Aarow Equipment & Services, Inc. v. Travelers Casualty & Surety Co. of America , 417 F. App'x 366 ( 2011 )


Menu:
  •                              UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 10-1375
    AAROW EQUIPMENT & SERVICES, INCORPORATED, United States of
    America for the use and benefit of,
    Plaintiff - Appellant,
    v.
    TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA,
    Defendant - Appellee.
    Appeal from the United States District Court for the Eastern
    District of Virginia, at Alexandria.     Anthony J. Trenga,
    District Judge. (1:09-cv-00861-AJT-TCB)
    Argued:   January 27, 2011                 Decided:   March 18, 2011
    Before NIEMEYER, DAVIS, and KEENAN, Circuit Judges.
    Vacated and remanded by unpublished per curiam opinion.
    ARGUED: Michael Jacob Kalish, WALSH COLUCCI LUBELEY EMRICH &
    WALSH, PC, Prince William, Virginia, for Appellant.       James
    Dennis Coleman, WATT, TIEDER, HOFFAR & FITZGERALD, LLP, McLean,
    Virginia, for Appellee. ON BRIEF: Eugene Andrew Burcher, WALSH
    COLUCCI LUBELEY EMRICH & WALSH, PC, Prince William, Virginia,
    for Appellant.
    Unpublished opinions are not binding precedent in this circuit.
    PER CURIAM:
    This appeal concerns an action brought by a subcontractor
    against a surety under the Miller Act (the Act), 
    40 U.S.C. §§ 3131
     through -3134.         Under the Act, before a general contractor
    is awarded a contract by the federal government in an amount
    greater than $100,000, the general contractor is required to
    obtain    a   “payment     bond”   “for    the    protection     of   all   persons
    supplying labor and material in carrying out the work provided
    for in the contract.”         
    40 U.S.C. § 3131
    (b)(2).            The Act provides
    a cause of action, such as the one asserted here, permitting a
    subcontractor to file suit seeking payment from a surety on a
    payment bond when the subcontractor has not been paid by the
    general       contractor     within       90     days      of    completing     the
    subcontractor’s work.         
    40 U.S.C. § 3133
    (b)(1).            For the reasons
    that follow, we vacate the district court’s award of summary
    judgment in favor of the surety and remand the case for further
    proceedings.
    I.
    We review the facts in the light most favorable to Aarow,
    the non-moving party in the district court.                      Hooven-Lewis v.
    Caldera, 
    249 F.3d 259
    , 265 (4th Cir. 2001).                       In 2007, Syska
    Hennessy Group Construction, Inc. (Syska) was awarded a contract
    (the   prime     contract)    by   the        United    States   government    (the
    2
    government) to construct a training facility for the District of
    Columbia    Army    National     Guard       at       Fort   Belvoir,   Virginia   (the
    project).     Syska served as the general contractor on the project
    and obtained a payment bond, as required by the Miller Act, from
    Travelers Casualty and Surety Company of America (Travelers).
    Syska     awarded    Aarow     Equipment          &     Services,    Inc.    (Aarow)   a
    subcontract, which set forth the “work” that Aarow was required
    to perform on the project.
    Section 11.1 of the subcontract stated that Syska may “make
    changes in the [w]ork covered by this [s]ubcontract,” and that
    any   changes     must    be   made    in    writing.          The   subcontract   also
    provided that Aarow must submit in writing to Syska any claims
    for changes in the price or payment due under the contract.
    According    to     the   subcontract,           any    such   change   in    price    or
    payment to Arrow “shall be made” “only to the extent that” Syska
    is entitled to relief from the government, and payment to Aarow
    shall be equal to Aarow’s share of any adjustment to the prime
    contract.
    When changes to the “work” under the subcontract were made,
    Aarow generally submitted the proposed cost of the change to
    Syska, and Syska issued a “change order” to the subcontract.
    Aarow’s    “work”    described        in    the       subcontract    included   several
    categories of responsibilities, including “earthwork” relating
    to water distribution and drainage.                     During Aarow’s performance
    3
    of this “earthwork,” the government determined that the “erosion
    control      plan”    Aarow    was     implementing       was       “not    up    to
    standard[s].”         Aarow   ceased    working    until       it   received     new
    erosion      plan   “drawings,”   which     required     the    construction      of
    sedimentary ponds and other water management measures (the pond
    work).
    Aarow and Syska agreed that the pond work was not included
    in the “work” defined in the subcontract.                  In September 2007,
    Aarow submitted a proposal of $402,500 to Syska for the pond
    work.       Syska directed Aarow to perform the pond work, but did
    not issue a “change order” for the pond work at that time.
    Aarow completed the pond work, with the understanding that Syska
    would issue a “change order” at some point in the future.
    Upon      Syska’s   determination      that   the    pond      work   was   not
    included in the scope of the prime contract, 1 Syska asked that
    the government agree to a “modification” of the prime contract. 2
    Syska requested that Aarow wait to submit its invoice for the
    1
    The record does not contain a copy of the prime contract,
    and there were no depositions taken during discovery in this
    case of the government officials involved with the prime
    contract.
    2
    According to deposition testimony provided by a Syska
    employee, a “modification” is essentially the same as a “change
    order,” except that the prime contract was amended by a
    “modification,” while the subcontract was amended by a “change
    order.”
    4
    pond work until after the government issued a “modification” to
    the prime contract and Syska issued a “change order” to the
    subcontract.
    Several    months       later,    neither         a   “modification”      nor    a
    “change order” had been issued.                     Nevertheless, Aarow submitted
    an   invoice      to    Syska    for     the       completed    pond    work.      Syska
    instructed Aarow to use a billing procedure that would allow
    Syska to pay Aarow for the pond work even though a “change
    order” had not been issued.                    This billing procedure required
    Aarow to list the pond work under a “line item” designated for
    certain “finishing” work on the project that had not yet been
    completed. 3      According to Syska, the government had authorized
    this billing procedure while Syska’s “modification” request was
    pending.
    After Aarow complied with this different billing procedure
    in accordance with Syska’s directions, Syska submitted a similar
    invoice     to    the     government       identifying          the     pond    work    as
    “finishing” for a “three-story building.”                       The government paid
    Syska    $484,980,      which    included          the   invoice   in   the    amount   of
    $402,500 submitted by Aarow, plus a fee representing Syska’s
    “normal markup.”          Syska, in turn, paid Aarow $402,500 for the
    3
    The “finishing” work was included in the “work” described
    by the subcontract.
    5
    pond work.         Syska advised Aarow that after Syska received a
    “modification”          and    issued    a       “change    order,”        Aarow    could
    reallocate the funds received for the pond work to the proper
    “line    item.”         Shortly    after     the    government      paid     Syska    the
    requested amount of $484,980, the government determined that the
    pond work was included in the prime contract.                       Accordingly, the
    government denied Syska’s request for a “modification” of the
    prime contract based on the government’s construction of the
    prime contract’s terms.
    The government later withheld several payments to Syska to
    recover      the   funds      previously     paid    for     the    pond    work.     In
    response,     Syska      withheld    payment       from     Aarow   for     other    work
    completed by Aarow between May 2009 and June 2009.
    On July 1, 2009, Aarow sent Syska a letter stating that
    Syska had a “significant outstanding and past balance due,” and
    that Aarow would stop work on the project at the end of the week
    unless payment was made.            When Syska did not submit payment to
    Aarow under the terms of the demand, Aarow ceased work on the
    project.
    On July 17, 2009, Syska sent Aarow a letter notifying Aarow
    that    it   was   in    default    of     the     subcontract      for    failing   “to
    proceed with the work” according to the project schedule.                             In
    that    letter,    Syska      instructed     Aarow     to    correct      and   complete
    specific alleged defaults.              Aarow did not return to work on the
    6
    project or otherwise attempt to cure the alleged defaults.                      On
    July 23, 2009, Syska sent another letter to Aarow stating that
    because Aarow had not cured the defaults, Syska was terminating
    the subcontract as provided in Section 12.1 of that agreement.
    Section 12.1 of the subcontract stated, in relevant part:
    If, in the opinion of [Syska], [Aarow] shall at any
    time . . . fail in any respect to prosecute the Work
    according to the current schedule. . . then, after
    serving three (3) days written notice, unless the
    condition specified in such notice shall have been
    eliminated within such three (3) days, [Syska] may at
    its option . . . terminate the Subcontract for default
    . . . . [Aarow] shall not be entitled to receive any
    further payment until the Work shall be fully
    completed and accepted by [the government].
    Under     Section    12.2    of   the   subcontract,      however,      if   Syska
    wrongfully terminated the subcontract, Syska would be liable for
    “the reasonable value of [the] Work performed by [Aarow] prior
    to [Syska’s] wrongful action.”
    With regard to payment, the subcontract required that Syska
    pay   Aarow   monthly,      provided    that    Syska   already   had    received
    payment    from     the   government.        This   “pay-when-paid”     provision
    stated, in relevant part:
    Conditioned upon the satisfactory progress of [Aarow],
    compliance with the documentation requirements of this
    Subcontract, and [Syska] has received payment from the
    [government] THEN [Syska] will make monthly payments
    to [Aarow].   [Aarow] acknowledges and agrees that in
    the event payment is not made to [Syska] for any
    reason . . . [Aarow] shall look exclusively to [the
    government] for payment of any and all funds due under
    this Contract.   [Aarow] further agrees that the delay
    in payment or nonpayment by the [government] does not
    7
    create any separate obligation of [Syska]                              to    pay
    regardless of the extent of the delay.
    In its complaint filed against Travelers, the surety on
    Syska’s payment bond, Aarow asserted that Syska breached the
    subcontract by failing to pay Aarow for several months.                                  Aarow
    sought from Travelers the sum of Aarow’s past-due invoices to
    Syska, in the amount of $484,870.71.
    In response, Travelers filed an answer and a motion for
    summary judgment.           Aarow opposed the motion, and the parties
    filed    a   series    of    briefs     addressing         numerous      issues.           In
    December 2009, the district court held a hearing on the motion
    for summary judgment.
    In its pleadings and during the hearing, Travelers asserted
    two primary arguments in support of its motion.                        Travelers first
    maintained      that     because      the       terms     of     the   “pay-when-paid”
    provision in the subcontract were clear and the government did
    not   pay    Syska    for   several    months,          Syska    did   not    breach       its
    payment obligation to Aarow under the subcontract.                                Travelers
    thus contended that Syska properly terminated the subcontract
    under Section 12.1 based on Aarow’s failure to perform, and that
    Aarow was not entitled to payment under the terms of Section
    12.1.        Travelers      argued    alternatively             that   even       if   Syska
    wrongfully had terminated the subcontract, Syska paid Aarow more
    8
    than Aarow was due under the subcontract and, therefore, Aarow
    was not entitled to additional payment.
    Two months after the hearing, but before the district court
    entered its judgment, Travelers requested leave to supplement
    its motion for summary judgment to discuss a new decision issued
    by this Court.     In that supplemental pleading, Travelers argued
    that under this Court’s decision in Universal Concrete v. Turner
    Construction Co., 
    595 F.3d 527
     (4th Cir. 2010), “pay-when-paid”
    provisions are valid defenses in a breach of contract action
    when the terms of such provisions are unambiguous.
    Aarow filed a brief in response, arguing that the holding
    in Universal Concrete did not establish a new principle of law.
    (J.A. 649.)      Aarow also cited in its supplemental brief the
    “prevention doctrine,” a principle of contract law establishing
    that one who prevents the performance or the happening of a
    condition to     his   performance    may   not    take   advantage    of   that
    condition.    See Barnhill v. Veneman, 
    524 F.3d 458
    , 474 (4th Cir.
    2008).   Aarow contended that this doctrine barred Syska from
    relying on the “pay-when-paid” provision of the contract because
    Syska was partially at fault for the government’s failure to
    make the requested payment to Syska.              Aarow argued that Syska’s
    fault was demonstrated by its failure to obtain the appropriate
    “modification”    to   the   prime   contract,     and    by   its   failure   to
    issue a “change order” to the subcontract for the pond work.
    9
    The district court entered an order permitting both parties to
    supplement the record with these pleadings.
    Three      weeks    later,   the       district     court    entered    an    order
    granting       summary    judgment     in    favor      of   Travelers.       In    its
    memorandum opinion, the district court held that because the
    subcontract contained an enforceable “pay-when-paid” provision,
    and because it was undisputed that the government failed to pay
    Syska    for    several    months,     Aarow      was    unable   to   “justify     its
    [w]ork     stoppage      based    on    Syska’s         failure   to   pay    Aarow.”
    Notably, the district court did not address Aarow’s prevention
    doctrine argument.
    The district court concluded that Syska’s “termination for
    default” was proper under Section 12.1 of the subcontract based
    on Aarow’s failure to complete its work under the subcontract.
    Accordingly, the district court held that Aarow was not owed
    payment under the subcontract and that, therefore, Travelers had
    “no payment obligation to Aarow.”                  Aarow filed a timely appeal
    in this court.
    II.
    We review the district court’s award of summary judgment de
    novo.     See S.C. Green Party v. S.C. State Election Comm’n, 
    612 F.3d 752
    , 755 (4th Cir. 2010).                Under Rule 56(a) of the Federal
    Rules of Civil Procedure, summary judgment is appropriate when
    10
    the moving party “shows that there is no genuine dispute as to
    any material fact” and when the moving party “is entitled to
    judgment     as   a   matter     of    law.”        Fed.    R.    Civ.    P.    56(a);       see
    Anderson     v.     Liberty     Lobby,    Inc.,      
    477 U.S. 242
    ,    247    (1986)
    (construing       former     Rule     56(c)    of   the    Federal       Rules    of       Civil
    Procedure).
    A.
    Aarow argues on appeal that the district court erred in
    failing to apply the prevention doctrine in determining whether
    Travelers was entitled to judgment as a matter of law.                                     Aarow
    asserts that Syska was responsible for the government’s failure
    to    make    the     requested        payment      under        the    prime     contract.
    Therefore, according to Aarow, a jury should determine whether
    Syska breached the terms of the subcontract by failing to pay
    Aarow for the work it had completed.
    In     response,       Travelers     argues         that    the    district          court
    properly     granted     summary       judgment      in    its    favor.         Initially,
    Travelers contends that Aarow’s prevention doctrine argument was
    not   asserted        timely     and    should      not     be     considered         in     the
    resolution of this appeal.                Addressing the merits of Aarow’s
    argument, Travelers asserts that because the government withheld
    payment from Syska, the terms of Syska’s subcontract with Aarow
    permitted     Syska     to     withhold       the   requested       payment      to    Aarow.
    11
    Travelers        therefore         maintains        that,        as    a     matter     of    law,
    Travelers        did   not    owe     any    payment        to    Aarow         under   the   bond
    because Syska complied with the terms of the subcontract and
    Aarow      wrongfully        abandoned       the     project.              We     disagree    with
    Travelers’ arguments.
    We find no merit in Travelers’ assertion that Aarow failed
    to preserve its prevention doctrine argument in the district
    court.       Although Aarow used the term “prevention doctrine” for
    the    first     time    in    a    later-filed        supplemental               pleading,    the
    district court accepted that supplemental pleading and included
    it    in   the    record      three    weeks       before        the   court       rendered    its
    judgment.          Furthermore,         in     Aarow’s       initial            brief    opposing
    summary judgment, Aarow set forth the factual predicate for its
    prevention doctrine argument by asserting that Syska directed
    Aarow to complete the pond work before issuing a “change order”
    for that work, and that Syska acted in bad faith by attempting
    to “back charge” Aarow for the pond work.                                  Thus, we conclude
    that       Aarow’s      prevention          doctrine        argument            was     presented
    adequately       to    the    district       court     and       was       not,    as   Travelers
    argues, articulated for the first time on appeal.                                  See Evans v.
    Metro. Life Ins. Co., 
    358 F.3d 307
    , 310 n.2 (4th Cir. 2004)
    (explaining that although appellant’s argument was not raised in
    district court until oral argument on the motion for summary
    judgment, the argument was preserved for appellate review).
    12
    B.
    We turn to examine the present record to determine whether
    Travelers was entitled to judgment as a matter of law at the
    summary judgment stage of the proceedings.                       Based on Aarow’s
    argument      before    the   district         court,     we        give   particular
    consideration to the evidence before the district court bearing
    on the issue of the prevention doctrine.
    Under the prevention doctrine, when a general contractor
    materially contributes to the failure of a condition limiting
    the duty to perform under a contract, the general contractor may
    not rely on that failure as a defense to its performance of its
    contractual obligations.        See Moore Bros. Co. v. Brown & Root,
    Inc., 
    207 F.3d 717
    , 725 (4th Cir. 2000).                 In Moore Brothers, we
    applied the prevention doctrine in a dispute involving a “pay-
    when-paid” provision in a subcontract.                   There, in response to
    two    subcontractors    seeking    payment       for     completed        work,   the
    general    contractor    asserted   as     a    defense       the    “pay-when-paid”
    condition in the subcontract and the owner’s failure to pay the
    general contractor.      
    Id. at 724-25
    .
    We affirmed the district court’s award of summary judgment
    in favor of the subcontractors because the record established
    that    the   general    contractor      materially           contributed    to    the
    owner’s failure to pay.       
    Id. at 725-26
    .            Thus, we concluded that
    the    general   contractor   was   liable       to     its    subcontractors      for
    13
    payment    notwithstanding            the    “pay-when-paid”           provision     in    the
    subcontract.         
    Id. at 725
    .        Applying         our    analysis     in    Moore
    Brothers     to     the    present      case,       we    consider       whether     a     jury
    reasonably        could      find       that        Syska’s          actions      materially
    contributed to the government’s failure to pay Syska under the
    prime contract, thereby preventing Travelers from relying on the
    “pay-when-paid”       condition         in    the    subcontract          in     defense       of
    Syska’s failure to pay Aarow.
    Travelers maintains that the government directed the method
    of billing for the pond work and that, therefore, Syska was not
    responsible for the government’s refusal to pay Syska when the
    government later determined that the billing for the pond work
    was improper.        In support of its position, Travelers relies on
    the   deposition      testimony        of    Robert       F.   Geremia,        Syska’s     vice
    president      in    charge      of    construction,            who     stated    that     the
    government had “instructed my people in the field to bill for
    some [finishing] work that actually wasn’t done.”
    Aarow,      however,       asserts     that        Syska’s      actions     materially
    contributed to the government’s failure to make the payment at
    issue.      Aarow     points      to    evidence         in    the    record     that    Syska
    directed Aarow to perform the pond work even though Syska had
    not issued a “change order” or received a “modification” to the
    prime contract.           The record also contains evidence that Aarow
    completed    the     pond     work,     relying      on       Syska’s    promise        that    a
    14
    “change order” was forthcoming.                          However, when Syska did not
    obtain a        “change        order,”    Syska         directed    Aarow      to    remove    its
    invoice references to “sediment ponds and associated work,” and
    to categorize the pond work as “finishes” for a “three-story
    building,” which had not yet been constructed.
    Based     on    these     facts,       a   jury       reasonably      could    return    a
    verdict for Aarow if the jury concluded that Syska’s actions, in
    directing       Aarow      to    perform        the      pond    work    before       issuing    a
    “change order,” and in agreeing to employ an arguably improper
    billing procedure that obscured the expanded scope of the “work”
    under       the        subcontract,            materially          contributed         to      the
    government’s           later    decision        to      withhold    certain         payments    to
    Syska.          If     Syska’s     actions           materially      contributed        to     the
    government’s decision, Travelers could not rely on the “pay-
    when-paid”        provision        of     the        subcontract        to    excuse     Syska’s
    failure      to      pay       Aarow     for       its    work     performed         under     the
    subcontract.           See Moore Bros., 207 F.3d at 725.
    We are not persuaded by Travelers’ assertion that it was
    entitled to summary judgment based on Geremia’s testimony that
    the     government         instructed      Syska         to     employ       the    questionable
    billing procedure.              In essence, Travelers seeks to absolve Syska
    of    any    responsibility              for       the    arguably       improper       billing
    procedure because “the project owner told us to do it.”                                        The
    allocation of responsibility for the billing practices, however,
    15
    raises   credibility      issues   and    other   issues    of   fact    that   are
    matters for a jury’s consideration.                Therefore, we hold that
    Travelers was not entitled to summary judgment on the issues
    whether Syska breached the subcontract and whether Aarow was
    entitled to payment from Travelers under the bond. 4
    For      these   reasons,   we   conclude    that     the   district   court
    erred    in    granting   summary     judgment    in     favor   of     Travelers.
    Accordingly, we vacate the district court’s judgment and remand
    the case for further proceedings consistent with this opinion.
    VACATED AND REMANDED
    4
    Based on our holding, we do not address Aarow’s remaining
    argument regarding the issue whether the district court erred in
    relying on letters from Syska’s counsel to Aarow relating to
    Syska’s termination of the subcontract.        We also need not
    address Aarow’s contention that the district court’s judgment
    violated the policy underlying the Miller Act.
    16