Century Marine Inc v. United States ( 1998 )


Menu:
  •                      UNITED STATES COURT OF APPEALS
    For the Fifth Circuit
    No. 97-20281
    CENTURY MARINE INCORPORATED,
    Plaintiff-Appellant;
    VERSUS
    UNITED STATES OF AMERICA,
    Defendant-Appellee.
    Appeal from the United States District Court
    For the Southern District of Texas
    August 27, 1998
    Before BARKSDALE, BENAVIDES and DENNIS, Circuit Judges.
    DENNIS, Circuit Judge:
    Appellant   Century    Marine,      Inc.     (“Century”),      appeals the
    district   court’s     dismissal    of      its    claims     for   additional
    compensation under a fixed-price vessel repair contract with the
    Maritime   Administration    of    the    United     States    Department   of
    Transportation (“MARAD”). MARAD terminated the contract because of
    Century’s default in failing to complete the work within the time
    specified by the contract.     Century filed suit against the United
    States seeking to have the termination for default converted to a
    termination for the Government’s convenience; and for payments in
    addition to the amount MARAD had paid Century under the terminated
    contract.    After   a   bench    trial,      the   district     court   rejected
    Century’s demands and dismissed its suit with prejudice.                       We
    affirm.     On appeal Century does not contest the trial court’s
    determination   that     its    contract      was   properly     terminated   for
    default.    Despite its default, Century argues that it is entitled
    to recover an amount equal to the unpaid balance of the full fixed
    price of the contract less the cost of completion of the unfinished
    work under the contract.         Century’s argument is contrary to well
    established law and federal regulations.              Under the Government’s
    termination of a fixed-price contract because of the contractor’s
    default, the    Government       is   not   liable   to    the   contractor   for
    unperformed or undelivered work.            Anticipated but unearned profits
    are   not   recoverable    by     the   contractor        when   the   Government
    terminates the contract for the contractor’s default or for the
    convenience of the Government.              Century’s additional contention
    that it should be compensated for extra work is also without merit.
    There is warrant in the record and an applicable basis in law for
    the district court’s rejection of this claim after a trial on the
    merits.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    In September 1992, Century and MARAD entered into a fixed-
    price contract for the repair and renovation of cargo and ballast
    tanks of the S.S. MOUNT WASHINGTON, a public vessel of the United
    States.     Thereafter, MARAD issued three contract modifications
    (“Mods”) that increased the contract value by $1,050,000.000, for
    a total contract amount of $8,521,910.000.                   When Century fell
    2
    behind schedule on the original completion date of May 3, 1993,
    MARAD issued three additional Mods that extended the completion
    date until September 15, 1993.       Despite these extensions, Century
    continued to fall behind its work schedule. When it became evident
    that Century could not complete the contract timely, by letter
    dated September 8, 1993, MARAD terminated Century for default.1           At
    the time of termination, MARAD had made progress payments to
    Century of $5,903,135.50.      On September 22, 1993, the Government
    issued Modification     No.   0009   (“Mod   9")   to   the   contract   that
    adjusted the contract price for the value of the unfinished work,
    and calculated the final progress payment to Century based on its
    completed work.     MARAD eventually retained another contractor to
    finish Century’s work.2
    Mod 9, admitted as a Government exhibit at trial, sets forth
    the percentage of completion of each work item, and adjusts the
    total contract price by deducting the contract value of Century’s
    1
    Pursuant to the Federal Acquisition Regulations, the
    Government may, by written notice of default to the contractor,
    terminate the contract in whole or in part if the contractor fails
    to perform the services within the time specified in the contract
    or any extension.     48 C.F.R. § 52.249.8(a)(1)(i).      “Federal
    regulations which are based upon a grant of authority ‘have the
    force and effect of law, and, if they are applicable, they must be
    deemed terms of the contract even if not specifically set out
    therein, knowledge of which is charged to the contractor.’”
    General Eng’g & Mach. Works v. O’Keefe, 
    991 F.2d 775
    , 780 (Fed.
    Cir. 1993).
    2
    Under the Federal Acquisition Regulations, when the services
    to be provided by the terminated contractor are still required
    after default, the contracting officer shall repurchase the same
    services against the contractor’s account as soon as practicable,
    48 C.F.R. § 49.402-6(a), and the contractor is liable to the
    Government for any excess costs incurred in acquiring services
    similar to those terminated for default. 48 C.F.R. § 49.402-2(e).
    3
    uncompleted work, estimated at $1,260,861.00.                 In Mod 9, MARAD
    based the percentage of completion in part on Century’s own percent
    completion figure provided in its last progress payment request
    submitted to MARAD one week prior to termination, with this figure
    adjusted for work accomplished by Century during the final week of
    the terminated contract. The Government’s estimate in Mod 9 of the
    contract value of Century’s uncompleted work also was based on a
    thorough inspection and videotaping of each item of unfinished work
    by    Richard    Volkmann,   the     contracting       officer’s         technical
    representative, who testified at trial.
    Based on the Government’s calculations in Mod 9, MARAD made a
    final payment to Century of $409,023.56, representing compensation
    for all work performed after the latest progress payment but before
    Century was terminated for default.            According to the contracting
    officer’s decision denying Century’s administrative claims for
    additional compensation, this final payment to Century represented:
    (1) payment for the progress made by Century between the time of
    its   last    progress   payment    and      termination     of    the   contract
    ($51,532.00); (2) payment of the balance of retainage owed to
    Century      after   deducting     the       excess   cost    of    procurement
    ($285,539.06)3; and (3) payment of funds withheld at the direction
    of the Government‘s legal department until a separate claim on
    another contract was settled ($71,952.50).
    3
    Under the Federal Acquisition Regulations, “the contracting
    officer shall use all retained percentages of progress payments
    previously made to the contractor and any progress payments due for
    work completed before the termination to liquidate the contractor’s
    liability to the Government.” 48 C.F.R. § 49.406.
    4
    In July 1994, Century submitted a “Request For Equitable
    Adjustment and For Conversion of a Termination For Default to a
    Termination For Convenience.”                Century’s Request For Equitable
    Adjustment      presented     an     administrative     claim    for    additional
    payments of almost $1.3 million under the contract, based on
    Century’s allegations that MARAD had underestimated the percentage
    of completion of finished work items in Mod 9, and that MARAD was
    not entitled to retain excess costs of reprocurement from the
    retainage withheld from the final payment to Century because
    Century was wrongfully terminated.              Century also asserted a claim
    for $21,254 in extra work performed pursuant to Century’s Request
    For Delivery Orders (RDOs).               Finally, Century requested that its
    termination      for   default       be    converted   to   a   termination   for
    convenience.
    In December 1994, the Government’s contracting officer issued
    a final administrative decision on Century’s claims, denying any
    further payments to Century.              This 48-page decision, with attached
    supporting exhibits, rebuts in detail each allegation in Century’s
    Request   For     Equitable        Adjustment,    concluding     that   Century’s
    “termination for default is valid,” and that Century “is not
    entitled to a further equitable adjustment.”
    In September 1994, pursuant to the Contract Disputes Act, 41
    U.S.C. § 603, and the Suits in Admiralty Act, 46 U.S.C. § 741 et
    seq., Century sued the United States in the Court of Federal
    Claims, which transferred the case to the Southern District of
    5
    Texas.4   The United States elected not to file a counterclaim
    against Century for liquidated damages, which are recoverable
    against a contractor terminated for default.             See 48 C.F.R. §§
    49.402-6(c), 49.402-7, 49.402-2(e). Century’s claims were tried to
    a judge in December 1996.
    In   the    district   court,    Century      presented   no   evidence
    supporting the claim in its administrative level Request For
    Equitable Adjustment that it was entitled to recover the excess
    costs of reprocurement that the Government had deducted from
    Century’s retainage.        Exhibit K of the Contracting Officer’s
    decision, which was the only evidence of the Government’s excess
    reprocurement    costs   and   the   amount   of   retainage   withheld   at
    termination, was withdrawn at trial after Century objected to its
    admissibility.
    On January 3, 1997, the district court issued findings of fact
    and conclusions of law rejecting Century’s claims, finding that the
    United States’ termination of Century for default was justified by
    Century’s breach of the contract, and that Century had no valid
    claim for an equitable adjustment to the contract.         Also on January
    3, 1997, the district court rendered a final judgment dismissing
    Century’s claims against the United States with prejudice.
    4
    Under § 603 of the Contract Disputes Act, subject matter
    jurisdiction in appeals of administrative decisions involving
    federal maritime contracts vests in the federal district courts,
    rather than in the Court of Claims (now the Court of Federal
    Claims) or the Court of Appeals for the Federal Circuit. Bethlehem
    Steel Corp. v. Avondale Shipyards, Inc., 
    951 F.2d 92
    , 93, 94 (5th
    Cir. 1992). Government maritime contracts are otherwise governed
    by the Contract Disputes Act. 
    Id. at 94.
    6
    On January 10, 1997 Century filed a Motion to Amend or Make
    Additional Findings of Fact, asserting that Century had made a
    prima facie case on two claims that had not been rebutted by the
    United States: (1) a claim for extra work performed on seven RDOs
    in the amount of $20,583; and (2) a claim for the “contract
    balance”   due    of    $1,293,218.54           resulting   from   the   following
    computation:
    Modified Contract Amount                    $8,521,910.00
    Less-Payments and Deducts                   $6,492,159.46
    Less-Work not performed                     $ 714,187.00
    Less-Tow credit and Item 058                $   22,345.00
    Contract Balance Due                        $1,293,218.54
    On March 4, 1997 the district court entered an order denying
    Century’s Motion to Amend or Make Additional Findings of Fact.
    Century appealed.
    II.    STANDARD OF REVIEW
    The district court’s findings of fact must be reviewed under
    the “clearly erroneous” standard of Fed R. Civ. P. 52(a).                       A
    finding    of    fact   is     said    to       be   “clearly   erroneous”   when,
    notwithstanding there is evidence to support it, the reviewing
    court upon examination of the entire evidence is left with the
    definite and firm conviction that a mistake has been committed.
    Justiss Oil Co. v. Kerr-McGee Refining Corp., 
    75 F.3d 1057
    , 1062
    (5th Cir. 1996) (citing United States v. United States Gypsum Co.,
    
    333 U.S. 364
    , 395 (1948)).            With respect to the legal conclusions
    reached by the trial court on the basis of the facts so found, this
    court will conduct a de novo review.                 Reich v. Lancaster, 
    55 F.3d 7
    1034, 1045 (5th Cir. 1995).
    III. DISCUSSION
    On appeal, Century does not contest the district court’s
    determination that MARAD properly terminated the contract for
    Century’s default.       Nor does Century reurge its administrative
    level   claim   that    MARAD    had   withheld    an   excessive   amount   of
    retainage from the final payment to Century.             Century argues only
    that the district court’s judgment denying its claims for the
    “contract balance” and extra work was clearly erroneous and must be
    reversed because: (1) Century made a prima facie case at trial for
    its contract balance and extra work claims; (2) MARAD failed to
    rebut Century’s proof on these claims; (3) the district court made
    no express findings on each of these claims; and (4) no such
    findings can be implied because an implied finding is not supported
    by the evidence.
    A.    Century’s “Contract Balance” Claim
    Century contends that it made out a prima facie case for
    recovery   of   a    “contract   balance”     of   either   $1,293,218.54    or
    $768,889.54.    It is undisputed that the total amount of the fixed-
    price contract, including all modifications, was $8,521,910.00, and
    that MARAD had paid Century $6,492,159.46 for work completed prior
    to Century’s termination for default, leaving an unpaid balance of
    $2,029,750.54 under the contract at that time. MARAD and Century
    presented conflicting technical expert evidence as to the estimated
    cost of completing the contract: Century’s estimate was $736,532.00
    and MARAD’s was $1,260,861.00.              Consequently, Century asserts,
    8
    after subtracting the estimated cost of completing the work under
    the contract from the unpaid balance, Century is entitled to the
    difference, viz., either $1,293,218.54 or $768,889.54, depending on
    whether the Century or the MARAD estimate is used.
    Century’s argument lacks a sound basis in law.               Termination
    for    default   is    generally   the    exercise      of    the   Government’s
    contractual right to completely or partially terminate a contract
    because of the contractor’s actual or anticipated failure to
    perform its contractual obligations.            48 C.F.R. § 49.401(a).       The
    Government has the right to terminate a fixed-price contract for
    default if the contractor fails to deliver the supplies or to
    perform the services within the time specified in the contract. 48
    C.F.R. § 49.402-1. Under a termination for default, the Government
    is not liable for the contractor’s costs on undelivered work. 48
    C.F.R. § 49.402-2(a).       In contrast, under a fixed-price contract
    terminated for the convenience of the Government, a settlement
    should compensate the contractor fairly for the work actually done
    and for the preparations made for the terminated portions of the
    contract, including a reasonable allowance for profit applicable to
    that   work   and     preparations.       48   C.F.R.    §§    49.201,   49.202.
    Anticipatory profits and consequential damages shall not be allowed
    under either a termination for convenience or a termination for
    default of a fixed-price contract.             48 C.F.R. §§ 49.201, 49.202,
    49.402-2;     See Mega Constr. Co. v. United States, 
    29 Fed. Cl. 396
    ,
    475 (1993); G.L. Christian & Assocs. v. United States, 
    312 F.2d 418
    , 426 (Ct. Cl.), cert. denied, 
    375 U.S. 954
    (1963).
    9
    Consequently, as a contractor terminated for default, Century
    cannot, as a matter of law, recover the “unpaid balance” of the
    contract less the “cost of completion” of the work under the
    contract.      To allow such recovery would permit Century to do
    indirectly what it could not do directly, viz., recover anticipated
    but unearned profits after the contract has been terminated because
    of its default.     A contractor’s right to recover for anticipated
    profits arises only if the termination of the contract by the
    Government is wrongful and constitutes a breach.                G.L. 
    Christian, 312 F.2d at 423
    (citing United States v. Behan, 
    110 U.S. 338
    , 346
    (1884); United     States    v.   Spearin,     
    248 U.S. 132
    ,    138   (1918);
    Broadbent Portable Laundry Corp. v. United States, 
    56 Ct. Cl. 128
    ,
    132 (1921)).    Any recovery of profits by a contractor on a contract
    terminated because of its own default is limited to earned profit
    on work actually performed prior to the termination. Mega 
    Constr., 29 Fed. Cl. at 475
    .
    B. Century’s Claim For Extra Work
    Century    argues     that   the    district     court’s      findings   and
    conclusions are legally insufficient because the court made no
    express finding addressing its extra work claim, and that any
    implied finding by the court on the extra work issue is not
    supported by the evidence.
    Rule 52(a) of the Federal Rules of Civil Procedure provides
    that “[i]n all actions tried upon the facts without a jury. . .,
    the court shall find the facts specially and state separately its
    conclusions of law thereon. . . .”           The articulation of findings of
    10
    fact and conclusions of law allows this court to ascertain the
    factual and legal bases for the district court’s decision, thereby
    providing a sufficiently definite predicate for appellate review.
    Chandler v. City of Dallas, 
    958 F.2d 85
    , 90 (5th Cir. 1992).            But
    Rule 52(a) “exacts neither punctilious detail nor slavish tracing
    of the claims issue by issue and witness by witness.”                 Burma
    Navigation Corp. v. Reliant Seahorse M/V, 
    99 F.3d 652
    , 656 (5th
    Cir. 1996) (quoting Schlesinger v. Herzog, 
    2 F.3d 135
    , 139 (5th
    Cir. 1993)); see also United States v. Northside Realty Assocs.,
    Inc., 
    474 F.2d 1164
    , 1170 n.5 (5th Cir. 1973) (“‘Courts need not
    indulge in exegetics, or parse or declaim every fact and each
    nuance and hypothesis.’”) (quoting Gulf King Shrimp Co. v. Wirtz,
    
    407 F.2d 508
    , 516 (5th Cir. 1969)).       The rule is satisfied if the
    district   court’s    findings   give   the   reviewing   court   a   clear
    understanding of the basis for the decision.       Burma 
    Navigation, 99 F.3d at 656
    .
    If a trial judge fails to make a specific finding on a
    particular fact, the reviewing court may assume that the court
    impliedly made a finding consistent with its general holding so
    long as the implied finding is supported by the evidence.             In re
    Texas Mortgage Servs. Corp., 
    761 F.2d 1068
    , 1075 n.12 (5th Cir.
    1985); Gilbert v. Sterrett, 
    509 F.2d 1389
    , 1393 (5th Cir.), cert.
    denied, 
    423 U.S. 951
    (1975).
    According   to   the   district    court’s   factual   findings    and
    conclusions of law, Century had been compensated for the ten valid
    delivery orders under which it performed “extra work” to repair
    11
    weld fractures.    The     court also reached the legal conclusion that
    “there is no valid basis for an equitable adjustment to the
    contract.”     In rejecting Century’s general claim for equitable
    adjustment, which encompassed the extra work claim, the district
    court impliedly found that Century was not entitled to compensation
    for any other extra work.
    The district court’s 12-page findings of fact and conclusions
    of law are sufficiently detailed to adequately state the factual
    and legal bases for the district court’s denial of Century’s claim
    for extra work, thereby providing a sufficiently definite predicate
    for proper     appellate    review.      The    court’s    implied   denial    of
    Century’s extra work claim is fully supported by the evidence,
    particularly Mod 9, which sets forth the percentage of completion
    for unfinished delivery orders; the contracting officer’s decision,
    which provides detailed reasons for MARAD’s denial of Century’s
    claims   for   extra   work;     and   the     testimony   of   Volkmann,     the
    contracting officer’s technical representative, who testified that
    he personally inspected and videotaped Century’s unfinished work
    and that he researched and drafted 90% of the contracting officer’s
    decision with the assistance of Billy Greer, another MARAD employee
    who testified at trial.
    In so doing, we reject Century’s argument that the contracting
    officer’s decision is a “pleading” and therefore cannot be used as
    evidentiary    support     for   the   trial    court’s    implied   denial    of
    Century’s claim for extra work.          Under the Contract Disputes Act,
    contracting officers are not required to make specific findings of
    12
    fact, but, if made, they “shall not be binding in any subsequent
    proceeding.”          41 U.S.C. § 605(a).     However, there is nothing in the
    Contract Disputes Act that prohibits the use of the contracting
    officer’s findings and conclusions as evidence in a subsequent de
    novo proceeding.5         Cupey Bajo Nursing Home, Inc. v. United States,
    
    36 Fed. Cl. 122
    , 130 (1996) (“[T]his court reviews the facts and
    law decided by a contracting officer similar to other evidence
    before it[.]”).           Accord Lathan Co. v. United States, 
    20 Cl. Ct. 122
    , 125 (1990) (“This court may weigh the [contracting officer’s]
    findings and conclusions as it would any other evidence.”).                   See
    Wilner v. United States, 
    24 F.3d 1397
    , 1403-04 (Fed. Cir. 1993) (en
    banc) (expressly overruling pre-Contracts Dispute Act precedent
    holding that a contracting officer’s decision “constitutes a strong
    presumption or an evidentiary admission. . . albeit subject to
    rebuttal,” but cautioning that its opinion does not “suggest[] that
    a contracting officer’s final decision has no place in . . .
    litigation in the Court of Federal Claims”).                Therefore, in its
    role       as   the    finder-of-fact,   a    district   court   may   give   the
    contracting officer’s administrative determinations weight, not
    deference.       Mega 
    Constr., 29 Fed. Cl. at 414
    .       Cf. Universal Camera
    Corp. v. National Labor Relations Bd., 
    340 U.S. 474
    , 493-94 (1951)
    (holding that the nonbinding findings of an NLRB “trial examiner”
    5
    The Contract Disputes Act provides that, after a contracting
    officer renders a decision on a claim, a contractor may bring an
    action directly on the claim in the United States Court of Federal
    Claims (formerly the United States Claims Court), 41 U.S.C. §
    609(a)(1), where the action “shall proceed de novo in accordance
    with the rules of the appropriate court.” 41 U.S.C. § 609(a)(3).
    13
    may be considered in a subsequent appeal to establish whether an
    employee’s removal was supported by substantial evidence); Chandler
    v. Roudebush, 
    425 U.S. 840
    , 864 n.39 (1976) (holding that prior
    administrative findings can be used as evidence of the ultimate
    matters at issue in a subsequent de novo proceeding).
    Accordingly, we conclude that the Contract Disputes Act does
    not preclude the use of the contracting officer’s decision as
    evidence of the ultimate matters at issue in a subsequent de novo
    proceeding, provided that it is not given deference or a rebuttable
    presumption of correctness.
    IV.    CONCLUSION
    Having reviewed the record and considered all of Century’s
    arguments, we conclude that the district court did not commit any
    error of law or clear error of fact in finding Century in default
    and in rejecting Century’s claims with prejudice. As for Century’s
    “contract balance” argument, we conclude that there is no basis in
    law for a defaulted contractor to recover the difference between
    the unpaid balance of the contract and the cost of completing the
    unfinished work under the contract.         It is well settled that a
    defaulted   contractor   cannot   recover   anticipated   but   unearned
    profits.    Accordingly, the judgment of the district court is
    AFFIRMED.
    14
    RHESA HAWKINS BARKSDALE, Circuit Judge, specially concurring:
    I concur in the judgment being AFFIRMED, but would do so on
    the basis that, pursuant to the district court’s findings of fact
    and conclusions of law, and the underlying evidence upon which they
    are based (especially, modification No. 009 and the Government
    contacting officer’s written response to the request for equitable
    adjustment), Century Marine’s claims presented in this court fail,
    to include its primary claim that it was not paid for work which it
    performed.
    Concerning that primary claim, the references in the majority
    opinion concerning anticipated but unearned profits seem wide of
    the mark.    Such a “lost-profit” claim is not raised by Century
    Marine; and, contrary to the approach taken by the majority, I
    would not assume that this is the indirect or implied thrust of the
    position asserted here.   To do as the majority has done results, in
    my view, in this court reaching outside the record—something we
    should not, indeed cannot, do.
    15