Entergy Texas, Incorporated v. Donna Nelson , 889 F.3d 205 ( 2018 )


Menu:
  •      Case: 17-50042   Document: 00514447565        Page: 1   Date Filed: 04/26/2018
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    United States Court of Appeals
    No. 17-50042
    Fifth Circuit
    FILED
    April 26, 2018
    ENTERGY TEXAS, INCORPORATED,                                      Lyle W. Cayce
    Clerk
    Plaintiff - Appellee
    v.
    DONNA L. NELSON, In her official capacity as Chairman of the Public
    Utility Commission of Texas; BRANDY MARTY MARQUEZ, In her official
    capacity as a Commissioner of the Public Utility Commission of Texas;
    KENNETH W. ANDERSON, JR., In his official capacity as a Commissioner
    of the Public Utility Commission of Texas,
    Defendants - Appellants
    TEXAS INDUSTRIAL ENERGY CONSUMERS,
    Intervenor Defendant - Appellant
    Appeals from the United States District Court
    for the Western District of Texas
    Before REAVLEY, SMITH, and OWEN, Circuit Judges.
    REAVLEY, Circuit Judge:
    The Federal Energy Regulatory Commission (“FERC”) and the Public
    Utility Commission of Texas (“PUCT”) both play a role in the regulation of
    energy production and sale. If they issue conflicting orders, FERC’s controls.
    This case is about whether, as the district court found, a certain PUCT order
    conflicts with a prior FERC order. On one side, we have PUCT and a trade
    Case: 17-50042     Document: 00514447565      Page: 2   Date Filed: 04/26/2018
    No. 17-50042
    association, the Texas Industrial Energy Consumers (“TIEC”). As appellants,
    they seek to persuade us that PUCT’s order was consistent with the relevant
    FERC order and should therefore be enforced. On the other side, we have
    Entergy Texas, Inc. (“ETI”), an operating company of Entergy Corporation.
    ETI brought this action to enjoin enforcement of the PUCT order and now
    defends the district court’s ruling. We decide that PUCT’s order is not in
    conflict with any FERC order.       We reverse the district court and render
    judgment in favor of PUCT and TIEC.
    I.     BACKGROUND
    Entergy Corporation is a public utility holding company dealing in
    electricity through its subsidiary “Operating Companies,” including ETI.
    Entergy Operating Companies are split along state lines. Entergy serves
    customers in Texas, Arkansas, Louisiana, and Mississippi, and its Operating
    Companies are ETI; Entergy Arkansas, Inc.; Entergy Gulf States Louisiana,
    L.L.C. (“EGSL”); Entergy New Orleans, Inc.; and Entergy Mississippi, Inc.
    This strict division did not always exist. Prior to 2008, an entity called Entergy
    Gulf States, Inc. (“Entergy Gulf States”) served markets in both Texas and
    Louisiana. Its split led to the creation of ETI and EGSL.
    Electricity is highly regulated, and both state and federal authorities
    play significant roles. FERC “regulates the sale of electricity at wholesale in
    interstate commerce.” Entergy La., Inc. v. La. Pub. Serv. Comm’n (“LPSC”),
    
    539 U.S. 39
    , 41, 
    123 S. Ct. 2050
    , 2053 (2003). But at the intrastate level, state
    regulatory bodies have sole jurisdiction. F.E.R.C. v. Electric Power Supply
    Ass’n, 
    136 S. Ct. 760
    , 767–68 (2016), as revised (Jan. 28, 2016). In Texas, PUCT
    is the regulating authority. Because Entergy sells electricity across state lines
    at both wholesale and retail levels, it must work with FERC, PUCT, and other
    state authorities.
    2
    Case: 17-50042    Document: 00514447565    Page: 3   Date Filed: 04/26/2018
    No. 17-50042
    Entergy’s Operating Companies must maintain roughly equal costs of
    production, and FERC must make it so. The obligation to equalize costs comes
    primarily from FERC’s Section 206 duty to ensure “reasonable” rates that are
    not “unduly discriminatory,” 16 U.S.C. § 824e(a), but also from the “System
    Agreement”     entered   into    between    the   Operating     Companies—a
    FERC-approved “filed rate” for purposes of the filed rate doctrine. See Entergy
    Louisiana, 
    Inc., 539 U.S. at 42
    , 123 S.Ct. at 2053 (explaining that the System
    Agreement is “a tariff approved by FERC”). In 2005, a variety of factors led
    FERC to conclude that the Entergy System was “out of rough production cost
    equalization.” LPSC v. F.E.R.C., 
    522 F.3d 378
    , 388 (D.C. Cir. 2008) (per
    curiam) (quoting 113 FERC ¶ 61282, 62134 (Dec. 19, 2005)). It took action.
    FERC’s remedy to the problem of unequal costs was that entities with
    low costs would make payments to entities with high costs as necessary to
    achieve “rough” equalization. More specifically, rough equalization was re-
    achieved through a “bandwidth remedy.” “Pursuant to this remedial measure,
    each calendar year the production costs of each operating company are
    calculated and, if necessary, ‘payments [are] made by the low cost Operating
    Company(ies) to the high cost Operating Company(ies) such that, after
    reflecting the payments and receipts, no Operating Company [has] production
    costs more than 11 percent above the Entergy System average or more than 11
    percent below the Entergy System average.’” LPSC v. FERC, 
    771 F.3d 903
    ,
    906 (5th Cir. 2014) (quoting LPSC v. Entergy Servs., Inc., 146 FERC ¶ 61,152
    at P 3 (2014) (second bracket added)). These payments are known as rough
    production cost equalization payments, or “Bandwidth Payments.”           Once
    Bandwidth Payments reach an Operating Company, a question arises: what
    becomes of the money?
    Here we reach a jurisdictional watershed. For FERC’s jurisdiction over
    the Bandwidth Payments ends when the funds reach the recipient Operating
    3
    Case: 17-50042     Document: 00514447565      Page: 4   Date Filed: 04/26/2018
    No. 17-50042
    Companies. State regulators determine the effect Bandwidth Payments will
    have on retail rates. Or, in FERC’s words, states handle “any issues related to
    the allocation of an individual utility’s payments or receipts to retail
    customers.” 127 FERC ¶ 61126, 61548 (May 8, 2009).
    Bandwidth Payments do not represent profit.           Rather, because the
    purpose of cost equalization is to ensure reasonable rates, the benefit flows to
    the customer. Accordingly, an entity that receives a Bandwidth Payment
    passes it through to its customers.    And an Operating Company that makes
    a Bandwidth Payment saddles its customers with that cost. This is a simple
    dollar-for-dollar pass-through in the ordinary case, where the Operating
    Company functions solely within one state and is therefore subject to the
    jurisdiction of only that state.
    While Entergy Gulf States existed, however, both Louisiana and Texas
    regulators had lawful authority to regulate its Bandwidth Payment receipts.
    This shared jurisdiction affected only the Bandwidth Payments made in one
    year—2007, the first year the bandwidth remedy was in place. That was more
    than a decade ago, but it is where our story really begins.
    The 2007 Bandwidth Payments reflected the “2006 test year.” In other
    words, they were calculated based on 2006 data. Entergy Gulf States received
    a $120.1 million Bandwidth Payment while still in existence astraddle the
    Texas and Louisiana state lines. Under the system we have already described,
    both Texas and Louisiana regulators had authority to determine how that
    payment would affect retail rates in their respective jurisdictions. Thus, each
    state had to decide what portion of the $120.1 million Bandwidth Payment
    should be passed through to customers within that state.
    After receiving the payment, but before state regulators could act,
    Entergy Gulf States split into two separate entities divided by the state line—
    ETI (Texas) and EGSL (Louisiana). This separation was immaterial to the
    4
    Case: 17-50042          Document: 00514447565        Page: 5   Date Filed: 04/26/2018
    No. 17-50042
    division of the original $120.1 million payment because it occurred after
    Entergy Gulf States received that payment. It solved a problem for future
    years, but as FERC has since made entirely clear, Texas and Louisiana
    retained their shared jurisdiction of the $120.1 million payment. See 127
    FERC ¶ 61126, 61548 (May 8, 2009).
    Louisiana regulators acted first, splitting the $120.1 million by
    allocating an $80.948 million share to Louisiana and a $30.399 million share
    to Texas. Entergy then sought PUCT’s adoption of the same division, warning
    PUCT that FERC would “resolve” the matter if PUCT opted for “a different
    jurisdictional allocation methodology.” 1          Entergy feared that PUCT would
    decide Texas customers were entitled to more than a $30.399 million share of
    the $120.1 million, which would mean that Entergy would have to pass a
    greater benefit to Texas and Louisiana customers than it actually received.
    That is just what happened. PUCT viewed the split as disproportionally
    favoring Louisiana customers, found Louisiana’s method “not equitable,” and
    instead split the $120.1 million “on the basis of actual production costs,”
    resulting in a $62.37 million share for Louisiana and a $48.977 million share
    for Texas. 2      In short, while Bandwidth Payments represent a zero-sum game,
    Louisiana claimed $80.948 million of Entergy Gulf State’s $120.1 million piece
    of the pie, and Texas claimed $48.977 million—leaving an $18.6 million
    discrepancy that Entergy had to swallow.
    Entergy found this unfair. As foreshadowed, it took its complaint to
    FERC in the form of a proposed amendment to the System Agreement—an
    amendment that would allow FERC to allocate Entergy Gulf State’s 2007
    1   ETI Compliance Filing, Dkt. No. 35269, pg. 6, available at http://perma.cc/Q8BN-
    LC8C.
    2 Order on ETI Compliance Filing, Dkt. No. 35269, pg. 6, available at
    http://perma.cc/2RLL-QFZK.
    5
    Case: 17-50042      Document: 00514447565        Page: 6    Date Filed: 04/26/2018
    No. 17-50042
    bandwidth receipts between Louisiana and Texas retail jurisdictions. See 127
    FERC ¶ 61126, 61546. But there it found an unsympathetic ear. FERC
    recognized a jurisdictional impediment to granting Entergy relief, ruling that
    “any issues related to the allocation of an individual utility’s payments or
    receipts to retail customers” were beyond its jurisdiction. 
    Id. at 61548.
    Of
    course, no jurisdictional problem would exist if PUCT had transgressed any
    FERC order, but FERC confirmed there was no conflict because PUCT
    accepted “the Commission’s determination of the amount of receipts to be
    distributed to [Entergy Gulf States] under” the filed rate. 3 
    Id. Ultimately, the
    inconsistent-treatment problem was a problem of Entergy’s own creation:
    The potential for retail regulators to adopt different retail
    allocations of payments for multi-jurisdictional utilities has
    always existed, and the Commission has never claimed that a
    Commission-approved allocation has been violated because two
    states allocated the receipts differently among their respective
    retail customers. As has long been recognized, when more than
    one jurisdiction is involved there is an inherent operating risk that
    one jurisdiction may allocate on a different basis and the
    allocations may not mesh perfectly. It is axiomatic that different
    regulatory bodies are not bound to apply the same ratemaking
    principles, and therefore, the possibility of such imperfection is
    inherent in this nation’s dual system of retail and wholesale rate
    regulation. This is a risk that Entergy assumed when it
    established its operating structure.
    
    Id. (footnotes omitted).
    3  See also 
    id. (“[T]he Texas
    Commission has accepted the Commission’s interstate
    allocation of bandwidth receipts to [Entergy Gulf States] and merely determined what share
    of those payments should be allocated to Texas retail customers. The Louisiana Commission
    acted similarly. Thus, no conflict with the Commission’s regulations exists.”).
    6
    Case: 17-50042     Document: 00514447565      Page: 7    Date Filed: 04/26/2018
    No. 17-50042
    Entergy’s fight was not over yet. It sued PUCT in federal and state
    courts. Those suits were resolved by settlement in 2010, with ETI agreeing to
    let the matter go in return for a PUCT-approved rate increase. 4
    That could have been the end of it, but in Entergy’s eyes, the issue was
    not fully resolved because the bandwidth calculation for the 2006 test year
    remained in flux as various aspects of the bandwidth formula were litigated
    and ruled upon, meaning additional payments were necessary to “true-up” the
    rough equalization of production costs. Accordingly, in 2014, FERC found that
    its orders since the initial bandwidth calculation “affect the test year 2006
    bandwidth calculation.” It ordered Entergy “to file a comprehensive bandwidth
    recalculation report showing the updated payments and receipts” for both that
    year and 2007 in light of the changes.
    Entergy submitted its recalculations in the form of a “compliance filing.”
    TIEC opposed not the calculations but that portion of the compliance filing
    allocating the additional payment between ETI and EGSL; TIEC thought that
    the payments should be treated as being made to Entergy Gulf States. In the
    order now made the subject of this litigation, FERC accepted Entergy’s filing
    and rejected TIEC’s objection, finding “it was reasonable for Entergy to
    recalculate the 2007 bandwidth filing and allocate refunds and surcharges for”
    ETI and EGSL because those entities had succeeded the now-defunct Entergy
    Gulf States. 151 FERC ¶ 61112, 61701 (May 14, 2015).
    This “2015 FERC Order” also contained the following table, which
    “summarizes the remaining or true-up amounts to be paid/received on
    September 24, 2014.” 
    Id. at 61699.
    4  See Order on ETI Application for Authority to Change Rates, Dkt. No. 37744,
    available at https://perma.cc/32HU-J55B.
    7
    Case: 17-50042          Document: 00514447565      Page: 8   Date Filed: 04/26/2018
    No. 17-50042
    Company        Total 2007 bandwidth     2007 bandwidth amounts Remaining 2007
    (payments)/receipts      previously (paid)/received bandwidth amounts
    including interest       per the May 27, 2007       to be (paid)/received
    initial filing
    Entergy              ($278.3)                   ($251.7)                   ($26.5)
    Arkansas
    Entergy Gulf         $108.7                    $89.7                      $19.0
    States
    Louisiana
    Entergy              $93.8                     $91.1                      $2.7
    Louisiana
    Entergy              $34.5                     $40.6                      ($6.1)
    Mississippi
    Entergy New          $0.0                      $0.0                       $0.0
    Orleans
    Entergy              $41.3                     $30.4                      $10.9
    Texas
    It is undisputed that the 2015 FERC Order authorized ETI to receive an
    additional $10.9 million Bandwidth Payment stemming from the 2006 test
    year. It did that and more, according to ETI. Based upon this table, ETI
    concluded that FERC had reversed itself with respect to the earlier
    Texas/Louisiana allocation dispute and retroactively reallocated to ETI a mere
    $30.4 million share of the original $120.1 million, meaning PUCT had
    overcharged ETI by more than $18 million.
    ETI informed PUCT of this conclusion in late 2014, asserting that, under
    FERC’s order, “retail customers have received from ETI an overpayment of
    $8.6 million for the 2007 Bandwidth filing.” This statement implied ETI would
    be keeping the new $10.9 million Bandwidth Payment as partial recompense
    for the prior overpayment. If PUCT cooperated, ETI would be content to let
    sleeping dogs lie: ETI assured PUCT that, “[i]n the interest of its customers,”
    ETI did not “intend to revisit the over-payment of 2007 receipts” but warned
    that “if other parties decide to revisit issues related to the overpayment, then
    ETI will respond accordingly.” In short, ETI would litigate if PUCT deemed
    the $10.9 million payment to be a new Bandwidth Payment subject to ordinary
    pass-through procedures.
    8
    Case: 17-50042    Document: 00514447565     Page: 9   Date Filed: 04/26/2018
    No. 17-50042
    PUCT ordered the $10.9 million payment be passed through to
    customers. ETI sued, seeking to enjoin enforcement of PUCT’s order on the
    basis that it conflicted with the 2015 FERC Order in light of the table set forth
    above. TIEC intervened and participated in the litigation. The district court
    found ETI’s contentions persuasive and enjoined enforcement of the PUCT
    order. PUCT and TIEC appealed.
    II.   STANDARD OF REVIEW
    Orders granting or denying a permanent injunction are typically
    reviewed for abuse of discretion. N. Alamo Water Supply Corp. v. City of San
    Juan, Tex., 
    90 F.3d 910
    , 916 (5th Cir. 1996). But when the dispute turns on
    the legal question of preemption, review is de novo. VRC LLC v. City of Dallas,
    
    460 F.3d 607
    , 611 (5th Cir. 2006). The issue facing this court is preemption vel
    non, and review is de novo.
    III.   DISCUSSION
    This is a single-question case: did the 2015 FERC Order merely identify
    the proper amount of remaining Bandwidth Payments to be made to various
    Operating Companies including ETI, or did it also retroactively reallocate all
    previously made 2007 Bandwidth Payments, thus establishing that PUCT had
    already ordered ETI to pass through more funds than ever it received in
    Bandwidth Payments?
    A. The Arguments
    PUCT and TIEC argue that the purpose of the 2015 FERC Order was to
    allocate remaining Bandwidth Payments attributable to the 2006 test year,
    payments that were now due in light of changes and clarifications to the
    bandwidth formula. Under this view, ETI was entitled to an additional $10.9
    million Bandwidth Payment, which it duly received and which PUCT duly
    ordered passed through to customers. Any gripes relating to the alleged initial
    overcharge are water under the bridge because PUCT already won that battle,
    9
    Case: 17-50042        Document: 00514447565       Page: 10     Date Filed: 04/26/2018
    No. 17-50042
    and Entergy’s attempt to read the 2015 FERC Order in a way that effectively
    abrogates past PUCT and FERC rulings amounts to a collateral challenge of
    those long-final orders.
    According      to   ETI,   the    2007    Bandwidth        Payments    were   only
    “conditionally” approved.        In subsequent years, the bandwidth formula
    changed, and FERC ultimately ordered a backward-looking recalculation and
    reallocation, which Entergy performed and FERC approved. Thus, with the
    2015 FERC Order, FERC conclusively determined that ETI’s “total” 2007
    Bandwidth Payment was $41.3 million. The new payment of $10.9 million
    approved in that same order is off limits to PUCT because PUCT has already
    claimed more than $41.3 million in 2007 Bandwidth Payments. Put another
    way: PUCT must abide by the determination that ETI received a mere $41.3
    million in 2007 Bandwidth Payments, and because it has already passed
    through 2007 Bandwidth Payments in excess of that figure, it cannot touch the
    $10.9 million payment.
    B. Relevant Principles
    FERC has “exclusive jurisdiction to regulate the transmission and
    wholesale sale of electric energy in interstate commerce.” AEP Tex. N. Co. v.
    TIEC, 
    473 F.3d 581
    , 584 (5th Cir. 2006). The Federal Power Act both supplies
    FERC with this jurisdiction and limits it, establishing “a zone of exclusive state
    jurisdiction.” Electric Power 
    Supply, 136 S. Ct. at 767
    . It is for states to regulate
    both “within-state wholesale sales” and, “more pertinent here, retail sales of
    electricity.” 
    Id. at 768.
          There is no overlap of jurisdiction. See New Orleans Pub. Serv., Inc. v.
    Council of City of New Orleans, 
    911 F.2d 993
    , 1001 (5th Cir. 1990). But there
    is a risk that one regulator acting in its proper capacity can disrupt the
    regulatory efforts of the other. See Electric Power 
    Supply, 136 S. Ct. at 776
    . In
    cases of conflict, the Constitution’s Supremacy Clause controls. See Entergy
    10
    Case: 17-50042   Document: 00514447565      Page: 11   Date Filed: 04/26/2018
    No. 17-50042
    Louisiana 
    Inc., 539 U.S. at 47
    , 123 S.Ct. at 2056. “The filed rate doctrine
    requires ‘that interstate power rates filed with FERC or fixed by FERC must
    be given binding effect by state utility commissions determining intrastate
    rates.’” 
    Id. (quoting Nantahala
    Power & Light Co. v. Thornburg, 
    476 U.S. 953
    ,
    962, 
    106 S. Ct. 2349
    , 2354 (1986)). Thus, as applied to state regulators, the
    filed rate doctrine polices the jurisdictional line and protects FERC’s authority.
    
    Id. C. Interpreting
    the 2015 FERC Order
    When interpreting an order, we start with the order. What does it say?
    What, on its face, does it do? ETI seeks to convince us that FERC’s order
    retroactively reallocates 2007 Bandwidth Payments, but the order simply says
    nothing about that. The word “reallocation” is not used; nor is any synonym or
    functionally equivalent phrasing. There are no broad statements from which
    an objective reader can infer any intent to retroactively reallocate the 2007
    Bandwidth Payments.        And there are no statements shedding light on a
    supposed need or motivation to do so. ETI’s position looks suspect already.
    FERC was specific about what its order does. Most basically, the order
    approves ETI’s compliance filing.       151 FERC ¶ 61112, 61698 (“Entergy’s
    compliance filing is accepted.”). Indeed, assessing the acceptability of the
    compliance filing was the order’s raison d’être. This observation raises two
    question. First, with its filing, what did FERC order with respect to Entergy’s
    compliance filing? (If FERC had previously ordered a retroactive reallocation,
    then we have our answer.)        Second, did Entergy’s compliance filing itself
    purport to effect a retroactive reallocation? (If so, FERC’s acceptance of the
    filing would likely establish a retroactive reallocation, even if FERC had not
    previously contemplated such a measure.) If the answers to these questions
    do not point to a retroactive reallocation, then ETI is left with the difficult task
    11
    Case: 17-50042     Document: 00514447565    Page: 12   Date Filed: 04/26/2018
    No. 17-50042
    of persuading us that the 2015 FERC Order somehow effectuated a retroactive
    reallocation by the way.
    1. FERC’s orders requiring the Entergy compliance filing did
    not call for a retroactive reallocation of 2007 Bandwidth
    Payments.
    As noted already, the bandwidth formula remained in flux for years after
    the 2007 Bandwidth Payment had been made, meaning the initial payment
    had necessarily been calculated incorrectly. Once FERC got the formula ironed
    out, it became clear that two Entergy Operating Companies needed to make
    further payments to achieve rough cost equalization. FERC ordered Entergy
    to submit a single filing that would “comply with” its “final orders regarding
    the annual bandwidth calculations pending in numerous dockets.” 148 FERC
    ¶ 61085, 61514 (July 31, 2014). The formal directive was:
    to file, within 45 days of this order, a comprehensive bandwidth
    recalculation report showing the updated payments and receipts
    based on the 2006 and 2007 calendar year data in compliance with
    all bandwidth formula and bandwidth calculation adjustments
    that the Commission accepted or ordered, effective as of June 1,
    2007 and June 1, 2008, respectively, along with supporting
    calculations for each identified adjustment.
    
    Id. at 61514.
          In its briefing, ETI points us to the words “comprehensive” and
    “recalculation.”   But those words don’t help its cause.    FERC required a
    comprehensive compliance filing because it was allowing Entergy to comply
    with several orders in one submission. And FERC required a recalculation
    because a recalculation was patently necessary in light of its rulings that
    changes to the bandwidth formula impacted the original calculations. FERC
    did not order Entergy to submit a compliance filing retroactively reallocating
    12
    Case: 17-50042       Document: 00514447565        Page: 13     Date Filed: 04/26/2018
    No. 17-50042
    the 2007 Bandwidth Payments, and its subsequent acceptance of the
    compliance filing did not perforce achieve such an outcome. 5
    ETI’s reading of the procedural history is different. ETI places great
    importance on an alleged 2007 FERC statement that the initial Bandwidth
    Payments were approved “expressly subject to revision and refund.” From this,
    ETI contends that the initial calculation was subject to a complete do-over,
    which occurred in 2015.          Even if ETI accurately described FERC’s 2007
    statement, use of the word “revision” would be a thin reed upon which to hang
    its reallocation arguments.        But in fact FERC never said that its initial
    allocation decision was subject to revision and refund, which explains ETI’s
    telling failure to quote the cited FERC order. Rather, FERC stated that its
    initial decision was simply “subject to refund.” 120 FERC ¶ 61094, 61536.
    ETI’s attempt to rewrite the FERC order speaks volumes, and there is no
    textual support for its assertion that the initial determination was effectively
    tentative. FERC’s actual 2007 phrasing favors PUCT and TIEC, who are
    arguing that the 2015 FERC Order resolved only the issue of “refunds and
    surcharges.” The process they describe—an initial payment followed by a true-
    up years later—is consistent with FERC’s original approval “subject to refund.”
    120 FERC ¶ 61094, 61536.
    We have located only one FERC statement that favors ETI. In the July
    31, 2014 order already discussed, FERC said that “now is the appropriate time
    for Entergy to recalculate and reallocate the bandwidth payments and receipts
    among the Operating Companies.” 148 FERC ¶ 61085, 61514 (emphasis
    added). Here we have the word reallocate, but its use does not necessarily
    5To illustrate, in another FERC order accepting an Entergy compliance filing, FERC
    stated that the filing contained a “comprehensive bandwidth recalculation report showing
    the payment/receipt amounts based on 2009 test year data, including all workpapers.” 156
    FERC ¶ 61195 (Sept. 22, 2016). This language is nearly identical to the language used in the
    2015 FERC Order. It is not indicative of an extraordinary retroactive reallocation.
    13
    Case: 17-50042       Document: 00514447565          Page: 14     Date Filed: 04/26/2018
    No. 17-50042
    indicate an intent that Entergy conduct a retroactive reallocation as opposed
    to a supplemental true-up process with no retroactive effect. Both processes
    could be said to involve a reallocation. In any event, FERC used the word only
    in passing.     When it came time to issue a specific directive, the word is
    conspicuously absent. FERC’s detailed formal instruction—quoted above—
    does not include a mandate to “reallocate” payments and receipts. See 
    id. 2. Entergy’s
    compliance filing did not contain a retroactive
    reallocation that FERC approved in the 2015 FERC Order.
    Given     that   FERC       accepted     Entergy’s     compliance      filing,   then
    (notwithstanding its instructions regarding the scope of that filing) perhaps
    ETI would prevail if its compliance filing included a retroactive reallocation.
    The compliance filing did no such thing. FERC itself described the substance
    of the relevant document: “Entergy’s compliance filing consists of the
    recalculation of the true-up payments and receipts based on 2006 test year data
    and supporting workpapers for each identified adjustment, along with the
    applicable interest calculation through September 24, 2014, the date the
    payments and receipts will be made among the Entergy Operating
    Companies.” 151 FERC ¶ 61112, 61698 (emphasis added). This description is
    inconsistent with Entergy’s claim that its filing “consisted of the recalculation
    and reallocation of” 2007 Bandwidth Payments. 6 But it corresponds with the
    account put forth by PUCT and TIEC.
    Our examination of Entergy’s compliance filing likewise fails to unearth
    a hidden retroactive reallocation of 2007 Bandwidth Payments. 7                          The
    6The phrase “recalculation and reallocation” occurs at least five times in ETI’s brief.
    But Entergy never used the phrase prior to this litigation.
    7 ETI makes much of the fact that neither TIEC nor any other party “protested the
    bandwidth formula recalculation amounts.” But if this lack of protest is relevant, it only
    demonstrates that no party even conceived of the possibility that Entergy’s bandwidth
    compliance filing included a retroactive reallocation of already-litigated-and-paid 2007
    Bandwidth Payments. Similarly, the fact that neither PUCT nor TIEC challenged the 2015
    14
    Case: 17-50042       Document: 00514447565          Page: 15     Date Filed: 04/26/2018
    No. 17-50042
    compliance filing describes itself as a mere “bandwidth recalculation report” or
    “recalculation report.” 8        The bulk of the filing is a series of substantive
    explanations. Thus, headings “A” through “H” describe various accounting
    methods and decisions in a high level of detail.                   Despite this granular
    explanation, the compliance filing nowhere mentions any sort of retroactive
    reallocation.
    If the filing did contain a retroactive reallocation, it would presumably
    be found in Section III of the document, titled “Comprehensive Calculation of
    the Bandwidth Payments and Receipts.” This section is the original source of
    the table that later appeared in the 2015 FERC Order. According to Entergy’s
    compliance filing, the table does not represent a retroactive reallocation of 2007
    Bandwidth Payments and instead simply summarizes “remaining or true-up
    amounts” to be allocated in light of the recalculation. In this section of the
    filing, Entergy also explains that Entergy Gulf States’ share is being
    “allocate[d]” between ETI and EGSL according to a predetermined method.
    But, again, no mention of reallocation. Having reviewed Entergy’s filing, we
    conclude that FERC’s acceptance of the document did not necessarily
    effectuate a retroactive reallocation of 2007 Bandwidth Payments.
    3. The 2015 FERC Order does not retroactively reallocate 2007
    Bandwidth Payments
    FERC Order only lends credence to their present contention that the order is copacetic and
    that PUCT’s order adheres. ETI’s characterization of the PUCT order as “an improper
    collateral attack on FERC’s final decision” is not sensible.
    8 Indeed FERC’s characterization of the compliance filing comes from the filing itself,
    which states: “The instant compliance filing consists of the recalculation of the true-up
    payments and receipts based on 2006 test year data and supporting workpapers for each
    identified adjustment, along with the applicable interest calculation through September 24,
    2014.” Compare that description with the description ETI now provides on appeal: “Entergy’s
    filing consisted of the recalculation and reallocation of the Bandwidth payments and receipts
    based on 2006 test period cost data and supporting workpapers for each identified
    adjustment, along with the applicable interest calculation from June 1, 2007 through
    September 24, 2014.” (Emphasis added.) Entergy’s pre-litigation description is helpful, and
    in its own way, so is the tell-tale revision on appeal.
    15
    Case: 17-50042     Document: 00514447565     Page: 16   Date Filed: 04/26/2018
    No. 17-50042
    Here is what we know so far: FERC did not ask for a compliance filing
    that performed a retroactive reallocation of the 2007 Bandwidth Payments,
    and the compliance filing FERC approved contained no such reallocation. ETI
    cannot point to any clear FERC statement imposing a retroactive reallocation,
    and the measure is not necessary to achieve FERC’s goal of roughly equalizing
    the Operating Companies’ productions costs on a prospective basis. See 137
    FERC ¶ 61029 P.157 (explaining that Bandwidth Payments “occur
    prospectively”). Lastly, Entergy did not ask for a retroactive reallocation, and
    no party made it an issue before FERC.
    Nonetheless, ETI says the retroactive reallocation is there on the face of
    the order.    For this proposition, ETI relies almost entirely on the order’s
    inclusion of the table listing $41.3 million as the “Total 2007 bandwidth
    (payments)/receipts including interest.”      Here we have the retroactive
    reallocation of the 2007 Bandwidth Payments, or so says ETI. We now consider
    that claim.
    As already seen, Entergy created the table, and FERC reproduced it in
    the 2015 FERC Order. The table does list $41.3 million as the “Total 2007
    bandwidth (payments)/receipts including interest.” But this table was not
    created in a vacuum and cannot be interpreted in a vacuum. In light of the
    context already provided, we will not hastily conclude that Entergy hid a
    dramatic retroactive reallocation in plain sight, nor that FERC blessed it.
    What is this table and what does each column represent? In its order,
    FERC described the table as a summary of “the remaining or true-up amounts
    to be paid/received on September 24, 2014.” If that is what this table is, then
    only its third column is operative, for that is the column that documents the
    “Remaining 2007 bandwidth amounts to be (paid)/received.”           Under this
    reading, the district court was correct in dubbing the middle column “merely
    an accounting assumption,” and it erred by failing to recognize that the
    16
    Case: 17-50042     Document: 00514447565     Page: 17    Date Filed: 04/26/2018
    No. 17-50042
    adjacent column also contained a mere accounting assumption.            The last
    column is substantive; the other columns show the math.
    There is nothing strange about using hypothetical inputs to determine
    ETI and EGSL’s share of the remaining Bandwidth Payments seeing as how
    they did not exist in 2007 to receive the initial Bandwidth Payments. Because
    neither ETI nor EGSL actually received a 2007 Bandwidth Payment, FERC
    had to assign them a hypothetical share of the original $120.1 million payment
    to determine what portion of the remaining true-up each should receive. This
    does not mean there was some sort of retroactive reallocation with
    consequences far outreaching FERC’s objective or Entergy’s compliance task.
    We are satisfied that the table does not call for a retroactive reallocation
    of 2007 Bandwidth Payments. Indeed, this entire dispute ultimately boils
    down to whether the table is a summary of “the remaining or true-up amounts
    to be paid/received on September 24, 2014,” or whether it is instead a summary
    of “the comprehensive recalculation/reallocation of 2007 Bandwidth Payments
    and remaining or true-up amounts to be paid/received on September 24, 2014.”
    On its face, the FERC order declares that it is the former.
    Other textual clues abound.       The 2015 FERC Order recounts that
    Entergy first calculated “the incremental 2006 bandwidth receipts due” and
    then allocated Entergy Gulf State’s share between ETI and EGSL. 151 FERC
    ¶ 61112, 61699. And the order distinguishes between “original bandwidth
    payments and receipts” previously at issue and the associated “refunds and
    surcharges” presently at issue. 
    Id. at ¶
    61701 (“[W]hile the original bandwidth
    payments and receipts in 2007 for the 2006 test year involved Entergy Gulf
    States, . . . any refunds and surcharges associated with the 2007 bandwidth
    payments and receipts now must reflect the current members of the System
    Agreement . . . .”). Thus, the order does not resolve issues relating to the
    “original bandwidth payments” and merely addresses remaining “refunds and
    17
    Case: 17-50042     Document: 00514447565       Page: 18    Date Filed: 04/26/2018
    No. 17-50042
    surcharges,” which it “allocate[s].” 
    Id. These features
    conform precisely to
    PUCT’s and TIEC’s shared interpretation.
    ETI’s textual quiver has but one remaining arrow. It, too, misses the
    mark. ETI contends that the 2015 FERC Order must represent a “redo” of the
    2007 Bandwidth Payments because the accepted compliance filing was to be
    deemed “effective as of June 1, 2007.” The June 1, 2007 effective date is no
    more consistent with a retroactive reallocation than it is with an allocation of
    true-up payments. Here, the effective date was used to calculate interest. See
    
    id. at 61698
    (noting that FERC’s order requiring the compliance filing “directed
    that interest be included with the bandwidth payments/receipts made
    pursuant to the comprehensive recalculation from June 1, 2007”). It does not
    establish a retroactive reallocation of past receipts.
    In summation, our review of the 2015 FERC Order and its underlying
    orders and filings persuades us that its effect was merely to distribute true-up
    Bandwidth Payments among the Operating Companies entitled to receive
    them. 9 There was no retroactive reallocation of past Bandwidth Payments.
    D. PUCT’s Order Is Consistent with the 2015 FERC Order
    In the ordinary course an Operating Company receiving a Bandwidth
    Payment passes the benefit through to customers, thus ensuring reasonable,
    nondiscriminatory rates. And so it was here. The 2015 FERC Order entitled
    ETI to an additional $10.9 million Bandwidth Payment for the 2006 test year.
    PUCT’s straightforward reading of the order was that the Bandwidth Payment
    was an “incremental” or further payment that had to be passed along to
    customers. We affirm the rightness of this reading today.
    9  PUCT has additional arguments—an argument invoking the presumption against
    preemption and an argument premised on stipulations ETI entered into when settling its
    lawsuits against PUCT in 2009. We do not need to reach these arguments to render our
    decision, and so we do not address them.
    18
    Case: 17-50042     Document: 00514447565    Page: 19   Date Filed: 04/26/2018
    No. 17-50042
    In 2009, FERC recognized that PUCT’s pass-through order properly
    “accept[ed] the Commission’s determination of the amount of receipts to be
    distributed to” Entergy Gulf States under the filed rate. 127 FERC ¶ 61126,
    61548. The same is true of the order we review today. PUCT has accepted
    FERC’s determination of the amount of receipts to be distributed to ETI under
    the filed rate.   It had authority to order that same sum passed along to
    customers pursuant to routine procedure. There is no conflict.
    IV.   CONCLUSION
    The PUCT order is not inconsistent with the FERC Order and is not
    preempted. Rather, it is enforceable. The district court’s contrary judgment is
    REVERSED. All we have said disposes of this case entirely and judgment is
    therefore RENDERED in favor of the defendants.
    19
    Case: 17-50042          Document: 00514447565         Page: 20   Date Filed: 04/26/2018
    No. 17-50042
    PRISCILLA R. OWEN, Circuit Judge dissenting:
    I would affirm the district court’s judgment. I therefore respectfully
    dissent.
    First, the panel’s majority opinion fails to recognize that the payment of
    $120.1 million that Entergy Gulf States, Inc. (Gulf States) received in 2007
    from affiliated companies referable to 2006 wholesale production costs was
    permitted to go into effect by the Federal Energy Regulatory Commission
    (FERC) only conditionally.            When the FERC conditionally approved this
    payment, it ordered a full hearing as to what the FERC tariff, which governed
    the allocation of wholesale costs among the Entergy affiliates, required. 1 The
    conditional authorization of the $120.1 million payment to Gulf States was not
    a final determination that Gulf States, as a utility that served customers in
    more than one state, would ultimately be the entity to whom payments under
    the FERC tariff were owed for 2006, nor was it a final determination as to the
    amounts that should be allocated among the Entergy affiliates under the
    FERC tariff. Therefore, even though the Public Utility Commission of Texas
    (PUCT) required the pass through of payments set forth in FERC’s conditional
    approval in 2007, that pass through was only of wholesale production costs
    approved on a conditional basis, subject to change by the FERC, and therefore
    potentially subject to recoupment.             After protracted proceedings spanning
    years, the FERC held that Gulf States had ceased to exist by the time final
    determinations were made regarding the allocation of wholesale production
    costs among Entergy entities. The FERC concluded that the FERC tariff
    1   Entergy Servs., Inc., 120 F.E.R.C. ¶ 61,094 (2007).
    20
    Case: 17-50042       Document: 00514447565        Page: 21     Date Filed: 04/26/2018
    No. 17-50042
    governed to whom payments among the Entergy affiliates would be allocated
    for 2006 production costs and the final amount of those payments. 2
    Second and relatedly, the outcome of this case should be resolved by at
    least two decisions of the FERC that are final and binding on the parties to
    this proceeding. The first issued on October 2, 2011, 3 and the second on May
    14, 2015. 4 In each, the FERC held that as a jurisdictional matter, when Gulf
    States ceased to exist, two new entities that each served only one jurisdiction
    (that is, only one state) succeeded Gulf States under the FERC tariff. 5 That
    meant that state regulators could not allocate wholesale costs incurred by
    either of these entities between two different jurisdictions (states). Therefore,
    the wholesale costs attributable to each of the new entities, as finally
    determined by FERC in 2015, were recoverable in total, through state rates. 6
    The FERC held that even though Gulf States was still in existence and still
    providing services to two jurisdictions (Texas and Louisiana) throughout 2006
    and 2007, the creation of the two new companies changed the analysis of how
    to allocate wholesale production costs for those years, because the two new
    entities became the parties to the tariff instead of Gulf States, and it was the
    tariff, not “historical facts” that governed to whom broadband remedy
    payments were to be allocated. 7 Under the FERC tariff setting forth the
    bandwidth remedy, the payments were to be allocated once the FERC resolved
    2  Entergy Servs., Inc., 151 F.E.R.C. ¶ 61,112 (2015).
    3  Entergy Servs., Inc., 137 F.E.R.C. ¶ 61,029 (2011).
    4 151 F.E.R.C. ¶ 61,112.
    5 See 137 F.E.R.C. ¶ 61,029 at PP 154-55; 151 F.E.R.C. ¶ 61,112 at P 16.
    6 See Nantahala Power & Lighting Co. v. Thornburg, 
    476 U.S. 953
    , 970 (1986) (“The
    filed rate doctrine ensures that sellers of wholesale power governed by FERC can recover the
    costs incurred by their payment of just and reasonable FERC-set rates. When FERC sets a
    rate between a seller of power and a wholesaler-as-buyer, a State may not exercise its
    undoubted jurisdiction over retail sales to prevent the wholesaler-as-seller from recovering
    the costs of paying the FERC-approved rate.”).
    7 See 137 F.E.R.C. ¶ 61,029 at PP 154-59.
    21
    Case: 17-50042         Document: 00514447565       Page: 22   Date Filed: 04/26/2018
    No. 17-50042
    what the final amounts were to be, which was after December 31, 2007, when
    Gulf States ceased to exist. The FERC held that, with regard to the calendar
    year 2007 production costs, “[t]he split requires that the bandwidth remedy
    payments be allocated among the two successor Operating Companies, not
    between two retail jurisdictions.” 8          The FERC specifically referenced and
    adopted the same reasoning as to the 2006 calendar year. 9 None of the parties
    to this suit challenged the FERC’s orders, and they are final and binding even
    if the FERC ruled incorrectly regarding its jurisdiction to allocate payments to
    the new Entergy entities, rather than Gulf States. The FERC unequivocally
    held that is was allocating wholesale costs among affiliates that each served
    only one state. It was not allocating costs incurred by the now-dissolved Gulf
    States.
    The final FERC order regarding the Entergy entities’ 2006 costs
    establishes the wholesale rates that Entergy Texas may recover under the
    applicable FERC tariff. Entergy Texas is entitled, as a matter of federal law,
    to recover the full amount of the wholesale costs allocated to it. The FERC
    determined that Entergy Texas was entitled to a total bandwidth remedy
    payment for 2006 wholesale costs of $41.3 million, which was the sum of $30.4
    in bandwidth remedy payments from affiliates in 2007, and an additional $10.9
    million that FERC found in 2015 was due from affiliates. As a matter of federal
    law, Texas Entergy was only required to pass through a total of $41.3 million
    in bandwidth remedy payments to Texas ratepayers.                    The PUCT had
    previously required it to pass through $57.733 million in bandwidth remedy
    payments. The difference is $16.033 million—$57.733 million (the amount
    already passed through) minus $41.3 million (the most that the PUCT could
    8   
    Id. at P
    154.
    9   151 F.E.R.C. ¶ 61,112 at P 15-19.
    22
    Case: 17-50042      Document: 00514447565          Page: 23   Date Filed: 04/26/2018
    No. 17-50042
    require Entergy Texas to pass through), which equals a $16.033 million under-
    recovery of wholesale costs by Entergy Texas for 2006. The PUCT cannot
    require Entergy Texas to pass through the $10.9 million payment as a
    bandwidth remedy that is at issue in this appeal.
    I
    Entergy Services, Inc. (Entergy), a utility holding company, made a
    bandwidth remedy filing regarding its affiliates’ wholesale production costs for
    the 2006 calendar year. At time of that filing, Gulf States was still in existence
    and served both Texas and Louisiana. The FERC described this filing as “rates
    pursuant to Service Schedule MSS-3 of the Entergy System Agreement
    (System Agreement) implementing the Commission's decisions in Opinion Nos.
    480 and 480-A.” 10 The FERC conditionally approved these rates in a June 2007
    order. 11 That order reflected that Gulf States would receive a payment of
    $120.1 million from other of the Entergy Operating Companies. However, it
    was clear from that order that these rates could, and in all likelihood would,
    be subject to revision:
    18. Entergy's proposed rates raise issues of material fact that
    cannot be resolved based on the record before us. These issues of
    material fact are more appropriately addressed in the hearing
    procedures and settlement judge procedures ordered below.
    19. Our preliminary analysis indicates that Entergy's proposed
    rate schedule has not been shown to be just and reasonable and
    may be unjust, unreasonable, unduly discriminatory or
    preferential, or otherwise unlawful. Therefore, we will accept
    Entergy's proposed rates for filing, suspend it for a nominal period,
    make it effective June 1, 2007, as requested, subject to refund, and
    set it for hearing and settlement judge procedures. 12
    10 Entergy Servs., Inc., 120 F.E.R.C. ¶ 61,094 (2007).
    11 Id.
    12 
    Id. at P
    P 18-19.
    23
    Case: 17-50042       Document: 00514447565          Page: 24   Date Filed: 04/26/2018
    No. 17-50042
    The proceedings regarding the 2006 calendar year wholesale production costs
    and the bandwidth remedy spanned several years and resulted in numerous
    FERC orders and decisions. 13
    Long before the FERC proceedings reached a final conclusion as to the
    justness and reasonableness of the $120.1 million amount conditionally
    approved in 2007, the PUCT allocated the $120.1 million as between the
    service provided by Gulf States in Texas and the service it provided in
    Louisiana differently than the Louisiana Public Service Commission
    (Louisiana Commission) allocated the same $120.1 million. The PUCT ordered
    that Gulf States pass through $48.977 million to Texas retail customers and
    $8.756 million to Texas wholesale customers, for a total of $57.733 million. The
    Louisiana Commission ordered Gulf States to pass through $80.948 million to
    Louisiana customers. Therefore, Gulf States passed through $18.581 million
    more than the $120.1 million conditional payment that was made by Entergy
    affiliates pursuant to the FERC’s June 26, 2007 order.
    Entergy sought to remedy this by proposing to the FERC that it be
    permitted to amend the Entergy System Agreement. 14 The FERC denied that
    request, concluding that because Gulf States served both Texas and Louisiana,
    “[t]he potential for retail regulators to adopt different retail allocations of
    payments for multi-jurisdictional utilities has always existed,” and “[t]his is a
    risk that Entergy assumed when it established its operating structure.” 15
    On January 1, 2008, Gulf States ceased to exist as an entity. Entergy
    Texas, Inc. and Entergy Gulf States Louisiana, Inc. (Entergy Gulf States
    13 See 151 F.E.R.C. ¶ 61,112 at n. 1-27.
    14 Entergy Servs., Inc., 127 F.E.R.C. ¶ 61,126 (2009).
    15 
    Id. at P
    25.
    24
    Case: 17-50042       Document: 00514447565          Page: 25     Date Filed: 04/26/2018
    No. 17-50042
    Louisiana) were formed. 16 Entergy Texas serves only Texas, and Entergy Gulf
    States Louisiana serves only Louisiana. 17
    Subsequently, Entergy filed with the FERC its proposed allocation of
    wholesale production costs among its affiliates for the calendar year 2007. 18
    Entergy proposed, and the FERC approved, an allocation of production costs
    to Entergy Texas, with no costs allocated to the now-dissolved Gulf States. 19
    But the FERC did so only after a lengthy consideration of jurisdictional issues
    raised by the Louisiana Commission and a thorough discussion of the
    proceedings in which it had denied Entergy’s request to amend the Entergy
    System Agreement that Entergy has proposed as a result of the PUCT’s and
    Louisiana Commission’s differing treatment of the conditional $120.1 million
    bandwidth payment. 20
    The Louisiana Commission and others argued that because Gulf States
    was the entity that operated throughout 2007 and served both Texas and
    Louisiana, broadband remedy payments owed by other Entergy affiliates that
    were referable to 2007 wholesale costs must be allocated to Gulf States, and
    therefore subject to reallocation by the Louisiana Commission (and the PUCT)
    at the intrastate level. 21 In rejecting this argument, the FERC explained that
    it had denied the proposed amendments to the Entergy System Agreement
    because that proceeding involved “an allocation of the bandwidth entitlement
    of a single Operating Company, Entergy Gulf States, between two retail
    16  Entergy Servs., Inc., 137 F.E.R.C. ¶ 61,029 at P 121 (2011).
    17  Id.
    18 
    Id. at P
    P 123-125.
    19 
    Id. at P
    189.
    20 
    Id. at P
    P 126-189.
    21 
    Id. at P
    154 (“[T]he Louisiana Commission and Industrial Consumers argue that
    the [FERC] rejected in earlier proceedings Entergy's argument that the [FERC] has
    jurisdiction to determine the share of the bandwidth receipts allocated to Entergy Gulf States
    and then allocated to its Louisiana and Texas retail customers.”).
    25
    Case: 17-50042        Document: 00514447565    Page: 26   Date Filed: 04/26/2018
    No. 17-50042
    jurisdictions in which it operated.” 22 The FERC reasoned that “Entergy Gulf
    States split into two successor Operating Companies, Entergy Gulf States
    Louisiana and Entergy Texas.” 23 That “split requires that the bandwidth
    remedy payments be allocated among the two successor Operating Companies,
    not between two retail jurisdictions. This issue does not deal with an allocation
    to any retail jurisdiction. Instead, it involves the rough equalization of
    production costs among Entergy Operating Companies.” 24 The FERC made
    clear that because each of the two new Entergy entities served only a single
    retail jurisdiction (a single state), there was no allocation for the state
    regulatory commissions to resolve:
    155. Entergy Gulf States ceased to exist on December 31, 2007 and
    its two successor companies—Entergy Gulf States Louisiana and
    Entergy Texas—are Operating Companies in 2008 as provided in
    Service Schedule MSS-3. It is the [FERC] that has the jurisdiction
    to determine the rough production cost equalization under Service
    Schedule MSS-3 among all of the Operating Companies, including
    Entergy Gulf States Louisiana and Entergy Texas.
    156. The Presiding Judge properly recognized that the [Federal
    Power Act] and [FERC] precedent specific to the Entergy System
    Agreement give the [FERC] jurisdiction over the Entergy System
    Agreement. The Presiding Judge explained, and Entergy and
    Trial Staff emphasized in their Briefs Opposing Exceptions, that
    the [FERC] is “the only entity that can review the justness and
    reasonableness of charges under the Entergy System
    Agreement.” 25
    The FERC expressly recognized that this allocation may have an impact
    on state retail rates but explained that the tariff required allocation based on
    the entity that was subject to the Entergy System Agreement and rate tariffs
    22 
    Id. 23 Id.
          24 Id.
    25 
    Id. at P
    P 155-56.
    26
    Case: 17-50042     Document: 00514447565     Page: 27   Date Filed: 04/26/2018
    No. 17-50042
    at the time that FERC’s allocation was made, not based on the entity that was
    in existence at the time that the costs were actually incurred. To minimize the
    risk of characterizing the FERC’s reasoning inaccurately, I quote the FERC
    order at length:
    157. First, we agree with the Presiding Judge that payments and
    receipts, while based on costs for 2007, occur prospectively in 2008.
    While Entergy Gulf States Louisiana and Entergy Texas were not
    in existence in 2007, the Presiding Judge recognized that it was
    only logical to place them into Entergy Gulf States’ position in
    order to ensure rough production cost equalization among the
    Operating Companies. He emphasized, and we agree, that while
    this allocation may have an impact on retail rates (much like
    virtually every other Commission decision), the determination
    being made is not a retail allocation; it is an allocation, made
    pursuant to the System Agreement, between Operating
    Companies.
    158. Moreover, we agree with Entergy that Industrial Consumers
    misinterpret the bandwidth formula by construing the term
    “Receiving Company” in Service Schedule MSS-3 as being
    qualified by reference to companies that were in existence during
    the historical test year used in the bandwidth calculation.
    Industrial Consumers claims that neither Entergy Texas nor
    Entergy Gulf States Louisiana can logically be classified as a
    “Receiving Company,” which is defined in Service Schedule MSS-3
    as “a Company or Companies with a positive Disparity.”
    Industrial Consumers argues that it is illogical to interpret this
    term to include a company for which no disparity could be
    calculated under the tariff. However, as Entergy points out, the
    term “Company” is defined in the System Agreement to include,
    for calendar year 2008, Entergy Gulf States Louisiana and
    Entergy Texas. As of June 1, 2008, the date of the commencement
    of bandwidth payments under the bandwidth formula, Entergy
    Gulf States Louisiana and Entergy Texas each were a “Company”
    under the Entergy System Agreement. Therefore, they are each a
    “Company” eligible for bandwidth payments as provided for by the
    bandwidth formula contained in Service Schedule MSS-3, and that
    defined term cannot be given a different meaning simply because
    a formula rate is populated with data from a historical test year.
    27
    Case: 17-50042    Document: 00514447565     Page: 28   Date Filed: 04/26/2018
    No. 17-50042
    While this is consistent with Service Schedule MSS-3, it does, as
    Entergy recognizes, create an implementation issue requiring a
    division and assignment of historical costs. However, this fact does
    not mean that the filed rate (the formula) has been changed in any
    manner. Further, the determination of how to populate the
    formula rate under the circumstances presented does not deprive
    this Commission of jurisdiction. To the contrary, the creation of
    Entergy Texas and Entergy Gulf States Louisiana requires, as a
    matter of law, that the Commission decide how to apply a
    wholesale rate schedule to the facts presented.
    159. Industrial Consumers' argument to the contrary is based on
    the erroneous presumption that the tariff is applied on an
    historical basis. It asserts that its position is correct because the
    2008 bandwidth payments are “remedial payments to settle
    production cost disparities from 2007.” However, while the
    Commission has characterized the bandwidth payments as
    “remedial payments,” the Commission has made clear that the
    remedy is prospective in nature:
    The bandwidth remedy does not involve refunds.
    Rather, as Entergy explains, the bandwidth remedy
    payments made under Section 30.09(d) bring the
    Operating Companies within the Opinion No. 480
    bandwidth on a prospective basis.
    160. Accordingly, allowing Entergy Texas and Entergy Gulf States
    Louisiana to take the place of Entergy Gulf States’ position as
    Receiving Companies, while using Entergy Gulf States production
    costs in the calculation of bandwidth payments and receipts is a
    reasonable way to address this unique problem with the
    bandwidth formula.
    161. As the Presiding Judge points out, “in order to roughly
    equalize costs among the Operating Companies in existence in
    2008, Entergy Gulf States’ 2007 production costs must be used in
    the bandwidth formula.” Entergy Gulf States Louisiana and
    Entergy Texas are the successors of Entergy Gulf States. Allowing
    the two companies to step into the shoes of Entergy Gulf States for
    purposes of application of Service Schedule MSS-3 is a reasonable
    way to roughly equalize production costs for the 2007 calendar
    28
    Case: 17-50042       Document: 00514447565          Page: 29    Date Filed: 04/26/2018
    No. 17-50042
    year. We agree with Trial Staff that Industrial Consumers’
    argument, which would prevent Entergy Texas and Entergy Gulf
    States Louisiana from being considered Receiving Companies, is
    at best an overly restrictive interpretation of Service Schedule
    MSS-3’s provisions.     We find that the Presiding Judge’s
    interpretation of Service Schedule MSS-3 is a reasonable
    interpretation under the unique circumstances at hand. 26
    Though these determinations were made with respect to the wholesale
    production costs of Entergy affiliates for the calendar year 2007, and the only
    year at issue in this appeal is 2006, it is important to understand the FERC’s
    rulings because they were cited and applied regarding the 2006 cost
    allocations. 27 The final resolution of the 2007 costs occurred, in FERC Opinion
    No. 514, before the resolution of the 2006 cost allocations.
    Years after the initial filing in 2007 that set forth the proposed
    allocations among Entergy affiliates for 2006, including the $120.1 million
    payment to Gulf States, the FERC required Entergy to file “a comprehensive
    bandwidth recalculation report,” and Entergy complied on September 15,
    2014. 28 The FERC approved the allocations proposed by Entergy, and they
    differed from the conditional allocations that had been allowed to go into effect
    in 2007. 29 Importantly for the purposes of this appeal, there is no allocation,
    at all, for Gulf States in the allocations the FERC finally approved in 2015 for
    the calendar year 2006. 30 Instead, there are only allocations for Entergy Texas
    and Entergy Gulf States Louisiana. 31 As discussed above, the FERC had
    previously approved, with respect to the 2007 calendar year, a methodology to
    26 
    Id. at P
    P 157-61.
    27 Entergy Servs., Inc., 151 F.E.R.C. ¶ 61,112 at P 16-18.
    28 
    Id. at P
    1.
    29 See 
    id. at PP
    15-19.
    30 
    Id. at P
    P 4-6.
    31 
    Id. 29 Case:
    17-50042       Document: 00514447565         Page: 30     Date Filed: 04/26/2018
    No. 17-50042
    apportion production costs between Entergy Texas and Entergy Gulf States
    Louisiana after the “jurisdictional separation of Entergy Gulf States into”
    those two entities. 32
    The FERC’s order reflects that in 2007, Entergy Texas had received
    bandwidth payments in the amount of $30.4 million for calendar year 2006
    costs, and Entergy Gulf States Louisiana had received $89.7 million. 33 The
    total of those amounts is $120.1 million, the amount conditionally approved for
    payment in 2007 to Gulf States. 34 In 2015, the FERC expressly approved
    allocations to Entergy Texas and Entergy Gulf States Louisiana, rather than
    Gulf States, with respect to the payments in 2007, and the FERC approved an
    additional amount found to be due to each of these entities in the 2015
    proceeding.    A group called Texas Consumers objected, arguing that “the
    [FERC] has previously rejected Entergy’s requests to modify the Entergy
    System Agreement so that bandwidth receipts owed to [Gulf States] could be
    allocated between [Gulf States’] retail jurisdictions,” and Texas Consumers
    “contended that that is exactly what Entergy’s bandwidth recalculations
    attempts to accomplish.” 35        The FERC was unmoved.                It recounted its
    determinations in Opinion No. 514, which decided the allocations among
    Entergy affiliates for the calendar year 2007, as discussed above. 36 The FERC
    explained with regard to its order denying Entergy’s request to amend the
    Entergy System Agreement that the circumstances were now different:
    Texas Consumers also contends that its theory is supported by a
    [FERC] order in which the [FERC] determined that it did not have
    jurisdiction to address the allocation of an individual utility’s
    bandwidth receipts among the utility's retail jurisdictions.
    32 Entergy Servs., Inc., 137 F.E.R.C. ¶ 61,029 at P 123 (2011).
    33 151 F.E.R.C. ¶ 61,112 at P6.
    34 Entergy Servs., Inc., 120 F.E.R.C. ¶ 61,094 at P 7 (2007).
    35 151 F.E.R.C. ¶ 61,112 at P 10.
    36 
    Id. at P
    16.
    30
    Case: 17-50042         Document: 00514447565    Page: 31   Date Filed: 04/26/2018
    No. 17-50042
    However, the circumstances that existed in that case—Entergy
    Gulf States was still in existence and the Texas Commission and
    the Louisiana Commission adopted different methods to allocate
    payments between the respective retail jurisdictions—no longer
    exist. Entergy Gulf States has ceased to exist and is no longer able
    to receive bandwidth payments. 37
    In sum, the allocations of costs for the calendar year 2006 that FERC
    had allowed to go into effect in 2007 were conditional because they were subject
    to the outcome of future hearings, and FERC made no findings in 2007 that
    the allocations were just and reasonable or conformed to the applicable tariff.
    Gulf States was no longer in existence when, in 2015, the FERC approved
    allocations among the Entergy affiliates for the 2006 costs. Since no allocation
    could be made under the FERC tariff to Gulf States, FERC allocated the
    bandwidth payments for the 2006 calendar year to Entergy Texas and Entergy
    Gulf States Louisiana, in accordance with the governing tariff.
    Entergy Texas serves only Texas customers, and it is entitled to recover
    the 2006 wholesale productions costs allocated to it by passing those costs
    through in state rates. Entergy Texas has not yet recovered the full amount of
    those costs, because the PUCT required it to pass through $57.733 million that
    the PUCT attributed to bandwidth remedy payments. However, the FERC
    allocated to Entergy Texas only $41.3 million in bandwidth remedy payments,
    which is comprised of the $10.9 million that FERC ordered Entergy affiliates
    to pay to Entergy Texas in 2015 and the initial $30.4 million paid in 2007, that
    was allocated to Entergy Texas rather than Gulf States. The district court did
    not err in concluding that the PUCT’s order requiring Entergy Texas to pass
    through the $10.9 million to Texas ratepayers conflicted with the FERC’s
    orders.
    37   
    Id. at P
    19.
    31
    Case: 17-50042        Document: 00514447565      Page: 32   Date Filed: 04/26/2018
    No. 17-50042
    II
    The PUCT contends that Entergy Texas entered into a rate settlement
    agreement and accepted a higher rate in PUCT Docket No. 35269, in exchange
    for abandoning its then-pending appeals that included an appeal of the
    allocation of the 2007, $120.1 million bandwidth payment to Gulf States. That
    rate settlement does not affect the issues in this appeal.
    Texas rate proceedings involve two rate components, base rates and a
    fixed fuel factor rate. The fuel factor is periodically reconciled such that actual,
    eligible fuel costs are trued-up to fuel factor revenues collected. The fuel-factor
    true-up is then refunded or surcharged to customers. 38 The proceeding in
    Docket No. 35269 involved a base rate increase, which does not include fuel
    costs, and an application to reconcile fuel costs on an historical basis. The
    order in Docket No. 35269 reflects that the 2007 bandwidth payments were
    treated as fuel costs, and an order in Docket No. 37744 addressed the 2007
    bandwidth payments as part of the fuel reconciliation portion of that
    proceeding.       When Entergy Texas abandoned its appeal of the PUCT’s
    allocation of the $120.1 million between Texas and Louisiana, that left the
    allocation order in Docket No. 35269 intact, which meant only that the PUC
    had made an allocation of wholesale costs that were recovered by Gulf States
    on a conditional basis. If the FERC had subsequently ordered, for example,
    that Texas Entergy actually owed bandwidth payments to one or more of its
    affiliates for 2006, then the PUCT would have had to reallocate, and permit
    Entergy Texas to recover from Texas ratepayers the bandwidth payments that
    Entergy Texas made. The rate settlement in Docket No. 35269 did not require
    Entergy Texas to forego any rights it might have if, in the future, the FERC
    38   See TEX. ADMIN. CODE §§ 25.235-25.237.
    32
    Case: 17-50042      Document: 00514447565    Page: 33   Date Filed: 04/26/2018
    No. 17-50042
    approved bandwidth payments that differed from the conditional 2007
    bandwidth payments.
    *****
    Because the district court’s judgment should be affirmed, rather than
    reversed, I dissent.
    33