St. Paul Fire & Marine Insurance v. Wittman Mechanical Contractors, Inc. ( 2008 )


Menu:
  •                              UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 06-2031
    ST. PAUL FIRE & MARINE INSURANCE COMPANY, as
    subrogee   of  A.G.   Van  Metre   Services,
    Incorporated,
    Plaintiff - Appellee,
    versus
    WITTMAN MECHANICAL CONTRACTORS, INCORPORATED,
    Defendant - Appellant,
    and
    MID-SOUTH BUILDING SUPPLY COMPANY, INCORPORATED;
    DAE SOP YOON,
    Defendants.
    Appeal from the United States District Court for the Eastern
    District of Virginia, at Alexandria.  Walter D. Kelley, Jr.,
    District Judge. (1:04-cv-01303-WDK)
    Argued:   November 1, 2007              Decided:     February 6, 2008
    Before NIEMEYER, MICHAEL, and MOTZ, Circuit Judges.
    Vacated and remanded with instructions by unpublished per curiam
    opinion.
    Francis Joseph Prior, Jr., SICILIANO, ELLIS, DYER & BOCCAROSSE,
    Fairfax, Virginia, for Appellant.    Jim H. Fields, Jr., COZEN
    O’CONNOR, Philadelphia, Pennsylvania, for Appellee.
    Unpublished opinions are not binding precedent in this circuit.
    2
    PER CURIAM:
    On the morning of January 12, 2004, Wittman Mechanical
    Contractors, Inc., the mechanical subcontractor on a new house
    under   construction    in     Loudoun       County,    Virginia,     activated   a
    propane gas line feeding the gas system in the house and turned on
    the furnace. Approximately one hour later, an explosion occurred,
    destroying the house.           Experts concluded that the explosion
    resulted from a gas leak at the connection between the main gas
    pipeline in the basement and the spur gas pipeline running up to
    the kitchen island cooktop on the first floor.
    Under the “scope of work” provision in the contract between
    Wittman Mechanical and the general contractor, Wittman Mechanical
    was responsible for installing and starting up the furnace, but it
    was not responsible for installing the gas pipeline system or
    testing   it   for     leaks     before        the     system   was    activated.
    Nonetheless, Wittman Mechanical activated the gas pipeline system
    at the request of the general contractor and, before activating
    the system, did not test for leaks in the system.
    The general contractor’s insurance company, St. Paul Fire &
    Marine Insurance Company (“St. Paul Insurance”) paid the loss and
    then commenced this subrogation action against Wittman Mechanical,
    alleging breach of warranty and negligence in activating the gas
    system and starting the furnace without testing for leaks.
    3
    Following a three-day trial, a jury found in favor of Wittman
    Mechanical on both claims.       The district court, however, granted
    St.       Paul   Insurance’s    post-trial        motion     for     judgment
    notwithstanding the verdict, concluding that Wittman Mechanical
    breached its express warranties by failing to perform a pressure
    test for leaks.     The court thus entered judgment in favor of St.
    Paul Insurance for $445,685, plus interest.
    We conclude on appeal that based on the “scope of work”
    clause in the subcontract between Wittman Mechanical and the
    general contractor, Wittman Mechanical was responsible only for a
    breach of warranty given in connection with installation of the
    furnace, which required Wittman Mechanical to perform a soap-and-
    water test* at the connection between the furnace and the gas line
    system, but not a pressure test on the entire gas pipeline system,
    which was required only of the contractor doing the gas pipeline
    work.       Accordingly,   we   conclude   that    the     jury    could   have
    concluded, based on the evidence at trial, that any failure by
    Wittman Mechanical to perform a soap-and-water test was not the
    cause of the explosion.         We therefore vacate the judgment and
    remand to the district court with instructions to reinstate the
    verdict and enter judgment for Wittman Mechanical.
    *
    A soap-and-water leak test is the familiar test used, for
    example, in checking bicycle tires for leaks. Soap and water is
    put on a suspected leak, and if bubbles occur, they indicate the
    site of a leak.
    4
    I
    Wittman    Mechanical       was     hired    by   Virginia      Residential
    Construction,       Inc.,    as   a   subcontractor        to   provide   heating,
    ventilation,     and   air    conditioning        services      to   houses   under
    construction in Loudoun County, including the house in question.
    Virginia Residential was a residential real estate developer in
    the Washington, D.C. metropolitan area and was the owner of and
    contractor for the house in question.                   The contract between
    Wittman Mechanical and Virginia Residential included a “scope of
    work” provision that required Wittman Mechanical to perform only
    the HVAC work, including the installation and starting of the
    furnace.    But the contract did not include within the scope of the
    work any work related to installation and testing of the gas
    pipeline system. The contract provided that all gas pipeline work
    was to be performed by Peed Piping, another subcontractor retained
    by Virginia Residential.
    After Peed Piping had initially installed the gas pipes in
    the house, Loudoun County inspectors performed an inspection of
    the pipes.      This inspection required that all gas pipes in the
    house first be tied to an appliance, be capped off, or have a shut
    off valve.      The county inspectors performed a pressure test to
    detect any leaks in the system by injecting a specified amount of
    air pressure into the pipes.            Because the pipes held the pressure
    for   24   hours,    the    house’s     system    passed    inspection    and   was
    5
    approved in October 2003.     Approximately three months passed,
    during which a spur gas line running from the main gas pipeline in
    the house’s basement to the island cooktop in the kitchen became
    disconnected.   It was at this connection between the main gas
    pipeline and the spur line from which gas leaked, causing the
    explosion on January 12, 2004.
    On the morning of January 12, 2004, Robert Casteel and Lloyd
    Henry Dignazio, employees of Wittman Mechanical, arrived at the
    house to install brackets for air conditioning units.     At some
    point during the morning, Virginia Residential’s superintendent at
    the site, Russell Rolle, asked Casteel to start the furnace for
    warmth.   By that time, Wittman Mechanical had already installed
    the furnace but had not started it up. After receiving permission
    from his supervisors at Wittman Mechanical, Casteel opened the
    line at the furnace to bleed out air that could prevent the
    furnace from starting.    On doing this, he felt no pressure and
    smelled no gas, indicating to him that the line from the propane
    tank had not yet been activated.     When Casteel advised Rolle of
    this fact, Rolle asked Casteel to activate the gas line leading
    from the propane tank to the house.    This task, however, was one
    that did not fall within the scope of work for Wittman Mechanical.
    Nonetheless, feeling pressure from Rolle, Casteel called Wittman
    Mechanical’s main office and asked permission to activate the
    line.   Wittman Mechanical’s operations manager authorized Casteel
    6
    to activate the line once he was informed that Rolle had assured
    Casteel that the gas pipeline system was ready to receive propane
    gas.    Wittman Mechanical’s operations manager testified at trial
    that he had assumed that, based on Rolle’s request to activate the
    system and his assurance that the system was in good condition and
    ready to receive propane gas, Rolle was accepting responsibility
    for any adverse consequences that might arise from the activation
    of the system.
    After conducting a visual inspection of the gas appliances in
    the house to confirm that the gas line valves were set in the off
    position, Casteel activated the propane gas line and started the
    furnace in the basement. In starting the furnace, Casteel did not
    perform    any    type   of   leak   test,    nor    did   he   consult     the
    manufacturer’s instruction manual that came with the furnace
    itself, testifying that he had never done so.              He also testified
    that he was not aware of any codes or industry standards that he
    was required to follow before or after turning on the gas and
    starting the furnace.
    The explosion occurred approximately one hour after Casteel
    activated the gas line and started the furnace.
    Following the explosion, St. Paul Insurance, who was the
    insurer   of     Virginia   Residential,     paid   Virginia    Residential’s
    insurance claim and commenced this subrogation action against
    Wittman Mechanical for breach of warranty and negligence.                 After
    7
    the jury returned a verdict in favor of Wittman Mechanical on both
    claims, St. Paul Insurance moved for a judgment under Federal Rule
    of Civil Procedure 50, and the district court granted the motion,
    awarding St. Paul Insurance $445,685, with interest at 9 percent
    from January 12, 2004.
    Wittman Mechanical filed this appeal.
    II
    A trial court may direct judgment as a matter of law only
    when there is no legally sufficient evidentiary basis for a
    reasonable jury to find in favor of the non-moving party.   Fed. R.
    Civ. P. 50(a)(1); Babcock v. Bell South Advertising & Publishing
    Corp., 
    348 F.3d 73
    , 76 (4th Cir. 2003).   In considering to grant
    a motion as a matter of law, notwithstanding the verdict, the
    court must view the evidence in the light most favorable to the
    non-moving party and draw all reasonable inferences in that
    party’s favor without weighing the evidence or considering the
    witnesses’ credibility.   Baynard v. Malone, 
    268 F.3d 228
    , 234-35
    (4th Cir. 2001).   Stated otherwise, judgment as a matter of law
    can be granted only if the evidence “supports only one reasonable
    conclusion as to the verdict” under the governing law.      Bank of
    Montreal v. Signet Bank, 
    193 F.3d 818
    , 831 (4th Cir. 1999).
    Our review of a district court’s grant of a Rule 50 motion
    applies the same standards de novo.   Brown v. CSX Transportation,
    Inc., 
    18 F.3d 245
    , 248 (4th Cir. 1994).
    8
    In this case, the district court found as a matter of law
    that Wittman Mechanical breached its express warranty when it
    failed to conduct a leak test before or after starting the
    furnace.     The court properly recognized that Wittman Mechanical
    could not have breached any warranty with regard to activating the
    gas pipeline system, because “the contract between [Virginia
    Residential] and Wittman Mechanical does not unambiguously cover
    propane gas piping and installation.”
    To find that Wittman Mechanical breached its warranties in
    connection with starting the furnace, the district court relied on
    the contract between Virginia Residential and Wittman Mechanical,
    in   which   Wittman    Mechanical     warranted   its   qualifications      to
    perform the “Work,” as defined in the contract; warranted it was
    familiar with and had sufficient knowledge of the “Work”; and
    warranted that its “Work” would be performed free of defects and
    in   accordance      with   sound   engineering    standards,    as   well   as
    standards of the industry.
    The    court    also    relied   on   the    furnace   manufacturer’s
    installation manual, which directed that the installer “pressure
    test” the “piping system”; inspect the “entire [piping] system”
    before turning on the gas; and test “the piping system” for
    leakage after gas is “turned on into” the system.               In connection
    with the particular task of installing the furnace, the furnace
    9
    manual    provided         a    warning     pertaining          to    “furnace          start-up
    procedures” as follows:
    Never purge a gas line into a combustion chamber. Never
    use matches, candles, flame or other sources of ignition
    for the purpose of checking leakage. Use a soap-and-
    water solution to check for leakage. Failure to follow
    this warning can cause fire, explosion, personal injury,
    or death.
    (Emphasis added).
    The court concluded that “Wittman Mechanical breached the
    express    warranties           contained       in    the    contract          [with    Virginia
    Residential] by failing to follow the practices and standards
    referenced      in    the       contract    and       specified           in   the      [furnace]
    installation manual and the National Fuel Gas Code.” It concluded
    that “[h]ad Wittman Mechanical’s workmen followed these practices
    --    specifically,        conducting       a    leak       test     --    they      would   have
    discovered the leak and thus have avoided the explosion.”
    It is undisputed in this case that Wittman Mechanical did not
    conduct any leak test.                  Nonetheless, a question still remains
    whether    its       failure       to    conduct       the     appropriate           leak    test
    conclusively caused the explosion.                     The jury obviously found that
    Wittman Mechanical’s failure to perform a leak test did not cause
    the    loss,    and    it       returned    a        verdict    in        favor    of     Wittman
    Mechanical.         We find that the jury’s verdict was reasonable and
    was supported by substantial evidence.
    The duties contained in the furnace installation manual, as
    outlined       by    the       district    court,       implied       that        the    furnace
    10
    installation subcontractor was also the subcontractor installing
    the “gas pipe system” and therefore was responsible for testing
    and turning on the gas pipeline system.       But, of course, in this
    case,   as   the   district   court    appropriately   recognized,   the
    responsibilities were divided between Wittman Mechanical and Peed
    Piping.      The “scope of work” assigned the responsibility of
    installing, testing, and activating the gas pipeline system to
    Peed Piping, and it assigned the responsibility of installing,
    testing, and starting up the furnace to Wittman Mechanical.          When
    reading the furnace installation manual in the light of these
    divided responsibilities, it becomes apparent that the furnace
    manual required the furnace installer to do only a soap-and-water
    leak test at the furnace’s connection with the gas pipe system,
    specifically warning the furnace installer not to conduct a
    pressure test.     The pressure test was reserved for testing the
    entire system.
    Reading from the furnace manual, which includes instructions
    relating to installation of the gas pipeline system as well as
    installation of the furnace, it states first with respect to the
    pipeline system:
    Piping should be pressure and leak tested in accordance
    with [the National Fuel Gas Code] . . . local, and
    national plumbing and gas codes before the furnace has
    been connected.
    11
    (Emphasis added).   But it states that after the furnace has been
    connected, the installer should perform a soap-and-water test
    where the furnace connects with the pipeline system:
    Never purge a gas line into a combustion chamber. Never
    test for gas leaks with an open flame.           Use a
    commercially available soap solution made specifically
    for the detection of leaks to check all connections. A
    failure to follow this warning could result in fire,
    explosion, personal injury, or death.
    The manual goes on to repeat this statement as a warning, stating
    again to “[u]se a soap-and-water solution to check for leakage.”
    Thus, while some portions of the furnace manual address the
    installation of a gas pipeline system, a task assigned to Peed
    Piping, other portions address installation and start-up of the
    furnace, which in this case was assigned to Wittman Mechanical.
    While it is undisputed that Wittman Mechanical did not
    perform the soap-and-water test, it is also undisputed that had it
    performed this test, the test would not have detected the leak.
    The leak was at a location away from the furnace’s connection to
    the system.   It was located where the main gas line connects with
    a spur gas line rising to the kitchen island.      Thus, the jury
    could well have concluded that Wittman Mechanical’s failure to
    conduct the only test the manual required it to perform -- the
    soap-and-water test at the furnace connection -- did not cause the
    explosion.    It was, thus, error for the district court to have
    disregarded the jury verdict when evidence existed to support the
    verdict.
    12
    For similar reasons, the district court would not be able to
    grant judgment notwithstanding the verdict on the negligence
    claim.    Even if it found that Wittman Mechanical was negligent in
    activating the gas system, as requested by Virginia Residential,
    the court would still have to recognize the possibility that the
    jury     could   have   found   Virginia   Residential   contributorily
    negligent in assuring Casteel that the system was ready to be
    activated, thus denying the possibility of its recovering from
    Wittman Mechanical.       See Jenkins v. Pyles, 
    611 S.E.2d 404
    , 407
    (Va. 2005) (citing Sawyer v. Comerci, 
    563 S.E.2d 748
    , 752 (Va.
    2002)).
    For the foregoing reasons, we vacate the judgment entered by
    the district court and remand this case to the district court with
    instructions to reinstate the verdict and to enter judgment in
    accordance with the reinstated verdict.
    IT IS SO ORDERED.
    13
    

Document Info

Docket Number: 06-2031

Judges: Niemeyer, Michael, Motz

Filed Date: 2/6/2008

Precedential Status: Non-Precedential

Modified Date: 10/19/2024