Construcciones Ind v. Searex Inc ( 1999 )


Menu:
  •                 IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    _____________________
    No. 98-20898
    Summary Calendar
    _____________________
    CONSTRUCCIONES INDUSTRIALES DEL GOLFO,
    S.A. DE C.V.,
    Plaintiff-Appellant,
    versus
    SEAREX, INC.,
    Defendant-Appellee.
    _________________________________________________________________
    Appeal from the United States District Court
    for the Southern District of Texas, Houston
    (H-97-CV-3588)
    _________________________________________________________________
    May 28, 1999
    Before JOLLY, SMITH, and WIENER, Circuit Judges.
    E. GRADY JOLLY, Circuit Judge:*
    The dispositive issue in this appeal is whether the parties
    entered into a binding contract.    We conclude that they did not,
    and we therefore affirm the district court in all respects.
    *
    Pursuant to 5TH CIR. R. 47.5, the court has determined that
    this opinion should not be published and is not precedent except
    under the limited circumstances set forth in 5TH CIR. R. 47.5.4.
    I
    The facts relevant to our decision are undisputed.                  During
    1997, Searex, Inc. and Construcciones Industriales Del Golfo, S.A.
    de C.V. (“CIGSA”) entered negotiations over a proposed joint
    venture.      The object of this joint venture would have been to
    construct and charter several new vessels for use in oil and gas
    exploration. Searex possessed the proprietary design for these new
    vessels.          Eventually, however, the negotiations over a joint
    venture failed. Soon thereafter, on July 24, 1997, the two parties
    executed      a    document   entitled    “Agreement    to   Time   Charter   and
    Subcharter Vessels.”          This document’s preamble expressed CIGSA’s
    “desire[] to time charter the first two vessels” produced using
    Searex’s proprietary design.            The document also expressed Searex’s
    willingness        to   charter   the    vessels   to   CIGSA   under   certain
    conditions, and the document contains the following provisions:
    [T]he parties hereto agree to the following basic terms:
    1.       Upon delivery of each of the Vessels by Alabama Shipyard
    Inc. (“Builder”), it will be chartered by SEAREX to CIGSA
    under the Master Time Charter Agreement in similar form
    of Exhibit 1 attached hereto.
    2.       Each initial vessel time charter will be for a period of
    not less than two years on a 365-day “Hell or high Water”
    basis at the charter hire rate of not less than $12,500
    per day, plus 25% of the net remaining charter hire, up
    to $25,000 per day, received from PEMEX1 or other company
    1
    Pemex is Petroleos Mexicanos, the Mexican national oil
    company. As is evident from the document, the parties initially
    thought that Pemex would be the third party to whom CIGSA would
    subcharter the vessels.
    2
    or under the PEMEX Subcharter or other company subcharter
    of the vessels.
    3.      CIGSA will subcharter each of the vessels to PEMEX or
    other company acceptable to MARAD,2 under a subtime
    charter in similar form to Exhibit B attached hereto.
    4.      This agreement will become effective upon MARAD approval
    and shall terminate if such approval is not obtained by
    October 31, 1997.
    These    provisions   mention   several   non-existent    documents.
    Although provision (3) contemplates a subtime charter form, no such
    form was ever attached to the document.            Furthermore, a subtime
    charter agreement involving CIGSA has never been entered.                The
    Master Time Charter form, mentioned in provision (1), was attached
    to the document.       This form, essentially a red-lined, working
    draft, stated (in Article 3 of the form) that “Each vessel Vessel
    shall be delivered to CHARTERER at the time and place and for the
    duration and subject to the extensions specified in the applicable
    Short Form.”     The parties, however, never created a Short Form.
    After    executing    the   document,   the   parties   continued   to
    negotiate over the terms of a Master Time Charter Agreement.             In
    the midst of these negotiations, on August 8, 1997, Searex sent
    CIGSA proposed changes to the Agreement form. The relevant changes
    were indicated in a new, draft version of the proposed Agreement:
    Article 2 - Charter
    Subject to the conditions set forth herein OWNER
    agrees to charter the Vessels to CHARTERER, and CHARTERER
    2
    MARAD is the federal government’s Maritime Administration.
    Searex sought financing for the vessels from MARAD.
    3
    agrees to hire the Vessel Vessels from OWNER on the terms
    and conditions set forth herein. Each Vessel shall be
    subjected to this Agreement by the execution by the
    parties of a Short Form. Each Vessel shall be subjected
    to this Agreement upon delivery of the Vessel to the
    Owner by its builder, Alabama Shipyard, Inc. (the
    “Builder”). OWNER shall give CHARTERER at least 30 days
    notice of the delivery date proposed by the Builder, but
    OWNER shall have no liability to CHARTERER or any one
    claiming by, through or under CHARTERER for failure to
    deliver the Vessel as per any notice given by OWNER or
    for any delay in delivery of either Vessel for any reason
    whatsoever. CHARTERER’s sole and exclusive remedy for
    any delay in delivery shall be to cancel this Agreement
    in accordance with the provisions of the last sentence of
    Article 1 hereof.3
    OWNER shall have no obligation to charter any Vessel
    to CHARTERER hereunder unless, (i) at least 90 days
    before the projected delivery date of a Vessel (of which
    delivery date OWNER shall have notified CHARTERER),
    CHARTERER has secured a subcharter of the Vessel to PEP;
    and a Permitted Subcharterer; (ii) prior to the
    commencement of the term of the charter of such Vessel,
    OWNER shall have received the consent of MarAd to charter
    the Vessel to CHARTERER and to subcharter it to PEP. such
    Permitted Subcharterer; and (iii) MarAd shall have
    approved proceeding with the construction and financing
    of the second Vessel pursuant to the terms of the
    Commitment to Guarantee referred to in the second recital
    of this Agreement.
    In response to Searex’s proposed changes, CIGSA sent a reply
    memorandum on August 11, 1997, with the following language:
    We have   received your last form of the charter agreement
    between   Searex and CIGSA and are in agreement with its
    terms.    However there is a point that has to be clarified
    . . . .   Regarding delivery date of the Vessel, according
    to the     information we had originally received from
    Searex,   we have negotiated with Pemex to prepare a tender
    3
    The referenced sentence states, “Each party may cancel the
    this Agreement upon the giving of thirty (30) days prior written
    notice to the other, provided, however, that any unexpired Short
    Form shall continue in effect subject to the terms and conditions
    hereof until expiration of such Short Form.”
    4
    for the contract of the Vessels with a delivery of no
    later than April 30 of next year. Said delivery must be
    guaranteed with a performance bond equal to 10% of the
    total value of the contract.
    As you can understand we must comply with said date, and
    therefore can not accept your proposal that owner shall
    have no responsibility whatsoever in regard to late
    delivery. . . . In short, we must insert language that
    explains that both Searex and CIGSA, will make its best
    efforts to guarantee delivery in Mexico by no later than
    April 30, and in case of fault to that deadline, if such
    is pertaining to any other party, they in turn shall face
    the responsibilities that may arise.
    What must be clearly understood is that the tender will
    be published in the next 10 days, and we are not in a
    position to negotiate deliveries later than April 30.
    The remaining conditions of the charter . . . are acceptable.
    No other relevant communication occurred between Searex and
    CIGSA until October 1, 1997, when Searex sent CIGSA a letter
    stating that the parties had not reached an agreement sufficient to
    pursue “the SEAREX/CIGSA project,” and that Searex would explore
    other   opportunities   for   the   use   of   its   vessels.   One   last,
    important fact to note is that MARAD never gave its approval (see
    provision (4)).
    II
    After receiving Searex’s letter, CIGSA filed suit against
    Searex for breach of contract.4      CIGSA sought damages and specific
    performance as relief for the alleged breach.           The district court
    issued a very able, comprehensive opinion addressing Searex’s
    4
    CIGSA also included other claims, none of which CIGSA
    presents on appeal.
    5
    motion for summary judgment and CIGSA’s partial motion for summary
    judgment and its motion for leave to amend its complaint.             The
    district court concluded that Searex and CIGSA never entered a
    binding contract.      Accordingly, the district court found that
    Searex could not be held liable under any of CIGSA’s breach of
    contract theories.     The     district court then reviewed CIGSA’s
    proposed waiver and estoppel arguments (which CIGSA sought to add
    to an amended complaint), and concluded that those arguments had no
    merit. The district court therefore decided to deny CIGSA’s motion
    to amend its complaint as futile.         In its final judgment, the
    district   court   granted   Searex’s   motion   for   summary   judgment,
    denied CIGSA’s motion for partial summary judgment, denied the
    motion to amend the complaint, and dismissed the complaint.
    III
    We review the grant of summary judgment de novo, using the
    same standard as the district court.     Burditt v. West American Ins.
    Co., 
    86 F.3d 475
    , 476 (5th Cir. 1996).     We will affirm the grant of
    summary judgment if the record shows “that there is no genuine
    issue as to any material fact and that the moving party is entitled
    to a judgment as a matter of law.”       Fed. R. Civ. P. 56(c).       Upon
    our thorough review of the record, and with the standards for
    granting summary judgment well in mind, we conclude that the
    district court was exactly correct in granting Searex’s motion for
    summary judgment after finding that the parties did not enter a
    binding contract.
    6
    A
    We begin by noting that the parties never agreed on a Master
    Time Charter Agreement. Contrary to CIGSA’s arguments on appeal,
    CIGSA did not accept the Master Time Charter Agreement proposed by
    Searex on August 8.     CIGSA’s August 11 letter effectively rejected
    the proposed agreement by rejecting various terms and demanding
    that any Agreement contain newly suggested language.            See, e.g.,
    Restatement (Second) of Contracts § 59 (“A reply to an offer which
    purports to accept it but is conditional on the offeror’s assent to
    terms additional to or different from those offered is not an
    acceptance but is a counter-offer.”); Blackstone v. Thalman, 
    949 S.W.2d 470
    , 473 & n.4 (Tex. Civ. App. 1997, no writ).         For example,
    CIGSA’s August 11 letter stated that CIGSA “[could] not accept
    [Searex’s]   proposal    that   owner   shall   have   no   responsibility
    whatsoever in regard to late delivery.” The CIGSA letter then went
    on to say that “we must insert language that explains that both
    Searex and CIGSA will make its best efforts to guarantee delivery
    in Mexico no later than April 30, and in case of fault to that
    deadline . . . they in turn shall face the responsibilities that
    may arise.” Thus, although CIGSA did begin its letter by informing
    Searex that CIGSA was in agreement with the proposed Agreement’s
    terms, CIGSA clearly did not accept all of those terms and demanded
    the inclusion of others.
    Given that the parties never agreed to a Master Time Charter
    Agreement, we are left to consider whether the July 24 document
    7
    binds Searex to enter a charter agreement with CIGSA. CIGSA argues
    that the document does exactly this because it contains all of the
    necessary terms, including price (see provision (2) of the July 24
    document) and delivery date.           The document specifies the date,
    CIGSA argues, in provision (1):             “Upon delivery of each of the
    Vessels by Alabama Shipyard Inc. (“Builder”), it will be chartered
    by SEAREX to CIGSA . . .”          Although the document does not specify
    a date that one can locate on a calendar, CIGSA argues that this
    provision indicates that the parties agreed to the condition--i.e.,
    delivery by Alabama Shipyard, Inc.--that would fix that date at
    some time in the future.
    This argument has no merit.             The undisputed evidence shows
    that the parties did not, in fact, intend for the statement in
    provision (1) to bind the parties to any preordained delivery date.
    First, the attached Master Time Charter Agreement form stated that
    the exact delivery date would be specified in a “Short Form”
    (which, again, was never created). Second, CIGSA’s own statements,
    in its August 11 letter, reveal that it did not intend for the
    July 24 document to fix a binding delivery date.                  In its letter,
    CIGSA   stated   that   it   was    “not    in   the   position    to   negotiate
    deliveries later than April 30.” Obviously, CIGSA thought that the
    delivery date was open to negotiation.
    But we need not rest our decision on the fact that the July 24
    document was defective for failing to contain essential elements of
    an agreement.    The July 24 document, by its own terms, would not
    8
    become effective until MARAD approved the agreement (see provision
    (4)).        MARAD   never   granted   its      approval   and     the   document,
    therefore, never had any legal effect.                CIGSA argues that Searex
    should not be able to defend itself by pointing to this provision
    because Searex ended its attempts to come to an agreement (as
    stated in Searex’s October 1st letter) before the October 31
    deadline.       Therefore, CIGSA argues, it was still possible for
    Searex to obtain MARAD approval, but Searex prematurely gave up; in
    legal terms, CIGSA argues that Searex anticipatorily repudiated the
    contract. Searex counters this argument by pointing out that CIGSA
    did not cooperate with Searex (by supplying necessary documents) in
    gaining MARAD approval.        But all of this is beside the point: the
    July    24    document   had   absolutely        no   effect--and    could     not,
    therefore,     bind   Searex   in   any       way--until   MARAD    approved   the
    document.      In other words, and as the district court’s incisive
    opinion notes, Searex could not anticipatorily repudiate a contract
    when there was no contract.               See Texas Dept. of Housing and
    Community Affairs v. Verex Assurance, Inc., 
    68 F.3d 922
    , 928 (5th
    Cir. 1995) (“‘When a promise is subject to a condition precedent,
    there is no liability or obligation on the promisor and there can
    be no breach of contract by him until and unless such condition or
    contingency is performed or occurs.’ Reinert v. Lawson, 
    113 S.W.2d 293
    , 294 (Tex. Civ. App.--Waco, 1938, no writ).”); Valencia v.
    Garza, 
    765 S.W.2d 893
    , 898 (Tex. Civ. App. 1989, no writ) (“[A]
    9
    valid   contract   must   first   be    established   in   order   to   prove
    repudiation.”).
    In sum, the July 24 document never became effective.               As no
    contract existed, CIGSA’s breach of contract claim must fail.
    B
    Finally, we consider whether the district court abused its
    discretion in denying CIGSA the opportunity to amend its complaint
    by adding arguments based on waiver and estoppel.              See Ashe v.
    Corley, 
    992 F.2d 540
    , 542 (5th Cir. 1993) (stating that district
    court’s denial of leave to amend a complaint is reviewed for abuse
    of discretion).
    Aside from the fact that the deposition testimony CIGSA points
    to, see CIGSA Br. at 42-44, does not, in any way, support its
    stated characterizations of the alleged nefarious behavior by
    Searex, we are able nevertheless easily to conclude that the
    district court was correct in finding that amendment would be
    futile.   To support its arguments, CIGSA cites the same two cases
    that it cited in the district court and does not attempt to explain
    why the district court’s plain reading of Fifth Circuit precedent
    is somehow erroneous.     CIGSA cites Wheeler v. White, 
    398 S.W.2d 93
    (Tex. 1965), for the proposition that “a party can be estopped by
    its conduct from claiming that a contract is not sufficiently
    specific to be enforced.”    CIGSA Br. at 45.     CIGSA thus argues that
    Searex’s conduct estops it from denying the existence of a contract
    based on alleged indefiniteness.
    10
    As we have explained above, however, the July 24 document is
    not a contract that has failed for indefiniteness.             Instead, it is
    a document that never went into effect--not because of legal
    indefiniteness, but because of its own terms (in provision (4)).
    As the district court explained, we have recognized that “[i]t is
    a well-established principle in Texas that ‘contract rights cannot
    be created by estoppel [but estoppel can] prevent a parties conduct
    and actions from operating as a denial of the right of enforcement
    of a contractual obligation already created.’”               Oliver Resources
    PLC v. International Finance Corp., 
    62 F.3d 128
    , 131 (5th Cir.
    1995)     (bracketed       phrase   in   original)      (quoting   Roberts    v.
    California-Western States Life Ins. Co., 
    470 S.W.2d 719
    , 726 (Tex.
    Civ. App. 1971)).       Furthermore, and, again, as the district court
    noted, we have said that Wheeler does not contravene the basic
    principle that estoppel does not affirmatively create contract
    rights.       Oliver 
    Resources, 62 F.3d at 131
    n.5.          Wheeler does not
    contravene      this   basic   principle      because   “Wheeler   involved    a
    contract between the parties that was later found defective.”                
    Id. See also
    Wheeler, 398 S.W.2d at 96 
    (“[Promissory estoppel] does not
    create a contract where none existed before, but only prevents a
    party from insisting upon his strict legal rights when it would be
    unjust to allow him to enforce them.           The function of the doctrine
    of promissory estoppel is, under our view, defensive in that it
    estops    a     promisor    from    denying    the   enforceability    of    the
    promise.”).      As CIGSA has cited no other authority to support its
    11
    arguments, we are certain that the district court has not abused
    its discretion.
    III
    For the foregoing reasons, we AFFIRM the district court’s
    judgment in all respects.
    A F F I R M E D.
    12