Taj Al Khairat Ltd. v. Swiftships Shipbuilders, L.L.C. ( 2015 )


Menu:
  •      Case: 15-30195       Document: 00513295846         Page: 1     Date Filed: 12/04/2015
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    No. 15-30195                       United States Court of Appeals
    Fifth Circuit
    FILED
    TAJ AL KHAIRAT LIMITED,                                                   December 4, 2015
    Lyle W. Cayce
    Plaintiff - Appellee                                              Clerk
    v.
    SWIFTSHIPS SHIPBUILDERS, L.L.C.,
    Defendant - Appellant
    Appeal from the United States District Court
    for the Western District of Louisiana
    USDC No. 6:13-CV-2609
    Before DAVIS, BARKSDALE, and DENNIS, Circuit Judges.
    PER CURIAM:*
    For Swiftships Shipbuilders, L.L.C.’s challenge to the summary
    judgment awarded Taj Al Khairat, Ltd., on its breach-of-contract claim
    regarding their settlement agreement, primarily at issue is whether a genuine
    dispute of material fact exists for whether Swiftships and Taj reached an oral
    agreement constituting a novation of the settlement agreement. AFFIRMED.
    * Pursuant to 5th Cir. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5th Cir.
    R. 47.5.4.
    Case: 15-30195    Document: 00513295846     Page: 2   Date Filed: 12/04/2015
    No. 15-30195
    I.
    Two contracts form the basis for this dispute. The first is the settlement
    agreement, executed in August 2011 by Taj and Swiftships.            To resolve
    disputes arising from a contract the parties executed the year before, the
    settlement agreement required Swiftships to pay Taj either a lump sum of $5.2
    million, or monthly installments totaling $6.8 million; if Swiftships failed to
    make timely payment, Taj was entitled to default judgment, which Swiftships
    expressly waived its right to challenge. A choice-of-law provision designated
    Texas law as governing. Rahman, the United States representative for Taj
    through its United States subsidiary, Crown Contracting, Inc., signed the
    agreement for Taj.
    The second contract is a master services agreement (MSA) between
    Swiftships and IWG, Inc., executed in February 2013. The MSA obligated
    Swiftships to pay IWG for consulting services on a shipbuilding contract with
    South Oil Company in Iraq (SOC contract). The MSA included a merger
    provision, identifying the MSA as “the entire agreement between the parties
    . . . , supersed[ing] any oral promises, proposals, representations,
    understandings and negotiations between the parties respecting the subject
    matter” of the MSA. In addition to being the United States representative for
    Taj, Rahman served as an officer for IWG, and executed the MSA for it.
    Taj filed this action in September 2013, claiming Swiftships breached
    the settlement agreement by failing to make timely payment. Swiftships did
    not dispute that it only made one payment under that agreement. Instead, it
    claimed, inter alia, a novation occurred when the MSA was executed, relieving
    it of obligations under the settlement agreement. Along that line, Swiftships
    contended: an oral agreement in the summer of 2012 between its then-new
    owners, brothers Shehraze and Khurram Shah, and Rahman (again, United
    States representative for Taj and officer for IWG), substituted the MSA for the
    2
    Case: 15-30195     Document: 00513295846     Page: 3   Date Filed: 12/04/2015
    No. 15-30195
    settlement agreement; and, under the MSA, Swiftships’ payments to IWG
    satisfied Swiftships’ debt to Taj. The Shah brothers’ attorney, Nubani, was
    also present at the summer-2012 meeting at which Swiftships contends it and
    Taj reached an oral agreement.
    In awarding summary judgment to Taj, the district court ruled that
    “nothing in the testimony of the parties permits the conclusion that a meeting
    of the minds ever occurred concerning how the Taj debt would be handled, and
    therefore, a new oral agreement was never formed which could be considered
    a novation of the Settlement Agreement”. Taj Al Khairat, Ltd. v. Swiftships
    Shipbuilders, L.L.C., No. 13-02609, 
    2015 WL 464749
    , at *5 (W.D. La. 3 Feb.
    2015). Additionally, the court held, inter alia, “the merger clause in the MSA
    bars any novation defense”. 
    Id. II. Summary
    judgment is reviewed de novo, applying the same legal
    standards as the district court. E.g., Nobel Energy, Inc. v. Bituminous Cas.
    Co., 
    529 F.3d 642
    , 645 (5th Cir. 2008). Viewing all evidence and drawing all
    reasonable inferences in the nonmovant’s favor, summary judgment is
    appropriate when “no genuine dispute [of] material fact” exists and “the
    movant is entitled to judgment as a matter of law”. Fed. R. Civ. P. 56(a); see,
    e.g., Nunez v. Allstate Ins. Co., 
    604 F.3d 840
    , 844 (5th Cir. 2010). No such
    dispute exists “[i]f the record, taken as a whole, could not lead a rational trier
    of fact to find for the nonmoving party”. Dediol v. Best Chevrolet, Inc., 
    655 F.3d 435
    , 439 (5th Cir. 2011). Once the movant satisfies its burden of demonstrating
    no such dispute exists, the nonmovant must point to specific evidence in the
    summary-judgment record to demonstrate there is a material-fact dispute
    regarding the essential elements of the case. Forsyth v. Barr, 
    19 F.3d 1527
    ,
    1533 (5th Cir. 1994). On the other hand, “if the nonmoving party rests merely
    upon conclusory allegations, improbable inferences, and unsupported
    3
    Case: 15-30195     Document: 00513295846       Page: 4    Date Filed: 12/04/2015
    No. 15-30195
    speculation”, summary judgment may be proper.                
    Id. (quoting Krim
    v.
    BancTexas Grp., Inc., 
    989 F.2d 1435
    , 1449 (5th Cir. 1993)).
    A.
    Before reaching whether there is a genuine dispute of material fact, two
    points must be addressed.
    1.
    The district court found no basis for Swiftships’ challenges to the validity
    of the settlement agreement. Taj, 
    2015 WL 464749
    , at *5–6 & n.4. Those
    issues are not raised on appeal; therefore, they are waived. E.g., United States
    v. Whitfield, 
    590 F.3d 325
    , 346 (5th Cir. 2009).
    2.
    Similarly, Swiftships does not contest the district court’s ruling that the
    MSA’s merger clause bars Swiftships’ novation defense. Taj, 
    2015 WL 464749
    ,
    at *5. The court cited New York law, which the parties agreed governed the
    MSA, to articulate the enforceability of merger clauses: “The purpose of a
    merger clause is to require the full application of the parol evidence rule . . . to
    bar the introduction of extrinsic evidence to alter, vary or contradict the terms
    of the writing. . . . by evincing the parties’ intent that the agreement is to be
    considered a completely integrated writing”. 
    Id. at *5
    n.4 (quoting Jarecki v.
    Shung Moo Louie, 
    95 N.Y.2d 665
    , 669 (2001)) (internal quotation marks
    omitted). Merger clauses are also generally enforceable under Texas law. See,
    e.g., ISG State Operations, Inc. v. Nat’l Heritage Ins. Co., 
    234 S.W.3d 711
    , 719
    (Tex. App.—Eastland 2007).
    Swiftships waives any issue concerning the MSA merger provision by
    failing to challenge this part of the district court’s ruling. Tewari De-Ox Sys.,
    Inc. v. Mountain States/Rosen, L.L.C., 
    637 F.3d 604
    , 609–10 (5th Cir. 2011).
    As a result, it arguably forfeits its right to dispute the summary judgment. See
    
    id. “We will
    not raise and discuss legal issues that [the appellant] . . . failed to
    4
    Case: 15-30195     Document: 00513295846      Page: 5   Date Filed: 12/04/2015
    No. 15-30195
    assert.” Brinkmann v. Dallas Cty. Deputy Sheriff Abner, 
    813 F.2d 744
    , 748
    (5th Cir. 1987).
    Assuming this point may be considered, and for our de novo review, a
    plain reading of the MSA merger provision calls into question its applicability
    regarding the claimed novation. The clause prevents the parties to the MSA
    from presenting evidence of prior oral agreements between the same parties
    concerning the subject matter of the MSA. The alleged summer-2012 oral
    agreement was, according to the Shah brothers, between Taj and Swiftships,
    not IWG. And, the parties to the MSA were Swiftships and IWG, not Taj.
    Although Swiftships contends the debt to Taj was satisfied by payments to
    IWG under the MSA, Taj is not a party to the MSA. On the other hand,
    Rahman could execute contracts for both Taj and IWG.
    Even assuming arguendo the merger clause does not bar our considering
    evidence of an oral agreement, Swiftships’ challenge still fails, for the following
    reasons.
    B.
    In maintaining the district court erred in holding Swiftships and Taj did
    not reach an oral agreement, Swiftships contends: had the court construed all
    the evidence in the light most favorable to the nonmovant, it would have
    concluded the Shah brothers’ deposition testimony created a genuine dispute
    of material fact on whether the parties reached an oral agreement and
    novation; and, therefore, summary judgment was improper.
    Under Texas law, novation is an affirmative defense to a breach-of-
    contract claim. Honeycutt v. Billingsley, 
    992 S.W.2d 570
    , 577 (Tex. App.—
    Houston [1st Dist.] 1999). A “[n]ovation is the substitution of a new agreement
    between the same parties or . . . of a new party on an existing agreement”. N.Y.
    Party Shuttle, LLC v. Bilello, 
    414 S.W.3d 206
    , 214 (Tex. App.—Houston [1st
    Dist.] 2013).   “Where a novation occurs, only the new agreement may be
    5
    Case: 15-30195     Document: 00513295846       Page: 6   Date Filed: 12/04/2015
    No. 15-30195
    enforced.” 
    Id. The party
    asserting novation as a defense must show: “(1) a
    previous, valid obligation; (2) a mutual agreement of the parties to the
    acceptance of a new contract; (3) the extinguishment of the old contract; and
    (4) the validity of the new contract”. Vickery v. Vickery, 
    999 S.W.2d 342
    , 356
    (Tex. 1999). In other words, a “novation is never presumed”. In re Bath Junkie
    Franchise, Inc., 
    246 S.W.3d 356
    , 365 (Tex. App.—Beaumont 2008). Obviously,
    the party claiming a novation must present evidence showing the parties’
    intent to effect one. 
    Id. Furthermore, the
    requisite “elements of both written and oral contracts
    are the same and must be present for a contract to be binding”. Searcy v. DDA,
    Inc., 
    201 S.W.3d 319
    , 322 (Tex. App.—Dallas 2006). An agreement must detail
    its essential terms such that a court could enforce it. E.g., id.; T.O. Stanley
    Boot Co. v. Bank of El Paso, 
    847 S.W.2d 218
    , 221 (Tex. 1992). And, the parties
    must have, inter alia, a meeting of the minds, and intend the agreement to be
    mutual and binding. See, e.g., Labor Ready Cent. III, L.P. v. Gonzalez, 
    64 S.W.3d 519
    , 522 (Tex. App.—Corpus Christi 2001). Moreover, the requisite
    meeting of the minds is evaluated “on the objective standard of what the
    parties said and did—and not on their subjective state of mind”. Wal-Mart
    Stores, Inc. v. Lopez, 
    93 S.W.3d 548
    , 556 (Tex. App.—Houston [14th Dist.]
    2002). “It is well settled law that when an agreement leaves material matters
    open for future adjustment and agreement that never occur, [the agreement]
    is not binding upon the parties and merely constitutes an agreement to agree.”
    Fort Worth Indep. Sch. Dist. v. City of Fort Worth, 
    22 S.W.3d 831
    , 846 (Tex.
    2000).
    Swiftships points to the Shah brothers’ deposition testimony, regarding
    the summer-2012 meeting, as evidence the parties reached an oral agreement,
    which substituted the MSA for the settlement agreement. Nevertheless, that
    testimony―viewed      in    the   light   most   favorable   to   the   nonmovant,
    6
    Case: 15-30195    Document: 00513295846     Page: 7   Date Filed: 12/04/2015
    No. 15-30195
    Swiftships―fails to demonstrate a rational finder of fact could find a meeting
    of the minds took place, essential terms were articulated, and a court could
    enforce the articulated terms. See, e.g., 
    Dediol, 655 F.3d at 439
    ; Stanley 
    Boot, 847 S.W.2d at 221
    –22.
    In support of an oral agreement, Swiftships asserts Shehraze Shah
    understood the Taj debt would be satisfied by the amounts Swiftships paid
    IWG under the MSA. He based this assumption in part on his recollection of
    Rahman’s statements at the summer-2012 meeting: “[W]e will settle the
    disagreement, and the disbursement will take care of the Taj settlement and
    whatever is the balance would be considered as a fee for the services” provided
    under the future MSA. But the rest of his deposition testimony is ambiguous
    on whether the parties reached an agreement. According to him, Rahman said
    “we will settle all the past dues, and we will move forward if we can procure
    this contract, the SOC contract, and the performance bond”. (Emphasis added.)
    He also was unclear about whether the SOC contract or the MSA was the
    vehicle for discharging Taj’s debt.    Similarly, he could not articulate the
    essential terms concerning payment. Regarding the amount to which the
    parties allegedly agreed, he testified, “The debt was part of the settlement that
    we had with $3 million as the principal amount of the debt. . . . [It] was agreed
    upon [ ] that’s what the Taj people wanted, and that’s all we [would] pay as
    part of our settlement”.
    Like his brother, Khurram Shah testified he believed the payments
    under what would become the MSA would satisfy the debt to Taj; but, his
    testimony demonstrates his understanding was contingent on procuring the
    SOC contract and lacked concrete essential terms. When asked whether he
    thought the debt to Taj would be resolved by the future MSA, he answered, “I
    specifically recall using the words ‘bygones are bygones’ and ‘let’s move
    forward,’ and [Rahman] agreed, yes, we’re [going to] move forward”. He also
    7
    Case: 15-30195    Document: 00513295846     Page: 8   Date Filed: 12/04/2015
    No. 15-30195
    conceded he was uncertain what Rahman’s understanding was: “I don’t recall
    distinctly stating that the monies -- I mean, the idea was that, okay, let’s move
    forward. . . . [F]or [Swiftships], I’m very clear what moving forward means, and
    I don’t know what part of that [Rahman] didn’t rec- -- didn’t understand”.
    Finally, he further confused the issue when he testified that he understood the
    entire debt was not “being dismissed or [ ] forgotten”: “[W]hy would somebody
    want to give that up?”
    Even if the deposition testimony by the Shah brothers could be seen as
    suggestive of an oral agreement, neither their attorney, Nubani, nor Rahman’s
    deposition testimony supports an oral agreement. Nubani stated “there was a
    reference made to an agreement that would be . . . produced, [but] there was
    no discussion at the time of what the provisions of that agreement would be”.
    Swiftships’ attorney further testified: “I don’t know if there was ever a formal
    sitting down between all of the parties involved in this matter”; “no one had
    the full picture at any given time[,] [b]ecause things were not defined”; and
    “people were talking based on their assumptions”. And, Rahman denied the
    formation of any agreement that replaced the debt to Taj with Swiftships’
    payment to IWG.
    Moreover, the Shah brothers believed Rahman represented Taj, not
    IWG, at the summer-2012 meeting. Although their attorney Nubani’s
    imprecise recollection of the summer-2012 meeting included IWG, the Shahs
    suggest in their deposition testimony that Rahman created IWG to collect on
    the original Taj debt and render their oral agreement unnecessary. The parties
    do not brief this contention, however; and no other evidence in the record
    besides the Shahs’ deposition testimony supports it.
    Furthermore, any such suggestion fails to explain why Swiftships signed
    the MSA, which contained references only to IWG, and not Taj. As the district
    court noted, the “MSA makes no mention of Taj, the Settlement Agreement, or
    8
    Case: 15-30195    Document: 00513295846     Page: 9     Date Filed: 12/04/2015
    No. 15-30195
    Swiftships’ obligations thereunder”. Taj, 
    2015 WL 464749
    , at *5. Instead, the
    MSA provides Swiftships’ payments to IWG are in consideration for IWG’s
    services.   As self-serving testimony unsupported by any other summary-
    judgment evidence, and left un-briefed by Swiftships, this suggestion fails to
    overcome summary judgment. See DIRECTV, Inc. v. Budden, 
    420 F.3d 521
    ,
    531 (5th Cir. 2005); Hardison v. Abdon Callais Offshore, L.L.C., 551 F. App’x
    735, 738–39 (5th Cir. 2013) (unpublished).      If the MSA in 2013 was the
    memorialization of the alleged oral agreement in the summer of 2012, it does
    not demonstrate satisfaction for Swiftships’ debt to Taj.
    III.
    For the foregoing reasons, the judgment is AFFIRMED.
    9