William Crace v. Northrop Grumman Ship Systems , 670 F. App'x 196 ( 2016 )


Menu:
  •      Case: 16-30205      Document: 00513725593         Page: 1    Date Filed: 10/19/2016
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    United States Court of Appeals
    Fifth Circuit
    No. 16-30205                                FILED
    Summary Calendar                       October 19, 2016
    Lyle W. Cayce
    Clerk
    WILLIAM PAUL CRACE,
    Plaintiff - Appellant
    v.
    HUNTINGTON INGALLS, INCORPORATED, formerly known as Northrop
    Grumman Ship Systems, Inc.,
    Defendant - Appellee
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    USDC No. 2:12-CV-1986
    Before JONES, WIENER, and CLEMENT, Circuit Judges.
    PER CURIAM:*
    William Paul Crace appeals the district court’s grant of summary
    judgment in favor of Huntington Ingalls, Incorporated, formerly known as
    Northrop Grumman Ship Systems, Inc. We affirm.
    I.
    Huntington Ingalls contracted to build a ship for the United States Navy.
    Crace worked for a subcontractor responsible for inspecting the ship prior to it
    * Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH
    CIR. R. 47.5.4.
    Case: 16-30205     Document: 00513725593      Page: 2   Date Filed: 10/19/2016
    No. 16-30205
    being commissioned and delivered to the Navy. While attempting to inspect a
    lower compartment on the ship, Crace ducked under a chain, went down a
    hatch, and began to descend a ladder. He fell from the ladder and was injured.
    Crace alleged that Huntington Ingalls defectively designed, constructed,
    and installed the ladder. He further alleged that Huntington Ingalls
    negligently installed a locked safety chain that restricted access to the hatch
    and ladder. Crace claimed that the safety chain forced him to awkwardly duck
    under the chain to climb down the hatch and ladder, contributing to his fall.
    Crace brought claims for negligence under the Longshore and Harbor
    Workers Compensation Act, 33 U.S.C. § 905(b), general maritime law, and
    state law. The district court held, first, that it lacked jurisdiction over Crace’s
    federal maritime claims because the ship was not a completed vessel at the
    time of the accident. Second, the district court held that government contractor
    immunity shielded Huntington Ingalls from liability for Crace’s state-law
    negligence claim for defective design, construction, and installation of the
    ladder. Third, the district court held that Crace’s state-law claim for negligent
    placement of a safety chain failed because the chain was an open and obvious
    condition. Crace challenges each of these holdings on appeal.
    II.
    We review the district court’s grant of summary judgment de novo,
    “applying the same standards as the district court.” Malin Int’l Ship Repair &
    Drydock, Inc. v. Oceanografia, S.A. de C.V., 
    817 F.3d 241
    , 249 (5th Cir. 2016).
    III.
    Crace first argues that the district court erred in holding that the ship
    on which he was injured was still under construction at the time of the
    accident. To bring a maritime tort claim, the tort must occur on navigable
    waters and the alleged wrong must “bear a significant relationship to
    traditional maritime activity.” Richendollar v. Diamond M Drilling Co., 819
    2
    Case: 16-30205       Document: 00513725593         Page: 3    Date Filed: 10/19/2016
    No. 16-30205
    F.2d 124, 127 (5th Cir. 1987) (en banc). There is no significant nexus to
    maritime activity if a ship is under construction, because shipbuilding is not a
    traditional maritime activity. Cain v. Transocean Offshore USA, Inc., 
    518 F.3d 295
    , 301-03 (5th Cir. 2008); Alfred v. MV Margaret Lykes, 
    398 F.2d 684
    , 685
    (5th Cir. 1968).
    Crace argues that the ship was sufficiently complete at the time of his
    accident such that it qualifies as a vessel. Although the ship had successfully
    completed sea trials, it was still being outfitted and inspected prior to final
    delivery. This court has held that “a structure under construction remains a
    non-vessel until it is complete and ready for duty upon the sea.” Cain, 518 F.3d
    at 301; see also Lowe v. Ingalls Shipbuilding, 
    723 F.2d 1173
    , 1187 (5th Cir.
    1984) (stating that “an injury to a ship construction worker on board a ship
    under construction and lying in navigable waters is not a maritime tort” (citing
    Hollister v. Luke Constr. Co., 
    517 F.2d 920
    , 921 (5th Cir. 1975)); Casas v. U.S.
    Joiner, LLC, 372 F. App’x 440, 441 (5th Cir. 2010). We affirm the district
    court’s holding that the incomplete ship was not a vessel under maritime law. 1
    Crace next argues that the district court erred in holding that
    government contractor immunity shielded Huntington Ingalls from liability for
    Crace’s state-law negligence claim for defective design, construction, and
    installation of the ladder. The district court held that the ladder was designed,
    built, and placed by Huntington Ingalls in compliance with reasonably precise
    Navy specifications. See Boyle v. United Techs. Corp., 
    487 U.S. 500
    , 512 (1988)
    (holding that liability for defects in military equipment cannot be imposed
    under state law when, inter alia, “the United States approved reasonably
    1 Crace alternatively asks that this court hold that the Supreme Court’s decision in
    Stewart v. Dutra Construction Co., 
    543 U.S. 481
     (2005), overruled prior Fifth Circuit
    precedent holding that a ship under construction is not a vessel. As Crace acknowledges, this
    argument is foreclosed. See Cain, 518 F.3d at 301 (“We do not read Stewart to change this
    body of law . . . .”).
    3
    Case: 16-30205    Document: 00513725593      Page: 4   Date Filed: 10/19/2016
    No. 16-30205
    precise specifications” and “the equipment conformed to those specifications”).
    While it was Huntington Ingalls that prepared drawings regarding the design
    and installation of the ladder, it did so in accordance with reasonably precise
    Navy parameters, and the Navy ultimately approved the drawings and actual
    placement of the ladder. The district court correctly applied the government
    contractor immunity defense.
    Finally, Crace argues that the district court erred in granting summary
    judgment to Huntington Ingalls on his negligence claim as to the safety chain.
    “Under Louisiana law, a defendant generally does not have a duty to protect
    against that which is obvious and apparent.” Bufkin v. Felipe’s La., LLC, 2014-
    0288, p. 7 (La. 10/15/14); 
    171 So. 3d 853
    , 856. The safety chain was in place so
    that personnel would not fall through the open hatch in the deck. Crace’s
    testimony demonstrates that to save time, he chose to climb under the locked
    chain rather than opening it with a key. The risk created by climbing under a
    chain meant to prevent individuals from falling into a hatch was open and
    obvious. The district court properly held that Huntington Ingalls had no duty
    to protect against this open and obvious risk.
    IV.
    AFFIRMED.
    4