Halkias v. General Dynamics ( 1998 )


Menu:
  •                  UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    NO. 97-10334
    JOHN HALKIAS, ET AL.,
    Plaintiffs
    DAWN DEE BRYANT; BARRY JACKSON,
    Plaintiffs-Appellants
    VERSUS
    GENERAL DYNAMICS CORPORATION,
    Defendant-Appellee
    JAMES ANTHONY CUREINGTON,
    Plaintiff
    VERSUS
    GENERAL DYNAMICS CORPORATION,
    Defendant
    Appeal from the United States District Court
    For the Northern District of Texas
    April 1, 1998
    Before JOLLY, DUHE’ and PARKER, Circuit Judges.
    ROBERT M. PARKER, Circuit Judge:
    I.
    FACTS & PROCEDURAL HISTORY
    On January 13, 1988, General Dynamics and McDonnell Douglas
    Corporation were awarded a contract by the United States Navy to
    1
    jointly develop a new generation of carrier-based, medium attack
    aircraft to be known as the A-12 “Avenger”. The contract contained
    several provisions reflecting a concern for the abusive cost
    overruns of the past.        Costs between the target price of $4.4
    billion and the ceiling price of $4.8 billion would be shared by
    the government and the contractors (60% by the government and 40%
    by the contractors).       All costs over the ceiling price would be
    absorbed by the contractors.
    By May, 1990, the A-12 contractors had incurred substantial
    unforeseen production difficulties and by its own estimate, General
    Dynamics concluded that the cost of completion would be $700
    million more than planned.         On June 13, 1990, the contractors
    notified the Navy that the costs of completion would overrun the
    contract ceiling by an amount that the contractors could not
    absorb.   Throughout the remainder of 1990 production continued
    amidst various attempts to restructure the contract, which did
    result in a new delivery schedule.             However, the Navy would not
    agree to change the contract ceiling price.           Meanwhile, the threat
    of contract cancellation loomed overhead.
    On December 14, 1990, the Secretary of Defense directed the
    Navy to show cause by January 4, 1991, why the A-12 contract should
    not be canceled.     Later that same day, General Dynamics received
    informal notice of the Secretary’s show cause order.               On December
    17,   1990,   the   Navy   gave   the       contractors   notice   that   their
    performance on the A-12 contract was “unsatisfactory” and that
    unless specified conditions were met by January 2, 1991, the
    2
    contract might be terminated.             On December 20, 1990, General
    Dynamics   issued   a    special   bulletin   to   all    of   its   employees
    notifying them that the A-12 contract was in jeopardy and promising
    to provide notices the next day to each individual employee who
    might lose his or her job.         As promised, on December 21, 1990,
    General Dynamic sent out individual notices to all potentially
    affected employees, providing official but conditional notification
    that they might be terminated in the event that the A-12 contract
    were canceled.   On January 7, 1991, Secretary Cheney announced his
    decision to terminate the A-12 contract effective immediately.              As
    a result General Dynamics immediately began laying off affected
    employees.   Approximately 2000 non-union salaried employees were
    laid off from General Dynamics’ Fort Worth, Texas, and Tulsa,
    Oklahoma, facilities.
    On November 24, 1992, Plaintiff John Halkias filed suit under
    the Worker Adjustment and Retraining Notification Act, 
    29 U.S.C. §§ 2101-2109
     (1988)(the “WARN” act), claiming that General Dynamics
    had failed to comply with the Act’s sixty-day notice requirement.
    The   district   court    certified   a    class   of    non-union   salaried
    employees and designated John Halkias as class representative.              On
    June 24, 1993, the district court granted General Dynamics’ Fed. R.
    Civ. P. 12(c) motion to dismiss holding that the six-month statute
    of limitations of the National Labor Relations Act, 
    29 U.S.C. § 160
    (b), was applicable to actions under the WARN Act, and Plaintiff
    appealed to this Court.      On July 11, 1995, this Court reversed the
    district court and remanded the case following North Star Steel v.
    3
    Thomas, ___ U.S. ___, 
    115 S. Ct. 1927
    , 
    132 L. Ed. 2d 27
     (1995),
    which held that state law rather than the NLRA provided the
    relevant statute of limitations for actions under the WARN Act.
    Halkias v. General Dynamics Corp., 
    56 F.3d 27
     (5th Cir. 1995).1
    On October 3, 1995, the district court determined that the
    Texas four-year statute of limitations for actions for debt, 
    Tex. Civ. Prac. & Rem. Code Ann. § 16.004
    (a)(3)(Vernon 1986), was the
    most analogous to actions under the WARN Act and denied General
    Dynamics’ Rule 12(c) motion.        Since this holding was at odds with
    a holding by the district court for the western district of Texas,
    the district court granted General Dynamics the right to take an
    interlocutory appeal on October 6, 1995, which invitation General
    Dynamics accepted.       Over one year later, on October 22, 1996,
    following the decision in Staudt v. Glastron, Inc., 
    92 F.3d 312
    (5th Cir. 1996), this Court affirmed the district court’s ruling
    concerning the statute of limitations and remanded the case.
    Halkias   v.   General   Dynamics    Corp.,   
    101 F.3d 698
       (5th   Cir.
    1996)(table).
    On December 12, 1996, the district court issued a scheduling
    order establishing July 31, 1997, as the deadline for completion of
    discovery.     On January 16, 1997, General Dynamics filed its motion
    for summary judgment, arguing that sixty-day advance written notice
    was not required in this case, because the layoffs were “caused by
    business circumstances that were not reasonably foreseeable as of
    1
    During the pendency of this appeal, Plaintiff John Halkias passed
    away, and on remand his widow, Billie Halkias, was substituted as Plaintiff
    and Appellant Dawn Dee Bryant was substituted as class representative.
    4
    the time that notice would have been required.” 
    29 U.S.C. § 2102
    (b)(2)(A).      In response Appellants sought to have General
    Dynamics’ motion for summary judgment continued so that more
    discovery might be conducted in accordance with Fed. R. Civ. P.
    56(f) .   That motion was denied.       The motion for summary judgment
    was fully briefed, and on March 5, 1997, the district court granted
    it.    Plaintiffs-Appellants have taken this appeal raising the
    following issues:
    1.    Did the district court err by refusing to continue General
    Dynamics’ motion for summary judgment so that additional discovery
    might be conducted in accordance with Fed. R. Civ. P. 56(f)?
    2.    Did the district court err by granting General Dynamics’
    motion for summary judgment?
    II.
    LAW & ANALYSIS
    A.
    The WARN Act
    The WARN Act provides that:
    “[a]n employer shall not order a plant closing or mass
    layoff until the end of a 60-day period after the
    employer serves written notice of such an order ... to
    each representative of the affected employees as of the
    time of the notice, or if there is no such representative
    at that time, to each affected employee....”
    
    29 U.S.C. § 2102
     (a)(1).    However, the Act further provides that;
    “[a]n employer may order a plant closing or mass layoff
    before the conclusion of the 60-day period if the closing
    or mass layoff is caused by business circumstances that
    were not reasonably foreseeable as of the time that
    notice would have been required ... An employer relying
    on this subsection shall give as much notice as is
    practicable and at that time shall give a brief statement
    5
    of the basis for reducing the notification period.”
    
    29 U.S.C. § 2102
     (b)(2)(A) & (b)(3)(emphasis added).           This case
    centers around the proof in support of and against the proposition
    that General Dynamics should have reasonably foreseen the impending
    contract cancellation and therefore cannot avail itself of the
    exception in § 2102(b)(2)(A).     This Court reviews a district court
    decision to grant summary judgment de novo, applying the same
    standard as the district court.           Wynn v. Washington National
    Insurance Company, 
    122 F.3d 266
    , 268 (5th Cir. 1997), citing
    Bodenheimer v. PPG Indus., Inc., 
    5 F.3d 955
    , 956 (5th Cir. 1993).
    General Dynamics argues that the cancellation of the A-12
    contract and the resultant layoffs did not become reasonably
    foreseeable until December 14, 1990, at the earliest if at all,
    when   General   Dynamics   learned   through   informal   channels   that
    Secretary Cheney had issued an order to the Navy requiring it to
    show cause why the A-12 program should not be terminated.        General
    Dynamics argues that from December 14 until official notice was
    given to all affected employees on December 21, 1990, it acted with
    due diligence in an attempt to identify those employees who would
    be affected and to prepare the appropriate notices in compliance
    with § 2102 (b)(3).     General Dynamics argues that it reasonably
    believed that the program would not be terminated, in spite of
    serious cost overruns and a projected production delay of 22
    months, because both the Navy and Secretary Cheney still expressed
    very high support for the program.
    Appellant argues that General Dynamics knew or should have
    6
    known that the A-12 contract would be canceled.                As evidence that
    the cancellation was reasonably foreseeable, Appellant offered the
    testimony of its expert, Dr. Lawrence Korb, in another WARN Act
    case arising out of these layoffs, wherein Dr. Korb testified that
    General Dynamics knew as early as October, 1990, that if it did not
    pass the Defense Acquisition Board’s review in December, 1990, the
    project would not go forward.2                 Appellant also offered various
    minutes from General Dynamics’ board of directors meetings wherein
    the A-12 project and its possible termination were discussed.
    Appellant argued that those minutes showed that General Dynamics’
    CEO Stanley Pace was aware of the cancellation of a similar
    Lockheed aircraft project because of cost overruns and production
    delays.
    Before we may review the evidence, some clarification of the
    precise question before this Court is in order.               We must determine
    whether the evidence before the district court supported a finding,
    as a matter of law, that 60-days before the layoffs in this case
    General       Dynamics     could   not     reasonably     have     foreseen   the
    cancellation of the A-12 contract which precipitated these layoffs.
    Yet,    the    question    of   reasonable       foreseeability    begs   another
    question:      by adopting “reasonable foreseeability” as a standard,
    does the      WARN   Act   envision      the    probability   of   an   unforeseen
    business circumstance (i.e. the contract cancellation) or instead
    the mere possibility of such a circumstance?              We can only conclude
    2
    The cited testimony of Dr. Korb was in International Association of
    Machinists and Aerospace Workers, AFL-CIO v. General Dynamics Corp., 
    821 F. Supp. 1306
     (E.D. Missouri 1993).
    7
    that it is the probability of occurrence that makes a business
    circumstance “reasonably foreseeable” and thereby forecloses use of
    the § 2102(b)(2)(A) exception to the notice requirement.                A lesser
    standard    would   be   impracticable.          Since      cancellation    is    a
    possibility every time there is a cost overrun, defense contractors
    like   General   Dynamics    would   be    put   to   the    needless   task      of
    notifying    employees      of   possible    contract        cancellation        and
    concomitant lay-offs every time there is a cost overrun, and
    experience teaches us that there are invariably cost overruns,
    which most often do not lead to contract cancellation.
    B.
    The Evidence
    Having reviewed the summary judgment evidence closely, we must
    conclude that the district court properly granted summary judgment.
    There is no doubt that the evidence showed General Dynamics’ board
    of directors knew of the possibility of contract cancellation and
    mass lay-offs as early as June, 1990.            In particular, as early as
    June 6, 1990, minutes of the General Dynamics board of directors
    meeting indicate that the board was aware of the likelihood of a
    substantial cost overrun and production delay, that the Navy and
    Department of Defense were aware of these problems and that General
    Dynamics had begun negotiations with the Navy and Department of
    Defense to restructure the contract.
    At the August 1, 1990, meeting of the board of directors, the
    Chairman of the board, Mr. Stanley Pace discussed with the board
    members the recent experience of the Lockheed corporation in its
    8
    development of an aircraft for the Navy.                 It was reported by Mr.
    Pace that Lockheed had received insufficient assistance from the
    Navy when it experienced the same sort of problems that General
    Dynamics was experiencing with the A-12 program. Mr. Pace reported
    that   the   Lockheed      contract   was    eventually        canceled       and    that
    Lockheed’s experience might be indicative of what General Dynamics
    could expect.       On October 16, 1990, Mr. Pace again addressed the
    board of directors regarding the A-12 contract.                     He indicated that
    the program was due to be reviewed by the Defense Acquisition Board
    (“DAB”) on December 7, 1990, and that the DAB would be considering
    all aspects of the program, including termination of the contract.
    Finally, on November 7, 1990, Mr. Pace informed the board that,
    although     recent    congressional       enactments         did    not    cancel    the
    remaining options under the A-12 contract, those bills did allow
    Secretary Cheney to take action to address the huge cost overruns
    and production delays in the program.
    Therefore,     by   November   7,    1990,   it    is        clear   that    three
    possibilities existed.        Either the contract would be restructured,
    the contract would be canceled, or General Dynamics would simply
    default rather than absorb the cost overruns.                         The minutes of
    various board meetings would support a jury’s conclusion that the
    board was aware of the possibility that the contract would be
    canceled.      Nevertheless,      the      evidence      in    mitigation      of     the
    potential for contract cancellation, precludes that possibility
    from becoming a probability.            As noted previously, the Navy and
    Secretary Cheney had expressed their continuing support for the A-
    9
    12 program up to the last minute.     Given that unwavering support,
    it seemed less than probable that the contract would be canceled.
    Therefore, even if the evidence presented a good faith dispute as
    to the possibility of contract cancellation, in the face of the
    Navy’s and Secretary Cheney’s continuing support, no rational jury
    could have concluded that contract cancellation was a foreseeable
    probability until the last minute, i.e., December 14, 1990.
    III.
    CONCLUSION
    Having concluded that summary judgment was appropriate, we
    affirm. We do not reach the question of whether the district court
    erred by refusing to allow further discovery before ruling on
    General Dynamics’ motion for summary judgment. Appellants have not
    demonstrated to this Court that further discovery would lead to any
    evidence, which might raise the A-12 contract cancellation from a
    possibility to a probability any sooner than December 14, 1990.
    AFFIRMED.
    10