Balfour Beatty Infrastructure, Inc. v. Mayor of Baltimore , 855 F.3d 247 ( 2017 )


Menu:
  •                                       PUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 16-1322
    BALFOUR BEATTY INFRASTRUCTURE, INC.,
    Plaintiff - Appellant,
    v.
    MAYOR AND CITY COUNCIL OF BALTIMORE,
    Defendant - Appellee.
    Appeal from the United States District Court for the District of Maryland, at Baltimore.
    Richard D. Bennett, District Judge. (1:15-cv-01745-RDB)
    Argued: January 25, 2017                                       Decided: April 25, 2017
    Before GREGORY, Chief Judge, and THACKER and HARRIS, Circuit Judges.
    Affirmed by published opinion. Judge Harris wrote the opinion, in which Chief Judge
    Gregory and Judge Thacker joined.
    ARGUED: Gregory S. Martin, MARTIN HILD, P.A., Maitland, Florida, for Appellant.
    Patrick Donald Sheridan, BALTIMORE CITY DEPARTMENT OF LAW, Baltimore,
    Maryland, for Appellee. ON BRIEF: Lucas F. Webster, HUDDLES, JONES,
    SORTEBERG & DACHILLE, P.C., Columbia, Maryland, for Appellant. Thomas P.G.
    Webb, Assistant Solicitor, BALTIMORE CITY DEPARTMENT OF LAW, Baltimore,
    Maryland, for Appellee.
    PAMELA HARRIS, Circuit Judge:
    Balfour Beatty Infrastructure, Inc. (“BBII”) sued the City of Baltimore for breach
    of contract, alleging that the City unlawfully assessed liquidated damages against the
    company for failure to complete a construction project on time. The issue in this appeal
    is whether BBII must exhaust its administrative remedies against the City before suing in
    federal court. We agree with the district court that BBII is not excused from the normal
    requirement of administrative exhaustion under Maryland law, and therefore affirm the
    district court’s dismissal for lack of subject matter jurisdiction.
    I.
    A.
    This case involves two public works contracts entered into by the City of
    Baltimore and BBII, 1 under which BBII agreed to build certain parts of a wastewater
    treatment system aimed at reducing pollution in the Chesapeake Bay. The contracts
    stipulate that “[t]ime is of the essence,” J.A. 72, 75, and BBII committed to completing
    its work by February 28, 2015. If it did not, then the City would have the right to assess
    liquidated damages for each day past the deadline, by withholding a portion of its
    monthly payments to BBII.
    1
    The City originally contracted with Fru-Con Construction Corporation, which
    assigned its contract to Fru-Con Construction, LLC, which in turn merged into Balfour
    Beatty Infrastructure, Inc. For ease of reference, we refer to all three as BBII.
    2
    The contracts also incorporate provisions for the resolution of claims and disputes,
    which require BBII to seek administrative review of any dispute related to its contracts
    with the City before suing in court. Those provisions are grounded in the City’s Charter,
    which authorizes the City to establish an administrative process for the resolution of
    disputes arising from City construction contracts. See Charter of Baltimore City, art.
    II, § 4(A)(g) (2002 revision). Pursuant to that authority, the City has provided for an
    administrative dispute resolution process that governs all claims by contractors related to
    public works projects, set forth in the City’s “Department of Public Works Specifications
    – Materials, Highways, Bridges, Utilities and Incidental Structures 2006,” generally
    known as the “Green Book.”
    Neither party disputes that the Green Book dispute resolution process is
    incorporated into the contracts at issue here. Under that dispute resolution process, a
    contractor is required to give “prompt notice” of any claim or dispute to the Department
    of Public Works engineer assigned to its project. J.A. 99. That engineer, along with the
    project’s inspector and division head, is charged with initial review of the claim, with the
    contractor responsible for providing any additional information requested by the City. If
    the contractor chooses to appeal, then review proceeds up through a Department of Public
    Works bureau head and, if the contractor remains dissatisfied, to ultimate review by the
    Director of Public Works, who acts as a hearing officer during an on-the-record
    administrative hearing and issues a final decision. At that point – and only at that point –
    the contractor may bring its claim to a “court of competent jurisdiction.” J.A. 101.
    3
    B.
    During the course of its work on the wastewater treatment system, BBII ran into
    what it calls a “series of design errors, omissions and inconsistencies” on the part of the
    City that made it impossible to finish the project by the February 28, 2015 deadline. J.A.
    11. On March 2, 2015, two days after the deadline had expired and before final action on
    several BBII extension requests, the City informed BBII that it would exercise its
    contractual right to assess liquidated damages at the rate of $20,000 per day on each
    contract, until the projects were completed. The City then began to deduct $40,000 per
    day from its monthly payments to BBII.
    BBII bypassed the administrative process incorporated into its contracts with the
    City and went directly to federal court to file this suit. 2 Naming as defendants the Mayor
    and City Council of Baltimore (“the City”), BBII alleged that the City had materially
    breached its contracts with BBII by declaring BBII in default and assessing liquidated
    damages without first pursuing its own claims through the administrative dispute
    resolution process and affording BBII an administrative hearing. According to BBII, the
    City’s actions amounted to an illegal and ultra vires “abandonment” of the Green Book
    administrative process, relieving BBII of any obligation to use that process itself. J.A.
    366.
    2
    This is not the first time that BBII has sued the City for breach of contract
    without first exhausting its administrative remedies. As the district court noted, it has
    once before dismissed an action by BBII arising out of a City contract for failure to
    exhaust the administrative procedures set out in the City’s standard public works
    contract. See Fru-Con Constr., LLC v. Mayor of Baltimore, No. RDB-14-434, 
    2014 WL 6675625
    , at *6 (D. Md. Nov. 24, 2014).
    4
    The district court disagreed, and held that BBII was required to exhaust the
    administrative remedies provided for by its City contracts. The court began by describing
    Maryland law’s “strong preference for administrative exhaustion,” J.A. 362 – a
    preference, it noted, that is consistent with federal law, as well. Under Maryland law, the
    court explained, it is well established that “[w]here an administrative agency has primary
    or exclusive jurisdiction over a controversy, the parties to the controversy must ordinarily
    await a final administrative decision before resorting to the courts for resolution of the
    controversy.” J.A. 363 (quoting Heery Int’l, Inc. v. Montgomery Cty., Md., 
    862 A.2d 976
    , 981 (Md. 2004)). And that general principle, the court determined, governs this
    case, where the Green Book provisions incorporated into BBII’s contracts “mandate[]
    that the prescribed administrative procedures are the exclusive procedures for the
    prosecution and resolution of all claims and disputes.” J.A. 365 (internal quotation marks
    omitted).
    The district court recognized that the exhaustion requirement applies only where
    the agency designated to hear a dispute actually has “jurisdiction over [the] controversy,”
    
    Heery, 862 A.2d at 981
    – or, correspondingly, that there is an exception to the exhaustion
    requirement when the “reviewing agency is ‘palpably without jurisdiction’” to adjudicate
    a party’s claim. J.A. 365 (quoting 
    Heery, 862 A.2d at 989
    ). That exception, the district
    court explained, also “requires a complaining party to plead an ‘irreparable injury’ if it is
    forced to navigate the prescribed administrative process.” J.A. 365–66 (quoting 
    Heery, 862 A.2d at 989
    ). Because BBII could show neither that the City officials designated to
    review its contract dispute are “palpably without jurisdiction” to do so, nor that it would
    5
    be irreparably damaged if required to postpone litigation until completion of the
    administrative process, the court concluded, the exception does not apply.
    Whether the City acted unlawfully by assessing liquidated damages without first
    engaging in the Green Book administrative process, as alleged by BBII, is a different
    question, the court explained – and precisely the kind of regulatory interpretation issue
    that “should be decided administratively before proceeding to judicial review” under
    Maryland law. J.A. 367 (citing 
    Heery, 862 A.2d at 986
    ). Even assuming, as BBII
    argued, that the City acted without authority in taking liquidated damages absent
    administrative review, that would not excuse BBII from exhausting its administrative
    remedies: Maryland courts have not adopted an exception to exhaustion for cases in
    which “the act of an administrative agency is alleged to be ultra vires or illegal.” J.A.
    368 (quoting Soley v. State Comm’n on Human Relations, 
    356 A.2d 254
    , 258 (Md.
    1976)).
    Finally, the district court rejected BBII’s claim that it need not exhaust its
    administrative remedies because the City employees who would review its claims are
    biased against BBII and naturally predisposed to favor the City’s own positions. If that
    were so, the court reasoned, then an administrative agency involved in a dispute could
    never require exhaustion of administrative remedies – undermining a “fundamental
    purpose” of exhaustion, the “protection of an administrative agency’s authority to
    interpret its own regulations, statutes, and other guidelines.” J.A. 370 (quoting Fru-Con
    Constr., LLC v. Mayor of Baltimore, No. RDB-14-434, 
    2014 WL 6675625
    , at *6 (D. Md.
    Nov. 24, 2014)).
    6
    Because BBII failed to exhaust its administrative remedies, the district court
    dismissed its action against the City for lack of subject matter jurisdiction. This timely
    appeal followed.
    II.
    This Court reviews de novo a district court’s dismissal for lack of subject matter
    jurisdiction pursuant to Federal Rule of Civil Procedure 12(b)(1). Pitt Cty. v. Hotels.com,
    L.P., 
    553 F.3d 308
    , 311 (4th Cir. 2009). A Rule 12(b)(1) motion to dismiss should be
    granted “only if the material jurisdictional facts are not in dispute and the moving party is
    entitled to prevail as a matter of law.” Evans v. B.F. Perkins Co., a Div. of Standex Int'l
    Corp., 
    166 F.3d 642
    , 647 (4th Cir. 1999) (internal quotation marks omitted).
    We agree with the district court that on the undisputed record facts and as a matter
    of law, BBII was required to exhaust its contractual administrative remedies before filing
    this action in federal court. BBII’s principal argument to the contrary is that it was
    excused from administrative exhaustion under Maryland law because the “City acted
    ‘palpably without jurisdiction’ in taking liquidated damages against BBII without first
    following the contractual dispute resolution procedure.” Br. of Appellant at 2. But that
    position reflects a fundamental misunderstanding of the “palpably without jurisdiction”
    exception to the exhaustion requirement under Maryland law.
    As the district court explained, although Maryland law generally requires that
    administrative remedies be exhausted before proceeding to court, it admits of an
    exception when the administrative tribunal charged with considering a party’s claim is
    7
    “palpably without jurisdiction” to hear and resolve that claim or class of claims. See
    
    Heery, 862 A.2d at 985
    (administrative agency is “palpably without jurisdiction” for
    purposes of exhaustion exception where it “lacks a clear authority to adjudicate a given
    class of claims” designated for exhaustion); see also, e.g., State v. Md. State Bd. of
    Contract Appeals, 
    773 A.2d 504
    , 511 (Md. 2001) (“palpably without jurisdiction”
    exception applies where dispute is pending before adjudicatory administrative agency
    that does not have jurisdiction to review the matter). It is easy to understand why such an
    exception might exist: There is little, if anything, to be gained by insisting that a party
    take its dispute to a tribunal that lacks the authority to rule on it, or to provide a remedy.
    See United Ins. Co. of Am. v. Md. Ins. Admin., 
    144 A.3d 1230
    , 1249 (Md. 2016)
    (recognizing exhaustion exception “[w]here the administrative agency cannot provide to
    any substantial degree a remedy”).        Indeed, the Supreme Court has observed that
    exhaustion may be excused as futile when the agency charged with administrative review
    is not empowered to adjudicate the issue presented or to grant effective relief. See
    McCarthy v. Madigan, 
    503 U.S. 140
    , 147–48 (1992), superseded by statute on other
    grounds, 42 U.S.C. § 1997e(a).
    But that exception has no application here. Nobody disputes that BBII’s contracts
    with the City are public works contracts governed by the Department of Public Works
    Green Book and its dispute resolution procedures. And as the Green Book makes clear,
    the Department of Public Works officials charged with administrative review of
    contractor claims arising from public works contracts have the authority to hear and
    resolve those claims. See, e.g., J.A. 99–100 (project engineer has discretion to grant
    8
    extensions on public works projects); J.A. 100 (bureau head has “all of the authority and
    powers to settle disputes” arising from public works contracts); J.A. 101 (Director of
    Public Works shall “resolve any and all claims and/or disputes” under public works
    contracts). That is all that is required to take this case outside the “palpably without
    jurisdiction” exception to the normal expectation of administrative exhaustion. See State
    Bd. of Contract 
    Appeals, 773 A.2d at 511
    ; 
    Heery, 862 A.2d at 985
    –86.
    BBII does not even allege that the relevant agency officials lack the authority to
    review its breach of contract claims against the City. Instead, it argues that the City
    lacked authority to deduct liquidated damages from its payments to BBII without first
    engaging in the Green Book dispute resolution process. But that, as the district court
    recognized, is an entirely different issue, going to the merits of the underlying dispute
    between BBII and the City rather than to the “palpably without jurisdiction” exception.
    BBII reads the Green Book regulations incorporated into its contracts as requiring
    administrative exhaustion by the City, as well as by contractors; the City disagrees, and
    construes the contractual dispute resolution process as binding on contractors but not on
    the City. Under Maryland law, that is precisely the kind of interpretive question that is to
    be “determined by a final administrative decision and to be judicially reviewed only after
    the administrative remedy has been exhausted.”         
    Heery, 862 A.2d at 986
    (internal
    quotation marks omitted). Indeed, Maryland’s highest court held just that in Heery, on
    facts remarkably similar to those before us now, finding that whether Montgomery
    County’s administrative dispute resolution process governed claims by the County as
    9
    well as by contractors was a matter to be exhausted before the relevant county agency.
    
    Id. It may
    well be, as the district court suggested, that the City has the better of the
    interpretive argument here, and that the Green Book does not require that the City follow
    its administrative review procedures prior to taking liquidated damages. But we need not
    reach that question, because as the district court also recognized, the outcome does not
    matter for purposes of exhaustion. Even assuming that the City is wrong, and that it
    impermissibly assessed liquidated damages without engaging in the contractual dispute
    resolution process, that would not relieve BBII from its own obligation to exhaust
    administrative remedies.     The Maryland courts have made clear that even when an
    interpretive dispute is “phrased in terms of the agency’s ‘authority,’ ‘power’ or
    ‘jurisdiction’ to take a certain type of action in a specific case,” it must be submitted first
    to the agency for decision. 
    Id. at 982
    (quoting Md. Comm’n on Human Relations v. Mass
    Transit Admin., 
    449 A.2d 385
    , 389 (Md. 1982)); see 
    Soley, 356 A.2d at 258
    (requiring
    exhaustion even “where the act of an administrative agency is alleged to be ultra vires or
    illegal”). Under Maryland law, that is, “[a] party’s argument that an agency will be
    exceeding its authority if it ultimately . . . decides the case contrary to that party’s
    position[] does not excuse the failure” to exhaust administrative remedies. 
    Heery, 862 A.2d at 982
    –83 (quoting Mass Transit 
    Admin., 449 A.2d at 389
    ).
    Nor need we address the district court’s conclusion that BBII would not suffer
    “irreparable injury” if required to exhaust administrative remedies, given that an eventual
    judgment in BBII’s favor would compensate it adequately for any losses. As the district
    10
    court explained, Heery suggests that the “palpably without jurisdiction” exception
    requires not only that the designated administrative tribunal clearly lack jurisdiction over
    the parties’ dispute, but also that involvement in the administrative process would cause
    “irreparable injury” to the party invoking the exception. 
    See 862 A.2d at 989
    . Because
    BBII has not shown or even alleged that the Department of Public Works lacks
    jurisdiction over its breach of contract claim, we have no occasion to further explore this
    other aspect of Maryland’s exhaustion exception or its application to this case.
    Finally, like the district court, we find no merit to BBII’s argument that it is
    excused from exhaustion because the City has predetermined the outcome of the
    administrative proceeding. Again, we need not decide whether and under precisely what
    circumstances Maryland law provides for a “bias” exception to the general requirement
    of administrative exhaustion. Here, BBII has failed to allege any facts showing “bias” on
    the part of the City that would render inadequate BBII’s administrative remedies. BBII
    points to a letter from the Department of Public Works expressing concern about the
    status and timeliness of BBII’s work, but that does not bear on whether the City has
    predetermined the outcome of BBII’s legal claim regarding the City’s obligations under
    the Green Book’s administrative review process. And as the district court observed, if
    BBII’s theory that City officials inevitably will be “predisposed” to favor the City’s
    position was enough to excuse exhaustion, the “bias” exception would swallow the rule:
    Under no circumstances could a government agency require that its own officials or
    tribunals be given the first opportunity to address a claim against it. BBII’s conclusory
    11
    allegation of “bias,” without more, does not entitle it to bypass the administrative dispute
    resolution process for which it contracted.
    III.
    For the foregoing reasons, the judgment of the district court is affirmed.
    AFFIRMED
    12