Wilds v. South Carolina Department of Transportation , 9 F. App'x 114 ( 2001 )


Menu:
  •                           UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    NANCY WILDS, individually and on          
    behalf of all others similarly
    situated,
    Plaintiff-Appellant,
    v.
         No. 00-1808
    SOUTH CAROLINA DEPARTMENT OF
    TRANSPORTATION; NORMAN Y.
    MINETA, SECRETARY, UNITED STATES
    DEPARTMENT OF TRANSPORTATION,
    Defendants-Appellees.
    
    Appeal from the United States District Court
    for the District of South Carolina, at Columbia.
    Dennis W. Shedd, District Judge.
    (CA-97-1608-8-13BD)
    Argued: March 1, 2001
    Decided: May 9, 2001
    Before NIEMEYER, LUTTIG, and WILLIAMS, Circuit Judges.
    Affirmed by unpublished per curiam opinion.
    COUNSEL
    ARGUED: Charles Russell Horner Shearer, CADWALADER,
    WICKERSHAM & TAFT, Washington, D.C., for Appellant. John
    Luther Smeltzer, UNITED STATES DEPARTMENT OF JUSTICE,
    2                  WILDS v. SOUTH CAROLINA DOT
    Washington, D.C., for Appellees. ON BRIEF: Geraldine E. Edens,
    CADWALADER, WICKERSHAM & TAFT, Washington, D.C., for
    Appellant. Lois J. Schiffer, Assistant Attorney General, Environment
    & Natural Resources Division, UNITED STATES DEPARTMENT
    OF JUSTICE, Washington, D.C.; Kenneth W. Ebener, S. Jahue
    Moore, WILSON, MOORE, TAYLOR & THOMAS, P.A., West
    Columbia, South Carolina, for Appellees.
    Unpublished opinions are not binding precedent in this circuit. See
    Local Rule 36(c).
    OPINION
    PER CURIAM:
    Nancy Wilds filed suit in the United States District Court for the
    District of South Carolina against United States Transportation Secre-
    tary Norman Mineta1 and the South Carolina Department of Transpor-
    tation (SCDOT) (collectively, the DOT) challenging two federal-aid
    highway projects in Aiken, South Carolina — the "Eastern Connec-
    tor" and the "Pine Log" projects. On appeal from the district court’s
    grant of summary judgment in favor of the DOT, Wilds argues that
    the DOT improperly segmented its environmental analysis into two
    projects; that the DOT improperly undertook the Pine Log project
    without issuing a final environmental assessment (EA); that the DOT
    failed properly to determine whether the Eastern Connector project
    would have significant induced growth and air quality impacts; that
    the DOT failed adequately to consider alternatives to the Eastern Con-
    nector project; and that the DOT improperly issued the EA and find-
    ing of no significant impact (FONSI) for the Eastern Connector
    project on the same day and without giving proper notice or consider-
    ing relevant new information. Finding no reversible error, we affirm.
    1
    The case was originally captioned against Rodney Slater, who is no
    longer the United States Secretary of Transportation.
    WILDS v. SOUTH CAROLINA DOT                         3
    I.
    The City of Aiken, South Carolina, is served by two major high-
    ways that intersect downtown — U.S. Route 78, which is an east-west
    route, and S.C. Route 19, which is a north-south route. These two
    intersecting highways connect to, inter alia, a series of roads that form
    an "Outer Loop" around Aiken. The roads in the Outer Loop include
    Rutland Drive, University Parkway, Richard M. Bell Parkway, Hitch-
    cock Parkway, and Pine Log Road. Although termed the "Outer
    Loop," the series of roads does not form a continuous loop. Rather,
    the loop lacks a direct connection between the intersection of Route
    78 and Pine Log Road, where the loop ends, and the Route 1 and Rut-
    land Drive intersection, where the loop begins. Route 19 also con-
    nects to Interstate 20, a freeway that connects Atlanta, Georgia and
    Columbia, South Carolina.
    In 1975, the SCDOT, in conjunction with the Federal Highway
    Administration (FHWA) and local government officials, prepared an
    "Aiken Area Transportation Study," which recommended improve-
    ments to the Outer Loop in order to divert traffic from downtown
    Aiken. In November 1989, the Aiken Comprehensive Plan incorpo-
    rated these recommendations. The Plan recommended constructing
    the Eastern Connector and widening Pine Log Road.
    A. The Eastern Connector
    The Eastern Connector project is designed to improve SC Route
    118 between SC Route 19 and US Route 78 by (1) widening Rutland
    Drive from a four-lane to a five-lane roadway and (2) building a new
    five-lane connecting roadway from the end of Rutland Drive to the
    intersection of Route 78 and Pine Log Road. The new roadway would
    remove another road, Beaufort Street, from the bypass system and
    make the Outer Loop more or less continuous. The purpose of the
    project is to address traffic and circulation difficulties in the project
    area, to handle projected traffic levels,2 and to improve traffic flow
    2
    The traffic volume as of July 7, 1995, the date of the final EA for the
    Eastern Connector, ranged from 10,100 vehicles per day to 16,400 vehi-
    cles per day. This exceeds the desired traffic volume of 7,800 vehicles
    per day. It is projected that the route will see 21,300 to 26,600 vehicles
    per day by the year 2015.
    4                      WILDS v. SOUTH CAROLINA DOT
    along the existing bypass system. The Eastern Connector would also
    provide a northeast bypass for drivers traveling between Route 78 and
    Interstate 20 interchanges.
    In January 1994, the DOT issued its draft EA3 for the Eastern Con-
    nector. On February 11, 1994, the FHWA approved the draft EA. The
    DOT sent notice to city, county, and state officials announcing the
    public availability of the EA and a public hearing on the Eastern Con-
    nector project, and on May 3, 1994, the DOT also published notice
    in the Aiken Standard, a local newspaper. On May 24, 1994, the DOT
    held a public hearing on the project. On January 10, 1995, the DOT
    forwarded its final EA to the FHWA. On July 7, 1995, the FHWA
    approved the location and preliminary design of the Eastern Connec-
    tor project, approved the final EA, and issued a FONSI. On October
    6, 1995, the DOT published notice in a local newspaper, the Aiken
    Standard, announcing public availability of the FONSI.
    B. Pine Log Road
    The Pine Log Road project is designed to widen S.C. Route 302
    from two lanes to four lanes and add a median strip and a fifth multi-
    purpose lane. There also would be a slight relocation of the end of the
    3
    
    40 C.F.R. § 1508.9
     (2000) provides that
    Environmental Assessment:
    (a) Means a concise public document for which a Federal agency
    is responsible that serves to:
    (1) Briefly provide sufficient evidence and analysis for
    determining whether to prepare an environmental impact
    statement or a finding of no significant impact.
    (2) Aid an agency’s compliance with the Act when no envi-
    ronmental impact statement is necessary.
    (3) Facilitate preparation of a statement when one is neces-
    sary.
    (b) Shall include brief discussions of the need for the pro-
    posal, of alternatives as required by section 102(2)(E), of the
    environmental impacts of the proposed action and alterna-
    tives, and a listing of agencies and persons consulted.
    WILDS v. SOUTH CAROLINA DOT                      5
    roadway where it intersects with Route 78 to allow for a direct con-
    nection with the proposed Eastern Connector. The project is designed
    to relieve congestion and improve traffic flow between Route 19 and
    Route 78 and would also help complete the Outer Loop.
    On March 19, 1996, the DOT issued a draft EA that evaluated
    potential impact of the project. On May 16, 1996, the FHWA sent a
    letter to the DOT recognizing that the DOT’s draft EA had success-
    fully addressed certain key concerns raised by the FHWA prior to
    submission of the draft EA. On the same day, the FHWA approved
    the draft EA. On July 18, 1996, after issuing a public notice, the DOT
    held a public hearing on the Pine Log project. On September 13,
    1996, the DOT notified the FHWA that it had complied with the
    National Environmental Policy Act, 
    42 U.S.C.A. § 4332
     (NEPA) and
    that NEPA review was complete. On September 19, 1996, the FHWA
    approved the location and preliminary design of the Pine Log project,
    and issued a FONSI for the project.
    C.
    In 1995, Wilds began lobbying to stop the highway projects
    because she believed that her property would be adversely impacted.
    On September 20, 1995, the South Carolina subcommittee of the
    Augusta Regional Transportation Study held a special meeting on the
    Eastern Connector project at Wilds’s request. Approximately 80 other
    area residents attended the meeting and many of them objected to the
    project. Despite the objections, the subcommittee found no reason to
    alter the proposed project.
    On June 2, 1997, Wilds filed suit against the Secretary of Transpor-
    tation and the SCDOT.4 She simultaneously filed a motion for prelim-
    inary injunction seeking to enjoin the Eastern Connector project
    pending further NEPA evaluations. The district court denied the
    motion for preliminary injunction. After the parties filed cross-
    motions for summary judgment, the magistrate judge issued a report
    recommending that summary judgment be granted in favor of the
    DOT. The district court accepted the magistrate judge’s recommenda-
    tion and granted the DOT’s motion for summary judgment.
    4
    Wilds filed suit pro se but later obtained counsel.
    6                   WILDS v. SOUTH CAROLINA DOT
    Wilds raises several issues on appeal. First, Wilds argues that the
    DOT improperly segmented its environmental analysis for the Eastern
    Connector and Pine Log projects from each other and from the Outer
    Loop. Second, Wilds argues that the DOT improperly undertook the
    Pine Log project without issuing a final EA. Third, Wilds argues that
    the DOT failed properly to determine whether the Eastern Connector
    project would have significant induced growth and air quality
    impacts. Fourth, Wilds argues that the DOT failed adequately to con-
    sider alternatives to the Eastern Connector project. Finally, Wilds
    argues that the DOT improperly issued the EA and the FONSI for the
    Eastern Connector project on the same day and that the DOT failed
    to give proper notice or to consider relevant new information.
    II.
    We review the district court’s grant of summary judgment de novo.
    We must determine whether the DOT’s decision was "arbitrary, capri-
    cious, or otherwise not in accordance with law, or unsupported by
    substantial evidence." Roanoke River Basin Ass’n. v. Hudson, 
    940 F.2d 58
    , 61 (4th Cir. 1991) (internal quotation marks omitted). "To
    apply the standard, we must make a searching and careful inquiry into
    the facts and a review of whether the decision was based on a consid-
    eration of the relevant factors and whether there has been a clear error
    of judgment, although naturally we are not empowered to substitute
    [our] judgment for that of the agency." City of Alexandria v. Fed.
    Highway Admin., 
    756 F.2d 1014
    , 1017 (4th Cir. 1985) (internal quo-
    tation marks omitted). Rather, our role is "to see that the official or
    agency take[s] a ‘hard look’ at all relevant factors." Coalition For
    Responsible Reg’l Dev. v. Coleman, 
    555 F.2d 398
    , 400 (4th Cir.
    1977) (internal quotation marks omitted).
    NEPA provides that "all agencies of the Federal Government shall"
    (C) include in every recommendation or report on proposals
    for legislation and other major Federal actions significantly
    affecting the quality of the human environment, a detailed
    statement by the responsible official on—
    (i) the environmental impact of the proposed
    action,
    WILDS v. SOUTH CAROLINA DOT                        7
    (ii) any adverse environmental effects which can-
    not be avoided should the proposal be imple-
    mented,
    (iii) alternatives to the proposed action,
    (iv) the relationship between local short-term uses
    of man’s environment and the maintenance and
    enhancement of long-term productivity, and
    (v) any irreversible and irretrievable commitments
    of resources which would be involved in the pro-
    posed action should it be implemented.
    
    42 U.S.C.A. § 4332
    (2)(C)(i)-(v) (West 1994).
    "NEPA declares a national policy of protecting and promoting
    environmental quality. To implement this policy, NEPA requires fed-
    eral agencies to follow certain procedures before undertaking projects
    that will affect the environment." Hughes River Watershed Conser-
    vancy v. Glickman, 
    81 F.3d 437
    , 443 (4th Cir. 1996) (Hughes River
    I). "Thus, although NEPA establishes environmental quality as a sub-
    stantive goal, it is well settled that NEPA does not mandate that agen-
    cies reach particular substantive results. Instead, it simply sets forth
    procedures that agencies must follow." 
    Id.
     (internal citations omitted).
    "In other words, if the adverse environmental effects of . . . proposed
    actions are adequately identified and evaluated, agencies are not con-
    strained by NEPA from deciding that other values outweigh the envi-
    ronmental costs." 
    Id.
     (internal quotation marks and alterations
    omitted). "Central to NEPA’s procedural focus is the requirement that
    federal agencies prepare [environmental impact statements (EIS)] to
    be included in every recommendation or report on proposals for . . .
    major Federal actions significantly affecting the quality of the human
    environment." 
    Id.
     (internal quotation marks omitted). "Preparation of
    an EIS serves the national policy of protecting and promoting envi-
    ronmental quality in two ways." 
    Id.
     "First, it ensures that an agency,
    when deciding whether to approve a project, will carefully consider,
    or take a ‘hard look’ at, the project’s environmental effects." 
    Id.
     "Sec-
    ond, it ensures that relevant information about a proposed project will
    be made available to members of the public so that they may play a
    8                       WILDS v. SOUTH CAROLINA DOT
    role in both the decisionmaking process and the implementation of the
    decision." 
    Id.
     (internal citations omitted). In reviewing the agency’s
    decision to issue a FONSI rather than perform an EIS, a court must
    determine whether the agency took a "hard look" at the project’s
    effects and whether the decision was arbitrary or capricious. See 
    id.
    (addressing "hard look" in context of whether agency should have
    issued a supplemental EIS). "[A]n agency takes a sufficient ‘hard
    look’ when it obtains opinions from its own experts, obtains opinions
    from experts outside the agency, gives careful scientific scrutiny and
    responds to all legitimate concerns that are raised." Hughes River
    Watershed Conservancy v. Johnson, 
    165 F.3d 283
    , 288 (4th Cir.
    1999) (Hughes River II). "Although an agency should consider the
    comments of other agencies, it does not necessarily have to defer to
    them when it disagrees." 
    Id.
     "Agencies are entitled to rely on the view
    of their own experts. As long as the adverse environmental effects of
    a proposed action are sufficiently identified and evaluated, an agency
    is vested with discretion to determine under NEPA that other values
    outweigh the environmental costs." 
    Id.
     (internal quotation marks and
    citations omitted).
    In determining whether a project has a significant environmental
    impact, an agency may not avoid significant environmental impact by
    improperly "segmenting" a project by dividing the NEPA analysis of
    a larger action with significant impacts into smaller actions with
    insignificant impacts. Save Barton Creek Ass’n v. Fed. Highway
    Admin., 
    950 F.2d 1129
    , 1140 (5th Cir. 1992). "Segmentation analysis
    functions to weed out projects which are pretextually segmented, and
    for which there is no independent reason to exist. When the segmenta-
    tion project has no independent jurisdiction, no life of its own, or is
    simply illogical when viewed in isolation, the segmentation will be
    held invalid." 
    Id. at 1139
     (internal quotation marks and emphasis
    omitted); 
    23 C.F.R. § 771.111
    (f) (2000).5 "Segmentation becomes
    5
    
    23 C.F.R. § 771.111
    (f) provides:
    (f) In order to ensure meaningful evaluation of alternatives and
    to avoid commitments to transportation improvements before
    they are fully evaluated, the action evaluated in each EIS or find-
    ing of no significant impact (FONSI) shall:
    (1) Connect logical termini and be of sufficient length to
    address environmental matters on a broad scope;
    WILDS v. SOUTH CAROLINA DOT                         9
    suspect, however, only after an evaluation of such factors as whether
    the proposed segment (1) has logical termini; (2) has substantial inde-
    pendent utility; (3) does not foreclose the opportunity to consider
    alternatives; and (4) does not irretrievably commit federal funds for
    closely related projects." Save Barton Creek Ass’n, 
    950 F.2d at 1140
    .
    "In the context of a highway within a single metropolitan area, as the
    case at issue — as opposed to projects joining cities — courts have
    focused more on the factor of ‘independent utility.’" Id.; see also
    Coalition on Sensible Transp., Inc. v. Dole, 
    826 F.2d 60
    , 69 (D.C. Cir.
    1987) (noting that courts focus more heavily on the independent util-
    ity factor).
    The magistrate judge, whose recommendation the district court
    adopted, recognized the impermissibility of segmenting a project into
    smaller parts in order to avoid preparing an EIS. He concluded, how-
    ever, that the DOT did not improperly segment the projects because
    the Eastern Connector had independent utility and logical termini and,
    thus, was properly treated as a separate project from the Outer Loop
    and the Pine Log project.6 The magistrate judge also concluded that
    the EA for the Eastern Connector project adequately addressed air
    quality and induced growth impacts for the project; that the EA for
    the Eastern Connector project adequately considered alternatives to
    the project; that the DOT gave proper notice of the public hearing;
    and that the DOT did not act improperly by issuing its final EA on
    (2) Have independent utility or independent significance,
    i.e., be usable and be a reasonable expenditure even if no
    additional transportation improvements in the area are made;
    and
    (3) Not restrict consideration of alternatives for other reason-
    ably foreseeable transportation improvements.
    6
    It was likewise not improper for the DOT to segment the Pine Log
    project from the Eastern Connector project and the Outer Loop. It is clear
    that the widening of Pine Log Road will benefit traffic along Pine Log
    Road regardless of whether the other projects are completed. Because the
    Pine Log project merely widens a road that already exists, it is self-
    evident that the Pine Log project has independent utility beyond its con-
    nection to other projects.
    10                 WILDS v. SOUTH CAROLINA DOT
    the same day as the FONSI because, among other reasons, the DOT
    had issued its draft EA over a year before issuance of the FONSI.
    We have reviewed the record, briefs, and pertinent case law on this
    matter, and we have had the benefit of oral argument. Our careful
    review persuades us that the rulings of the district court were correct.
    See Wilds v. Slater, No. 3:97-1608-19BD (D. S.C. April 19, 2000).
    Accordingly, we affirm the judgment of the district court.
    AFFIRMED