ACS Const Co Inc v. General Power Corp ( 1999 )


Menu:
  •                IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    ____________________________
    No. 98-60491
    ____________________________
    ACS CONSTRUCTION CO., INC. OF MISSISSIPPI,
    Plaintiff-Appellee,
    V.
    GENERAL POWER CORPORATION, ET AL,
    Defendants,
    VENGROFF, WILLIAMS AND ASSOCIATES, INC.,
    Defendant-Appellant.
    _________________________________________________________________
    Appeal from the United States District Court
    Northern District of Mississippi
    Civil Action No. 4:96-CV-35-WB-B
    _________________________________________________________________
    December 30, 1999
    Before DAVIS and JONES, Circuit Judges, and LEMELLE*, District
    Judge.
    DAVIS, Circuit Judge:**
    Appellant Vengroff, Williams and Associates, Inc. ("Vengroff
    Williams") appeals the money judgment of the district court entered
    on a jury verdict.    Appellant contends that the district court
    erred in determining it had personal jurisdiction based on the
    *
    District Judge of the Eastern District of Louisiana, sitting by
    designation.
    **
    Pursuant to 5TH CIR. R. 47.5, the Court has determined that this
    opinion should not be published and is not precedent except under
    the limited circumstances set forth in 5TH CIR. R. 47.5.4.
    contract prong of the Mississippi long-arm statute. In particular,
    Vengroff Williams argues that the district court's determination
    that    it   had    personal    jurisdiction       was   erroneous     because    the
    evidence was        insufficient      to   establish     that   a     contract    was
    perfected in the meeting between Appellee ACS Construction Company,
    Inc. of Mississippi ("ACS") and Vengroff Williams.                       Appellant
    further argues that even if a contract was formed at the Greenwood,
    Mississippi        meeting,    none   of    the    contract     was   performed    in
    Mississippi.       We conclude that no enforceable contract was entered
    into at the Greenwood, Mississippi meeting and that the district
    court erred in finding that it had personal jurisdiction under the
    "contract prong" of the Mississippi long-arm statute. We therefore
    reverse the judgment of the district court.
    I.
    This case arises from a government contracting job gone
    awry.    In 1994, ACS sought two government building contracts, one
    at Fort Bragg in North Carolina and one at Fort Campbell in
    Kentucky.     General Power Corporation (“General Power”), a South
    Carolina corporation, submitted bids to ACS to perform the
    electrical work for both projects.                General Power was 50 percent
    owned by Albert B. Cialone.           Vengroff Williams--whose principals
    are Harvey Vengroff and Robert Williams--and Sheldon Electric
    Co., Inc (“Sheldon Electric”)--whose principal is Barry J. Beil--
    each owned 25 percent shares in General Power.                  ACS used General
    Power’s pricing in its bid to the government for both projects.
    2
    ACS was awarded both contracts and opened discussions with
    General Power about awarding General Power the electrical
    subcontract.    When General Power informed ACS that it was unable
    to provide a performance bond, as it had agreed to do, ACS became
    concerned with General Power’s stability and began to look
    elsewhere for an electrical subcontractor.   In an effort to allay
    these concerns, General Power invited ACS’s principals to a
    meeting in New York.   ACS declined the invitation and instead
    invited General Power to attend a meeting at ACS’s headquarters
    in Greenwood, Mississippi.
    General Power was well represented at the meeting with ACS
    in Greenwood, Mississippi.   The General Power representatives
    were Al Cialone, Barry Beil, and critically for purposes of this
    appeal, Harvey Vengroff, representing his company Vengroff
    Williams. General Power met with ACS for approximately one and a
    half hours.    The main topics discussed were the technical aspects
    of the electrical work that General Power would perform if it
    obtained the subcontracts from General Power.   The subject turned
    briefly to General Power’s financial ability to perform the
    subcontracts.   Mr. Vengroff assured ACS that his company was an
    investor in General Power and that it would provide the necessary
    financial support to assure completion of the subcontract.
    No contracts were signed at the Greenwood, Mississippi
    meeting, but later in North Carolina, ACS and General Power
    signed electrical subcontract agreements covering the two
    government construction projects.
    3
    In the course of completing the electrical work at the
    construction sites, General Power ran into a series of
    difficulties.   By all accounts, Cialone failed miserably as an
    administrator, and Vengroff Williams and Sheldon Electric came to
    his assistance.   Despite Vengroff Williams’ infusion of
    approximately $800,000 into General power and Mr. Williams’
    assumption of management duties at the Fort Bragg project,
    General Power continued losing money and it eventually filed for
    bankruptcy.   ACS then commenced the present suit, alleging that,
    by allowing General Power to default on the subcontract, Vengroff
    Williams failed to perform as it had promised.
    ACS initiated this action against General Power, Al Cialone;
    Vengroff Williams, Harvey Vengroff and Robert Willams; Sheldon
    Electric and Barry Beil.   ACS sued the parties under several
    theories, including breach of contract against General Power and
    breach of implied-in-fact contract against Vengroff Williams and
    Mr. Vengroff and Mr. Williams, individually.   ACS also sued
    Vengroff Williams, Sheldon Electric, and the individual
    principals of these firms for the torts of trover, conversion,
    and material misrepresentation and fraud.
    Shortly before trial ACS’s trover and conversion claims were
    dismissed pursuant to summary judgment.   At this time, Vengroff
    Williams and other parties to the suit filed motions to dismiss
    for lack of personal jurisdiction until the close of plaintiff’s
    case.   The district court postponed ruling on the motions for
    lack of personal jurisdiction.   At the conclusion of ACS’s case-
    4
    in-chief, the district court (1) dismissed ACS’s fraud and
    misrepresentation claims, and (2) determined that it had personal
    jurisdiction over Vengroff Williams.
    The district court allowed ACS’s breach of contract claim
    against Vengroff Williams to go to the jury, which returned a
    verdict for $83,000 in favor of ACS and against Vengroff
    Williams.    This appeal followed.
    II.
    In a federal diversity action, personal jurisdiction is
    determined by a two-step inquiry addressing: (1) the forum
    state's long-arm statute, and (2) federal due process.       Allred v.
    Moore & Peterson, 
    117 F.3d 278
    , 281 (5th Cir. 1997).     If the
    state long-arm statute is not first satisfied, the federal due
    process question is never reached and jurisdiction fails.      Cycles
    v. Digby, 
    889 F.2d 612
    , 616 (5th Cir. 1989).    The Mississippi
    long-arm statute provides in relevant part:
    Any nonresident person, firm, general or
    limited partnership, or any foreign or other
    corporation    not    qualified   under    the
    Constitution and laws of this state as doing
    business herein, who shall make a contract
    with a resident of this state to be performed
    in whole or in part by any party in this state
    ... shall by such acts be deemed to be doing
    business in Mississippi and shall thereby be
    subjected to the jurisdiction of the courts of
    this state.
    
    Miss. Code Ann. § 13-3-57
     (Supp.1998).    Thus, the existence of an
    enforceable contract is a prerequisite to a finding of personal
    jurisdiction under the "contract prong" of the Mississippi long arm
    5
    statute.
    We therefore turn to the principal argument on appeal: whether
    the evidence is sufficient to support the jury’s finding that a
    contract was perfected.     In order to find that a contract exists,
    a fact finder must determine that both parties agreed to all of the
    essential terms.     See Ham Marine, at 459; Knight v. Sharif, 
    875 F.2d 516
    , 525 (5th Cir. 1989).    Because the alleged contract arose
    from    the   parties’   conversations   at   the   Greenwood   meeting,
    Mississippi contract law governs.
    The district court held that the contract prong of the long-
    arm statute was satisfied because ACS produced prima-facie evidence
    of an oral agreement by Vengroff Williams to provide funding to
    General Power for the subcontracts.      The court further found that
    administrative functions performed in Mississippi by ACS, pursuant
    to the written subcontracts with General Power, satisfied the
    requirement that at least part of the contract be performed in
    Mississippi.
    Vengroff Williams argues that the conversation the trial
    court relied on is too vague and indefinite to constitute a
    completed contract.
    Several cases decided under Mississippi law refuse to
    enforce oral contracts where essential terms are too vague and
    indefinite.    Beck v. Goodwin, 
    456 So.2d 758
    , 761 (Miss. 1984);
    First Money, Inc. v. Frisby, 
    369 So.2d 746
    , 751 (Miss. 1979);
    Izard v. Jackson Production Credit Corp., 
    188 Miss. 447
    , 
    195 So. 331
    , 333 (1940).    Beck is particularly analogous to the facts-at-
    6
    hand.
    In Beck, the owner of a used car business brought an action
    against a bank for breach of contract and alleged that the bank
    agreed to finance the used car business but failed to do so.           456
    So.2d at 759.   The plaintiff asserted that he obtained a Small
    Business Administration loan through the bank in order to expand
    his business based on the bank’s specific assurances.          
    Id.
    According to the owner the bank specifically told him that
    “financing would never be a problem” and that the bank “would
    never arbitrarily cut off financing to him”.         
    Id.
       About a year
    after the owner obtained the loan, the financing agreement was
    terminated by the bank.       
    Id.
        The Supreme Court of Mississippi,
    in affirming the trial court's grant of a demurrer in favor of
    the bank, held that the agreement was too vague and indefinite to
    be enforced.    Id. at 761.
    In the case-at-hand the parties agree that Mr. Vengroff
    never stated how much money he was willing to contribute to
    General Power and never stated how long he was willing to
    continue funding General Power. Assuming as we must that Vengroff
    promised to fund General Power to the extent necessary to assure
    General Power's performance, such a vague and indefinite promise
    is insufficient as a matter of law to constitute an enforceable
    contract.   It is undisputed that the parties did not even discuss
    terms that would be essential to the formation of a contract. As
    the court observed in Beck:         “[a]ppellants did not allege how
    much money was to be advanced, when it was to be advanced, on
    7
    what security the advances were to be made, when the advances
    would be repaid, or what interest would be charged for the
    advances.”   456 So.2d at 761.
    Because we conclude that no contract was formed in
    Mississippi between ACS and Appellants, the district court had no
    personal jurisdiction over Vengroff Williams.
    III.
    For the reasons stated above, we REVERSE the judgment of the
    district court and REMAND this case so that the district court
    can dismiss this suit without prejudice.
    REVERSED and REMANDED.
    8
    

Document Info

Docket Number: 98-60491

Filed Date: 12/30/1999

Precedential Status: Non-Precedential

Modified Date: 12/21/2014