Wanda Stephenson v. Archer Western Contractors, et ( 2014 )


Menu:
  •      Case: 13-30327      Document: 00512457649         Page: 1    Date Filed: 12/02/2013
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    United States Court of Appeals
    Fifth Circuit
    No. 13-30327                              FILED
    December 2, 2013
    Summary Calendar
    Lyle W. Cayce
    Clerk
    United States of America, ex rel, WANDA STEPHENSON,
    Plaintiff - Appellant
    v.
    ARCHER WESTERN CONTRACTORS, L.L.C., formerly known as Archer
    Western Contractors, Limited; ALBERICI ENTERPRISES, also known as
    Alberici Constructors, Incorporated; PATCO TRANSPORT,
    INCORPORATED, doing business as Patco Logistics, L.L.C.; C.K.A., L.L.C.;
    R. PEADEN TRUCKING, INCORPORATED; TAMMANY HOLDING
    COMPANY, L.L.C., formerly known as Tammany Holding Corporation;
    WILLOW BEND VENTURES, L.L.C.; BAYOU SAND & GRAVEL, L.L.C.;
    BATOM ENTERPRISES, L.L.C.; BERTUCCI CONTRACTING COMPANY,
    L.L.C.; PEARLINGTON DIRT, L.L.C.; PATCO LOGISTICS, L.L.C.,
    Defendants - Appellees
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    USDC No. 2:21-CV-1043
    Before JOLLY, SMITH, and CLEMENT, Circuit Judges.
    PER CURIAM: *
    * Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH
    CIR. R. 47.5.4.
    Case: 13-30327     Document: 00512457649         Page: 2   Date Filed: 12/02/2013
    13-30327
    Wanda Stephenson appeals the district court’s grant of a motion to
    dismiss for failure to state a claim under Federal Rules of Civil Procedure
    12(b)(6) and 9(b). For the reasons stated below, we AFFIRM.
    FACTS AND PROCEEDINGS
    In   August    2005,    the   levees      surrounding    New    Orleans    failed
    catastrophically,    and    the   city    was    submerged     by    the   floodwaters.
    Subsequently, the United States Army Corps of Engineers (“USACE”)
    orchestrated the construction of a system of levees that was said to provide
    one hundred years of flood protection to the New Orleans area. To rebuild
    and construct these levees, USACE contracted with Archer Western
    Contractors, L.L.C. and Alberici Enterprises (the “prime contractors”). These
    companies contracted with trucking brokers and trucking companies to haul
    clay and other earthen materials to build up the levees, including Patco
    Transport, Inc., R. Peadon Trucking, Inc., Patco Logistics, L.L.C., Bertucci
    Contracting Company, L.L.C., and Batom Enterprises, L.L.C. (the “trucking
    brokers”). These truckers drew clay and sand materials from pits run by
    Tammany Holding Co., L.L.C., Willow Bend Ventures, L.L.C., Pearlington
    Dirt, L.L.C., and Bayou Sand & Gravel, L.L.C.                  (the “pit operators”).
    Collectively, these companies are the Defendants.
    The contract between the USACE and the prime contractors contained
    a provision mandating compliance with all “Federal, state, and municipal
    laws, codes and regulations applicable to the performance of the work.” This
    contract required express certification of compliance with all of the
    specifications, terms, and conditions of the contract in each pay application
    and payment voucher.
    2
    Case: 13-30327       Document: 00512457649          Page: 3    Date Filed: 12/02/2013
    13-30327
    Wanda Stephenson, the owner and manager of a trucking company,
    brought a qui tam suit under the False Claims Act (“FCA”) alleging that
    these companies filed false certifications with the USACE as a pre-requisite
    for payments under their contracts to provide earthen materials to the levee
    projects. Specifically, she alleges that truckers consistently hauled loads in
    excess of the weight limits on highways (80,000 lbs.) and bridges (40,000 lbs.).
    These truckers then made express certifications with USACE that they were
    complying with all provisions in their contract, including the provision that
    they were in compliance with all “Federal, State, and municipal laws, codes
    and regulations applicable to the performance of their work.” She accuses the
    trucking brokers of submitting claims for payment to the prime contractors in
    violation of contracts that required compliance with the weight laws. She
    alleges that the pit operators “were required by law to ensure that trucks
    leaving their pits were not violating the legal weight limits,” and they ignored
    this obligation to let “visibly overweight trucks” travel the highway.
    Stephenson filed her complaint under seal on April 24, 2012.                       The
    United States declined to intervene and Stephenson amended the complaint.
    The Defendants filed motions to dismiss under Rules 12(b)(1), 1 12(b)(6), and
    9(b) of the Federal Rules of Civil Procedure. On March 6, oral argument was
    held on the motions to dismiss and the district court ruled for the Defendants
    on the Rules 12(b)(6) and 9(b) motions. The court stated, “I don’t think the
    plaintiff has successfully alleged that any of the defendants have made false
    certifications of compliance on which payment was conditioned under the
    jurisprudence.” The district court gave Stephenson twenty days to file an
    amended complaint that would pass Rule 9(b) muster. Stephenson declined
    1
    Because the district court dismissed based on Rules 12(b)(6) and 9(b), it did not
    rule on the prime contractors’ Rule 12(b)(1) motion.
    3
    Case: 13-30327      Document: 00512457649   Page: 4   Date Filed: 12/02/2013
    13-30327
    to do so.    Final judgment of dismissal was entered on April 1, 2013.
    Stephenson appeals.
    The prime contractors respond that the government knew that some
    trucks were overweight, but any issues about the trucks’ weights or speeds
    were discussed with USACE during the project and resolved satisfactorily.
    The remedy under the contract was to issue a stop work order, which never
    occurred. The pit operators respond that Stephenson’s argument is not that
    the Defendants provided less or lower quality clay than required, but that the
    “clay was delivered too quickly, i.e. defendants should have utilized more
    trucks to deliver the same amount of clay.”
    STANDARD OF REVIEW
    “We review de novo a district court’s ruling on a Rule 12(b)(6) motion.”
    United States ex. rel. Steury v. Cardinal Health, Inc., 
    625 F.3d 262
    , 266
    (2010). “A dismissal for failure to plead fraud with particularity under Rule
    9(b) is treated as a dismissal for failure to state a claim under Rule 12(b)(6).”
    United States ex. rel. Thompson v. Columbia/HCA Healthcare Corp., 
    125 F.3d 899
    , 901 (1997).
    DISCUSSION
    Stephenson challenges the district court’s dismissal of her claims
    against the defendants for failure to state a claim under the FCA. To find a
    FCA violation, this court looks to see “(1) whether there was a false
    statement or fraudulent course of conduct; (2) made or carried out with the
    requisite scienter; (3) that was material; and (4) that caused the government
    to pay out money or to forfeit moneys due (i.e., that involved a claim).”
    United States ex. rel. Longhi v. Lithium Power Techs., Inc., 
    575 F.3d 458
    , 467
    (5th Cir. 2009) (internal quotation marks omitted).
    4
    Case: 13-30327   Document: 00512457649    Page: 5   Date Filed: 12/02/2013
    13-30327
    “The term ‘material’ means ‘having a natural tendency to influence, or
    be capable of influencing, the payment or receipt of money or property.’”
    
    Steury, 625 F.3d at 267
    . “The FCA is not a general ‘enforcement device’ for
    federal statutes, regulations, and contracts.” 
    Id. at 268.
    The key is whether
    the
    certification is a prerequisite to obtaining a government benefit. Thus,
    where the government has conditioned payment of a claim upon a
    claimant’s certification of compliance with, for example, a statute or
    regulation, a claimant submits a false or fraudulent claim when he or
    she falsely certifies compliance with a statute or regulation.
    
    Thompson, 125 F.3d at 902
    .
    We agree with the district court that the certification in this case was
    not a “prerequisite for payment.” The certification was one of compliance
    with the contract’s specifications, terms, and conditions.         The contract
    contained boilerplate language stating that the company would follow the
    law.    Absent a more specific certification of compliance, for example with
    traffic or roadway regulations, the FCA would here become a general
    enforcement device for traffic infractions.
    Most tellingly, both Stephenson and the Defendants point out that the
    government knew the trucks were overweight: Stephenson tells us this was
    visible, and the Defendants provide emails from the government discussing
    the issue with the contractors. Yet, no stop work order was issued. The clay
    continued to be delivered to the levees. The contractors were paid. How
    could such “fraud” be material to payment if the defrauded party knows
    about it and remains satisfied with the work? It appears beyond doubt that
    USACE was not defrauded and the focus of the contract was on rapidly
    providing earthen material to provide one hundred years of flood protection
    to New Orleans, not on policing roadway weight regulations. Any inaccurate
    certifications were not material to payment.
    5
    Case: 13-30327     Document: 00512457649     Page: 6   Date Filed: 12/02/2013
    13-30327
    In the alternative, Stephenson’s claims would fail under Rule 9(b).
    “Claims brought under the FCA must comply with Rule 9(b). At a minimum,
    Rule 9(b) requires that a plaintiff set forth the who, what, when, where, and
    how of the alleged fraud.” 
    Thompson, 125 F.3d at 903
    (internal citations and
    quotation marks omitted).         “The frequently stated, judicially-created
    standard for a sufficient fraud complaint . . . instructs a plaintiff to plead the
    time, place and contents of the false representation, as well as the identity of
    the person making the misrepresentation and what that person obtained
    thereby.” United States ex rel. Grubbs v. Kanneganti, 
    565 F.3d 180
    , 186 (5th
    Cir. 2009) (internal quotation marks and alteration omitted).
    We agree with the district court that Stephenson’s allegations fail to
    meet the requirements of specificity under Rule 9(b). Even if she were able to
    allege in part the particularity which the Rule requires, she has not alleged
    the “identity of the person making the misrepresentation and what that
    person obtained thereby.” The contractors were not paid more for having
    more clay in individual trucks; they were paid for providing the entirety of
    the clay required for the levee projects. The district court offered Stephenson
    the opportunity to amend her complaint with the specifics that would meet
    Rule 9(b) requirements, and she declined to do so.
    CONCLUSION
    We AFFIRM the district court’s dismissal of Stephenson’s complaint.
    6