below
    to the contrary must therefore be vacated, and the matter
    remanded to the district court for further remand to the Corps.
    2.
    The question remains as to what action the Corps may take
    on remand. The Council on Environmental Quality has pro-
    mulgated a regulation intended to guide federal agencies in
    ascertaining the likelihood that their actions will, within the
    meaning of NEPA, significantly affect the environment. See
    
    40 C.F.R. § 1508.27
    . Decisionmakers are required to consider
    both context and intensity, with the latter criterion "refer[ring]
    to the severity of impact." 
    Id.
     at § 1508.27(b).
    The regulation details ten intensity factors to be considered,
    of which the plaintiffs direct our attention to five they believe
    support the conclusion that an EIS must be prepared. Without
    discounting the potential applicability of any of the ten fac-
    tors, two in particular militate strongly in favor of the plain-
    tiffs’ position. Those are the "[u]nique characteristics of the
    geographic area such as . . . wetlands . . . or ecologically criti-
    cal areas," id. at § 1508.27(b)(3), and "[t]he degree to which
    the effects on the quality of the human environment are likely
    to be highly controversial," id. at § 1508.27(b)(4).
    FRIENDS OF BACK BAY v. U.S. ARMY CORPS           15
    The EA acknowledged that Back Bay is part of the
    Albemarle-Pamlico Estuarine Sound System, which has been
    "designated by EPA as an estuary of national significance."
    J.A. 248. The bay has been described "as one of the most
    diverse and extensive ecosystems in southeastern Virginia,"
    and though its marsh communities are characteristic of the
    area and that of northeastern North Carolina, "they are consid-
    ered globally rare." J.A. 249. It thus appears beyond question
    that the Refuge and its vicinity qualify as unique and ecologi-
    cally critical.
    Moreover, the debate concerning the potential effects of the
    Wilkins Project on the quality of the human environment in
    and around Back Bay has proved to be highly controversial.
    We say this not in the sense that all contested actions affect-
    ing the environment generate a degree of controversy, particu-
    larly among those whose sensitivities may be peculiarly
    attuned to such matters, but in the sense that no fewer than
    four respected governmental entities (including two of the
    Corps’s sister agencies of the federal government) unani-
    mously opposed the permit application as proposed. See
    Davis v. Mineta, 
    302 F.3d 1104
    , 1123 (10th Cir. 2002) (rec-
    ognizing that courts "may properly be skeptical" of the factual
    basis of agency conclusions "if the responsible agency has
    apparently ignored the conflicting views of other agencies
    having pertinent expertise" (quoting Sierra Club v. U.S. Army
    Corps of Eng’rs, 
    701 F.2d 1011
    , 1030 (2d Cir. 1983))).
    The FWS specifically recommended preparation of an EIS
    as an alternative to denying the permit, and we agree that is
    the preferred approach here. Even were the situation consider-
    ably less clear-cut, we remain mindful that "when it is a close
    call whether there will be a significant environmental impact
    from a proposed action, an EIS should be prepared." Hoffman,
    
    132 F.3d at 18
    . We concur with the view of the Second Cir-
    cuit in Hoffman that the policy goals underlying NEPA are
    best served if agencies "err in favor of preparation of an EIS
    16         FRIENDS OF BACK BAY v. U.S. ARMY CORPS
    when . . . there is a substantial possibility that the [proposed]
    action may have a significant impact on the environment." 
    Id.
    B.
    The plaintiffs also reassert on appeal their contention that,
    for several reasons, the permit should not have issued pursu-
    ant to § 404 of the CWA. Among other things, the plaintiffs
    maintain that, apart from the discrete movement of silt neces-
    sary to construct the mooring facility and boat ramp, the
    increase in watercraft traffic resulting from completion of the
    Wilkins Project may properly be considered as a secondary
    effect on the aquatic ecosystem "associated with a discharge
    of dredged or fill materials," though the presence of the addi-
    tional boats and jet skis "do not result from the actual place-
    ment of the dredged or fill material." 
    40 C.F.R. § 230.11
    (h)(1); see Fox Bay Partners v. U.S. Army Corps of
    Eng’rs, 
    831 F. Supp. 605
     (N.D. Ill. 1993).
    The district court rejected the plaintiffs’ § 404 challenge,
    but we need not address it here. Having already concluded
    that the Corps’s grant of the permit violated the applicable
    NEPA procedural requirements, we are not inclined to decide
    whether it should not have issued on different grounds.
    Depending on the result of the EIS and the implementation
    thereof undertaken by the Corps on remand, the plaintiffs’
    CWA objections may not again present themselves. In the
    event the issue recurs, however, it can be revisited by the
    Corps and, if necessary, the district court, in the normal
    course of events.
    IV.
    Pursuant to the foregoing, we vacate the judgment below
    and remand for the district court to remand to the Corps for
    preparation of an EIS, and for such other and further proceed-
    ings as may be appropriate.
    VACATED AND REMANDED