Atchafalaya Basinkeeper v. U.S. Army Corps ( 2018 )


Menu:
  •         IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    March 15, 2018
    No. 18-30257
    Lyle W. Cayce
    Clerk
    ATCHAFALAYA BASINKEEPER; LOUISIANA CRAWFISH PRODUCERS
    ASSOCIATION-WEST; GULF RESTORATION NETWORK;
    WATERKEEPER ALLIANCE; SIERRA CLUB, and its Delta Chapter,
    Plaintiffs - Appellees
    v.
    UNITED STATES ARMY CORPS OF ENGINEERS,
    Defendant
    BAYOU BRIDGE PIPELINE, L.L.C.,
    Intervenor Defendant - Appellant
    Appeal from the United States District Court
    for the Middle District of Louisiana
    Before DAVIS, CLEMENT, and OWEN, Circuit Judges.
    EDITH BROWN CLEMENT, Circuit Judge:
    Before the court is Defendant-Appellant’s motion for stay of the
    preliminary injunction pending appeal.
    Having reviewed the arguments submitted in the briefing and at oral
    argument, and having considered the factors for a stay, see Planned
    Parenthood of Greater Tex. Surgical Health Servs. v. Abbott, 
    734 F.3d 406
    , 410
    No. 18-30257
    (5th Cir. 2013), we determine that a stay is warranted. Defendant-Appellant
    is likely to succeed on the merits of its claim that the district court abused its
    discretion in granting a preliminary injunction. Rather than granting a
    preliminary injunction, the district court should have allowed the case to
    proceed on the merits and sought additional briefing from the Corps on the
    limited deficiencies noted in its opinion.
    It is ORDERED that the request for a stay of the district court’s
    extraordinary remedy pending appeal be GRANTED.
    It is FURTHER ORDERED that the pending appeal be EXPEDITED to
    the next available oral argument panel.
    No. 18-30287
    OWEN, Circuit Judge, concurring:
    I concur in granting a stay of the preliminary injunction pending appeal.
    However, it is not clear that additional briefing in the district court would
    remedy the United States Army Corps of Engineers’ order granting a
    construction permit to Bayou Bridge Pipeline, L.L.C. (BBP) if the order is
    deficient because of a failure to provide adequate reasons for permitting BBP
    to purchase out-of-kind mitigation bank credits as a means of environmental
    mitigation.   I nevertheless am persuaded that BBP has demonstrated a
    likelihood of success on the merits on appeal and that a stay of the preliminary
    injunction is warranted, provided that this court resolves this appeal on an
    expedited basis so that Atchafalaya Basinkeeper’s challenges to the permit are
    not mooted by the completion of construction or irreparable alterations to the
    Atchafalaya Basin.
    In assessing the likelihood of success on the merits of Atchafalaya
    Basinkeeper’s contentions that the Corps had unlawfully issued the permit,
    the district court implicitly concluded that vacatur of the order granting the
    permit would be the proper remedy were the court to conclude, on the merits,
    that the Corps’ order lacked adequate reasoning. Instead of vacating the
    permit, the district court could seek an additional or supplemental ruling from
    the Corps to address the lack of explanation that is of concern.
    As the D.C. Circuit has recognized, “[a]n inadequately supported [agency
    action] . . . need not necessarily be vacated.” Allied-Signal, Inc. v. U.S. Nuclear
    Regulatory Comm'n, 
    988 F.2d 146
    , 150 (D.C. Cir. 1993). “[I]n deciding whether
    to vacate a flawed agency action, the district court should be guided by two
    principal factors: (1) ‘the seriousness of the . . . deficiencies’ of the action, that
    is, how likely it is ‘the [agency] will be able to justify’ its decision on remand;
    and (2) ‘the disruptive consequences of vacatur.’” Heartland Reg'l Med. Ctr. v.
    No. 18-30287
    Sebelius, 
    566 F.3d 193
    , 197 (D.C. Cir. 2009) (quoting Fox Television Stations,
    Inc. v. FCC, 
    280 F.3d 1027
    , 1048-49 (D.C. Cir. 2002)). The Fifth Circuit has
    similarly held that an agency’s failure to provide reasons supporting a
    determination does not necessarily require vacatur, stating that “[c]ourts have
    explained that ‘remand is generally appropriate when “there is at least a
    serious possibility that the [agency] will be able to substantiate its decision”
    given an opportunity to do so, and when vacating would be “disruptive.” ’ ”
    Cent. & S.W. Servs., Inc. v. EPA, 
    220 F.3d 683
    , 692 (5th Cir. 2000) (quoting
    Radio–Television News Dirs. Ass'n v. FCC, 
    184 F.3d 872
    , 888 (D.C. Cir. 1999)
    (quoting Allied-Signal, 
    Inc., 988 F.2d at 151
    )). The district court could give the
    Corps the opportunity to provide any missing rationale regarding the
    mitigation credits without setting aside the order granting the permit to BBP.
    Given the familiarity that the Corps and other federal agencies have with the
    Atchafalaya Basin and the mitigation credit bank that was created specifically
    for the Basin, and given the Corps’ defense of its order in the district court,
    BBP has shown a likelihood of success on the merits that the Corps will be able
    to substantiate its decision, given the opportunity to do so. BBP has also made
    a showing that halting ongoing construction of the pipeline is disruptive.
    No. 18-30287
    W. EUGENE DAVIS, Senior Circuit Judge, dissenting:
    I respectfully dissent. I agree with the district court that the Section 404
    Environmental Assessment (“EA”) prepared by the U.S. Army Corps of
    Engineers (the “Corps”) did not comply with the National Environmental
    Policy Act, 42 U.S.C. §§ 4321 et seq., because it did not adequately explain how
    the proposed compensatory mitigation plan would reduce the impacts of the
    pipeline construction below a significant level. The district court held that the
    Corps did not explain how the bottomland hardwood credits Bayou Bridge
    Pipeline, LLC, proposed to purchase would mitigate the loss of function and
    services of the bald-cypress/tupelo swamp that Bayou Bridge planned to
    destroy.
    The majority recognizes this deficiency but concludes that the Corps can
    provide a ready explanation for the substitution of out-of-kind bottomland
    hardwoods as compensation for destroying bald-cypress/tupelo swamp in the
    Atchafalaya Basin. This ready explanation was not provided to the district
    court or to us. That should be the end of the inquiry for this motions panel. I
    have found no authority allowing this motions panel to act other than to grant
    or deny the stay; moreover, it is beyond the authority of this panel to suggest
    that the district court require additional action by the Corps.          That is
    particularly true here where Bayou Bridge neither requested this relief in the
    district court nor briefed this alternative to us.
    When out-of-kind mitigation measures are chosen by the Corps, it must,
    at the very least, explain and document its basis for doing so in the
    administrative record. 1 That is, the Corps must explain how the out-of-kind
    mitigation measures replace the “lost functions and services” of the bald-
    1   See 33 C.F.R. § 332.3(e)(2).
    No. 18-30287
    cypress/tupelo swamp. 2 When this is not done, the Administrative Procedure
    Act (the “APA”), 5 U.S.C. § 500 et seq., requires that the Corps’s action
    “shall . . . [be] set aside.” 3 Instead of affirming the district court’s grant of the
    relief the APA requires, the majority apparently hopes that the Corps can
    adequately explain this substitution if the district court remands to the Corps
    for that purpose. 4
    In permit cases where the merits panels of circuit courts have decided
    that further explanation by the Corps may fix the defects in the EA, the court
    has not vacated an injunction, but instead remanded to the district court to
    weigh the equities between remanding to the Corps and enjoining the work
    called for by the permit. 5
    My broader objection, noted above, is that this motions panel is
    preempting the merits panel’s consideration of whether this path should be
    followed.    In addition, even if we expedite the appeal of the preliminary
    injunction, Bayou Bridge’s work in the basin will continue for another four to
    eight weeks and may very well moot out the appeal.
    For these reasons, I would deny the emergency motion for stay.
    2 See 
    id. § 332.3(b)(1).
           3 5 U.S.C. § 706(2)(a). The DC Circuit and others have recognized that remand
    without vacatur is appropriate in certain circumstances. See, e.g., Allied-Signal, Inc. v. U.S.
    Nuclear Regulatory Comm’n, 
    988 F.2d 146
    (D.C. Cir. 1993). However, vacatur is the ordinary
    remedy. See, e.g., Nat’l Min. Ass’n v. U.S. Army Corps of Eng’rs, 
    145 F.3d 1399
    , 1409 (D.C.
    Cir. 1998). In any event, the decision whether to remand with or without vacatur has only
    been undertaken by merits panels with a complete record before them. See, e.g., Heartland
    Reg’l Med. Ctr. v. Sebelius, 
    566 F.3d 193
    , 194–96 (D.C. Cir. 2009).
    4 See 5 U.S.C. § 706(2)(a).
    5 I have found no cases where a motions panel of a circuit court has reached out to
    engage in discussing a remand to the agency.