US EX REL. AAROW/IET LLC. v. Hartford Fire Insurance ( 2020 )


Menu:
  •                                      UNPUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 19-1710
    UNITED STATES EX REL. AAROW/IET LLC,
    Plaintiff – Appellant,
    v.
    HARTFORD FIRE INSURANCE COMPANY,
    Defendant – Appellee,
    and
    HARPER CONSTRUCTION COMPANY,
    Intervenor/Defendant – Appellee.
    ------------------------------
    THE AMERICAN SUBCONTRACTORS ASSOCIATION; THE AMERICAN
    SUBCONTRACTORS ASSOCIATION OF METRO WASHINGTON,
    Amici Supporting Appellant.
    Appeal from the United States District Court for the Eastern District of Virginia, at
    Alexandria. Anthony John Trenga, District Judge. (1:19-cv-00085-AJT-JFA)
    Argued: September 10, 2020                                  Decided: December 10, 2020
    Before MOTZ, KING, and FLOYD, Circuit Judges.
    Vacated and remanded by unpublished per curiam opinion.
    ARGUED: Eli Robbins, HARRISON LAW GROUP, Towson, Maryland, for Appellant.
    Michael S. McNamara, PILLSBURY WINTHROP SHAW PITTMAN, LLP, Washington,
    D.C., for Appellees. ON BRIEF: Adam C. Harrison, HARRISON LAW GROUP,
    Towson, Maryland, for Appellant. William A. DeVan, CONSTRUCTIONLEX, PLC,
    Alexandria, Virginia, for Appellee Hartford Fire Insurance Company. Clare Cavaliero
    Pincoski, PILLSBURY WINTHROP SHAW PITTMAN LLP, Washington, D.C., for
    Appellee Harper Construction Company, Inc. Eric B. Travers, KEGLER, BROWN, HILL
    & RITTER CO., LPA, Columbus, Ohio, for Amici The American Subcontractors
    Association and The American Subcontractors Association of Metro Washington.
    Unpublished opinions are not binding precedent in this circuit.
    2
    PER CURIAM:
    In this Eastern District of Virginia civil action, plaintiff Aarow/IET LLC brought a
    breach of contract claim against defendant Harper Construction Company and a Miller Act
    claim against defendant Hartford Fire Insurance Company. On Harper’s motion seeking
    dismissal of the breach of contract claim against it, the district court dismissed the entire
    action, including the Miller Act claim against Hartford. See Aarow/IET LLC v. Hartford
    Fire Ins. Co., No. 1:19-cv-00085 (E.D. Va. June 3, 2019), ECF No. 56 (the “Dismissal
    Order”). Aarow has appealed from the court’s judgment and, as explained herein, we
    vacate and remand for further proceedings.
    I.
    A.
    Aarow is a subcontractor that performed electrical work on the Basic School Student
    Officer Quarters at Marine Corps Base Quantico in Virginia (the “Project”), pursuant to a
    May 2014 agreement with Harper (the “Subcontract”). Harper was the general contractor
    for the Project under its prime contract with the United States government. Hartford is a
    commercial surety company that provided a payment bond to protect Aarow and other
    subcontractors supplying labor and materials to the Project (the “Payment Bond”), in
    accordance with the requirements of the Miller Act. See 
    40 U.S.C. § 3131
    (b)(2); see also
    J.W. Bateson Co. v. United States ex rel. Bd. of Trs. of Nat’l Automatic Sprinkler Indus.
    Pension Fund, 
    434 U.S. 586
    , 589 (1978) (“[T]he Miller Act was designed to provide an
    alternative remedy to the mechanics’ liens ordinarily available on private construction
    3
    projects. Because a lien cannot attach to Government property, persons supplying labor or
    materials on a federal construction project were to be protected by a payment bond.”
    (citations and internal quotation marks omitted)).
    Under the Subcontract, Aarow agreed to perform building and site electrical work
    for Phases 5 and 6 of the Project for the “base contract amount” of $5,345,000. See J.A.
    105. 1 Aarow also agreed to perform similar work for Phase 7 of the Project as “pre-priced
    option[s]” specified in the Subcontract. 
    Id.
    There are several provisions of the Subcontract relevant to these proceedings.
    Article 5 provides, in pertinent part:
    Cooperation between Parties: The Contractor shall cooperate with the
    Subcontractor for the prosecution of the work, and the Subcontractor shall
    cooperate with the Contractor and with other Subcontractors employed by
    the Contractor and with other Contractors employed by the Owner, in order
    to insure first class workmanship in every respect and the proper sequence of
    the work.
    See J.A. 102. Article 6 pertains to the scheduling of the times for the start and finish of the
    work. Article 7 provides:
    Extension of Time of Completion: If the Subcontractor shall be obstructed
    or delayed in the prosecution or completion of the work by the neglect or
    default of the Contractor, . . . then the time, as fixed in Article 6 for the
    completion of the work, shall be extended for a period necessary to make up
    for lost time . . . .
    
    Id.
    1
    Citations herein to “J.A. __” refer to the contents of the Joint Appendix filed by
    the parties in this appeal.
    4
    Article 8 of the Subcontract, which is referred to in these proceedings as a “no-
    damages-for-delay” provision, states as follows:
    Delays:
    A.     In the event of any delays, entailed as a result of fault of Contractor
    . . . , then Contractor shall grant Subcontractor an extension of time
    equal to the delay and Subcontractor shall be entitled to no other or
    further damages against Contractor . . . .
    B.     Any delays or additional work entailed as a result of weather
    conditions, storms, acts of God, delays in construction, and delays by
    governmental bodies will not entitle the Subcontractor to any extras
    whatsoever.
    See J.A. 102. Finally, Article 26 provides:
    Claims by Either Party Against the Other: If either the Subcontractor or
    Contractor believes he has a claim of any nature whatsoever against the other
    party, he shall give the other written notice of the amount, whenever possible,
    and nature of such claim within ninety (90) days . . . of the occurrence of the
    event upon which such claim is based. In default of such notice the claim is
    waived.
    Id. at 103.
    During its work on the Project, Aarow gave Harper at least one written notice of a
    claim — an April 2018 request for equitable adjustment seeking an additional $2,900,619
    for work on Phases 5, 6, and 7 (the “REA”). The REA advises that it is “for actual costs
    related to additional time, labor, general conditions, overhead and bond costs for the
    completion of the electrical.” See J.A. 111. Furthermore, the REA states that this “proposal
    does not include any cost amounts for extended contract durations, overtime, unforeseen
    conditions, changes in the sequence of work, acceleration, disruptions, and impacts, unless
    specifically noted otherwise.” Id. at 110. The REA notes that Phases 5 and 6 of the Project
    5
    began on schedule on May 20, 2014, but did not end until September 3, 2016 — 174
    workdays after the scheduled end date of December 29, 2015. Phase 7 started late (on
    October 1, 2016, instead of August 6, 2016); was projected to finish late (on May 16, 2018,
    instead of November 7, 2017); and was therefore going to take 124 more workdays than
    had been scheduled. The REA cites a “Total Overall Project Extension of 298 working
    days” and calculates various “Delay Cost[s]” based on 298 “Delay Days.” Id. at 111, 113.
    The REA also twice asserts that 298 days was “not entire delay.” Id. at 113.
    B.
    After Harper refused to pay Aarow the additional compensation sought by way of
    the REA, Aarow initiated this civil action in January 2019. Aarow’s original Complaint
    named Hartford as the sole defendant and asserted only the Miller Act claim for recovery
    on the Payment Bond. See Aarow/IET LLC v. Hartford Fire Ins. Co., No. 1:19-cv-00085
    (E.D. Va. Jan. 23, 2019), ECF No. 1 (the “Complaint”). The Complaint alleged that “the
    Project suffered from numerous disruptions, all of which impacted Aarow’s ability to
    prosecute its work on the Project in the timely, efficient, and sequential manner which it
    originally anticipated and planned when it compiled its price to perform its work on the
    Project.” Id. ¶ 9. Notably, the Complaint did not expressly blame Harper for the alleged
    disruptions, and it sought the same amount of compensation — $2,900,619 — that had
    been demanded in the REA. The Complaint specified that “Aarow submitted [the REA]
    to Harper” in April 2018 and that “Harper refused to compensate Aarow for the additional
    labor it rendered to the Project.” Id. ¶¶ 16-17. The Payment Bond, Subcontract, and REA
    were attached to the Complaint as exhibits.
    6
    In early March 2019, Hartford responded to the Complaint with a motion to dismiss
    under Federal Rule of Civil Procedure 12(b)(6) for failure to state a claim upon which relief
    can be granted. To support its dismissal motion, Hartford contended that its Miller Act
    liability on the Payment Bond as surety is derivative of its principal Harper’s liability on
    the Subcontract. Hartford further asserted that, because the Complaint did not allege that
    Harper was responsible for the alleged disruptions to Aarow’s work or that Harper
    breached the Subcontract, Aarow failed to plead facts indicating that Harper was liable on
    the Subcontract. Consequently, Hartford argued, Aarow failed to state a plausible Miller
    Act claim against Hartford. On the same day that Hartford filed its dismissal motion,
    Harper filed a motion to intervene in this action, which the district court immediately
    granted.
    By its mid-March 2019 memorandum in opposition to Hartford’s dismissal motion,
    Aarow contested the predicate for the motion — that Hartford’s liability on the Payment
    Bond is derivative of Harper’s liability on the Subcontract. Under Aarow’s theory, the
    Miller Act requires Hartford to pay Aarow for uncompensated labor and materials provided
    to the Project, even if Harper’s failure to pay for the labor and materials was not in breach
    of contract. Moreover, Hartford is liable for the additional costs incurred by Aarow as a
    result of disruptions to its work on the Project, whether or not Harper was responsible for
    the disruptions. According to Aarow, its interpretation of the Miller Act is supported by
    persuasive authority, including decisions from district courts within our Circuit and
    decisions of other courts of appeals.
    7
    During a late March 2019 hearing on Hartford’s dismissal motion, the district court
    expressed skepticism as to the soundness of Aarow’s theory that the Miller Act authorizes
    a recovery against Hartford on the Payment Bond absent Harper’s liability on the
    Subcontract. Rather than ruling at the hearing, however, the court took the dismissal
    motion under advisement.
    C.
    1.
    In April 2019, having not yet ruled on Hartford’s motion to dismiss the Complaint,
    the district court granted Aarow leave to file a First Amended Complaint. See Aarow/IET
    LLC v. Hartford Fire Ins. Co., No. 1:19-cv-00085 (E.D. Va. Apr. 9, 2019), ECF No. 29
    (the “Amended Complaint”). The Amended Complaint asserts the two claims whose
    dismissal is contested in this appeal — the Miller Act claim against Hartford, plus the
    breach of contract claim against Harper. 2
    Significantly, the Amended Complaint includes allegations of Harper’s wrongdoing
    not found in its predecessor. For example, the Amended Complaint alleges that “Harper
    did not cooperate with [Aarow] in the scheduling and sequencing of Aarow’s work on the
    Project,” as required under Article 5 of the Subcontract. See Amended Complaint ¶ 19.
    Additionally, the Amended Complaint blames Harper for the disruptions that caused
    Aarow to incur additional labor costs, alleging:
    2
    The Amended Complaint had asserted a third claim — a claim against Harper for
    breach of the implied duty of good faith and fair dealing — that was also dismissed by the
    district court. On appeal, Aarow does not challenge the dismissal of that claim.
    8
    Due to Harper’s mismanagement of the Project, the Project suffered from
    numerous disruptions, all of which impacted Aarow’s ability to prosecute its
    work on the Project in the timely, efficient, and sequential manner which it
    originally anticipated and planned when it compiled its price to perform its
    work on the Project. By way of example, Harper’s mismanagement caused
    Aarow to experience labor inefficiencies and loss of productivity through
    comeback work, stacking of trades, out-of-sequence work, and idle labor
    crews due to areas not ready to receive Aarow’s work.
    Id. ¶ 20. The Amended Complaint seeks the same amount of damages as demanded in the
    Complaint and the REA — $2,900,619 — though it repeatedly attributes those damages to
    “Harper’s mismanagement.” Id. ¶¶ 20-23, 28-29, 31. Like the Complaint, the Amended
    Complaint explains that “Aarow submitted [the REA] to Harper” in April 2018 and that
    “Harper refused to compensate Aarow for the additional labor it rendered to the Project.”
    Id. ¶¶ 30, 32.
    Specific to the breach of contract claim against Harper, the Amended Complaint
    alleges that “Harper breached the Subcontract by failing to cooperate with Aarow and by
    failing to ensure that Aarow’s work on the Project was properly sequenced.” See Amended
    Complaint ¶ 49. The Amended Complaint further alleges that “[o]n numerous occasions
    throughout the course of working on the Project, Aarow notified Harper that it was
    encountering problems on the Project which were causing impacts to its ability to timely,
    properly, and efficiently perform its work on the Project.” Id. ¶ 50. Lastly, the Amended
    Complaint alleges that “Aarow has satisfied all conditions precedent under the Subcontract
    to bringing its [breach of contract] claim against Harper.” Id. ¶ 53. The Payment Bond,
    Subcontract, and REA are attached to the Amended Complaint as exhibits, just as they had
    been attached to its predecessor.
    9
    2.
    Although Hartford had moved to dismiss the Complaint, it opted to file an Answer
    to the Amended Complaint rather than another dismissal motion aimed at the Miller Act
    claim. In May 2019, however, Harper filed a motion to dismiss the Amended Complaint,
    seeking a Rule 12(b)(6) dismissal of the breach of contract claim. Thereafter, Hartford
    joined Harper in contesting the plausibility of the breach of contract claim, still without
    requesting dismissal of the Miller Act claim.
    The district court conducted a hearing on Harper’s dismissal motion in June 2019.
    By that time, Harper (with support from Hartford) was offering four principal reasons why
    the breach of contract claim should be dismissed. First, Harper maintained that —
    notwithstanding the Amended Complaint’s efforts to characterize the breach of contract
    claim as a “disruption” claim — the claim is actually a “delay” claim barred by the
    Subcontract’s Article 8 no-damages-for-delay provision. In that regard, Harper contended
    that disruption claims are tantamount to delay claims as a matter of contract law.
    Second, Harper argued that to the extent that the Amended Complaint may be
    interpreted to assert a viable disruption claim, the Amended Complaint conflicts with the
    attached REA and its clear declaration of a delay claim barred by Article 8 of the
    Subcontract. Therefore, under the exhibit-prevails rule, the REA negates the Amended
    Complaint. See Goines v. Valley Cmty. Servs. Bd., 
    822 F.3d 159
    , 166 (4th Cir. 2016)
    (explaining “the exhibit-prevails rule, which provides that in the event of conflict between
    the bare allegations of the complaint and any exhibit attached, the exhibit prevails”
    (alteration and internal quotation marks omitted)).
    10
    Third, Harper contended that any disruption claim is nevertheless barred by Article
    8 when read in conjunction with Article 7 of the Subcontract. More specifically, Harper
    suggested that because Article 7 refers to the Subcontractor being “obstructed or delayed,”
    see J.A. 102, Article 8 is not just a no-damages-for-delay provision, but a “no-damages-
    for-delay-or-obstruction” provision.
    And fourth, Harper argued that the breach of contract claim is proscribed under the
    Subcontract for violation of the Article 26 requirement for written notice of a claim within
    ninety days. On the premise that the Amended Complaint reflects that the REA was the
    sole written notice of Aarow’s claim, Harper contended that Aarow contravened the ninety-
    day notice deadline by submitting the REA in April 2018, approximately nineteen months
    after Phases 5 and 6 of the Project were belatedly completed and five months after the
    missed completion date for Phase 7.
    In response, Aarow insisted that the Amended Complaint asserts a disruption claim
    — not a delay claim — and that there are meaningful distinctions between disruption and
    delay claims that would become clearer with discovery. Contesting Harper’s argument
    with respect to the exhibit-prevails rule, Aarow argued that the rule is inapplicable because
    the REA does not state a delay claim and thus does not conflict with the disruption
    allegations contained in the Amended Complaint. Notably, Aarow acknowledged that the
    REA “entitled this a delay claim.” See J.A. 197. Aarow elaborated, however, that the REA
    actually asserts a disruption claim and simply utilizes delay days to estimate the additional
    costs caused by the disruptions. Furthermore, Aarow explained that it attached the REA
    11
    to the Amended Complaint merely to establish that it had demanded payment from Harper
    for disruption-related costs and had been rebuffed.
    To counter Harper’s contention that even a disruption claim is barred by Article 8
    of the Subcontract, Aarow emphasized that Article 8 references only “delays” when, like
    Article 7, it could have referenced both “obstruct[ions]” and “delay[s].” See J.A. 102. As
    such, according to Aarow, Article 8 is a narrow no-damages-for-delay provision and not a
    no-damages-for-delay-or-obstruction provision.
    Finally, Aarow disputed Harper’s argument that the breach of contract claim is
    proscribed for violation of the Subcontract’s Article 26 requirement for written notice of a
    claim within ninety days. That is, Aarow contested the premise that the Amended
    Complaint identifies the REA as Aarow’s only written notice of its claim against Harper.
    Aarow pointed to the Amended Complaint’s allegation that “[o]n numerous occasions
    throughout the course of working on the Project, Aarow notified Harper that it was
    encountering problems on the Project which were causing impacts to its ability to timely,
    properly, and efficiently perform its work on the Project.” See Amended Complaint ¶ 50.
    Aarow also highlighted the Amended Complaint’s separate allegation that “Aarow has
    satisfied all conditions precedent under the Subcontract to bringing its [breach of contract]
    claim against Harper.” See 
    id. ¶ 53
    . Expanding on those allegations, Aarow proffered that
    it had notified Harper more than ninety times, in writing on Harper’s forms, of various
    disruptions throughout the course of the Project. In sum, Aarow contended that the
    Amended Complaint is sufficient and that discovery should proceed on its breach of
    contract claim.
    12
    3.
    At the conclusion of the June 2019 hearing, following the parties’ arguments, the
    district court announced its decision. Addressing Aarow’s breach of contract claim against
    Harper, the court accepted that there may be meaningful distinctions between disruption
    claims and delay claims, and it declined to adopt Harper’s theory that Article 8 of the
    Subcontract constitutes a no-damages-for-delay-or-obstruction provision.         The court
    explained:
    As a matter of contract construction, the Court finds significant that while
    [Article 7] explicitly states that the [Sub]contractor shall be entitled to an
    extension in the event of delays or obstruction of work, [Article 8] prohibits
    any extras only for delays, and so it would appear that the [Sub]contract
    recognizes to some degree a distinction with respect to remedies for those
    pertaining to delays and those pertaining to disruptions.
    See J.A. 214. Nevertheless, the court criticized the Amended Complaint for “mak[ing]
    little more than conclusory allegations that damages it seeks were attributable to what
    would be within the scope of obstruction as opposed to delays.” 
    Id. at 215
    . Moreover, the
    court observed that “to the extent [the Amended Complaint] has alleged any facts, those
    allegations appear to be inconsistent to a large degree by the substance of the [REA].” 
    Id.
    As the court described it, the REA “makes clear . . . on its face that [Aarow’s] claim is a
    delay claim and that the increased costs [Aarow] sought reimbursement for were due to
    that delay.” 
    Id.
     Accordingly, the court applied the exhibit-prevails rule and concluded that
    Aarow has asserted a delay claim barred by the Article 8 no-damages-for-delay provision.
    Additionally, the district court determined that Aarow’s breach of contract claim is
    proscribed under the Subcontract for violation of the Article 26 requirement for written
    13
    notice of a claim within ninety days. The court reasoned that the REA is “the only written
    notice that appears from the face of the [Amended Complaint]” and that neither the
    Amended Complaint nor the REA reflect that any of the claimed costs were incurred within
    ninety days of the submission date of the REA. See J.A. 216.
    Having thus decided to dismiss the breach of contract claim against Harper, the
    district court proceeded to dismiss sua sponte the Miller Act claim against Hartford. In so
    doing, the court declared that the Miller Act “claim depends on Harper being liable as to
    the [breach of contract claim].” See J.A. 218. The court also explained that because the
    breach of contract claim was being dismissed, the Miller Act claim had to be dismissed “as
    well.” 
    Id.
    By its Dismissal Order of that same day, the district court granted Harper’s motion
    to dismiss and specified that it was dismissing the entire action. Aarow timely noted this
    appeal, and we possess jurisdiction pursuant to 
    28 U.S.C. § 1291
    .
    II.
    We review de novo the dismissal of a complaint pursuant to Federal Rule of Civil
    Procedure 12(b)(6). See Attkisson v. Holder, 
    925 F.3d 606
    , 619 (4th Cir. 2019). In our
    review, we accept all well-pleaded facts as true and draw all reasonable inferences in favor
    of the plaintiff. 
    Id.
     We are also cognizant that, under Federal Rule of Civil Procedure
    8(a)(2), a complaint needs “only a short and plain statement of the claim showing that the
    pleader is entitled to relief, in order to give the defendant fair notice of what the claim is
    14
    and the grounds upon which it rests.” See Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    , 555
    (2007) (alteration and internal quotation marks omitted).
    III.
    Limiting our review to the reasons given by the district court for its dismissal of
    Aarow’s claims, we conclude that the court erred. We therefore vacate the judgment and
    remand for further proceedings on the breach of contract claim against Harper and the
    Miller Act claim against Hartford.
    In dismissing the breach of contract claim, the district court determined that the
    REA clearly states a delay claim and thus conflicts with the Amended Complaint’s
    allegations of a disruption claim. Applying the exhibit-prevails rule, the court then
    pronounced that Aarow’s claim is a delay claim barred by the Subcontract’s Article 8 no-
    damages-for-delay provision. Contrary to the court’s ruling, the REA does not clearly state
    a delay claim. To be sure, the REA repeatedly uses the word “delay” and calculates “Delay
    Cost[s]” based on “Delay Days.”       See J.A. 111, 113.     But the REA also refers to
    “disruptions,” albeit ambiguously. See id. at 110 (stating that this “proposal does not
    include any cost amounts for . . . disruptions, . . . unless specifically noted otherwise”).
    Moreover, the Amended Complaint indicates that the REA followed “numerous” notices
    to Harper from Aarow about disruptions to its work on the Project — notices that may well
    shed light on the meaning of the REA.          See Amended Complaint ¶ 50.         In these
    circumstances, where the REA is ambiguous and potentially clarifying evidence awaits
    presentation, we cannot endorse the court’s reliance on the REA and the exhibit-prevails
    15
    rule to dismiss Aarow’s breach of contract claim. Simply put, this is not a situation in
    which it is readily apparent that “dismissal is appropriate [because] the document [attached
    to the complaint] negates the claim.” See Goines v. Valley Cmty. Servs. Bd., 
    822 F.3d 159
    ,
    166 (4th Cir. 2016) (internal quotation marks omitted). 3
    The other reason given by the district court for its dismissal of the breach of contract
    claim is that Aarow violated the Subcontract’s Article 26 requirement for written notice of
    its claim within ninety days. In so ruling, the court erroneously considered only the REA
    and disregarded the Amended Complaint’s allegations that Aarow provided “numerous”
    notices to Harper about work disruptions and “satisfied all conditions precedent under the
    Subcontract to bringing its [breach of contract] claim.” See Amended Complaint ¶¶ 50,
    53. Those allegations are sufficient to demonstrate Aarow’s compliance with Article 26.
    See Fed. R. Civ. P. 9(c) (“In pleading conditions precedent, it suffices to allege generally
    that all conditions precedent have occurred or been performed.”).
    Finally, the district court’s sua sponte dismissal of the Miller Act claim rested on
    two premises: (1) that Aarow failed to state a breach of contract claim against Harper; and
    (2) that Aarow therefore failed to state a Miller Act claim against Hartford, as Hartford’s
    liability on the Payment Bond as surety is derivative of its principal Harper’s liability on
    3
    Insofar as the district court ruled that the Amended Complaint does not adequately
    plead a disruption claim, we disagree. The Amended Complaint provides all that is
    required — “a short and plain statement of the [disruption] claim showing that [Aarow] is
    entitled to relief.” See Fed. R. Civ. P. 8(a)(2). Whether a disruption claim is tantamount
    to a delay claim as a matter of contract law is a separate question that we do not reach and
    address today.
    16
    the Subcontract. As explained heretofore, the court erred in dismissing the breach of
    contract claim, meaning that the first of those premises was faulty. On that ground, we
    conclude that the court also erred in dismissing the Miller Act claim. Notably, we do not
    unnecessarily evaluate the merits of the court’s second premise for the dismissal or the
    propriety of the court’s decision to act sua sponte.
    IV.
    Pursuant to the foregoing, we vacate the judgment of the district court and remand
    for such other and further proceedings as may be appropriate.
    VACATED AND REMANDED
    17
    

Document Info

Docket Number: 19-1710

Filed Date: 12/10/2020

Precedential Status: Non-Precedential

Modified Date: 12/10/2020