Galin Corp. v. MCI Telecommunications Corp. ( 1994 )


Menu:
  •                  IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    No. 92-2649
    GALIN CORPORATION and PETROPAK, INC.,
    Plaintiffs-Appellants,
    versus
    MCI TELECOMMUNICATIONS CORPORATION,
    Defendant-Appellee.
    Appeal from the United States District Court
    for the Southern District of Texas
    (    January 14, 1994        )
    Before WISDOM, HIGGINBOTHAM, and SMITH, Circuit Judges.
    HIGGINBOTHAM, Circuit Judge:
    This   is   a   diversity    suit   for   breach   of   a   construction
    contract.   The district court granted judgment denying relief to
    plaintiffs at the outset of trial, but without allowing the parties
    to present evidence to the jury.         We agree with the district court
    that plaintiffs' claims are barred by the terms of the release and
    notice of claim provisions of the construction contract.              We also
    conclude that the district court's unusual grant of judgment at the
    outset of trial was effectively a grant of summary judgment that
    had been argued earlier.      We affirm.
    I
    In March 1987, MCI Telecommunications Corporation invited bids
    on a fiber optic cable installation route comprising eight sections
    to   extend    through    Georgia,   Alabama   and   Tennessee.      Galin
    Corporation and Petropak, Inc., met with MCI personnel, made
    extensive visits to various future work sites, and analyzed MCI's
    plans, specifications, and bid instructions.          Galin and Petropak
    then submitted bids on six of the eight sections.        MCI accepted no
    bids on the project.       In late August of the same year, MCI issued
    new instructions for the installation of a shorter version of the
    same fiber optic cable route.        Before requesting a second set of
    bids, MCI released to the prospective contractors an estimate of
    the amount of subsurface rock that lay along the cable route.
    Galin and Petropak again submitted a bid, this time at a lower
    price,   which   MCI     accepted.   The   parties   executed   a   written
    contract.
    Galin and Petropak commenced work in early November.            During
    the project, MCI complained to Galin and Petropak of their lack of
    timely progress and, on December 18, MCI gave Galin and Petropak
    notice of termination by default for failure to meet the contract
    schedule.     On December 30, MCI eliminated the last seven miles of
    the cable route from the contract.
    Galin and Petropak say that they completed the installation of
    the cable on or about February 21, 1988, "except for areas where
    MCI had failed to obtain necessary permits or easements and where
    2
    MCI had misrepresented the existence of rocks"; and that they then
    commenced cleaning up their work sites.
    On April 22, 1988, MCI issued a proposed Final Modification of
    Contract, which Galin and Petropak did not sign.            As the project
    had progressed, however, Galin and Petropak had signed a series of
    releases in exchange for incremental payments from MCI.                 They
    signed the last of these releases on May 13, 1988.             Finally, in
    July of 1988, MCI terminated the contract for non-performance.
    Settlement negotiations failed and Galin and Petropak filed
    this suit in a Texas court seeking compensation from MCI for breach
    of contract, in quantum meruit, and in tort.               MCI removed to
    federal district court invoking the court's diversity jurisdiction.
    MCI and Galin and Petropak then both moved for summary judgment.
    The district court granted judgment to MCI on Galin and Petropak's
    claim for breach of a covenant of good faith and fair dealing, but
    left the remaining issues for trial.
    When the case was called for trial, MCI asserted that the
    district court should render judgment.        The district court granted
    the requested relief treating it as a motion for judgment as a
    matter   of   law   under   Federal   Rule   of   Civil   Procedure   50(a).
    Applying New York law, the court dismissed the case before the
    first witness was called.      Galin and Petropak appeal.
    3
    II
    Galin       and           Petropak        pursue     several      claims.
    Galin and Petropak allege that MCI deliberately underestimated
    the amount of subsurface rock that lay along the route to decrease
    the cost of construction. The subcontractor who performed the rock
    probes, Galin and Petropak assert, did not work long enough to
    produce the results that MCI released.                  Galin and Petropak argue
    that MCI must have fabricated either some or all of the site
    information.   They claim to have relied on this falsely optimistic
    information in their bid.
    According      to    Galin     and    Petropak,     MCI     engaged   in   other
    questionable business practices.                They allege that MCI's designs
    for installing the cable were faulty, that MCI failed to obtain
    timely permission for them work on several stretches of the route,
    that MCI interfered in their operations, that MCI forced them to
    meet more exacting standards during the clean up process than the
    contract required, and that MCI otherwise failed to support them.
    Galin and Petropak sue for recovery on the contract, in
    quantum    meruit        for     extra-contractual        work     performed,     for
    compensation for MCI's wrongful interference with their contract
    performance, and for compensation for MCI's breach of its duty of
    good faith and fair dealing.1             The district court decided the case
    1
    Galin and Petropak wish to recover the balance owed on
    their contract with MCI, compensation for the work they performed
    outside the scope of their contract with MCI, and damages which
    they incurred as a result of delays, acts of interference,
    improper administration of the contract, misrepresentations, and
    other reckless, grossly negligent, arbitrary and capricious acts
    by MCI.
    4
    based on provisions in the contract that protect MCI from liability
    and on the releases that Galin and Petropak signed.               Galin and
    Petropak argue that the protective provisions and releases are
    inapplicable   to   their    claims   and,     further,   that   MCI   waived
    application of the provisions. The parties agree that New York law
    controls.
    A.
    At the outset, Galin and Petropak argue that the district
    court improperly invoked Federal Rule of Civil Procedure 50(a) in
    dismissing their case.      First, they argue that Rule 50(a) required
    that MCI move for judgment as a matter of law and that when the
    court ruled MCI had not done so.          Second, they argue that they had
    not been fully heard by the court, as required by Rule 50(a),
    before it rendered judgment. We need not address these contentions
    as we construe the court's order as a grant of summary judgment and
    affirm on that basis.
    The district court early in the case denied MCI's motion for
    summary judgment, to which Galin and Petropak had fully responded.
    On reconsidering, the court concluded that the case did turn on the
    notice and release provisions of the contract. This interpretation
    presented no issues of fact and protected MCI from liability.             The
    court therefore ruled in MCI's favor, albeit under Federal Rule of
    Civil Procedure 50(a).
    Where a case does not require the resolution of material
    facts, summary judgment is appropriate.            See Seneca v. Phillips
    Petroleum Co., 
    963 F.2d 762
    , 765 (5th Cir. 1992).           We have in the
    5
    past affirmed summary judgment on grounds different than those
    adopted by the trial court.   
    Id. at 765;
    Church of Scientology v.
    Cazares, 
    638 F.2d 1272
    , 1281 (5th Cir. 1981).   Since both parties
    had adequate opportunity to address the issues involved in summary
    judgment prior to the district court's ruling, we see no impediment
    to treating the judgment below as a grant of summary judgment.
    Having so concluded, we consider the propriety of that judgment.
    B.   The Releases
    Galin and Petropak signed several partial releases in exchange
    for incremental payments from MCI, the last on May 13, 1988, after
    installation of the cable route.     They performed no work after
    execution of this release other than cleaning the work sites.
    The releases read in pertinent part:
    Partial Release and Indemnity
    In consideration of payments made heretofore, or to be
    made based upon this invoice for labor, material,
    equipment, subcontract work, and any and all costs
    incurred for the performance of the contract work
    invoiced thus far, the Contractor hereby unconditionally
    and without reservation releases and indemnifies MCI and
    their officers, agents, employees, assignees and heirs
    from any and all liens, claims, demands, penalties,
    losses, costs, damages and liability in any matter
    whatsoever.
    Galin and Petropak interpret the releases narrowly in two
    ways:   first, as applying only to the work specified in the
    invoices they submitted; and, second, as applying only to the
    contract work, as opposed to the extra work, which they performed.
    The language of the releases precludes this interpretation.
    Under New York law, where the language of a release admits of
    only one interpretation, the proper interpretation of the release
    6
    is a question of law.   Janos v. Peck, 
    251 N.Y.S.2d 254
    , 258 (N.Y.
    App. Div.), aff'd, 
    254 N.Y.S.2d 15
    (N.Y. 1964) ("Where... there is
    a question as to the construction of a written contract     between
    the parties and the determination of that question may be reached
    by reference to and a consideration of the plain and unambiguous
    wording of the contract, the question, as one of law, should be
    then and there resolved.")   See also Metz v. Metz, 
    572 N.Y.S.2d 813
    , 815 (N.Y. App. Div. 1991).      The releases that Galin and
    Petropak signed list as consideration all compensation that MCI
    paid Galin and Petropak in the past as well as the compensation the
    invoice required MCI to pay Galin and Petropak in the future.   The
    terms of the release, however, are broader.   The form releases MCI
    from "all liens, claims, demands, penalties, losses, costs, damages
    and liability in any matter whatsoever."      As Galin and Petropak
    signed nine releases in exchange for incremental payments, the
    court interpreted the language of each release to reach all claims
    of Galin and Petropak against MCI that existed at the time Galin
    and Petropak signed each one.   This interpretation is appropriate
    as, under New York law, a general release "will bar suit on any
    cause of action arising prior to the date of its execution and
    delivery, in the absence of fraud or other vitiating circumstances
    in its inducement or execution."      
    Metz, 572 N.Y.S.2d at 815
    (citation and internal quotation marks omitted).     See also Troy
    News Co. v. Troy, 
    563 N.Y.S.2d 301
    , 303 (N.Y. App. Div. 1990)
    (holding a release that so specifies applies to future claims but
    in the absence of specification applies to all claims in existence
    7
    when it is given).    But see Herman v. Malamed, 
    487 N.Y.S.2d 791
    ,
    793-94 (N.Y. App. Div. 1985) (holding that a specific release
    followed by an omnibus clause may be limited to the specified
    terms).   Galin and Petropak do not claim that MCI fraudulently
    induced them to sign the releases.         With the exception of their
    claim for cleaning the work sites, neither do Galin and Petropak
    deny that the claims which they now pursue existed when they signed
    the various partial releases.           Thus, they offer no basis for
    refusing enforcement of the releases.
    Galin and Petropak fail in their attempt to "marshal" case law
    for the proposition that we may modify or void these releases.            In
    De Costa v. Williams, 
    462 N.Y.S.2d 799
    (Sup. Ct. 1983), a New York
    court looked   to   the   actual   understandings   of   the   parties    in
    limiting the scope of a release.        In doing so, however, the court
    noted, "A mistaken belief as to the nonexistence of presently
    existing injury is a prerequisite to avoidance of a release."            
    Id. at 802
    (citation omitted).     Galin and Petropak do not claim that
    they were unaware at the time they signed the releases of the
    claims they now pursue.     They insist instead that they were aware
    of them but had a different intent.         They argue that they would
    have offered evidence to this effect at trial.
    Where a written agreement is unambiguous, as in the present
    case, New York law does not allow consideration of extrinsic
    evidence of the parties' intentions.        "It has long been the rule
    that when a contract is clear in and of itself, circumstances
    extrinsic to the document may not be considered and that where the
    8
    intention of the parties may be gathered from the four corners of
    the instrument, interpretation of the contract is a question of law
    and no trial is necessary to determine the legal effect of the
    contract."       
    Janos, 251 N.Y.S.2d at 259
    (citations and internal
    quotation marks omitted).               See also Rice v. Cohen, 
    555 N.Y.S.2d 800
    , 801 (N.Y. App. Div. 1990) (holding that clear and unambiguous
    language    in    a     document    precludes        consideration       of    extrinsic
    evidence to interpret its meaning).                  The releases are unambiguous.
    They bar Galin and Petropak's claims except those arising from
    cleaning the work sites.           The cleaning, as we explained, occurred
    after May 13, 1988, so the last release did not reach claims from
    that work.     Nevertheless, a provision in the construction contract
    precludes them.
    C.     The Notice of Claims Provision
    Paragraph 18 of the construction contract set a time frame for
    claims   arising      from      unexpected        circumstances.         The   paragraph
    required Galin and Petropak to notify MCI within five days of an
    event that could give rise to a claim on their part or that might
    extend   the     period    of    time    in       which   they   would    complete    the
    contract.      It then provided that Galin and Petropak should submit
    to MCI within fourteen days a statement substantiating the change
    in circumstances and estimating its impact.                      Upon request, Galin
    and Petropak would have to document any claims submitted for extra
    compensation or for an extension of time.
    Galin and Petropak do not deny that they failed to meet the
    terms of this provision in submitting their claims to MCI.                           They
    9
    argue instead that the provision applies to events that occurred
    during the completion of the contract, not to work that Galin and
    Petropak undertook on MCI's behalf that was unanticipated and,
    therefore, beyond the scope of the contract.      They describe the
    latter as "extra" work.
    The seminal case in New York defining "extra" work is Savin
    Brothers, Inc. v. State, 
    405 N.Y.S.2d 516
    (N.Y. App. Div. 1978),
    aff'd, 
    393 N.E.2d 1041
    (N.Y. 1979).     In Savin Brothers, the court
    held that a contractor who allegedly performed extra work could not
    recover for that work.    
    Id. at 521.
      In reaching that conclusion,
    the court defined extra work as "something necessarily required in
    the performance of the contract which arises from conditions which
    could not be anticipated."     
    Id. at 519
    (citation omitted).     The
    contract determines which party assumes the costs of extra work.
    
    Id. Galin and
    Petropak note that paragraph 15 of the contract
    addresses changes in the arrangement made at MCI's behest.      These
    changes would not seem to encompass extra work.       Paragraph 18,
    however, sets the time frame for reporting "the happening of any
    event" which Galin and Petropak believed might give rise to a claim
    "for an increase in contract price" or "the period of performance."
    Paragraph 18 addresses precisely the sort of unanticipated event
    that results in extra work and requires that Galin and Petropak
    report such events in a timely fashion.
    Galin and Petropak submitted none of their claims within the
    period of time prescribed by paragraph 18.     They submitted their
    10
    first claim for recovery in excess of the contract on May 16, 1988.
    They had ceased performing any work on the installation of the
    capable in February of 1988, three months earlier. Similarly, they
    did not submit their claim for cleaning the construction sites
    until August 8, 1988.   They had completed cleaning the sites on May
    1, 1988.   Galin and Petropak did not comply with the provision in
    paragraph 18 requiring written notice of the event within five days
    and an estimate of its impact within fourteen days.      Without such
    notice MCI could not respond to Galin and Petropak's concerns in a
    timely manner.   Because Galin and Petropak delayed in making their
    claims, paragraph 18 precludes them from recovering for any extra
    work they performed.
    D.   Waiver
    Galin and Petropak argue, in the alternative, that MCI waived
    its various defenses. They base this argument on MCI's willingness
    to consider their claims.
    "Waiver is an intentional relinquishment of a known right and
    should not be lightly presumed."       Gilbert Frank Corp. v. Federal
    Ins. Co., 
    520 N.E.2d 512
    , 514 (N.Y. 1988) (citations omitted).      A
    decision by MCI not to enforce its rights immediately, and instead
    to pursue completion of a contract, does not amount to such waiver.
    See Seven-Up Bottling Co. v. Pepsico, Inc., 
    686 F. Supp. 1015
    , 1023
    (S.D.N.Y. 1988).
    The New York Court of Appeals' treatment of waiver in a
    summary judgment context in Gilbert is 
    instructive. 520 N.E.2d at 513-14
    . First, of course, a defendant must produce evidence which,
    11
    if uncontroverted, would establish a defense.                  The unambiguous
    language of    the    releases   and   the    notice    of   claims    provision
    satisfies this requirement.            See 
    id. at 514
    (finding that a
    contractual limitation on the period of time in which a claim may
    be asserted carries defendant's burden in moving for summary
    judgment).    Second, the plaintiff must have the opportunity to
    offer evidence of waiver of defense.          
    Id. Applying this
    standard,
    the lower appellate court in Gilbert had held "that since defendant
    had not offered satisfactory explanations regarding the necessity
    for the intensive activity which was undertaken with regard to
    plaintiff's claim after the expiration of the limitations period,
    there were questions of fact . . . requiring further development."
    
    514 N.Y.S.2d 215
    , 218 (N.Y. App. Div. 1987).             Unwilling to draw an
    inference from the defendant's conciliatory posture, the Court of
    Appeals 
    reversed. 520 N.E.2d at 514
    .            The Court of Appeals
    explained that a plaintiff must offer "evidence from which a clear
    manifestation of intent by defendant to relinquish the protection
    of   the   contractual    limitations        period    could    be    reasonably
    inferred."    
    Id. Thus, as
    a matter of law, a defendant's apparent
    willingness to honor a plaintiff's claim is insufficient to prove
    waiver.    See also Silverstein Properties, Inc. v. Webber, Jackson
    & Curtis, Inc., 
    480 N.Y.S.2d 724
    , 726 (N.Y. App. Div. 1984), aff'd,
    
    482 N.E.2d 906
    (N.Y. 1985) (holding that evidence of landlord's
    willingness to address merits of tenant's claim, after time allowed
    for claim by contract had expired, is insufficient to support
    reasonable inference of waiver).
    12
    Galin and Petropak allege only that they had reason to believe
    that MCI would entertain their claims.          The letters from MCI on
    which Galin and Petropak rely are representative.           In one of these
    letters, MCI's agent, Richard Yeats, reminded Galin and Petropak,
    "Timely   submittal   of    claims   and   back-up   will   facilitate   the
    contract close out."       Yeats noted in another letter that "MCI has
    stressed making... changes [in the terms of the contract] as they
    occur, not at the end of the contract which makes negotiations and
    contract close laborious." While these letters suggest lenience in
    enforcing the notice requirement, they offer no basis for inferring
    that MCI deliberately waived that requirement.          Because Galin and
    Petropak offered nothing to support a finding of waiver, invoking
    waiver was insufficient to defeat summary judgment.
    E.    Evidence of Settlement
    Galin and Petropak also contest the ruling of the district
    court that evidence of the settlement process was inadmissible.
    Galin and Petropak wished to use MCI's attempt to settle as proof
    of the limited scope of the releases Galin and Petropak signed and
    as evidence that MCI waived the notice provision of the contract.
    As we hold that the releases are unambiguous on their face,
    evidence of any attempts by MCI to settle are not relevant.              See
    Gilbert Frank 
    Corp., 520 N.E.2d at 514
    .         We need not address the
    issue of admissibility.
    AFFIRMED.
    13