Purselley v. Lockheed Martin Corp. ( 2009 )


Menu:
  •            IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    April 22, 2009
    No. 08-10856                      Charles R. Fulbruge III
    Summary Calendar                            Clerk
    LEE PURSELLEY
    Plaintiff - Appellant
    v.
    LOCKHEED MARTIN CORPORATION
    Defendant - Appellee
    Appeal from the United States District Court
    for the Northern District of Texas
    No. 4:07-CV-372
    Before DAVIS, GARZA, and PRADO, Circuit Judges.
    PER CURIAM:*
    Lee Purselley appeals the district court’s grant of summary judgment in
    favor of Lockheed Martin Corporation (“Lockheed”). Because no material fact
    issues remain, we find summary judgment proper and affirm.
    Lockheed ’s Weight Incentive Program (“WIP”) offered monetary awards
    to spur employees’ weight-reduction suggestions for the F-35 aircraft under
    development for the government. Purselley states in late 2003 or early 2004 he
    *
    Pursuant to 5TH CIR . R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH CIR .
    R. 47.5.4.
    No. 08-10856
    submitted his idea to eliminate a piece of equipment to reduce weight and cost
    and the company began studying how to implement the idea. Lockheed states
    that the idea immediately became its property because when he was hired,
    Purselley signed an agreement assigning any employee inventions to the
    company.
    In April 2004, Lockheed planned Weight Stand Down Day (“WSDD”), a
    half-day project to focus on F-35 weight-savings ideas, and contemplated
    monetary awards for WSDD ideas implemented into the project. The company
    also considered awards with different scales of payment for two cost-savings
    components based on indirect weight savings—system development and design
    (“SDD”) and unit recurring flyaway (“URF”) components. Ultimately, Lockheed
    opted not to offer cost-savings awards.              It notified participants, including
    Purselley, before WSDD began that cost-savings awards were “off the table.”
    However, Purselley relies on preliminary documents posted before this decision,
    contemplating awards for SDD and URF cost-savings.1
    During WSDD, Purselley resubmitted the earlier-submitted suggestion.
    Lockheed initially rated his WSDD suggestion as “not recommended.” But
    Purselley still argued for a weight-savings award, and a year later he received
    $7500. In this suit, he initially sought hundreds of millions of dollars in a Texas
    state court on breach of contract and quantum meruit claims, arguing he also
    was due an SDD cost-savings award. He now claims Lockheed owes him an
    URF cost-savings award.
    1
    An earlier version of a document posted in contemplation of awards for WSDD
    suggestions twice listed SDD costs, rather than one entry for SDD costs and one entry for URF
    costs. The typographical error was corrected on a later version of the list of potential awards,
    with entries for both SDD and URF cost savings. Both parties address the error in their
    briefs, but the error does not seem to be of consequence given the overall balance of facts
    supporting Lockheed’s position that there was no offer of cost-savings awards. Lockheed
    further argues Purselley could not have expected payment for URF cost savings when URF
    was omitted from the earlier version of the possible awards.
    2
    No. 08-10856
    Lockheed removed the action to federal district court. The district court
    granted Lockheed’s motion for summary judgment. This appeal followed.
    “We review a district court’s grant of summary judgment de novo.
    Summary judgment is appropriate when the record indicates no genuine issue
    of material fact, and that the moving party is entitled to judgment as a matter
    of law.” Cont’l Airlines, Inc. v. Air Line Pilots Ass’n Int’l, 
    555 F.3d 399
    , 405 (5th
    Cir. 2009) (quoting Am. Eagle Airlines, Inc. v. Air Line Pilots Ass’n Int’l, 
    343 F.3d 401
    , 405 (5th Cir. 2003)) (internal quotation marks omitted). Defeating a motion
    for   summary     judgment    requires    more    than   “conclusory    allegations,
    unsubstantiated assertions, or only a scintilla of evidence.” Delta & Pine Land
    Co. v. Nationwide Agribusiness Ins. Co., 
    530 F.3d 395
    , 399 (5th Cir. 2008)
    (internal quotation marks omitted). The parties agree Texas law controls this
    diversity case.
    Purselley first argues there is a fact issue as to whether he gave
    consideration to support a unilateral contract. Specifically, Purselley asserts
    there was no requirement that WSDD suggestions be original and unique and
    that by his performance—expending time and effort to resubmit an idea—he
    accepted Lockheed’s offer to compensate employees for ideas suggested during
    WSDD. Lockheed argues that providing already-disclosed information is past
    consideration and, thus, no consideration.       Granting Lockheed’s motion for
    summary judgment, the district court found “[t]o whatever extent [Purselley]
    claims a breach of contract,” he gave no new consideration to Lockheed.
    Lockheed received nothing new from Purselley upon which it could act.
    In Texas, “[c]onsideration is a present exchange bargained for in return for
    a promise.” Roark v. Stallworth Oil and Gas, Inc., 
    813 S.W.2d 492
    , 496 (Tex.
    1991).   The formation of a unilateral contract in the employment context
    requires that “(1) the performance must be bargained-for so that it is not
    rendered past consideration . . . and (2) acceptance must be by performance”
    3
    No. 08-10856
    (citations omitted). Light v. Centel Cellular Co., 
    883 S.W.2d 642
    , 645 n.6 (Tex.
    1994).     Light dealt with an employee’s covenant not to compete with an
    employer, an issue the Texas Supreme Court has revisited, emphasizing new
    consideration is required to support an employee’s noncompete promise. Alex
    Sheshunoff Mgmt. Servs., L.P. v. Johnson, 
    209 S.W.3d 644
    , 651 (Tex. 2006). The
    court viewed such a covenant as a bilateral contract but agreed with Light’s
    recitation of basic contract law in footnote 6. 
    Id. at 650.
    “‘[P]ast consideration
    is not consideration.” 
    Id. at 659
    (Jefferson, C.J., concurring).
    We agree with the district court.            No fact issue as to consideration
    remains. The evidence showed the company indeed was looking for new ideas,
    not ideas previously submitted. 2 While the company still sought ideas despite
    notifying WSDD participants it was forgoing cost-savings awards, Purselley’s
    resubmission of the earlier suggestion was past consideration; the parties do not
    dispute that the company already owned the idea and had acted upon it when
    Purselley resubmitted it for WSDD. Therefore, the WSDD submission was not
    new consideration and was unable to support any new promise Lockheed made,
    as Purselley claims, to pay cost-savings awards under a unilateral contract.
    Purselley next argues that fact issues exist as to whether Lockheed owes
    him damages in quantum meruit for Lockheed’s unjust enrichment. He asserts
    that a jury should weigh an executive’s e-mail lauding Purselley as the
    originator of the idea and should decide whether Purselley’s WSDD suggestion
    fell within his ordinary job duties. Purselley admits he did not expect extra pay
    the first time he submitted the idea, but he argues the expectation arose because
    2
    Lockheed refers to: (1) an announcement calling for “changes” to reduce weight; (2)
    an e-mail stating the company wished for no stone to be left unturned in seeking weight-
    reduction ideas; (3) Purselley’s own acknowledgment that he was told to “come up with” ideas;
    and (4) instructions for submitting suggestions stating: “1. Come up with an idea. 2.
    Interrogate WIP database to see if idea is already submitted. 3. If idea is not yet submitted,
    fill out WIP form.”
    4
    No. 08-10856
    of the value of his idea to Lockheed and Lockheed’s past awards for suggestions.
    Lockheed argues Purselley is not entitled to damages in quantum meruit
    because they are available only for services rendered under implied contracts.
    The company also contends two express contracts—the inventions agreement
    and at-will employment agreement—covered Purselley’s suggestion, precluding
    quantum meruit. Rejecting Purselley’s claim, the district court found Lockheed
    “did not experience any enrichment by reason of [Purselley’s] WSDD submittal.”
    In Texas, quantum meruit “is founded [on] the principle of unjust
    enrichment.” Bashara v. Baptist Mem’l Hosp. Sys., 
    685 S.W.2d 307
    , 310 (Tex.
    1985). Unjust enrichment is an implied-contract theory stating one should make
    restitution when it would be unjust to retain benefits received. Walker v. Cotter
    Properties, Inc., 
    181 S.W.3d 895
    , 900 (Tex. App.—Dallas 2006, no pet.). Unjust
    enrichment allows recovery “when one person has obtained a benefit by another
    by fraud, duress, or the taking of an undue advantage.” Heldenfels Bros., Inc.
    v. Corpus Christi, 
    832 S.W.2d 39
    , 41 (Tex. 1992). In turn, quantum meruit allows
    for an equitable recovery “based upon the promise implied by law to pay for
    beneficial services rendered and knowingly accepted.” In re Kellogg Brown &
    Root, Inc., 
    166 S.W.3d 732
    , 740 (Tex. 2005) (emphasis added) (internal quotation
    marks omitted). If a valid contract covers the services provided, the party
    generally cannot recover under a quantum meruit theory. 
    Id. Recovery requires
    that: “(1) valuable services and/or materials were
    furnished, (2) to the party sought to be charged, (3) which were accepted by the
    party sought to be charged, and (4) under such circumstances as reasonably
    notified the recipient that the plaintiff, in performing, expected to be paid by the
    recipient.” Heldenfels 
    Bros., 832 S.W.2d at 41
    . The Texas Supreme Court has
    enumerated a few instances where damages in quantum meruit might be
    available for breach of an express contract. Truly v. Austin, 
    744 S.W.2d 934
    ,
    936–37 (Tex. 1988). These exceptions are: (1) where a plaintiff had partially
    5
    No. 08-10856
    performed but the defendant’s breach kept the plaintiff from completing
    performance; (2) when a plaintiff only partially performed a unilateral contract
    that imposed no legal obligations on the plaintiff and, thus, the plaintiff did not
    breach; and (3) when breaching plaintiffs “have been allowed to recover the
    reasonable value of services less any damages suffered by the defendant.” 
    Id. We agree
    with the district court that Lockheed does not owe quantum
    meruit damages to Purselley. Purselley did not furnish Lockheed valuable
    services because his WSDD submission did not enrich Lockheed, which already
    owned the idea and had acted upon it. And because Lockheed did not end up
    offering WSDD cost-savings awards, it could not have had reasonable notice that
    Purselley expected to be paid. Purselley did not argue that Lockheed obtained
    his idea by fraud or duress or by taking undue advantage of him. Lastly, even
    if there was an express contract for WSDD cost-savings awards, none of the
    exceptions allowing recovery apply.
    Finally, Purselley argues, for the first time on appeal, that Lockheed is
    quasi-estopped from denying him a cost-savings payment because employees are
    entitled to rely on Lockheed’s long-standing extra payments for employees’ ideas.
    However, “[a]rguments not raised in the district court are waived.” Jethroe v.
    Omnova Solutions, Inc., 
    412 F.3d 598
    , 601 (5th Cir. 2005); see also Keelan v.
    Majesco Software, Inc., 
    407 F.3d 332
    , 339 (5th Cir. 2005) (stating this Circuit’s
    “well settled” law limiting summary judgment review “to matters presented to
    the district court”). Because Purselley failed to make his quasi-estoppel
    argument adequately to the district court, he waived the issue and we do not
    reach it.
    For the foregoing reasons, we AFFIRM the district court’s order granting
    summary judgment.
    6