Nobles Construction, L.L.C. v. Washington Parish , 544 F. App'x 263 ( 2013 )


Menu:
  •      Case: 12-30675       Document: 00512157649         Page: 1     Date Filed: 02/27/2013
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    February 27, 2013
    No. 12-30675                          Lyle W. Cayce
    Summary Calendar                             Clerk
    NOBLES CONSTRUCTION, L.L.C.,
    Plaintiff–Appellant
    v.
    WASHINGTON PARISH; RICHARD N. THOMAS, JR., Individually and as
    President of Washington Parish; LEO LUCCHESI, Individually and as
    Director of Public Works for Washington Parish; CHARLES E. MIZELL,
    Individually and as Mayor of City of Bogalusa; LANDWORKS,
    INCORPORATED; BOGALUSA CITY,
    Defendants–Appellees
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    USDC No. 2:11-CV-2616
    Before SMITH, PRADO, and HIGGINSON, Circuit Judges.
    PER CURIAM:*
    Plaintiff–Appellant Nobles Construction, Inc. (“Nobles”) appeals the
    dismissal of its due process challenge for failure to state a claim. Because
    *
    Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH CIR.
    R. 47.5.4.
    Case: 12-30675    Document: 00512157649     Page: 2   Date Filed: 02/27/2013
    No. 12-30675
    Louisiana law provides adequate process and because the state officials’ alleged
    actions were not so arbitrary as to shock the conscience, we AFFIRM.
    I. BACKGROUND
    The Choctaw Road Landfill (the “Landfill”) is a Type II solid waste
    disposal facility located in Franklinton, Louisiana. In 1995, Washington Parish
    and the City of Bogalusa entered into a joint venture to acquire, operate, and
    maintain the Landfill. They granted Landworks, Inc. the exclusive right to
    operate the Landfill, and Landworks was to retain this right until its contract
    expired on June 1, 2011. The Parish and the City also established the Choctaw
    Road Landfill Joint Venture Solid Waste Committee (the “Committee”) to
    oversee the Landfill operations and the administration of Landworks’ contract.
    Louis Michael Creel, Landworks’ owner, served on the Committee.
    In March 2011, with Landworks’ contract soon to expire, the Parish and
    the City sent out a Request for Proposals regarding the future operation of the
    Landfill. Five companies responded, and a Review Panel was appointed to
    evaluate the proposals. The Review Panel consisted of four members appointed
    by Richard Thomas, the Parish’s president, and three members appointed by
    Charles Mizell, the City’s mayor.
    Of the five companies, Nobles submitted the lowest bid.         Under its
    proposal, operation of the Landfill would cost $49,860 per month. Landworks’
    bid was the second lowest, with a price of $69,674 per month. The Review Panel,
    however, awarded Landworks a higher evaluation score, which was based on
    ratings the Panel members gave each proposal in eight individual categories.
    The Review Panel also contacted Creel and requested that he lower Landworks’
    bid to $62,500 per month, which Creel agreed to do. Based on this revised
    proposal and the evaluation scores, the Review Panel voted to recommend
    awarding the contract to Landworks.
    2
    Case: 12-30675       Document: 00512157649         Page: 3    Date Filed: 02/27/2013
    No. 12-30675
    The Review Panel’s decision was covered in a May 17 article in the
    Bogalusa Daily News. After seeing the article, Nobles contacted Leo Lucchesi,
    the Parish’s Public Works Director, to discuss Nobles’s low evaluation score as
    well as the Review Panel’s decision to award the contract to Landworks despite
    Nobles’s lower bid. Lucchesi declined to discuss the matter. On May 23, the
    Parish Council introduced an ordinance to accept the recommendation to award
    the contract to Landworks. After a public hearing, the Council voted to approve
    the Review Panel’s recommendation and granted authority to execute the
    contract with Landworks on June 7, 2011.
    Four months later, Nobles sued the Parish, Richard Thomas, Leo Lucchesi,
    the City, Charles Mizell, and Landworks. Nobles argued that Louisiana’s Public
    Bid Law, La. Rev. Stat. Ann. §§ 38:2211–38:2227, governed the proposal process
    and required the Parish and the City to accept the lowest bid. Because they did
    not, Nobles requested a writ of mandamus to either reopen the proposal process
    or award the contract to Nobles. Nobles also sought damages under § 1983,
    alleging that its due process rights had been violated in the bidding process.
    Specifically, Nobles argued that it had obtained a property interest in the
    contract by submitting the lowest bid and that the Parish and the City deprived
    it of that property interest without due process.1
    Defendants moved to dismiss Nobles’s § 1983 claims under Federal Rule
    of Civil Procedure 12(b)(6), and the district court granted the motions. The court
    found that even if the Public Bid Law applied and Nobles had a property interest
    in the contract, the legal process available to Nobles was sufficient.
    Additionally, the court determined that the Parish’s and the City’s alleged
    behavior was not so egregious as to constitute a violation of substantive due
    1
    Louisiana courts have interpreted the Public Bid Law to create “a right in the lowest
    responsible bidder to receive the advertised contract.” Haughton Elevator Div. v. La. Div. of
    Admin., 
    367 So. 2d 1161
    , 1165 (La. 1979).
    3
    Case: 12-30675     Document: 00512157649     Page: 4   Date Filed: 02/27/2013
    No. 12-30675
    process. As a result, the court found that Nobles had failed to state a valid
    § 1983 claim and dismissed the case, declining to exercise supplemental
    jurisdiction over of the remaining state law issues. Nobles timely appealed.
    II. DISCUSSION
    Nobles argues that the district court incorrectly dismissed both its
    procedural due process claim and its substantive due process claim. We address
    each in turn.
    A.    Standard of Review
    We review a district court’s grant of a motion to dismiss de novo,
    “accepting all well-pleaded facts as true and viewing those facts in the light most
    favorable to the plaintiff.” Bustos v. Martini Club, Inc., 
    599 F.3d 458
    , 461 (5th
    Cir. 2010). Those facts, however, must “state a claim that is plausible on its
    face.” Amacker v. Renaissance Asset Mgmt. LLC, 
    657 F.3d 252
    , 254 (5th Cir.
    2011). A complaint is insufficient if it offers only “labels and conclusions,” or a
    “formulaic recitation of the elements of a cause of action.” Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009).
    B.    Procedural Due Process
    We have previously considered a procedural due process challenge
    involving Louisiana’s Public Bid Law. In Marco Outdoor Advertising, Inc. v.
    Regional Transit Authority, the Regional Transit Authority (“RTA”) sought to
    generate revenue by placing advertisements on its vehicles. 
    489 F.3d 669
    , 672
    (5th Cir. 2007).      It requested proposals from advertising contractors and
    reviewed six bids, including one from Marco Outdoor Advertising, Inc. and one
    from Clear Channel. 
    Id.
     Two days before the contract was to be executed, RTA
    informed Marco that Clear Channel would receive the contract. 
    Id.
     Believing
    it had submitted a superior bid, Marco sued RTA under § 1983. Id. Marco
    claimed it was deprived of the property interest it obtained in the contract by
    submitting the best bid and that this deprivation occurred without due process
    4
    Case: 12-30675     Document: 00512157649       Page: 5   Date Filed: 02/27/2013
    No. 12-30675
    of law. Id. The district court disagreed, concluding that Marco had no property
    interest in the contract because Louisiana’s Public Bid Law did not apply. Id.
    We affirmed on different grounds. Rather than analyze the applicability
    of Louisiana’s Public Bid Law, we assumed for purposes of appeal that it applied
    and that Marco had a property interest in the contract. Id. Thus, the only
    question remaining was whether “the state ha[d] failed to provide Marco some
    legal process to challenge RTA’s action.” Id. at 673. No such failure was shown.
    Instead, we held that “the state provides adequate notice when RTA announces
    a contract award, which puts losing bidders on notice that they will be deprived
    of any alleged property interest in the bid if they fail to take further action.” Id.
    at 674. Additionally, “the state guarantees unsuccessful bidders the right to a
    hearing through the Public Bid Law, which authorizes any unsuccessful bidder
    to sue in Louisiana state court to enjoin the public entity from awarding the
    contract.” Id. Thus, “[b]ecause an unsuccessful bidder may seek an immediate
    injunction through a summary proceeding, and because the injunction may
    enjoin the execution of the contract, the injunction prevents the deprivation ‘of
    any significant property interest’ and is therefore an adequate pre-deprivation
    remedy.” Id. at 675. The availability of this summary proceeding, coupled with
    the notice provided by the announcement of the award, “satisfie[d] the elements
    of the due process prong of the Due Process Clause.” Id.
    Faced with this contrary authority, Nobles has failed to show how its case
    is distinguishable. Even if we assume as the court did in Marco that Louisiana’s
    Public Bid Law applies and that Nobles has a property interest in the contract,
    the same procedures that were found to be adequate and available to Marco are
    also adequate and available to Nobles. Nobles attempts to argue that it should
    have received notice of any alleged deficiencies in its proposal and been given an
    opportunity to challenge those deficiencies. But as we noted in Marco, the
    announcement of the contract award itself is sufficient to notify losing bidders
    5
    Case: 12-30675       Document: 00512157649          Page: 6     Date Filed: 02/27/2013
    No. 12-30675
    of the potential deprivation of any alleged property interest. Nobles could have
    immediately challenged the validity of that award in the summary proceeding
    provided for under Louisiana’s Public Bid Law and protected its property
    interest by seeking to enjoin the contract’s execution.2 The availability of these
    options ensured that Nobles was provided with some legal process to challenge
    the Parish’s and the City’s actions.
    Nobles disputes the adequacy of this legal process by arguing that Marco
    was incorrectly decided. Whatever the merits of its challenges to Marco, we lack
    the authority to overrule the decision of another panel. See CRG Partners Grp.,
    LLC v. Neary (In re Pilgrim’s Pride Corp.), 
    690 F.3d 650
    , 663 (5th Cir. 2012) (“[A]
    panel of three judges may not unilaterally overrule or disregard the precedent
    that has been established by our previous decisions.”).3 As a result, Nobles’s
    procedural due process claim must fail.
    C.     Substantive Due Process
    We discussed the nature of a substantive due process claim in Marco as
    well: “Substantive due process bars certain arbitrary, wrongful government
    actions regardless of the fairness of the procedures used to implement them.”
    
    489 F.3d at
    672 n.3 (internal quotation marks omitted).                      Thus, a viable
    2
    The provision of the Public Bid Law authorizing the summary proceeding to enjoin
    the contract award provides as follows:
    [A]ny interested party may bring suit in the district court through summary
    proceeding to enjoin the award of a contract or to seek other appropriate
    injunctive relief to prevent the award of a contract which would be in violation
    of this Part, or through ordinary proceeding to seek appropriate remedy to
    nullify a contract entered into in violation of this Part.
    La. Rev. Stat. Ann. § 38:2220(B).
    3
    Nobles further contends that Bowlby v. City of Aberdeen, 
    681 F.3d 215
     (5th Cir. 2012),
    calls Marco’s holding into question. We reject this argument. Bowlby concluded that the state
    law right to appeal the revocation of a business license after the revocation took place did not
    constitute adequate pre-deprivation process. 
    681 F.3d at 222
    . By contrast, Marco held that
    the Louisiana procedure at issue here gives sufficient pre-deprivation process because it allows
    an unsuccessful bidder to enjoin a public entity from awarding a contract in the first place.
    
    489 F.3d at 674
    .
    6
    Case: 12-30675   Document: 00512157649    Page: 7   Date Filed: 02/27/2013
    No. 12-30675
    substantive due process claim requires a showing that the state official “acted
    with culpability beyond mere negligence.” 
    Id.
     The official’s abuse of power must
    be such that it “shocks the conscience.” McClendon v. City of Columbia, 
    305 F.3d 314
    , 326 (5th Cir. 2002). As a result, “only the most egregious official conduct
    can be said to be arbitrary in the constitutional sense.” Marco, 
    489 F.3d at
    672
    n.3.
    Nobles contends that its allegations would support such a showing.
    Specifically, Nobles alleges that the Parish and the City acted arbitrarily in the
    bidding process (1) by refusing to meet or discuss the bidding process with
    Nobles, (2) by not requiring Landworks to comply with all proposal
    specifications, (3) by overlooking material omissions in Landworks’ proposal, and
    (4) by giving Landworks preferential treatment in allowing it to revise its bid.
    Nobles also alleges improper conduct related to Creel, Landworks’ owner.
    Nobles argues that Creel was wrongly allowed to serve on the Solid Waste
    Committee and that he also took Charles Mizell, the City’s mayor, on a golf trip
    to Alabama during the proposal process. Nobles believes that these allegations
    taken together are sufficient to state a plausible substantive due process claim.
    But much of the behavior Nobles alleges was also present in Marco.
    Though the majority opinion did not discuss the factual background of the
    government’s actions in that case, Judge Wiener’s dissent provided a summary
    of Marco’s allegations. For example, Marco had alleged (1) that it submitted the
    best overall bid while Clear Channel’s was a distant third, (2) that “RTA
    subjectively evaluated the proposals with a previously-undisclosed, arbitrarily
    weighted formula,” (3) that RTA provided Clear Channel with bonus points that
    Clear Channel had not earned and that were not awarded to any other bidders,
    and (4) that RTA allowed Clear Channel, and Clear Channel alone, to revise its
    bid before awarding Clear Channel the contract. Marco, 
    489 F.3d at 677
    (Wiener, J., dissenting). Despite these actions, we held that there was “no merit
    7
    Case: 12-30675     Document: 00512157649      Page: 8    Date Filed: 02/27/2013
    No. 12-30675
    to Marco’s claim of substantive due process” because “RTA’s decision to award
    the Contract to Clear Channel instead of Marco [was] not so arbitrary so as to
    shock the conscience.” 
    Id.
     at 672 n.3 (internal quotation marks omitted).
    The result must be the same for Nobles. Nobles attempts to distinguish
    its allegations from those in Marco by challenging Creel’s influence in the
    decision-making process. But that does little to help Nobles’s claim, as those
    allegations are only tangentially related to the contract award. Nobles argues
    that Creel’s presence on the Solid Waste Committee was improper, but the only
    influence Nobles identifies is that Creel was allowed to assist in setting the
    specifications for the requested proposals—specifications that it does not
    challenge. Additionally, the only potential relevance of Nobles’s allegation
    regarding Creel’s golf trip with Mizell is that Mizell appointed three of the
    members of the Review Panel. These allegations do not elevate Nobles’s claim
    into a category different from the claim rejected in Marco. The underlying basis
    for both is the same: the arbitrary award of a public contract to an inferior
    bidder in contravention of Louisiana law. That basis was insufficient to state a
    valid substantive due process claim in Marco, and the addition of circumstantial
    allegations will not change that result here.
    III. CONCLUSION
    The district court properly relied on Marco in dismissing Nobles’s § 1983
    claim. Nobles does not challenge the district court’s decision to decline to
    exercise jurisdiction over the remaining state law claims, and we find nothing
    to indicate that the district court abused its discretion in declining to do so. See
    Batiste v. Island Records Inc., 
    179 F.3d 217
    , 226 (5th Cir. 1999) (“We review a
    district court’s decision to decline jurisdiction over pendent state-law claims for
    an abuse of discretion.”). The judgment of the district court is AFFIRMED.
    8