RCSH Operations, LLC v. Third Crystal Park Associates Ltd. Partnership , 115 F. App'x 621 ( 2004 )


Menu:
  •                              UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 02-2324
    RCSH OPERATIONS, L.L.C., a Louisiana Limited
    Liability Company,
    Plaintiff - Appellant,
    versus
    THIRD   CRYSTAL   PARK   ASSOCIATES   LIMITED
    PARTNERSHIP, a Virginia Limited Partnership;
    CHARLES E. SMITH MANAGEMENT, INCORPORATED, a
    District of Columbia Corporation; CESC PARK
    THREE LAND, LLC, a Virginia Limited Liability
    Company; CESC PARK THREE MANAGER, LLC, a
    Virginia Limited Liability Company,
    Defendants - Appellees.
    Appeal from the United States District Court for the Eastern
    District of Virginia, at Alexandria. Gerald Bruce Lee, District
    Judge; T. S. Ellis, III, District Judge. (CA-02-173-A)
    Argued:   October 30, 2003              Decided:     November 16, 2004
    Before WILKINSON and TRAXLER, Circuit Judges, and Robert E. PAYNE,
    United States District Judge for the Eastern District of Virginia,
    sitting by designation.
    Affirmed by unpublished per curiam opinion.
    ARGUED: Vernon Webster Johnson, III, JACKSON & CAMPBELL, P.C.,
    Washington, D.C., for Appellant.   John Henry Carstens, JORDAN,
    COYNE & SAVITS, L.L.P., Fairfax, Virginia, for Appellees.    ON
    BRIEF: Russell S. Drazin, JACKSON & CAMPBELL, P.C., Washington,
    D.C., for Appellant. Melissa A. Zeller, JORDAN, COYNE & SAVITS,
    L.L.P., Fairfax, Virginia, for Appellees.
    Unpublished opinions are not binding precedent in this circuit.
    See Local Rule 36(c).
    2
    PER CURIAM:
    RCSH Operations, L.L.C. (“RCSH”) appeals from an award of
    summary judgment dismissing its breach of contract and negligence
    claims    against    the    defendants,       Third    Crystal    Park   Associates
    Limited Partnership (“TCP”), Charles E. Smith Management, Inc.,
    CESC Park Three Land, LLC, and CESC Park Three Manager, LLC, and
    from a judgment, following a bench trial, in favor of TCP on its
    counterclaim against RCSH for breach of contract.                 For the reasons
    set forth below, we affirm both the entry of summary judgment in
    TCP’s favor on RCSH’s claims and the entry of judgment in favor of
    TCP on its counterclaim.
    I.
    In   1993,     TCP    and   Prime   L.L.C.       (“Prime”)   entered   into   a
    commercial lease agreement (the “Lease”) by which Prime leased
    space on the eleventh floor of a building owned by TCP.                   From then
    until August 1998, Prime operated a franchised Ruth’s Chris Steak
    House restaurant in the leased premises.1                  In August 1998, the
    franchise restaurant was purchased from Prime by Ruth’s Chris Steak
    House #28, Inc. (“RC #28"), a corporate subsidiary of Ruth U.
    Fertel, Inc., then the parent corporation of the Ruth’s Chris Steak
    House organization. Also, in August 1998, RC #28 assumed the Lease
    1
    Before Prime leased the premises for use as a Ruth’s Chris
    restaurant, the premises had previously been leased to another
    entity for use as a restaurant.
    3
    from Prime and thereafter operated the Ruth’s Chris restaurant
    under the Lease until March 2001 when RC #28 was merged into RCSH,
    which assumed the Lease.   Pursuant to   the merger agreement, RC #28
    ceased to exist.
    This action arises out of plumbing problems at the restaurant
    in 1999 while RC #28 was the tenant.     The principal drain line for
    the restaurant is a five inch drain (the “5" line”) that runs
    vertically and horizontally in a zig-zag pattern as it wends its
    way down and across the building from the eleventh floor to the
    sewer connection that is located in the basement.     The 5" line and
    other drains in the restaurant that lead to the 5" line, became
    clogged, resulting in flooding on the eleventh floor and four
    lower floors in the building.    The restaurant was damaged and so
    too were an adjacent tenancy on the eleventh floor, as well as
    other tenancies on the first, second, third and fifth floors.
    Extensive cleaning and repair of the restaurant was required and,
    while that was underway, the restaurant was closed.     According to
    the complaint, RC #28 incurred approximately $355,000 in direct
    repair costs, and it suffered approximately $1.15 million in lost
    profits while the restaurant was closed from January 3, 2000 to
    April 3, 2000.
    TCP also incurred expenses in its emergency response to the
    flooding in the restaurant, in the adjacent tenancy on the eleventh
    floor, and in the tenancies on the four lower floors.       TCP also
    4
    incurred expenses to repair flood damage to the restaurant and
    other tenant spaces.        According to TCP, it paid $110,372.14 to
    various contractors and its property manager in order to respond to
    the emergency and to remedy the damage caused by the flooding.
    Although RC #28 was the tenant at the time of the flooding in
    the summer of 1999, it ceased to exist after its merger into RCSH
    in 2001 and thus RCSH instituted this action, as RC #28's successor
    in interest.   The complaint asserted claims for breach of contract
    (Count   I),   negligence    (Count   II),   and   conspiracy    to   injure
    another’s trade reputation and business (Count III).            TCP filed a
    counterclaim against RCSH, seeking to recover the expense that it
    had incurred in responding to the emergency and in repairing damage
    to the other tenancies and the drain lines.
    Count III was dismissed early in the proceedings, and it is
    not at issue in this appeal.     Following the close of discovery, the
    district court granted summary judgment in favor of all defendants
    against RCSH on its breach of contract and negligence claims.
    Thereafter, a pretrial conference was held and the case was set for
    jury trial. Approximately a week later, TCP moved to strike RCSH’s
    request for a jury trial on the ground that the parties had waived
    their right to jury trial under Section 47 of the Lease.                 The
    district court granted that motion, and TCP’s counterclaim was
    5
    tried to the court sitting without a jury, after which a judgment
    was entered in TCP’s favor in the amount of $110,372.14.2
    II.
    We review de novo the district court’s grant of summary
    judgment, Inova Alexandria Hosp. V. Shalala, 
    244 F.3d 342
    , 349 (4th
    Cir. 2001).       That includes a de novo assessment of the legal issue
    whether the Lease was ambiguous.          Moore Bros. Co. V. Brown & Root,
    Inc., 
    207 F.3d 717
    , 722 (4th Cir. 2000).
    Section 7 of the Lease, “REPAIRS AND MAINTENANCE,” provides,
    in pertinent part, that the “[t]enant shall at its own expense make
    all repairs to the interior of the Demised Premises. . . .”           (JA
    67).       Section 49, entitled “TENANT REPAIRS AND MAINTENANCE” amends
    Section 7, by inserting immediately after the foregoing quoted
    text, the provision that: “[t]enant shall also maintain and repair
    all drain lines, grease traps, conduits, ducts and other facilities
    in the Building which are dedicated to serving the equipment in the
    Demised Premises.”3       (JA 85).
    2
    United States District Judge Gerald Bruce Lee decided the
    summary judgment motions and the motion to strike RCSH’s demand for
    jury trial. United States District Judge T.S. Ellis, III tried the
    counterclaim and entered judgment on it.
    3
    Section 49 adds several other provisions for insertion into
    Section 7 at this point, but none of them are pertinent to
    resolution of the issues presented in this appeal.
    6
    In 1999, the 5" line and other drain lines that connected to
    it became clogged.         Those lines were dedicated solely to service
    the restaurant. The 5" line received kitchen waste and sewage from
    the bathrooms in the restaurant and then carried the combined
    waste through the building to the county’s sewer line with which
    the 5" line connected at the garage level of the TCP building.
    The    record    also   reflects   that,   in   1995,   when   Prime   was
    operating a franchised Ruth’s Chris Steak House restaurant in the
    leased premises, the restaurant experienced two flooding problems
    in the 5" line and that, consequently, an outside plumbing company
    was called upon to unclog the drain lines.              The plumbing company
    used electrical “snaking” equipment and completely cleared the
    line.        Also, in 1995, the plumbing company installed special
    “clean-outs” so that future maintenance of the line would be
    easier, and advised that the 5" line should be “snaked” regularly.
    Roger    Pastore,    an     experienced   restaurant    manager,   became
    general manager of the restaurant in January 1997, and he was aware
    of the need to maintain the drain lines that served the restaurant.
    In fact, in 1997, TCP’s property management company reminded
    Pastore that maintenance of the 5" line was the restaurant’s
    responsibility under the Lease, (JA 517; 266), and Pastore passed
    this    along   to     corporate    headquarters.      The   plumber,   who   had
    “snaked” the line in 1995, returned to clean the line in the summer
    of 1997.      He observed that the condition of the 5" line was worse
    7
    than it had been in 1995 and concluded that the line did not appear
    to have been cleaned since 1995.         Nonetheless, and notwithstanding
    that the line was completely clogged, the plumber, using the same
    procedure followed in 1995, was able to clear out the entire line
    once again.   From the record, it appears that no “snaking” or other
    cleaning was performed between the summer of 1997 and the summer of
    1999 when the flooding that gave rise to this action occurred.
    The district court held that the applicable provisions of the
    Lease (Sections 7 and 49) unambiguously placed responsibility for
    maintaining and repairing the drain pipes on the tenant.               Finding
    no dispute respecting whether the 5" line and the connected lines
    served only the restaurant, and rejecting the contention of RCSH
    that the language at issue was ambiguous, the district court held
    that, “because the only reasonable construction and the plain and
    unambiguous meaning of Paragraph 49 allocates the maintenance and
    repair   responsibilities     of   the   drain   lines    at   issue   to   the
    Plaintiff-Tenant, Defendants had no obligation to maintain the
    drain lines and therefore did not breach the [Lease].”             (JA 335).
    As it did in the district court, RCSH argues here that Section
    49 is ambiguous because it does not define the term “equipment.”
    From   that   point   of   departure,     RCSH   argues   that   the   toilet
    facilities which drain into the 5" line were, under property law,
    generally regarded as “improvements,” not “equipment,” and that,
    8
    therefore, the 5" line at issue was not “dedicated to serving the
    equipment in the Demised Premises.”
    Mindful that the undisputed record was that the sewage from
    the toilets in the restaurant and the waste from the kitchen both
    are carried away from the restaurant by the 5" line and that the 5"
    line and the connected lines served only the restaurant, the
    district court rejected RCSH’s argument because:
    The five inch drain line at issue served only
    the Plaintiff-Tenant’s restaurant.    Reading
    the Lease as a whole, the only logical
    construction of Paragraph 49 is that the
    tenant is responsible for maintenance of the
    drains and drain lines that serve the
    restaurant’s equipment but do not serve the
    equipment of other tenants.       Plaintiff’s
    construction of Paragraph 49 would read the
    ‘drain line . . . dedicated to serving the
    equipment in the Demised Premises’ language
    right out of the [Lease].
    We agree with the district court that the Lease does not make a
    property    law-based    distinction   between     “equipment”    and
    “improvements.”     Instead, given its plain meaning, the text of
    Section 49 simply obligates the tenant to maintain and repair those
    drain lines that serve its facilities, as opposed to the facilities
    of other tenants.   We also agree that RCSH’s interpretation of the
    Lease is so cramped as to render Section 49, an important part of
    the Lease, a nullity.
    In this diversity case, the district court was obligated to
    apply the law of Virginia, the forum state.      The Supreme Court of
    Virginia has spoken to the issues here presented in TM Delmarva
    9
    Power, L.L.C. v. NCP of Va., L.L.C., 
    557 S.E.2d 199
    , 200 (Va. 2002)
    wherein the court held that:
    A contract is not ambiguous merely because the
    parties disagree as to the meaning of the
    terms used.   Furthermore, contracts must be
    considered as a whole ‘without giving emphasis
    to isolated terms.’      Finally, no word or
    clause in a contract will be treated as
    meaningless if a reasonable meaning can be
    given to it, and the parties are presumed not
    to have included needless words in the
    contract.
    Id. at 200 (citations omitted).        The attempt of RCSH to create
    ambiguity in the Lease runs afoul of these basic precepts because
    it wrenches the words “dedicated” and “equipment” out of their
    context and, in so doing, treats what is a highly relevant contract
    amendment as devoid of purpose.
    For the foregoing reasons, we affirm the decision of the
    district court to grant summary judgment on Count I, RCSH’s breach
    of contract claim.4
    4
    RCSH alleged that there was an oral agreement in 1997,
    pursuant to which RCSH agreed to increase the frequency of its
    maintenance of the 5" line to twice annual cleanings and the
    defendant, TCP, agreed to pay for property damage associated with
    the flooding of the 5" line. This alleged oral modification of the
    Lease is barred by the provision of the Lease in Section 24 which
    prohibits modification of the Lease except “in writing, signed by
    the parties hereto.” The district court properly applied Section
    24 to bar any oral modification of the Lease.
    10
    III.
    The district court also granted summary judgment on RCSH’s
    negligence claim which was predicated on the theory that the
    defendants owed a number of common law duties not governed “solely
    by virtue of the contractual relationships between the parties,”
    which the defendants negligently failed to fulfill. (JA 19) In the
    view of RCSH, “[t]he       leakage, flooding and related damage to the
    Restaurant   would   not    have   occurred   but   for   the   Defendants’
    negligent failure to ‘fulfill’ the duties.”           The district court
    rejected that contention, holding that:
    Plaintiff’s negligence claim fails for one
    simple reason.    Though Plaintiff argues at
    great   length   that   Virginia   and   other
    jurisdictions recognize common law duties in
    some cases where a commercial lease exists, it
    fails to set forth any evidence showing a
    specific common law duty that the Defendants
    breached in this case.
    (JA 337)
    It is true that, in the complaint, RCSH cataloged ten duties
    which the defendants supposedly had breached. However, by the time
    of summary judgment, none of those duties was tethered to any
    factual base other than the maintenance of the 5" line and the
    lines connected to it which, as outlined in Section II above, was
    a duty that, by contract, the parties had allocated to the tenant.
    Thus, after discovery, and at the time of summary judgment, the
    negligence claim was nothing more than a recasting of the breach of
    contract claim in negligence terms.           And, the only duty that
    11
    allegedly was breached by the defendants was the putative duty to
    maintain the 5" line and the connected lines.
    Although, under Virginia law, a negligence claim conceivably
    can exist in tandem with a breach of contract claim, that is so
    only if the negligence claim is based on the breach of some duty
    that is independent of the contract.       A&E Supply Co. v. Nationwide
    Mutual Fire Ins. Co., 
    798 F.2d 669
    , 671-72 (4th Cir. 1986) (citing
    Kamlar Corp. V. Haley, 
    229 S.E.2d 514
    , 517 (Va. 1983)).         It is the
    responsibility of the nonmoving party to identify the existence of
    a specific, independent duty that was breached.           As the district
    court correctly held, RCSH failed to discharge that fundamental
    responsibility demanded of it by now well-settled summary judgment
    jurisprudence.
    Instead, RCSH relied principally on a string of premises
    liability cases which, as the district court correctly held, had no
    applicability in this case in which the issue is: upon which party
    did the Lease place the obligation to maintain the 5" line and the
    connected drain lines that served the restaurant.              Also, RCSH
    cited:   (1)   a   number   of   inapplicable   cases   addressed   to   the
    obligation of landlords to protect business invitees from personal
    injury, a circumstance not here at issue; (2) a case decided under
    the 1974 Virginia Residential Landlord Tenant Act, a statute that
    does not apply to commercial leases (
    Va. Code Ann. §§ 55-248.2
     to
    28.40); and (3) decisions involving the Uniform Statewide Building
    12
    Code (Va. Code §§ 36-97 to 36-119.1) which, absent contractual
    provisions to the contrary, places repair and maintenance of a
    building upon the owner, a fact pattern that did not exist here.
    On the facts presented by this record, the district court correctly
    concluded that these decisions and statutes had no applicability in
    this case.
    Finally, RCSH argued that the tenant did not have access to,
    or control over, the entire length of the 5" line and that,
    therefore,      notwithstanding        the       language     of    the    Lease     that
    specifically allocated maintenance of that line to the tenant, the
    responsibility really remained with TCP.                    There are two flaws in
    that theory.      First, the record is replete with evidence that, at
    least   in   1995     and   1997,     TCP    afforded       the    tenant’s   plumbing
    contractor access to all areas necessary to clear the clogged 5"
    line from the restaurant all the way to the point where the line
    connected      with   the    sewer    (e.g.       across    and     down   the     entire
    building). Second, perhaps as a function of the foregoing, and, as
    held by the district court, “[P]laintiff does not come forward with
    any   evidence      that    Defendants       denied   access        to    Plaintiff    or
    Plaintiff’s contractor to maintain the drain line pursuant to the
    Lease.”   (JA 338).        We agree that, in opposing the entry of summary
    judgment, RCSH offered no factual support for its assertion that
    the   tenant    was   denied    the    access      necessary       to    discharge    the
    13
    maintenance obligation imposed on it by Sections 7 and 49 of the
    Lease.5
    For the foregoing reasons, we affirm the grant of summary
    judgment on Count II, RCSH’s negligence claim.6
    IV.
    TCP filed a counterclaim against RCSH alleging that the
    failure   of   the   tenant   to   perform   inspections,   repairs   and
    maintenance necessary to keep the drain lines that were dedicated
    to serving the restaurant in good working order was a breach of the
    Lease and that, as a direct and proximate cause of the breach, the
    pipes burst, causing flooding in the building, the consequence of
    which was the damage sustained by TCP.       The counterclaim was tried
    to the district court sitting without a jury.
    To recover on its counterclaim, TCP was obligated to prove, by
    a preponderance of the evidence, that a material breach of the
    Lease on the part of the tenant was the proximate cause of the
    damage of which TCP complains.       The district court held that TCP
    5
    RCSH also seems to argue that RC #28, the tenant, was
    unaware of the existence of some of the connected lines. That, of
    course, is no excuse because the Lease requires the tenant to
    maintain and repair all drains dedicated to serving the leased
    premises.
    6
    Given this resolution, it is unnecessary to address TCP’s
    argument that the negligence claim fails under Virginia’s economic
    loss rule.
    14
    had met its burden and entered judgment on the counterclaim.           RCSH
    appeals from that judgment.
    We begin by noting that, as explained above in Section II, the
    Lease imposes upon the tenant the obligation to “maintain and
    repair all drain lines, grease traps, conduits, ducts and other
    facilities in the building which are dedicated to serving the
    equipment in the Demised Premises.”         The district court found, as
    facts, that the drain lines at issue were dedicated to serving the
    kitchen and bathroom facilities      in the restaurant; that the drain
    lines had not been maintained by the tenant; and that the failure
    to maintain the drain lines proximately caused the drain lines to
    rupture and to release waste and sewage into the restaurant and
    other tenant spaces.    The district court also held, as a fact, that
    TCP consequently had incurred reasonable necessary expenses in the
    amount of $110,372.14 to address the emergency flooding and to
    remediate the damage caused by the tenant’s breach of the Lease.
    RCSH presents four reasons why the district court’s entry of
    judgment in favor of TCP on the counterclaim was error.                    We
    consider each in turn.
    A.    The Assumption and Assignment Agreement
    The   district   court   held   that   RCSH   was   the   successor   in
    interest to RC #28 and thus was liable by virtue of Sections 19 and
    34.2 of the Lease for the acts and omissions of RC #28 while it was
    the tenant.    RCSH does not dispute that it is the successor in
    15
    interest under the Lease to RC #28.7           Nor does RCSH dispute that
    Section 19 of the Lease devolves the liabilities of RC #28 upon
    RCSH when it provides that “[a]ll rights, remedies and liabilities
    herein given to or imposed upon either of the parties hereto, shall
    extend    to    their   respective   heirs,   executors,   administrators,
    successors, and assigns.”        And, RCSH agrees that Section 34.2 of
    the Lease permits the tenant to assign its rights to:
    Ruth U. Fertel, Inc. or any entity or
    individual designed by Ruth U. Fertel, Inc.,
    so long as (1) such assignee expressly assumes
    in writing all the obligations of Tenant under
    this Lease . . . and (2) Ruth U. Fertel, Inc.
    unconditionally guarantees the obligations of
    such assignee for the balance of the term of
    this Lease (and any extensions) . . .
    (JA 76)
    It also is undisputed that, in March 2001, by virtue of an
    Assignment       and    Assumption   of    Lease   Agreement   (“Assignment
    Agreement”), RC #28 assigned its rights under the Lease to RCSH, a
    subsidiary of, and an entity that was approved by, Ruth U. Fertel,
    7
    Nor could RCSH dispute that finding, given that, in its
    complaint, RCSH affirmatively asserted that it was “successor in
    interest to [RC #28]” and that, as such, it was the proper party to
    sue on the Lease. Complaint, ¶1, (JA 13-14). Moreover, RCSH’s
    complaint also describes RC #28 as RCSH’s predecessor in interest
    which incurred the very damages (repair expense and lost profits)
    that RCSH sought to recover in its complaint.
    16
    Inc.8       Under paragraph 2 of the Assignment Agreement, RCSH, as
    assignee of RC #28:
    agrees to pay, perform and fully discharge, in
    accordance with their respective terms, the
    payment and performance, liabilities and
    obligations of Assignor [RC #28] arising out
    of the Lease after the date hereof. Assignee
    does not assume or agree to pay any
    liabilities or obligations under the Lease
    arising prior to the date hereof.
    (JA 105).        Acting through its property manager, TCP consented to
    the assignment.         (JA 108)
    According to RCSH, TCP waived the rights it had under Sections
    19 and 34.2 of the Lease to recover from RCSH, as successor in
    interest to RC #28, for any breach of the Lease by RC #28 because
    TCP consented to the Assignment Agreement which provided that RCSH
    did “not assume or agree to pay any liabilities obligations under
    the Lease arising prior to the date hereof.”                  The district court
    rejected RCSH’s waiver argument for a number of reasons, (JA 1267-
    74) the first of which was that RCSH did not plead the affirmative
    defense of waiver in its answer to the counterclaim.                   (JA 1270)
    Under    Fed.   R.   Civ.   P.   8(c),   “a   party    shall    set   forth
    affirmatively . . . waiver, and any other matter constituting an
    avoidance or affirmative defense.” It is settled that a failure to
    raise an affirmative defense in the appropriate pleading results in
    8
    By the time of the Assignment Agreement, Ruth U. Fertel,
    Inc. had become Ruth’s Chris Steak House, Inc., and RCSH was a
    wholly owned subsidiary of that entity. (JA 105-111).
    17
    the loss of that defense.   Brinkley v. Harbor Recreation Club, 
    180 F.3d 598
    , 612 (4th Cir. 1999); Peterson v. Air Line Pilots Assoc.
    Intl, 
    795 F.2d 1161
    , 1164 (4th Cir. 1985).    It is beyond question
    that RCSH did not plead in its answer to the counterclaim, waiver,
    by virtue of paragraph 2 of the Assignment Agreement or otherwise.9
    However, even if a party fails to plead an affirmative defense, the
    opposing party still must show “prejudice or unfair surprise”
    before the waiver will be enforced.   Brinkley v. Harbor Recreation
    Club, 180 F.3d at 612; Peterson v. Air Line Pilots Assoc. Intl, 759
    F.2d at 1164.   The district court held that TCP was prejudiced
    because the failure of RCSH to plead the waiver defense disabled
    TCP from discovering, or presenting evidence about, the topic of
    waiver.
    The record does not show exactly when the issue of waiver
    first surfaced, but it clearly was not pleaded as an affirmative
    defense to the counterclaim.   The first mention of the topic in the
    record was in the proposed findings of fact and conclusions of law
    that both parties filed on Friday, August 23, 2002, two days before
    the trial began on Monday, August 26, 2002.   (JA 340-357).   On the
    morning of trial, TCP took the position that waiver had not been
    9
    Because the assignment provision contradicts the Lease and
    was not accompanied by consideration that would be necessary to
    effect a modification of the Lease, the consent to the Assignment
    Agreement, including paragraph 2, is properly categorized as a
    waiver of Sections 19 and 34.2 of the Lease. RCSH does not contest
    that characterization.
    18
    pleaded as an affirmative defense.             (JA 673-74).       RCSH did not
    contend   otherwise,    and,    although,     in    opening   statement,   RCSH
    pointed to paragraph 2 of the Assignment Agreement, it did so in
    context of discussing the topic of successor liability, not the
    topic of a waiver of the provisions of Sections 19 and 34.2 of the
    Lease (JA 687-89).     And, even then RCSH’s counsel stated that the
    successor   liability    issue       had    “just   come   up.”     (JA    689).
    Nonetheless, in its post-trial brief in support of a motion for a
    judgment as a matter of law, RCSH argued that paragraph 2 of the
    Assignment Agreement was a contractual waiver that foreclosed
    imposition of liability on RCSH as a successor in interest under
    the Lease provisions.          (JA    1093-94).      And, in its post-trial
    brief, TCP continued to press the point that RCSH had not pleaded
    waiver as an affirmative defense.           (JA 1110-12; 1133-37).
    The district court held that the waiver defense had not been
    pleaded and that TCP had been prejudiced by the failure to plead
    it.   In so doing, the district court held: (1) that “TCP did not
    have . . . fair warning that it was going to have to confront a
    waiver, a timely waiver defense. . . . (JA 1271); and (2) that, if
    it had received notice of the waiver defense, TCP would have
    presented two exhibits that “strike, I think, a fatal blow to a
    waiver claim, both on prejudice grounds and on other grounds.” (JA
    1271).
    19
    That reference was to a letter that attended TCP’s consent to
    the Assignment Agreement.   Both documents refuted paragraph 2 of
    the Assignment Agreement.   The letter, which was addressed to TCP,
    stated that:
    The purpose of this letter is to advise
    that Ruth U. Fertel, Inc. The parent company
    and sole shareholder of Ruth’s Chris Steak
    House #28, Inc. (“Tenant”), has changed its
    name to ‘Ruth’s Chris Steak House, Inc.’ The
    name change of Ruth U. Fertel, Inc. to Ruth’s
    Chris Steak House, Inc. is nominal and
    cosmetic only, and the ownership of Ruth U.
    Fertel, Inc. and the Tenant is not changing in
    any way whatsoever.
    In addition, all of the wholly owned
    subsidiaries of Ruth’s Chris Steak House, Inc.
    (formerly Ruth U. Fertel, Inc.) are being
    restructured    and   merged   for    internal
    operational purposes only.    As a result of
    this restructuring, the Tenant, Ruth’s Chris
    Steak House #28, Inc., will be merged with
    several other wholly owned subsidiaries of the
    parent into the newly created Louisiana
    limited liability company known as ‘RCSH
    Operations, LLC.’ The sole owner, member and
    manager of RCSH Operations, LLC is Ruth’s
    Chris Steak House, Inc. (formerly Ruth U.
    Fertel, Inc).
    As an accommodation to Tenant and Ruth’s
    Chris Steak House, Inc. (formerly Ruth U.
    Fertel, Inc.) and in light of our good working
    relationship,    we    ask   that    you,   as
    ‘Landlor/Intervenor,’ execute the attached
    Assignment and Assumption of Lease Agreement
    acknowledging the restructuring and renaming
    of Tenant to RCSH Operations, LLC; and the
    Assignment    of    Tenant’s   interests   and
    obligations in the Lease to RCSH Operations,
    LLC.
    20
    (JA   1141)   emphasis   added.   The    merger   agreement        explicitly
    provided, in paragraph 2.05, that RCSH “shall be responsible for
    all of the liabilities and obligations of” RC #28.           (JA    1147).
    The district court held that, if waiver by virtue of paragraph
    2 of the Assignment Agreement had been pleaded, TCP could have
    introduced    evidence   respecting    the   letter   from   RCSH     to   TCP
    explaining that the change in corporate structure was a cosmetic
    one, that ownership of the restaurant would remain the same, and
    that the tenant would be not changing in any way.        Also, TCP could
    have shown that RC #28 would be merged into the newly created RCSH
    and that this merger was occurring “for internal purposes only.”
    Further, TCP could have offered evidence that the merger agreement
    provided that RC #28 would cease to exist and that the surviving
    company, RCSH, would “be responsible for all of the liabilities and
    obligations of corporation A [RC #28].”
    That kind of evidence would have been highly probative of the
    effect, if any, of TCP’s consent to the Assignment Agreement and
    the effect, if any, of paragraph 2 of the Assignment Agreement on
    the provisions of Sections 19 and 34.2 of the Lease.          Undoubtedly,
    the failure to plead waiver as an affirmative defense prejudiced
    TCP because TCP did not pursue in discovery, and thus did not offer
    at trial, proof that the consent to the Assignment Agreement did
    21
    not have the effect of waiving Sections 19 and 34.2 of the Lease.10
    And, of course, significant evidence of that sort was available, so
    that the waiver issue, had it been pleaded, could have been
    explored in discovery and at trial.
    It is no answer to say, as does RCSH, that TCP had possession
    of these two documents before the litigation began and thus could
    have anticipated the defense of waiver.    Rule 8(c) imposed on RCSH
    the obligation to plead the waiver defense so that it could be
    addressed in discovery and at trial.   It is precisely the sort of
    procedural gamesmanship raised by the circumstances presented here
    that Rule 8(c) is intended to foreclose.   Thus, we find no error in
    the district court’s rejection of RCSH’s waiver defense.11
    10
    The district court also held that the two documents (which
    were not permitted in evidence), along with other testimony would
    call into play the rule, well-settled under Virginia law, that RCSH
    was a mere continuation of RC #28 and thus would be liable as a
    successor under any circumstances. It is unnecessary to address
    this issue given the fact that RCSH did not plead the affirmative
    defense of waiver as required by Rule 8(c) and because the district
    court was clearly correct in finding that TCP was prejudiced by the
    belated raising of that defense.
    11
    On appeal, as it did below, RCSH makes a pass at casting the
    waiver defense as a question of successor liability.       However,
    given its own pleadings, RCSH cannot be heard to assert that it is
    not RCSH’s successor in interest. Thus, it must stand or fall on
    the waiver defense.
    The district court, alternatively, held: (1) that if the
    letter and the merger agreement had been admitted, they would
    defeat the waiver defense on its merits; and (2) that RCSH did not
    prove waiver by clear and convincing evidence. We need not address
    either alternative holding.
    22
    B.     TCP’s Rule 26(a)(1) Disclosure Respecting Damages
    In the initial disclosure of its damages made under Rule
    26(a)(1), TCP disclosed damages in the amount of $78,346.87.             The
    proof at trial showed damages of $110,372.14 which, of course, was
    the amount of the judgment.          RCSH argued that TCP should be
    foreclosed from proving the greater sum because it varied from the
    amount of damages set out in TCP’s initial pretrial disclosure.
    The district court rejected that argument, holding that:
    There is no showing on this record of any
    prejudice that results from the difference . .
    . . In fact, as I see the discovery, these
    documents were made available, and it was gone
    through in some detail.
    (JA 1279).    We review that decision for abuse of discretion.
    Although RCSH continues on appeal to assert that there was a
    difference between the initial disclosure and the sum proved at
    trial, it does not contend that the district court erred in finding
    that the greater sum was disclosed in discovery and “gone through
    in some detail.”12         The mere fact that the damage claim was
    increased    after   the   initial   disclosure   does   not   operate    to
    foreclose proof of the greater amount where, as the district court
    held, the greater amount was the subject of discovery.            Indeed,
    Rule 26(a)(1) contemplates that the initial disclosure will be
    12
    The higher sum also appeared in TCP’s proposed findings of
    fact and conclusions of law filed on the Friday before trial.
    That, however, was not a basis for the district court’s finding
    respecting supplemental disclosure on TCP’s damages.
    23
    based on information available at the time of disclosure.     And,
    Rule 26(e) requires that initial disclosures be supplemented.
    Considering this record, the district court’s findings respecting
    supplemental disclosure, and the provisions of Rule 26(a)(1) and
    Rule 26(e), we find no abuse of discretion in the district court’s
    decision to allow proof of the larger damage sum.
    C.   Sufficiency of Proof: Causation
    RCSH contends that there was insufficient proof that the
    breach of the Lease was the proximate cause of the damages claimed
    by TCP.   Findings of proximate cause, usually described as mixed
    questions of law and fact, are to be reviewed for clear error
    pursuant to Fed. R. Civ. P. 52(a).    Exxon Co., U.S.A. v. Sofec,
    Inc., 830, 840-41 (1996); Cohen v. Boxberger, 
    544 F.2d 701
    , 704
    (4th Cir. 1976).13
    The district court’s findings on causation were articulated in
    great detail (JA 1255-58; 1263-66).      Measuring those findings
    13
    Most of our sister circuits adhere to this rule. Childress
    & Davis, Federal Standards of Review, § 2.28 (3d ed. 1999); Wright
    & Miller, Federal Practices and Procedure Civil, § 2589 (1995).
    One treatise points out that some of our decisions between 1966 and
    1983 appear to have departed from it (and employed a freely
    reviewable standard), Wright & Miller, Federal Practice and
    Procedure Civil, § 2589 (1995), but that we returned to it in 1983.
    Id.; Bonds v. Mortensen, 
    717 F.2d 123
    , 125 (4th Cir. 1983).
    Whatever may be said of this history, the Supreme Court, in 1996,
    seems to have settled the matter in favor of application of the
    clearly erroneous standard to the review of findings of proximate
    cause.   Exxon Co., U.S.A. v. Sofec, Inc., 
    517 U.S. 830
    , 840-41
    (1996) (“issues of proximate causation and superseding cause
    involve application of law to fact, which is left to the factfinder
    subject to limited review.”).
    24
    against the record as a whole, we find no error in the district
    court’s finding that the breach of the Lease obligation to maintain
    and repair the drain lines proximately caused the loss for which
    TCP sought redress in its counterclaim.
    D.    Sufficiency of Proof: Damages
    There was fulsome proof that the damages were incurred in the
    amounts   claimed   and   that   they   were   of   the   sort   that   were
    compensable for the breach of the Lease.            The challenge to the
    sufficiency of the proof made by RCSH is that the witnesses who
    were offered to prove TCP’s damages were not from TCP, but from its
    property manager.    Thus, says RCSH, there was no proof that TCP
    actually paid the bills that were admitted to support its damage
    claim.    The sufficiency of proof of damages is a fact issue which
    we review for clear error.14     Having done that and considering the
    record as a whole, we are satisfied that the district court did not
    err in finding that the proof was sufficient to support the award
    of damages in the amount claimed.
    V.
    RCSH argues that the district court erred in striking its
    demand for jury trial.      This issue comes to us as a request to
    direct a jury trial on remand.      Because of the disposition of the
    14
    Scott v. Vandiver, 
    476 F.2d 238
     (4th Cir. 1976); Childress
    & Davis, Federal Standards of Review, § 2.22 (3d ed. 1999).
    25
    foregoing issues, there will be no remand.             And, it is unclear from
    RCSH’s brief whether it even asserts error in the decision to
    strike the jury demand as to TCP’s counterclaim.15                   Assuming,
    however, that RCSH is pressing that issue, we will address it.
    In its complaint, RCSH asked for trial by jury.               Neither the
    answer nor the counterclaim contained any such request nor did the
    reply     to    the   counterclaim.        At   the     pretrial   conference,
    approximately five weeks before the commencement of trial, the case
    for set for a jury trial.       On July 25, 2002, seven days after the
    pretrial conference, TCP moved to strike RCSH’s jury demand,
    asserting as the ground therefor, the terms of Section 47 of the
    Lease which provides that:
    landlord and Tenant hereby expressly waive
    trial by jury in any action, proceeding or
    counterclaim brought by either of them against
    the other, on any matter whatsoever arising
    out or in any way connected this Lease, their
    relationship as landlord and Tenant, Tenant’s
    use and occupancy of the Demised Premises
    and/or any claim of any injury or damage.
    The district court held that the waiver of jury trial meant
    precisely what it said and enforced it.               We see no error in that
    decision.
    15
    In its opening brief, RCSH states: “[t]hus, on remand, this
    Court should direct that in at least the further proceedings as to
    [naming all defendants other than TCP], RCSH is entitled to a jury
    trial.” The issue is not addressed in RCSH’s reply brief.
    26
    VI.
    For the foregoing reasons, the judgment of the district court
    granting summary judgment on the claims of RCSH is affirmed, and
    the judgment of the district court awarding damages to TCP in the
    amount of $110,372.14 is affirmed.
    AFFIRMED
    27