Shaw Constructors v. PCS Nitrogen Fertilizer LP , 326 F. App'x 860 ( 2009 )


Menu:
  •            IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    June 17, 2009
    No. 08-30594                    Charles R. Fulbruge III
    Clerk
    SHAW CONSTRUCTORS,
    Plaintiff - Appellee Cross-Appellant
    v.
    PCS NITROGEN FERTILIZER LP,
    Defendant - Appellant Cross-Appellee
    Appeals from the United States District Court
    for the Middle District of Louisiana
    No. 3:99-CV-254
    Before KING, GARWOOD, and DAVIS, Circuit Judges.
    PER CURIAM:*
    In a previous appeal in this case, we held that PCS Nitrogen Fertilizer,
    L.P. was liable to Shaw Constructors under the Louisiana Private Works Act for
    subcontract work performed in connection with a construction project. Shaw
    Constructors v. ICF Kaiser Eng’rs, Inc., 
    395 F.3d 533
    (5th Cir. 2004).                     We
    rendered judgment only as to liability and remanded the case in order for the
    magistrate judge to determine the amount of liability. After a six-day trial, the
    magistrate judge entered a judgment in the amount of $1,455,060.47. PCS
    *
    Pursuant to 5TH CIR . R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH CIR .
    R. 47.5.4.
    Nitrogen Fertilizer appealed the judgment and Shaw Constructors filed a cross-
    appeal asserting that the magistrate judge erred in calculating interest. For the
    reasons stated below, we reverse and remand only on the issue raised in the
    cross-appeal.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    PCS Nitrogen Fertilizer, L.P. (“PCS”) entered into a contract with ICF
    Kaiser Engineers, Inc. (“Kaiser”) for the construction of a nitric acid production
    plant. Kaiser subcontracted the piping installation to Shaw Constructors, Inc.
    (“Shaw”). For reasons which are contested in this appeal, Shaw’s work fell
    significantly behind schedule. This delay resulted in Kaiser and Shaw entering
    into a change order that converted their original lump-sum contract into a cost-
    reimbursable contract. “Change Order No. 1” states, in relevant part:
    As compensation for the remaining Subcontract Work,
    commencing as of the start of business on August 3, 1998 through
    Project completion, the Subcontractor will be reimbursed for
    reasonable and necessary costs . . . .
    Furthermore, a Not-to-Exceed (NTE) total amount of
    $7,677,918.00 . . . has been established for compensation of costs
    incurred during the performance of all of the work associated with
    this Subcontract. It is mutually understood by the parties that the
    NTE amount may have to be adjusted if reasonable and necessary
    costs incurred during the performance of the work exceed the total
    NTE amount. If Contractor observes Subcontractor invoicing for,
    performing, or reporting work which falls outside of “reasonable and
    necessary,” Contractor will endeavor to transmit this information to
    the Subcontractor within 7 days of witnessing the non-conforming
    work so that billing or field work corrections can be made.
    The change order retained the unaltered provisions of the original subcontract
    including the following prohibition against oral modifications: “No amendment,
    variance or change in the provisions of this Subcontract shall be made except in
    writing signed by the authorized representatives of the parties hereto.”
    2
    Thereafter, Kaiser fell behind on its payments to Shaw and eventually
    terminated Shaw from the project prior to completion. Kaiser hired a different
    company to complete Shaw’s scope of work. Shaw then filed a lien against PCS
    and a lawsuit against both PCS and Kaiser seeking to collect its unpaid invoices.
    As a result of this lawsuit, Kaiser and Shaw, but not PCS, entered into a
    Compromise Agreement. In this agreement, Kaiser agreed to make 20 monthly
    payments to Shaw of $291,012, which represented the full amount of Shaw’s
    outstanding invoices plus two extra monthly payments for interest.
    Kaiser filed bankruptcy after making only 13 monthly payments under the
    Compromise Agreement. Rather than pursue its claim in Kaiser’s bankruptcy
    proceeding, Shaw elected to recover the remaining balance of its invoices from
    PCS by enforcing the statutory lien granted to it under the Louisiana Private
    Works Act (“LPWA”). PCS defended by relying on a provision in the original
    subcontract whereby Shaw waived its right to file liens against PCS’s property.
    This dispute was the basis of the first appeal in this case. We concluded that,
    under Louisiana law, Shaw could regard the subcontract as dissolved upon
    Kaiser’s breach and PCS could not prevent Shaw from enforcing its LPWA lien.
    Shaw 
    Constructors, 395 F.3d at 536
    .        We remanded the case solely for
    determination of the amount that PCS owed Shaw under the LPWA. 
    Id. at 555.
          After a six-day bench trial, the magistrate judge concluded that: (1) the
    reasonable and necessary costs of Shaw’s work totaled $11,631,045.20, which
    was the full amount that it had invoiced Kaiser; (2) Shaw and Kaiser mutually
    agreed to exceed the NTE amount stated in the change order; (3) under the
    LPWA, Shaw was entitled to recover from PCS the remaining balance of the
    price of the work performed pursuant to the subcontract and the change order;
    (4) the balance owed for work under the subcontract and change order was
    $5,238,217.90, but PCS received credit for the $3,783,157.43 in payments made
    by Kaiser under the Compromise Agreement; (5) PCS was therefore liable to
    3
    Shaw for $1,455,060.47 plus prejudgment interest on that amount from
    February 23, 1999, the date of judicial demand; and (6) Shaw did not breach its
    duty to mitigate damages by failing to pursue its claim in Kaiser’s bankruptcy
    proceeding. PCS filed a timely appeal of the judgment and Shaw filed a cross-
    appeal regarding the calculation of interest.
    II. DISCUSSION
    This appeal involves both findings of fact, which we review for clear error,
    and conclusions of law, which we review de novo. Triad Elec. & Controls, Inc.
    v. Power Sys. Eng’g, Inc., 
    117 F.3d 180
    , 186 (5th Cir. 1997). “Where there are
    two permissible views of the evidence, the factfinder’s choice between them
    cannot be clearly erroneous.” Anderson v. Bessemer City, 
    470 U.S. 564
    , 574
    (1985).
    PCS raises the following issues regarding the magistrate judge’s findings
    of fact and conclusions of law: (1) whether Kaiser and Shaw mutually agreed to
    exceed the NTE amount; (2) whether all of Shaw’s costs were reasonable and
    necessary; and (3) whether Shaw breached its duty to mitigate by failing to
    pursue its claim in Kaiser’s bankruptcy proceeding. Additionally, both parties
    challenge the magistrate judge’s calculation of interest.
    A.    Did Kaiser and Shaw mutually agree to exceed the NTE amount?
    Although PCS continues to assert that the NTE amount could only have
    been amended through a written agreement pursuant to the prohibition against
    oral modifications in the original subcontract, the magistrate judge correctly
    looked to the conduct of the parties to answer this question because, under
    Louisiana law, “‘[w]ritten contracts for construction may be modified by oral
    contracts and by the conduct of the parties, and this is true even when the
    written contract contains the provision that an owner is liable only if the change
    orders are in writing.’” L&A Contracting Co., Inc. v. Ram Indus. Coatings, Inc.,
    4
    
    762 So. 2d 1223
    , 1232 (La. Ct. App. 2000) (quoting Pelican Elec. Contractors v.
    Neumeyer, 
    419 So. 2d 1
    , 5 (La. Ct. App. 1982)).
    The magistrate judge concluded that Kaiser and Shaw had mutually
    agreed to exceed the NTE amount because: (1) Kaiser never advised Shaw that
    it could not exceed the NTE amount; (2) Kaiser never advised Shaw that it had
    exceeded the NTE amount and should cease performance; (3) Kaiser never
    advised Shaw that any of its work was not reasonable or necessary; (4) Kaiser
    later agreed that Shaw was owed an amount in excess of the NTE amount; and
    (5) Kaiser actually made payments to Shaw in excess of the NTE amount.
    The fourth and fifth facts were derived from the Compromise Agreement
    and the payments made under it.              PCS argues that this reliance on the
    Compromise Agreement violated Rule 408 of the Federal Rules of Evidence.
    Rule 408 provides that the compromise of a claim “is not admissible on behalf of
    any party, when offered to prove [the] . . . amount of a claim that was disputed.”
    It does not, however, “require exclusion if the evidence is offered for purposes not
    prohibited by subdivision (a).”
    PCS’s argument fails because the purpose behind the magistrate judge’s
    use of the Compromise Agreement was not to establish the amount of the claim.1
    Rather, the Compromise Agreement was used to refute PCS’s defense that the
    NTE amount limited its total potential liability to Shaw.2 The NTE amount
    1
    Shaw filed a Motion in Limine for Determination of the Proper Method of Measuring
    Damages, arguing that the amount owed by PCS was Kaiser’s balance due under the
    Compromise Agreement. The magistrate judge ruled that in order to determine the “price”
    of its work under the LPWA, the court would look to the terms of the subcontract between
    Shaw and Kaiser. Since the default judgment entered against Kaiser was not binding on PCS,
    Shaw would have to show that its work was recoverable under the subcontract (i.e., it was
    reasonable and necessary). Thus, the amount of the claim was determined based on the
    reasonable and necessary expenses that Shaw proved at trial.
    2
    PCS argued that the NTE amount was a strict cap such that it had the practical effect
    of converting the contract back into a lump sum contract based on Allan E. Amundson, Inc.
    v. Hoppmeyer, 
    442 So. 2d 1254
    (La. Ct. App. 1983). The fixed-price contract in Amundson
    5
    could be exceeded if it was “mutually understood by the parties that . . .
    reasonable and necessary costs incurred during the performance of the work
    exceed[ed] the total NTE amount.” Therefore, the material fact raised by PCS’s
    defense was whether Kaiser and Shaw’s conduct evidenced their mutual
    understanding that reasonable and necessary costs had exceeded the NTE
    amount. In other words, the magistrate judge used the Compromise Agreement
    as evidence of the fact that the parties had agreed to an upward adjustment of
    the NTE amount, but not as evidence for the specific amount of that upward
    adjustment.
    The other facts relied on by the magistrate judge relate to Kaiser’s failure
    to raise any objection to Shaw exceeding the NTE amount. PCS argues that
    Kaiser’s passivity was insufficient to “waive” the NTE amount and that there
    was no affirmative evidence that Kaiser ever intended to allow Shaw to exceed
    the NTE amount. However, the language of the change order does not require
    such an affirmative waiver from Kaiser. Rather, the change order suggests that
    Kaiser should notify Shaw of any non-conforming work within seven days so that
    it would not be charged for unreasonable or unnecessary work. It was within
    reason for the magistrate judge to infer that Kaiser’s failure to object to any of
    Shaw’s expenses was an implicit acknowledgment that the reasonable and
    necessary costs had exceeded the NTE amount.
    Therefore, we conclude that the magistrate judge’s finding of fact that
    Kaiser and Shaw mutually agreed to exceed the NTE amount was not clearly
    erroneous.
    B.     Were all of Shaw’s costs reasonable and necessary?
    stated that if the cost-plus amount was less than the fixed price, then the final price would be
    the cost-plus amount. 
    Id. at 1255.
    But, if the cost-plus amount exceeded the fixed price, then
    the final price would be the fixed price. 
    Id. That is
    not the case here where the change order
    does not contemplate Shaw bearing the risk of excess costs. If reasonable and necessary costs
    exceeded the NTE amount, Shaw would be paid all of its costs.
    6
    The parties presented competing versions of what caused Shaw’s portion
    of the project to run over its original deadline and budget. PCS contended that
    the delays were caused by Shaw’s inefficiency and poor workmanship. Shaw
    contended that the delays were caused by Kaiser’s voluminous revisions to the
    project’s engineering plans. Both parties put on evidence and called witnesses
    in support of their argument. The magistrate judge found Shaw’s version more
    credible and explained in detail why Kaiser’s alterations were the cause of
    Shaw’s delay.3
    PCS’s argument that this finding of fact was erroneous relies heavily on
    its expert witness, William Kelly, who testified that Kaiser’s alterations made
    after the date of the change order were minor and would have only cost between
    $184,000 and $336,000 to complete as a stand-alone project. The magistrate
    judge, however, discredited this testimony because it was “not supported by the
    undisputed facts that existed during and in the months immediately following
    Shaw’s work at the PCS site.” In other words, this estimate was based on usual
    and ordinary conditions, rather than the actual circumstances of Kaiser’s
    previous engineering errors.          We cannot say that the magistrate judge’s
    discrediting of this testimony was clearly erroneous, particularly in light of the
    testimony presented describing Kaiser’s engineering errors. See F ED. R. C IV. P.
    52(a)(6) (“[T]he reviewing court must give due regard to the trial court’s
    opportunity to judge the witnesses’ credibility.”).
    PCS also claims that the magistrate judge erred by placing the initial
    burden on it to establish that costs were unreasonable rather than on Shaw to
    3
    The magistrate judge concluded that “[e]ven after Change Order No. 1 . . . significant
    changes and difficulty with the engineering design continued. Kaiser’s defective engineering
    and engineering errors had a substantial impact on the completion and the cost of the project.
    The time and cost to complete the project greatly increased.” The magistrate judge’s final
    conclusion was that “a preponderance of the credible evidence established that the root cause
    of the delay and cost overruns, including the substantial increase in the time and costs of
    Shaw’s subcontract work, was Kaiser’s late, deficient and error-filled engineering design.”
    7
    prove that they were reasonable. This is not an accurate description of the
    record. After Shaw carried its initial burden of proving that its costs were
    reasonable and necessary, PCS countered with evidence that the costs were
    unreasonable. The judge was persuaded by Shaw’s evidence and disbelieved
    PCS.4
    Therefore, we conclude that the magistrate judge’s finding of fact that all
    of Shaw’s costs were reasonable and necessary is not clearly erroneous.
    C.      Did Shaw breach its duty to mitigate by failing to pursue its claim in
    Kaiser’s bankruptcy proceeding?
    PCS provides no direct authority holding that a party must pursue a claim
    in bankruptcy before seeking recovery from a solvent party that is liable on the
    same debt.5 It relies instead on the general principle of mitigation. See L A. C IV.
    C ODE A NN. art. 2002 (“An obligee must make reasonable efforts to mitigate the
    damage caused by the obligor’s failure to perform.”). Based on this, PCS argues
    that Shaw had a duty to file a proof of claim in Kaiser’s bankruptcy proceeding
    before seeking to recover from it under the LPWA.6
    4
    PCS notes that the magistrate judge concluded that “there is no contemporaneous
    evidence that Shaw was ever back charged for any delay or defective work, that any analysis
    or report was ever done during or after the project which showed that the delay or costs
    overruns on the job were caused by Shaw, or that any of Shaw’s invoices included in the total
    agreed to by Kaiser were not approved or were rejected because they were unreasonable,
    unnecessary or excessive.” This is not the magistrate judge placing the burden on PCS. It is
    an explanation of why he discredited PCS’s explanation of the delays. This quotation followed
    the magistrate judge’s review of the evidence supporting Shaw’s theory of causation.
    5
    PCS cites Gifford Hill & Company, Inc. v. Harper, 
    262 So. 2d 842
    (La. Ct. App. 1972)
    for the proposition that the owner should receive an offset for any recovery the subcontractor
    receives from the contractor’s bankruptcy estate. However, Gifford does not state that a
    subcontractor is required to participate in the contractor’s bankruptcy. Rather, it holds that
    if the subcontractor receives a distribution from the contractor’s estate, then that amount is
    deducted from the claim against the owner.
    6
    We note that a creditor is not obligated or required to file a proof of claim. See
    Simmons v. Savell (In re Simmons), 
    765 F.2d 547
    , 551 (5th Cir. 1985). Therefore, failing to
    file a proof of claim alone is unlikely to breach the duty to mitigate.
    8
    The magistrate judge determined that there was no duty to mitigate under
    the LPWA based on Jefferson Door Company, Inc. v. Forman Construction, Inc.,
    
    836 So. 2d 552
    (La. Ct. App. 2002). Jefferson Door involved a similar dispute
    between an owner, a bankrupt contractor, and—in that case—a material
    supplier rather than a subcontractor. 
    Id. at 553.
    Rather than pursue the
    bankrupt contractor, the supplier sought to enforce its materialman’s lien, which
    was also derived from the LPWA, against the owner. 
    Id. The owner
    argued that
    the supplier owed it a duty to determine that the contractor was not credit-
    worthy and to not supply it materials on credit. 
    Id. The court
    rejected such a
    duty. 
    Id. at 554–55.
    However, that preemptive duty is not the same one that
    PCS claims in this case. The duty here is an after-the-fact duty to mitigate by
    first pursuing the bankrupt contractor for payment before pursuing the solvent
    owner.
    Assuming arguendo that the general rules of mitigation apply to claims
    under the LPWA, Shaw’s conduct would not have breached that duty.
    [C]ourts generally do not determine damages based upon the
    making of these [mitigation] expenditures unless (1) they are small
    in comparison to the possible losses, and (2) it is virtually certain
    that the risks incurred will avoid at least a part of the loss.
    Damages will not be decreased through showing that a substantial
    expenditure would have minimized the total loss or that the
    suggested expenditure may or may not have decreased damages.
    Unverzagt v. Young Builders, Inc., 
    215 So. 2d 823
    , 825–26 (La. 1968). Pursuing
    its claim in Kaiser’s bankruptcy would have required Shaw to expend monies on
    legal fees and costs without a definite, certain amount to be gained. Shaw
    asserts that it made the calculated business decision, based on the advice of its
    counsel, that filing a proof of claim would increase the likelihood that it would
    be sued by the Kaiser estate for recovery of the final payment made under the
    9
    Compromise Agreement as a preferential transfer, thereby potentially resulting
    in a net loss.
    Therefore, we conclude that the magistrate judge did not err in concluding
    that Shaw did not breach its duty to mitigate damages. 7
    D.     Issues related to the calculation of interest
    Both parties raise issues regarding the magistrate judge’s calculation of
    interest.   PCS argues that interest should have started on the date of the
    judgment rather than the date of the judicial demand. See Lone Star Indus. v.
    Am. Chem., Inc., 
    461 So. 2d 1063
    , 1069 (La. Ct. App. 1984) (“Interest on the
    disputed, or unliquidated, portion of the contract price is due from the time the
    amount became ascertainable, that is from the date of judgment.”). Shaw’s
    cross-appeal argues that the magistrate judge miscalculated interest by
    deducting all of the Compromise Agreement payments from principal as a lump
    sum.
    1.     On what date should interest begin to accrue?
    The LPWA provides for interest but does not specify the date from which
    interest should be calculated. The magistrate judge followed Louisiana Civil
    Code Article 2000, which states in relevant part:             “When the object of the
    performance is a sum of money, damages for delay in performance are measured
    by the interest on that sum from the time it is due, at the rate agreed by the
    parties or, in the absence of agreement, at the rate of legal interest as fixed by
    7
    PCS’s argument that the magistrate judge erred in excluding the testimony of Kaiser’s
    CFO on Shaw’s theoretical distribution from Kaiser’s bankruptcy as expert testimony is moot
    because there was no breach of the duty to mitigate.
    10
    Article 2924.” 8 The issue, therefore, was on which date did PCS’s liability under
    the LPWA become due.
    Citing Alexander v. Burroughs Corp., 
    359 So. 2d 607
    (La. 1978), the
    magistrate judge concluded that interest began to run on the date of judicial
    demand. In Alexander, the state appellate court awarded the plaintiffs interest
    from the date of the trial court judgment. 
    Id. at 609.
    The Louisiana Supreme
    Court reversed, concluding that contractual damages are due from the moment
    of default and that a party may be in default “‘either by the commencement of
    a suit [or] by a demand in writing.’” 
    Id. at 613
    (quoting L A. C IV. C ODE A NN. art.
    1911). It found that “plaintiffs’ claim was ascertainable on the date of formal
    demand for ‘cancellation’ of the purchase . . . and hence interest should run from
    that date . . . .” 
    Id. at 613
    –14 (emphasis added).
    Lone Star Industries, the case relied on by PCS, concluded that the
    “disputed, or unliquidated, portion of a contract price is not due until the amount
    becomes ascertainable, that is from the date of the 
    judgment.” 461 So. 2d at 1069
    (citing Roques v. Alfonso, 
    399 So. 2d 1294
    (La. Ct. App. 1981)). Roques cites
    the same language in Alexander which was cited by the magistrate judge.
    The Louisiana Supreme Court has since rejected the implication in
    Alexander that interest runs from the date that a debt is ascertainable. See
    Trans-Global Alloy, Ltd. v. First Nat’l Bank of Jefferson Parish, 
    583 So. 2d 443
    ,
    457 (La. 1991) (“While we agree that the damages in this case were not
    ascertainable until reduced to judgment, we nevertheless find that interest
    should run from the date of judicial demand. That finding is consistent with
    longstanding Louisiana jurisprudence.”). The court determined that the rule
    8
    The legal interest rate is applicable in this case because the judgment is based on the
    LPWA and not the Compromise Agreement. See Long Leaf Lumber, Inc. v. Svolos, 
    258 So. 2d 121
    , 124 (La. Ct. App. 1972) (holding that the contractual interest rate was not binding when
    the owner was not a party to the agreement between the contractor and the subcontractor
    containing the interest rate and instead applying the legal rate).
    11
    that requires damages to be ascertainable is derived from the common law view
    of interest as punitive in nature.
    According to that view, when damages are reasonably ascertainable,
    the defendant can determine what his liability might be, and stop
    the accrual of interest by paying the claim; when the damages are
    uncertain, however, the defendant cannot determine the extent of
    his liability prior to trial, and it would be unjust to penalize him for
    failure to pay the damages before judgment.
    
    Id. Conversely, under
    civil law and the modern understanding of interest, the
    purpose of interest is to account for the lost time-value of money. 
    Id. at 458.
    Accordingly, the court awarded interest from the date of the judicial demand, not
    the date of judgment. 
    Id. at 459.
          Therefore, we conclude that the magistrate judge did not err in concluding
    that interest should run from the date of judicial demand rather than the date
    of the judgment.
    2.    How should the Compromise Agreement payments be imputed?
    The magistrate judge refused Shaw’s request to calculate interest as it
    actually accrued because “Shaw failed to establish that the unpaid principal
    amount of the price of its work includes this accrued interest.” However, Shaw
    was not required to prove that it was entitled to accrued interest under the
    LPWA because Louisiana law provides that “[a]n obligor of a debt that bears
    interest may not, without the obligee’s consent, impute a payment to principal
    when interest is due.    A payment made on principal and interest must be
    imputed first to interest.” L A. C IV. C ODE A NN. art. 1866; see also Ridenour v.
    Wausau Ins. Co., 
    627 So. 2d 141
    , 142–43 (La. 1993) (applying Article 1866
    because a payment made after the date of judicial demand must be applied to
    interest before principal). Thus, the LPWA provides for interest and other
    12
    Louisiana law provides that interest should be calculated as it accrued.9
    Therefore, we remand for entry of a judgment correctly calculating interest by
    applying the Compromise Agreement payments first to accrued interest and
    then to principal.
    III. CONCLUSION
    For the reasons stated above, the judgment of the district court is
    AFFIRMED except as to the award of interest, as to which the judgment is
    REVERSED. The case is REMANDED solely for the entry of a judgment with
    interest calculated as herein provided. PCS shall bear the costs of this appeal.
    9
    PCS argues that it should not be liable for interest while Kaiser was making
    payments under the Compromise Agreement because “extinguishment of the primary
    contractual obligation extinguishes the statutory liability.” LA . REV . STAT . ANN . § 9:4802. The
    flaw in this argument is that the Compromise Agreement never extinguished the primary
    contractual obligation, only suspended it. The debt would not be extinguished until the final
    payment was made, an event which never occurred.
    13