Brown & Pipkins, LLC v. Service Employees International Union, Local 32BJ ( 2017 )


Menu:
  •                                     PUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 15-1931
    BROWN & PIPKINS, LLC, d/b/a Acsential Services,
    Plaintiff – Appellant,
    v.
    SERVICE EMPLOYEES INTERNATIONAL UNION, LOCAL 32BJ,
    Defendant – Appellee.
    No. 15-1987
    BROWN & PIPKINS, LLC, d/b/a Acsential Services,
    Plaintiff – Appellee,
    v.
    SERVICE EMPLOYEES INTERNATIONAL UNION, LOCAL 32BJ,
    Defendant – Appellant.
    Appeals from the United States District Court for the Eastern District of Virginia, at
    Alexandria. Claude M. Hilton, Senior District Judge. (1:15−cv−00526−CMH−TCB)
    Argued: October 26, 2016                                   Decided: January 23, 2017
    Before KING, KEENAN, and DIAZ, Circuit Judges.
    Affirmed by published opinion. Judge Diaz wrote the opinion, in which Judge King and
    Judge Keenan joined.
    ARGUED: Stephen Gregory Joy, SMITH, CURRIE & HANCOCK LLP, Washington,
    D.C., for Appellant/Cross-Appellee. Andrew Lee Strom, SEIU, LOCAL 32BJ, New
    York, New York, for Appellee/Cross-Appellant. ON BRIEF: Stephen J. Kelleher,
    SMITH, CURRIE & HANCOCK LLP, Washington, D.C., for Appellant/Cross-Appellee.
    2
    DIAZ, Circuit Judge:
    Brown & Pipkins, LLC, doing business as Acsential Services (“B&P”) appeals the
    district court’s confirmation of four labor arbitration awards, and Service Employees
    International Union, Local 32BJ cross-appeals for attorneys’ fees after the district court
    failed to address its entitlement to fees. We affirm the confirmation of the arbitration
    awards, based in large part upon the limited scope of our review of a labor-arbitration
    decision pursuant to a collective bargaining agreement (a “CBA”), and hold that the
    Union waived its claim for attorneys’ fees by not complying with Federal Rule of Civil
    Procedure 54.
    I.
    A.
    In September 2012, B&P began providing janitorial services for the Department of
    the Army at Fort Belvoir in Fairfax County, Virginia. Janitorial employees worked
    without a CBA until May 17, 2013, when B&P and the Union signed a CBA which
    recognized the Union as the exclusive bargaining representative for B&P’s janitorial
    employees at Fort Belvoir. The CBA was retroactive to September 4, 2012.
    In the spring and summer of 2013, the Union filed notices that it intended to
    arbitrate four separate grievances with B&P related to alleged violations of the CBA.
    The parties chose Arbitrator Garvin Lee Oliver to hear each grievance, and no transcripts
    were taken at the hearings.       We describe relevant parts of the grievances and
    corresponding arbitration awards seriatim.
    3
    1.
    On May 29, 2013, the Union filed a grievance alleging that B&P violated the CBA
    by reducing the full-time work schedule from 40 to 35 hours per week on January 16,
    2013. The Shop Steward spoke with B&P management about the reduction in hours on
    the same day that B&P announced the change, but B&P would not recognize the Union
    or discuss grievance issues. B&P claimed that it cut employees’ hours as a result of a
    decision by the Army to decrease funding for the B&P contract from approximately
    $177,903 per month to approximately $154,500 per month.
    The arbitrator granted the grievance in part and issued what we refer to as the
    Hours Reduction Award. In granting the grievance, the arbitrator weighed conflicting
    provisions in the CBA. Article 3 of the CBA, titled “Management Rights,” comprises
    three Sections which, in sweeping language, vest certain “rights, prerogatives, and
    functions” in B&P. J.A. 261. Relevant here, Article 3, Section 2 reserves to B&P the
    right to “adjust schedules of work and work assignments based on its judgment of
    business requirements,” and Article 3, Section 3 provides that “[s]uch managerial right[s]
    shall not be the subject of any provision of the Agreement or of mandatory bargaining
    between” B&P and the Union. J.A. 261. But Article 6 of the CBA, titled “Hours of
    Work,” also addresses the scheduling of work.        Article 6, Section 1 provides: “An
    employee who is regularly schedule[d] for thirty five (35) hours or more per week shall
    be consider[ed] full time. The workweek for all full time employees shall be 40 hours
    per week, 8 hours per day, Monday through Friday.” J.A. 263.
    4
    The arbitrator reconciled these provisions by reasoning that “Article [3],
    Sections 2 and 3 gave [B&P] the general right to schedule work . . . but Article 6,
    Section 1 impliedly restricted [B&P’s] right to schedule work relating to the duration of
    work for full time employees.” J.A. 48. Accordingly, the arbitrator held that B&P
    “violated Article 6, Section 1 of the [CBA] on January 16, 2013 when it reduced the work
    day by one hour for all janitorial full time employees.” J.A. 48.
    The arbitrator also rejected B&P’s argument that the grievance was procedurally
    defective because the Union failed to comply with the CBA’s Grievance and Arbitration
    Procedure.     Article 11, Section 2 of the CBA splits the Grievance and Arbitration
    Procedure into three Steps, relevant parts of which we reproduce here:
    Step 1[:] The Shop Steward must discuss the grievance with the
    project manager within three (3) days of the incident. [B&P] shall render a
    decision in writing within twenty-four (24) hours after the conclusion of
    Step 1.
    ....
    Step 3: Arbitration: . . . .
    ....
    The Arbitrator shall have jurisdiction and authority to apply,
    interpret and determine compliance with the terms of this Agreement, but in
    no case add to, deviate from, detract from or alter in any way the provision
    of the Agreement.
    J.A. 266–67.
    The arbitrator began by noting that the Union had failed to abide by Step 1’s three-
    day limit to discuss grievances, as the parties, with B&P’s reserving its right to bring a
    timeliness challenge, “agreed to consider the [May 29, 2013] grievance initiation letter as
    [S]tep 1 of the grievance procedure.” J.A. 47. Nevertheless, the arbitrator reasoned that
    it would have been “unreasonable to require strict compliance with the time limits” in this
    5
    case. J.A. 48. In particular, the arbitrator identified two “mitigating circumstances”: (1)
    the National Labor Relations Board was “processing” a dispute between the Union and
    B&P regarding the “processing of grievances prior to the” adoption of the CBA in 2012,
    and (2) the violation was of a “continuing nature.” J.A. 47–48.
    The Hours Reduction Award orders B&P to, inter alia, restore the 40-hour
    workweek for full-time janitorial employees and pay employees for any lost hours
    incurred while the 35-hour workweek was in effect.
    2.
    On July 12, 2013, the Union filed a grievance alleging that B&P violated the CBA
    by paying two employees, Alicia Duran and Susana Cortez, at the “Custodians” rate
    instead of at the higher “Custodian/Driver” rate commensurate with their responsibilities.
    The arbitrator granted the grievance and issued what we refer to as the Drivers’ Pay
    Award.
    Article 16 of the CBA lists three wage classifications, including “Custodians” and
    “Custodian/Driver,” but does not define them other than by providing corresponding rates
    of pay. “Custodian/Drivers” are paid $0.60 more per hour than “Custodians.”
    The arbitrator traced the origins of the “Custodian/Driver” classification to a letter
    of understanding that the Union and one of B&P’s predecessors at Fort Belvoir
    negotiated in 2008. That letter of understanding provided that the predecessor would pay
    “$0.60 per paid hour more to the custodial service workers who drive our vehicles in
    order to transport workers to various sites.” J.A. 135. The arbitrator found that the letter
    of understanding was the “genesis” for, and thus informed the definition of, the
    6
    “Custodian/Driver” classification. The arbitrator noted that the rate appeared in previous
    CBAs between the Union and B&P’s predecessors, and that those predecessors had paid
    employees at that rate when they had transported workers to their worksites, brought
    equipment to their worksites, and driven to multiple locations within Fort Belvoir.
    The arbitrator then examined the type of work that B&P assigned to Duran and
    Cortez. He found that B&P assigned them to schedules that “included multiple buildings,
    some of which were far apart,” and “required [them] to alternate driving themselves and
    another custodian . . . in their own personal vehicles to the buildings they were required
    to clean.” J.A. 53. Additionally, he found that B&P required them to “carry equipment
    from the office to these buildings,” and that B&P generally refused to provide either with
    “a company car, driver’s pay, or regular gas reimbursement.” J.A. 53–54.
    Based upon the similarities between the work performed by Duran and Cortez and
    the work performed by employees whom B&P’s predecessors had paid at the
    “Custodian/Driver” rate, the arbitrator concluded that B&P violated Article 16 of the
    CBA by not paying Duran and Cortez at the higher rate. The arbitrator rejected B&P’s
    argument that, per the letter of understanding, neither employee could be characterized as
    a “Custodian/Driver” because each generally drove her own vehicle. The arbitrator
    reasoned that B&P’s predecessors had provided corporate vehicles in similar
    circumstances, and thus B&P could not escape paying the higher rate by requiring the
    employees to use their own vehicles.
    7
    The Drivers’ Pay Award ordered B&P to, inter alia, pay Duran and Cortez at the
    “Custodian/Driver” rate and provide back pay based upon an eight-hour day, pursuant to
    the Hours Reduction Award.
    3.
    The Union filed a second grievance on July 12, 2013, alleging that B&P violated
    the CBA by unreasonably denying employees’ requests for vacation time. According to
    the arbitrator, “[a]t the hearing on January 23, 2015 the parties stipulated to the issue:
    Whether custodial employees are owed unused vacation in the form of money, and what
    is the amount of accumulated vacation creditable to each employee.” J.A. 369. B&P,
    however, contends that it objected at the beginning of the hearing to recharacterizing the
    grievance from denying vacation time to withholding vacation pay, preserved its right to
    call the grievance untimely, and, rather than stipulating to the issue that the arbitrator
    described, stipulated only “that the grievance was agreed to have been presented to [it] as
    of [January 23, 2015].” J.A. 369.
    After the hearing, the parties agreed to submit the case for decision based on
    exhibits and briefs. In its brief, B&P argued, inter alia, that the vacation pay grievance
    was untimely because the Union did not present it to B&P management within three days
    of the incident giving rise to the grievance. In an interim order, the arbitrator rejected
    B&P’s timeliness argument, concluding that B&P had “waived its right to invoke the
    time limits of the [CBA] where the issue was raised for the first time after the hearing in
    which the parties stipulated to the issue in the case.”        J.A. 369.    The arbitrator
    8
    acknowledged B&P’s contention that the parties had made a different stipulation, but
    stated that he had “no recollection of [that] stipulation.” J.A. 369.
    The arbitrator subsequently granted the grievance in part and issued what we refer
    to as the Vacation Pay Award. The Vacation Pay Award ordered B&P to pay certain
    employees for accrued, unused vacation benefits and to comply with applicable
    regulations.
    4.
    On August 1, 2013, the Union filed a grievance alleging that B&P owed money to
    Maria Amaya and Ana Guerrero for 14 and 27 hours of work, respectively.             B&P
    allegedly paid each employee the amount requested in the grievance in 2014. B&P then
    allegedly paid each employee the amount requested in the grievance for a second time in
    2015, and sent purported records of those payments to the arbitrator and the Union on
    January 19, 2015. Nevertheless, the arbitrator held a hearing the next day, which only the
    Union attended.     According to B&P, it did not attend the hearing because it had
    submitted proof of payment to the arbitrator.
    The arbitrator granted the grievance and issued what we refer to as the Monies
    Owed Award. That award ordered B&P to, inter alia, pay Amaya and Guerrero for the
    number of hours specified in the grievance, with interest. The award also provided that
    B&P “shall be given credit for any back pay or other payments previously made that are
    consistent with this Award.” J.A. 155.
    In a later order, the arbitrator denied B&P’s request to “waive or reduce the fees
    for arbitration services” for the hearing. J.A. 431–34. The arbitrator noted that the
    9
    records of payment that B&P sent to him “did not indicate . . . that the case was settled,”
    and that he “could not determine from the two documents that the amounts were correct
    to cover all aspects of the grievance, including interest, etc.” J.A. 432. In March 2015,
    B&P allegedly paid each employee the interest amount contemplated in the Monies
    Owed Award.
    B.
    B&P filed a complaint in the Eastern District of Virginia seeking to vacate the
    Hours Reduction Award and the Drivers’ Pay Award. The Union filed an answer and
    counterclaim to confirm all four arbitration awards and to receive “reasonable attorneys’
    fees and costs.” J.A. 150. In a corresponding brief, the Union made its argument for
    attorneys’ fees. B&P then filed an answer—including an affirmative defense that the
    Monies Owed Award was moot—and a counterclaim-in-reply to vacate the Vacation Pay
    Award. In a corresponding brief, B&P responded to the Union’s argument for attorneys’
    fees.
    The district court confirmed all four arbitration awards. The court reasoned that
    “all of the Arbitrator’s awards arose directly from the [CBA] and his interpretation of that
    agreement,” and that “none of the[] awards were irrational or evidence manifest disregard
    of law.” J.A. 439–40. The court did not address the issue of attorneys’ fees, and the
    Union did not submit a motion for attorneys’ fees after the court entered its order.
    B&P’s appeal and the Union’s cross-appeal followed.
    10
    II.
    We address B&P’s appeal of the district court’s confirmation of the four
    arbitration awards and the Union’s cross-appeal for attorneys’ fees in turn.
    A.
    While B&P makes different arguments against confirmation for each arbitration
    award, our standard of review remains the same. This court “review[s] de novo the
    district court’s denial of a motion to vacate an arbitration award.” Jones v. Dancel, 
    792 F.3d 395
    , 401 (4th Cir. 2015). This case arises under § 301 of the Labor Management
    Relations Act, 
    29 U.S.C. § 185
    , “as the controversy involves an assertion of rights under
    an agreement between an employer and a labor organization.” Major League Baseball
    Players Ass’n v. Garvey, 
    532 U.S. 504
    , 509 (2001) (per curiam). Our review of a labor-
    arbitration decision pursuant to a CBA is “very limited”:
    Courts are not authorized to review the arbitrator’s decision on the merits
    despite allegations that the decision rests on factual errors or misinterprets
    the parties’ agreement. . . . [I]f an arbitrator is even arguably construing or
    applying the contract and acting within the scope of his authority, the fact
    that a court is convinced he committed serious error does not suffice to
    overturn his decision. It is only when the arbitrator strays from
    interpretation and application of the agreement and effectively dispenses his
    own brand of industrial justice that his decision may be unenforceable.
    When an arbitrator resolves disputes regarding the application of a contract,
    and no dishonesty is alleged, the arbitrator’s improvident, even silly,
    factfinding does not provide a basis for a reviewing court to refuse to
    enforce the award.
    
    Id.
     (internal citations and quotation marks omitted); see also PPG Indus., Inc. v. Int’l
    Chem. Workers Union Council of United Food & Commercial Workers, 
    587 F.3d 648
    ,
    652 (4th Cir. 2009) (applying the standard of review outlined in Garvey).
    11
    1.
    B&P makes two arguments for why the Hours Reduction Award should be
    vacated, and, in the alternative, an argument for why it should be modified to run from
    the date that the Union filed the grievance. We reject each argument.
    a.
    We first consider B&P’s argument for vacatur based on the arbitrator’s failure to
    sufficiently construe substantive provisions in the CBA. In particular, B&P says that the
    arbitrator “manifestly disregarded” the sweeping language in Article 3 of the CBA, which
    vests certain management rights in B&P, and exceeded his authority by using Article 6,
    Section 1 of the CBA to modify Article 3 while simultaneously disregarding the part of
    Article 6, Section 1 which authorizes a 35-hour workweek.
    Our review of the Hours Reduction Award shows that, rather than “manifestly
    disregarding” relevant portions of the CBA, the arbitrator construed that document in
    coming to his decision, which precludes vacatur on this ground. Garvey, 
    532 U.S. at 509
    ;
    see also PPG Indus., 
    587 F.3d at 653
     (reversing vacatur where arbitrator interpreted the
    CBA and characterizing company’s argument that arbitrator ignored plain language of
    the CBA as “an [impermissible] attack on the correctness of the arbitrator’s decision”).
    Specifically, the arbitrator weighed Article 3’s Management Rights provisions against the
    part of Article 6, Section 1 which provides that “[t]he workweek for all full time
    employees shall be 40 hours per week, 8 hours per day,” and concluded that the latter
    controlled because it “impliedly restricted [B&P’s] right to schedule work.” J.A. 48.
    12
    By balancing competing provisions in the CBA and coming to a conclusion, the
    arbitrator cleared the very low bar needed to insulate the award from a charge that he
    failed to construe the CBA. B&P’s arguments on this point amount to an impermissible
    attack on the correctness of the arbitrator’s decision. That is true notwithstanding the fact
    that, as B&P points out, the arbitrator failed to explicitly deal with the part of Article 6,
    Section 1 which provides that “[a]n employee who is regularly schedule[d] for thirty five
    (35) hours or more per week shall be consider[ed] full time.” J.A. 263.
    To require an arbitrator to address every single provision of any relevance
    whatsoever in a contract would be to require an arbitrator’s award to be free of
    ambiguity—a standard we have rejected. PPG Indus., 
    587 F.3d at
    652 (citing United
    Steelworkers of Am. v. Enter. Wheel & Car Corp., 
    363 U.S. 593
    , 598 (1960)). Indeed,
    the facts here are a far cry from those in the rare cases where this court has vacated a
    labor arbitrator’s award. See Kennametal, Inc. v. United Steelworkers Of Am., AFL-CIO
    CLC, 96 F. App’x 851, 854–55 (4th Cir. 2004) (per curiam) (affirming vacatur where
    arbitrator “intentionally ignored pertinent portions of the CBA”); Champion Int’l Corp. v.
    United Paperworkers Int’l Union, AFL-CIO, 
    168 F.3d 725
    , 731 (4th Cir. 1999) (vacating
    award where arbitrator based award on a contract from which he “had no contractual
    authority . . . to make” an award); Mountaineer Gas Co. v. Oil, Chem. & Atomic Workers
    Int’l Union, 
    76 F.3d 606
    , 609–10 (4th Cir. 1996) (affirming vacatur where “arbitrator
    blatantly ignored the unambiguous language of [the company’s] Drug Policy [which
    required employee’s termination] and [instead] fashioned a modified penalty that
    13
    appealed to his own notions of right and wrong” and lacked support from any part of the
    CBA).
    b.
    We next consider B&P’s argument that vacatur is warranted because the arbitrator
    exceeded his authority by finding the grievance timely under the continuing violation
    doctrine. We conclude that the arbitrator was within his authority to do so.
    There is no dispute that under Article 11, Section 2, Step 3, the question of
    procedural arbitrability was for the arbitrator to decide. As such, the deferential standard
    of judicial review which applies to a labor arbitrator’s determination on the merits also
    applies to the threshold decision of procedural arbitrability. Nat’l Postal Mail Handlers
    Union v. Am. Postal Workers Union, 
    589 F.3d 437
    , 441–42 (D.C. Cir. 2009) (citing AT &
    T Techs., Inc. v. Commc’ns Workers of Am., 
    475 U.S. 643
    , 649 (1986)). 1 Whether the
    arbitrator made the correct decision is, of course, disputed.
    By waiting until May 29, 2013, to file this grievance, the Union failed to comply
    with Article 11, Section 2, Step 1 of the CBA’s Grievance and Arbitration Procedure,
    technically rendering the grievance untimely.       The arbitrator nevertheless found the
    grievance timely for two reasons: (1) the existence of a dispute between the Union and
    B&P regarding the processing of grievances prior to the adoption of the CBA in 2012,
    1
    Though National Postal Mail Handlers Union arose in the postal context, the
    court noted that “the standard for judicial review of arbitration awards in the postal
    context is the same as the standard . . . for judicial review of labor arbitration awards
    under § 301 [of the Labor Management Relations Act].” 589 F.3d at 440–41.
    14
    and (2) the “continuing nature” of the violation. J.A. 48. Because B&P’s argument
    focuses on the arbitrator’s second justification and we find that justification sufficient to
    support the arbitrator’s decision on timeliness, we do not consider the validity of the
    arbitrator’s first justification.
    “The labor arbitrator’s source of law is not confined to the express provisions of
    the contract, as the industrial common law—the practices of the industry and the shop—
    is equally a part of the [CBA] although not expressed in it.” United Steelworkers of Am.
    v. Warrior & Gulf Navigation Co., 
    363 U.S. 574
    , 581–82 (1960). “There are too many
    people, too many problems, too many unforeseeable contingencies to make the words of
    the contract the exclusive source of rights and duties.” McCormick v. AT & T Techs.,
    Inc., 
    934 F.2d 531
    , 536 (4th Cir. 1991) (en banc) (quoting Warrior & Gulf Navigation
    Co., 363 U.S. at 579).
    One such substantive background principle of law is the common-law continuing
    violation doctrine, which arbitrators have invoked—and courts have to various degrees
    acknowledged—as standing for the proposition that a violation which is continuous in
    nature gives rise to a new grievance each day. See United Steel, Paper & Forestry,
    Rubber, Mfg., Energy, Allied Indus. & Serv. Workers Int’l Union AFL-CIO-CLC v. Wise
    Alloys, LLC, 
    807 F.3d 1258
    , 1272–73 (11th Cir. 2015) (affirming application of the
    continuing violation doctrine where violation was company’s failure to deduct a cost-of-
    living allowance from a weekly health-care premium); Nat’l Postal Mail Handlers
    Union, 589 F.3d at 439–44 (affirming arbitrator’s interpretation of agreement to
    “incorporate a ‘continuing violations’ theory under which” he could hear disputes about
    15
    pre-1992 work assignments that continued after 1992 even though agreement banned new
    disputes regarding pre-1992 work assignments); El Mundo Broad. Corp. v. United
    Steelworkers of Am., AFL-CIO CLC, 
    116 F.3d 7
    , 10 (1st Cir. 1997) (rejecting application
    of the continuing violation doctrine where the violation in question was the failure to post
    a job opening, but in dicta acknowledging the doctrine when the violation is a “daily
    failure to pay”).
    The underlying violation in this grievance is B&P’s failure to pay employees their
    bargained-for salary.     Because that violation is continuous in nature, the arbitrator
    arguably construed the CBA when he looked beyond the express provisions in the
    Grievance and Arbitration Procedure and applied the continuing violation doctrine to find
    the grievance timely. And even if we were “convinced he committed serious error” in
    doing so, which is an issue we do not reach, that would “not suffice to overturn” the
    Hours Reduction Award. Garvey, 
    532 U.S. at 509
    .
    c.
    Finally, we consider B&P’s contention that, in the alternative to vacatur, the Hours
    Reduction Award should not apply retroactively but rather should run from the date of
    the grievance.      As to this question, we give arbitrators wide latitude to formulate
    remedies:
    When an arbitrator is commissioned to interpret and apply the collective
    bargaining agreement, he is to bring his informed judgment to bear in order
    to reach a fair solution of a problem. This is especially true when it comes
    to formulating remedies. There the need is for flexibility in meeting a wide
    variety of situations.
    Enter. Wheel & Car Corp., 
    363 U.S. at 597
    .
    16
    We are mindful, however, that our deference is not unlimited. Some courts that
    have applied the continuing violation doctrine in the labor arbitration context have, in
    dicta, cautioned against using it to authorize relief that precedes the filing of the
    technically untimely grievance. See Wise Alloys, 807 F.3d at 1272–73 (implying in dicta
    that using the continuing violation doctrine to award retroactive relief could constitute
    reversible error, as it would effectively rewrite the grievance procedures); UMass Mem’l
    Med. Ctr., Inc. v. United Food & Commercial Workers Union, 
    527 F.3d 1
    , 7 (1st Cir.
    2008) (affirming arbitrator’s application of the continuing violation doctrine and in dicta
    noting that “there was no question of retroactivity of relief or harm to settled expectations
    because the arbitrator refused to award a retroactive remedy”).
    We understand the animating principle of these notes of caution to be respect for
    settled expectations. Under the deferential standard of review that we apply to the
    arbitrator’s remedy, Enter. Wheel & Car Corp., 363 U.S. at 597, and cognizant that
    “serious error” alone is insufficient to overturn this award, Garvey, 
    532 U.S. at 509
    , we
    find that whatever harm there is to B&P’s settled expectations is too insignificant to
    warrant relief. The Shop Steward spoke with B&P management about the reduction in
    hours on the day that B&P announced the change. In other words, B&P was on notice of
    a potential grievance from day one. Moreover, the Union did not wait for over four
    months to file the grievance in order to surprise B&P. Rather, employees worked without
    a CBA until May 17, 2013, and B&P would not recognize the Union or discuss grievance
    issues on January 16, 2013 (when the violation first occurred).
    17
    Based upon the peculiar facts of this case, we find that the arbitrator did not
    “dispense his own brand of industrial justice” by ordering damages retroactive to the day
    that B&P announced the reduction in hours.         Garvey, 
    532 U.S. at 509
     (alteration
    omitted).   Rather, we characterize the Hours Reduction Award as a product of the
    arbitrator’s bringing his “informed judgment to bear in order to reach a fair solution of a
    problem.” Enter. Wheel & Car Corp., 
    363 U.S. at 597
    .
    In sum, the district court did not err in confirming the Hours Reduction Award.
    2.
    B&P contends that the Drivers’ Pay Award should be vacated for three reasons.
    First, the arbitrator wrongly found that B&P refused to provide the grievants with
    company cars. Second, the arbitrator failed to credit relevant testimony favorable to
    B&P. Third, the arbitrator exceeded his authority by construing the word “drivers” to
    include employees like Duran and Cortez, who did not drive B&P’s vehicles.
    We reject B&P’s first two arguments, because they amount to an impermissible
    attack on the arbitrator’s honest findings of fact. Garvey, 
    532 U.S. at 509
    . As for B&P’s
    third argument, our review of the Drivers’ Pay Award reveals that the arbitrator did not
    come close to exceeding his authority. Instead, as arbitrators are allowed to do, he
    construed the CBA by looking to extrinsic evidence to define an ambiguous term. See
    PPG Indus., 
    587 F.3d at
    653–54 (upholding labor arbitrator’s right to look to extrinsic
    evidence to give meaning to ambiguous terms).
    Faced with wage classifications left undefined by the CBA, the arbitrator gave
    meaning to the “Custodian/Driver” classification by looking to a letter of understanding
    18
    between the Union and one of B&P’s predecessors and the work performed by
    employees whom B&P’s predecessors had paid at the “Custodian/Driver” rate. Based
    upon the similarities between the work performed by the grievants and the work
    performed by employees whom B&P’s predecessors had paid at the “Custodian/Driver”
    rate, the arbitrator concluded that the grievants were entitled to be paid at that rate as
    well. The arbitrator was at all times construing the CBA in the course of this analysis,
    including when he reasoned that B&P could not avoid paying the higher rate by requiring
    Duran and Cortez to drive their own cars.
    Accordingly, the district court did not err in confirming the Drivers’ Pay Award.
    3.
    B&P contends that the Vacation Pay Award should be vacated for two reasons.
    First, at the January 2015 hearing, the arbitrator improperly allowed the Union to
    recharacterize the grievance from denying vacation time to withholding vacation pay.
    Second, the Union violated the CBA’s Grievance and Arbitration Procedure by waiting
    until January 2015 to bring a grievance for a vacation-pay policy that B&P put into effect
    in April 2013. B&P also insists that it never waived its objection to the timeliness of the
    grievance. For its part, the Union contends that the arbitrator correctly found that B&P
    stipulated to recharacterizing the grievance.
    B&P’s arguments against confirmation of the Vacation Pay Award all fail for the
    same reason: the arbitrator found that B&P waived its objection to the timeliness of the
    grievance by stipulating to the issue at the January 2015 hearing. “[C]ourts presume that
    the parties intended arbitrators, not courts, to decide disputes about the meaning and
    19
    application of particular procedural preconditions for the use of arbitration.      These
    procedural matters include claims of waiver . . . .”      BG Grp. PLC v. Republic of
    Argentina, 
    134 S. Ct. 1198
    , 1207 (2014) (internal citation and quotation marks omitted).
    To that end, “[p]arties to an arbitration may stipulate the issues they want determined and
    increase or limit the arbitrator’s contractual authority by their express submission.” Hill
    v. Staten Island Zoological Soc’y, Inc., 
    147 F.3d 209
    , 214 (2d Cir. 1998). According to
    the arbitrator, the Union and B&P did just that—they stipulated to the arbitrability of a
    recharacterized and otherwise untimely grievance, thereby waiving any objections to
    timeliness.
    B&P’s argument amounts to an attack on the arbitrator’s finding that the parties
    stipulated to the recharacterized grievance at the January 2015 hearing. But there is no
    transcript of the hearing, and the Union contests B&P’s argument. Indeed, the arbitrator
    acknowledged B&P’s claim that the parties made a different stipulation, but stated that he
    had “no recollection of” the alternative stipulation and “wrote down for [his] record the
    one [that B&P contests on appeal] with information provided by both parties.” J.A. 369.
    Once again, we will not entertain an attack on the arbitrator’s honest findings of fact.
    Garvey, 
    532 U.S. at 509
    .
    Thus, the district court did not err in confirming the Vacation Pay Award.
    4.
    Finally, B&P contends that the dispute underlying the Monies Owed Award is
    moot, and therefore confirmation is improper. In particular, B&P argues that it has twice
    before paid the grievants the amounts awarded by the Monies Owed Award and that after
    20
    the arbitrator issued the award it paid the grievants the interest amounts specified in the
    award. B&P also claims that the district court treated its affirmative defense of mootness
    as a request for vacatur. The Union, however, refuses to concede that B&P made the
    payments it claims to have made to the grievants, and asks that we confirm this award.
    “[A] case is moot when the issues presented are no longer ‘live’ or the parties lack
    a legally cognizable interest in the outcome.” United States v. Springer, 
    715 F.3d 535
    ,
    540 (4th Cir. 2013) (quoting Powell v. McCormack, 
    395 U.S. 486
    , 496 (1969)). “A case
    becomes moot only when it is impossible for a court to grant any effectual relief whatever
    to the prevailing party.” 
    Id.
     (quoting Knox v. Serv. Emps. Int’l Union, Local 1000, 
    132 S. Ct. 2277
    , 2287 (2012)). As an initial matter, B&P is correct that the district court
    apparently analyzed the Monies Owed Award as if B&P had requested vacatur rather
    than as if B&P had raised mootness as an affirmative defense to confirmation. The
    district court never considered whether a live controversy existed. Notwithstanding that
    error and the evidence of payment that B&P has entered into the record, however, we
    find that confirmation of the Monies Owed Award is proper because a live controversy
    regarding the award exists. 2
    The arbitrator never found that B&P complied with the Monies Owed Award.
    Rather, in an order denying B&P’s request to modify his fees for the January 2015
    2
    We do not reach the question of whether a federal court may confirm a labor
    arbitration award where there is no live controversy between the parties regarding the
    award necessitating judicial enforcement. See 1199 SEIU United Healthcare Workers E.
    v. Civista Med. Ctr., Inc., No. DKC 10-0479, 
    2011 WL 310486
    , at *2 (D. Md. Jan. 28,
    2011) (collecting cases on the topic, which has divided the circuits).
    21
    hearing which B&P did not attend, the arbitrator wrote that the records of payment which
    B&P sent to him and which B&P argues here demonstrate compliance with the Monies
    Owed Award “did not indicate . . . that the case was settled.” J.A. 432. That statement
    by the arbitrator, the district court’s failure to address the issue, and the Union’s
    insistence that a controversy still exists convince us that it is not impossible to grant any
    effectual relief by affirming the confirmation of the Monies Owed Award. In arriving at
    that conclusion, we are mindful that the arbitrator’s award provides that B&P “shall be
    given credit for any back pay or other payments previously made that are consistent with
    this Award.” J.A. 155.
    For these reasons, the district court did not err in confirming the Monies Owed
    Award.
    B.
    The controlling issue in the Union’s cross-appeal for attorneys’ fees is whether its
    failure to submit a motion for fees pursuant to Federal Rule of Civil Procedure 54(d)
    waived the claim. Beyond rebutting that proposition, the Union makes a number of
    arguments in its cross-appeal. It contends that it should be awarded attorneys’ fees
    because B&P’s challenges to the awards were presumptively unjustified attempts to
    relitigate the arbitrations on the merits, and that the district court abused its discretion by
    not explaining why it denied attorneys’ fees. But antecedent to those arguments is the
    question whether the Union preserved its right to recover attorneys’ fees by properly
    asking for them. We think not, because the Union failed to abide by Rule 54(d)’s
    requirements, thereby waiving its claim.
    22
    “In general, ‘the decision whether and in what amount to award attorney fees is
    one commit[t]ed to the award court’s discretion, subject only to review for abuse of that
    discretion.’” Andrews v. Am.’s Living Ctrs., LLC, 
    827 F.3d 306
    , 312 (4th Cir. 2016)
    (alteration in original) (quoting United Food & Commercial Workers, Local 400 v.
    Marval Poultry Co., 
    876 F.2d 346
    , 350–51 (4th Cir. 1989)). But “it may be revealed
    upon inspection that such a decision actually turned on an express or implicit finding of
    fact or conclusion of law that dictated the ultimate result.” Marval Poultry, 
    876 F.2d at 351
    . We review questions of law, including an interpretation of a Federal Rule of Civil
    Procedure, de novo. Bosley v. Mineral Cty. Comm’n, 
    650 F.3d 408
    , 411 (4th Cir. 2011).
    1.
    In this case, we cannot undertake an “inspection” of the district court’s order to
    decipher whether it “turned on an express or implicit finding of fact or conclusion of law
    that dictated the ultimate result,” as opposed to an exercise of the district court’s
    “available discretion,” or even some combination of all of the above. Marval Poultry,
    
    876 F.2d at 351
    . That is because the district court said nothing about attorneys’ fees. On
    its face, that silence could be construed as an abuse of discretion, as “[p]erhaps [abuse of
    discretion’s] most obvious manifestation is in a failure or refusal, either express or
    implicit, actually to exercise discretion.” James v. Jacobson, 
    6 F.3d 233
    , 239 (4th Cir.
    1993).
    But we do not review the district court’s silence in a vacuum.        Instead, we
    consider the surrounding facts. The Union devoted a section of its brief in support of
    enforcing the arbitration awards to the issue of attorneys’ fees, and B&P did the same in
    23
    its rebuttal brief in support of its motion to vacate the Vacation Pay Award. After the
    district court confirmed the four awards, the Union failed to submit a motion for
    attorneys’ fees. Thus, the Union did not comply with Rule 54(d), which, subject to
    certain exceptions that we describe below and find inapplicable here, provides the
    procedural framework for requesting attorneys’ fees. Mindful that we cannot divine the
    district court’s intentions from its silence, we nevertheless find that its decision
    necessarily turned, at least in part, on an interpretation of Rule 54(d). Because we need
    only interpret Rule 54(d) to resolve this cross-appeal, and we review an interpretation of
    a Federal Rule of Civil Procedure de novo, we apply that standard.
    2.
    Rule 54(d) provides that “[a] claim for attorney’s fees . . . must be made by motion
    unless the substantive law requires those fees to be proved at trial as an element of
    damages.” Fed. R. Civ. P. 54(d)(2)(A). Section 301 of the Labor Management Relations
    Act, under which this case arises, does not require that attorneys’ fees be proved at trial
    as an element of damages or otherwise provide for an award of attorneys’ fees. Marval
    Poultry, 
    876 F.2d at 350
    . As a result, the plain language of Rule 54(d) required that the
    Union’s claim for attorneys’ fees be made by motion.
    Rule 54(d) goes on to specify:
    Unless a statute or court order provides otherwise, the motion must: (i) be
    filed no later than 14 days after the entry of judgment; (ii) specify the
    judgment and the statute, rule, or other grounds entitling the movant to the
    award; [and] (iii) state the amount sought or provide a fair estimate of it.
    24
    Fed. R. Civ. P. 54(d)(2)(B)(i)–(iii). Here, no statute or court order “provides otherwise,”
    and none of the other exceptions to Rule 54(d) apply. 3 Accordingly, Rule 54(d) required
    the Union to submit a motion for attorneys’ fees between 0–14 days after the district
    court issued its order. See Kona Enters., Inc. v. Estate of Bishop, 
    229 F.3d 877
    , 889 (9th
    Cir. 2000) (“Rule 54 expressly conditions a motion for attorneys’ fees on an entry of
    judgment.”). This the Union failed to do.
    The Union attempts to avoid the application of Rule 54(d) by arguing that the
    parties fully briefed the issue of attorneys’ fees before the district court. But Rule 54(d)
    makes clear that a motion for attorneys’ fees is not proper until after the district court has
    entered judgment. Even cases upon which the Union relies share this procedural posture.
    See, e.g., San Diego Police Officers’ Ass’n v. San Diego City Emps.’ Ret. Sys., 
    568 F.3d 725
    , 732–33, 742 (9th Cir. 2009) (parties briefed issue of attorneys’ fees in the district
    court after that court granted summary judgment); Prod. & Maint. Emps.’ Local 504 v.
    Roadmaster Corp., 
    954 F.2d 1397
    , 1400 (7th Cir. 1992) (plaintiffs filed a motion for
    attorneys’ fees with the district court after that court entered judgment); Marval Poultry,
    
    876 F.2d at 349
     (union “moved for an award of fees” in the district court after that court
    3
    Rule 54(d)(2)(D) provides that “[b]y local rule, the court may establish special
    procedures to resolve fee-related issues without extensive evidentiary hearings.” There is
    no Local Rule in the United States District Court for the Eastern District of Virginia
    relevant to this issue. Rule 54(d)(2)(E) further provides that Rule 54(d)(2)’s
    requirements “do not apply to claims for fees and expenses as sanctions for violating
    these rules or as sanctions under 
    28 U.S.C. § 1927
    .” Once again, these exceptions are
    inapplicable here.
    25
    entered judgment). We will not insist that a district court respond to each proffered
    argument, regardless of whether it is properly before it.
    Accordingly, the Union waived its claim for attorneys’ fees by not complying with
    Rule 54(d).
    III.
    For reasons given, we affirm the district court’s confirmation order.
    AFFIRMED
    26