U.S. for Use and Ben. of Straus Systems, Inc. v. Associated Indem. Co. ( 1992 )


Menu:
  •                    UNITED STATES COURT OF APPEALS
    For the Fifth Circuit
    No. 91-4517
    UNITED STATES OF AMERICA, FOR THE USE AND BENEFIT OF STRAUS
    SYSTEMS, INC,
    Plaintiff,
    STRAUS SYSTEMS, INC.,
    Plaintiff-Appellant,
    VERSUS
    ASSOCIATED INDEMNITY COMPANY,
    NATIONAL SURETY CORPORATION,
    FIREMAN'S FUND INSURANCE COMPANY, AND
    CONTRACT SURETY CONSULTANTS, INC,
    Defendants-Appellees.
    Appeal from the United States District Court
    For the Eastern District of Texas
    ( June 25, 1992 )
    Before   GARWOOD   and   DeMOSS,    Circuit   Judges,   and   DUPLANTIER,*
    District Judge.
    PER CURIAM:
    I.
    In June 1983, Pyramid International, Inc. (Pyramid), as the
    prime contractor, subcontracted with Straus Systems, Inc. (Straus)
    for Straus to perform all mechanical work on the Red River Army
    Depot Project (Project), a federal construction project for the
    *
    District Judge of the Eastern District of Louisiana, sitting
    by designation.
    maintenance and modernization of an army depot in Hooks, Texas.
    When Pyramid    defaulted    in   the       summer   of   1985,   the     Sureties,
    hereinafter defined, took over as prime contractor of the project
    pursuant to their performance bond.             The Sureties hired Contract
    Surety Consultants, Inc. (CSCI) as their agent to oversee and
    manage the completion of the Project. Straus executed an Agreement
    of Assignment Subcontract assenting to the assignment of the
    subcontracts to the Sureties.
    Between October 1984 and November 1985, Straus sent a series
    of fifteen letters to Pyramid and later to the Sureties giving
    notice of the delays encountered by Straus in completing its work
    on the project.     Straus never requested any additional time to
    complete its work on the project, nor did it demand payment of a
    specific amount of delay damages until October 1987, five months
    after it completed its work on the project on May 31, 1987.
    Straus    finally    brought    suit      in    district     court     against
    Associated    Indemnity   Company,      National     Surety     Corporation    and
    Fireman's Fund Insurance Company, and their agent, Contract Surety
    Consultants, Inc. (collectively the Sureties), the construction
    sureties for Pyramid, for delay damages of approximately $1,000,000
    arising out of its construction subcontract. Straus alleged claims
    based on the Miller Act (40 U.S.C. § 270), breach of contract,
    quantum meruit, and negligence. The district court granted summary
    judgment for the defendants on all claims and denied Straus's
    motion for a new trial.
    Paragraph 17 of the subcontract, which describes the procedure
    that Straus was to follow in the event of a delay in its work due
    to the action or negligence of Pyramid, reads as follows:
    DELAYS AND EXTENSION OF TIME: Should Subcontractor
    be obstructed or delayed in the completion of the
    work hereunder by the neglect, delay or default of
    the Contractor or by any act of the Owner or by
    substitutions or additions which may be required by
    2
    Contractor or Owner, or by the unusual action of
    the elements, then the date of substantial
    completion shall be extended, such extension to be
    equal to the duration of such obstruction or delay,
    as reasonably determined by Contractor, but no such
    extension shall be made unless a claim shall be
    presented in writing by Subcontractor to Contractor
    within 48 hours of the occurrence of such
    obstruction or delay. (Emphasis added).
    Paragraph 20 deals with compensation and payment to Straus.
    and reads as follows:
    COMPENSATION AND PAYMENT: Subcontractor agrees to
    accept   the   specified   compensation   as   full
    compensation for doing all work, furnishing all
    materials, and performing all provisions embraced
    in this subcontract; for all loss or damage arising
    out of the nature of the work as from the action of
    the elements or from any unforeseen or unknown
    difficulties or obstructions which may arise or be
    encountered in the prosecution of the work until
    its acceptance; and for all risks of every
    description connected with the work.      (Emphasis
    added).
    The trial court found that Straus failed to comply with the
    procedural requirements found in Paragraph 17 that it give notice
    for delay in order to maintain its suit for damages.   Additionally,
    the trial court noted in its order and opinion denying Straus's
    motion for a new trial that a claim made for extension of time due
    to delay was the only recourse open to Straus under the contract.
    The issues raised by Straus on appeal are:
    1.   Whether   paragraphs   17   and  20   of   the
    subcontract prohibit Straus from seeking delay
    damages.
    2.   Whether Straus complied with the notice requirement
    of the subcontract to maintain its suit for delay
    damages.
    3.   Whether   the  sureties   agreed  to   assume
    liability for Pyramid's breach of contract.
    3
    Because this Court has determined that Straus is precluded
    from asserting claims for monetary delay damages by the terms of
    the contract, and such holding is dispositive of Straus's claims,
    we do not address issues numbers two and three.
    We AFFIRM.
    II.
    The definitive issue on appeal in this case is whether the
    subcontract allows a claim for monetary delay damages or whether
    Straus was limited to an extension of time as compensation for the
    delay caused by Pyramid.   The interpretation of the subcontract is
    a question of law which this Court reviews de novo.   Hall v. State
    Farm Fire and Casualty Co., 
    937 F.2d 210
    , 213 (5th Cir. 1991).
    Texas law provides that when a Court construes a contract it
    must look to the intent of the parties as expressed in the
    contract. Fuller v. Phillips Petroleum Co., 
    872 F.2d 655
    , 657 (5th
    Cir. 1989).   In addition, the Court should consider the objective,
    rather than the subjective intent of the parties.     Where, as in
    this case, there are no allegations of ambiguity as to the contract
    language, the Court will determine the intent of the parties from
    the instrument alone. 
    Id. at 657.
    Contract provisions indicating that the delay was within the
    contemplation of the Parties have been found to be sufficient to
    preclude recovery of damages for delay in a construction contract,
    City of Houston v. R. F. Ball Constr. Co., Inc., 
    470 S.W.2d 75
    , 77
    (Tex. Civ. App.--Houston [14th Dist.] 1978, writ ref'd n.r.e.).
    Parties to a contract might foresee or consider the possibility of
    4
    delay and contractually provide for a remedy to be applied upon
    such occurrence. 
    Id. It is
    not necessary that exclusion of delay
    damages be express.         
    Id. A provision
    in the contract for an
    extension of time in case of delay caused by the contractor has
    been   held   to   afford    the   subcontractor   an   exclusive   remedy,
    precluding the recovery of damages from the contractor. Ericksen v.
    Edmonds School Dist. No. 15, Snohomish County, 
    125 P.2d 275
    , 
    13 Wash. 2d 398
    (Wash., 1942); See Burgess Constr. Co. v. M Morrin &
    Son Co., Inc., 
    526 F.2d 108
    , 115 (10th Cir. 1975).         See also United
    States, to Use of Brown v. Miller-Davis Co., 
    61 F. Supp. 89
    , 90 (D.
    Conn. 1945). (provisions in the principal contract for extension of
    the completion date were held a bar to the subcontractors recovery
    against the general contractor for delay).
    Straus contends that Sureties owe it delay damages because
    Pyramid and Sureties breached the implied obligation not to delay
    Straus's performance; and that Sureties must make good on all loses
    due to delays in the progress of the work because there is no
    express provision in the subcontract to the contrary that releases
    Sureties from this obligation. R.F. Ball, 
    570 S.W.2d 75
    .
    The Sureties argue that the parties addressed the subject of
    delay in Paragraph 17 of the subcontract and provided that the only
    remedy was extension of time.             They contend that Paragraph 20
    confirms the parties intention to limit Straus to the compensation
    provided by the subcontract.
    While the subcontract itself might have been more clearly
    drafted, we believe that when read as a whole and giving due
    5
    consideration to Paragraphs 17 and 20, it indicates that the
    parties thought about the problem of delay when they initially
    contracted and agreed at that time that the sole remedy for delay
    would be the extension of time. It is evident by these contract
    provisions that delay was within the contemplation of the Parties
    and that such provisions preclude recovery of damages for delay in
    this construction contract.    R.F. 
    Ball, 570 S.W.2d at 77
    .
    III.    CONCLUSION
    We affirm the trial court's holding that Sureties are not
    liable for damages caused by the delay.
    6