Millgard Corp. v. McKee/Mays ( 1995 )


Menu:
  •               IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    No. 94-10066
    MILLGARD CORP.,
    Plaintiff-Appellee,
    Cross-Appellant,
    versus
    McKEE/MAYS, A JOINT VENTURE,
    Defendant-Third-Party
    Plaintiff-Appellant-
    Appellee,
    Cross-Appellee,
    versus
    DALLAS COUNTY AND THE COMMISSIONERS'
    COURT OF DALLAS COUNTY,
    Third-Party Defendants-
    Appellants,
    Cross-Appellees.
    Appeal from the United States District Court
    for the Northern District of Texas
    (March 31, 1995)
    Before HIGGINBOTHAM, SMITH, and STEWART, Circuit Judges.
    PATRICK E. HIGGINBOTHAM, Circuit Judge:
    This Texas diversity case raises the familiar question of a
    price adjustment to a construction contract.   Here a subcontractor
    encountered wet soil while sinking piers for a foundation.      A soil
    report accompanying the bid documents signaled dry soil, but the
    bid documents stated that this soil report was not part of the
    contract documents.   A provision in the subcontract allowed for
    price adjustment if the subcontractor encountered conditions at
    variance    with     those     indicated       in   the    subcontract    or    those
    ordinarily     encountered.            Another        clause     disclaimed       all
    responsibility for the accuracy of the soils investigation.                       We
    hold that the subcontract provided for adjustment of contract price
    in two circumstances and neither was present.                     We reverse the
    judgment of the district court entered upon a jury verdict and
    vacate a judgment against the owner that passed the price increases
    through to the owner.
    I.
    On April 5, 1978, Dallas County contracted with McKee/Mays for
    the construction of a new county jail and courthouse, called the
    Lew   Sterrett      Justice    Center.         In   November    1978,    McKee/Mays
    solicited    bids    to   subcontract      the      pier   drilling     for   caisson
    foundations for the project.          McKee/Mays gave Millgard a packet of
    information about the project, including a set of instructions to
    bidders, the project specifications, and a copy of some soil boring
    logs.      Mason-Johnston       &   Associates       had    conducted    the    soils
    investigation at Dallas County's request.                  Section 1.21(b)(3) of
    the instructions to bidder warned that the soil "[r]eport and log
    of borings is available for Bidders' information only.                   The report
    is not a warranty of subsurface conditions, nor is it a part of the
    Contract Documents."          Section 1.21(c) continued:
    1.    Bidders are expected to examine the site and the
    subsurface investigation reports and then decide
    for themselves the character of the materials to be
    encountered.
    2
    2.   The Owner, Architect and Construction Manager
    disclaim any responsibility for the accuracy, true
    location and extent of the soils investigation that
    has been prepared by others. They further disclaim
    responsibility for interpretation of that data by
    Bidders, as in projecting soil-bearing values, rock
    profiles, soil stability and the presence, level
    and extent of underground water.
    On January 10 and 11, 1979, Millgard's officials met in Dallas
    with McKee/Mays's officials and discussed the project, including
    subsurface conditions.   McKee/Mays's officials gave them a copy of
    the soil report written by Mason-Johnston.    Millgard's officials
    visually inspected the site, examined soil samples, and spoke with
    Bill Howard, one of the authors of the soil report.       Millgard
    interpreted the data to indicate no problem water in the soil, and
    Howard concurred.   At the scheduled pre-bid conference on January
    11, Howard told bidders that the driller would encounter dry,
    cohesive soil that was probably clay, except in the fill and shale
    layers.   He stated that there was no reason to anticipate problem
    water, and told bidders to look at the soil report and samples.
    Though one other bidder drilled its own test hole, Millgard did not
    do so.
    On January 18, 1979, Millgard submitted a winning bid of
    $2,987,000.   Millgard then submitted proposed drilling plans to
    McKee/Mays for approval.    Millgard proposed to insert temporary
    casings through the fill layer.   These casings would clear the way
    for drilling through the dry clay until the drill reached the sand
    and gravel layer above the shale, at which point Millgard would
    insert another casing. The plan reiterated Howard's statement that
    3
    "problem volumes of water would not be expected."                   McKee/Mays,
    Dallas County, and Mason-Johnston reviewed and approved the plans.
    McKee/Mays signed the subcontract with Millgard on March 6,
    1979.        Section   12.2.1   of   the   subcontract    contained      a   clause
    entitled "CONCEALED CONDITIONS":
    Should concealed conditions encountered in the
    performance of the Work below the surface . . . be at
    variance with the conditions indicated by the Contract
    Documents, or should unknown physical conditions below
    the surface of the ground . . . differing materially from
    those ordinarily encountered . . . be encountered, the
    Contract Sum shall be equitably adjusted by Change Order
    . . . .
    Millgard began work in late June 1979. It encountered a layer
    of quicksand-like material, between five and fifteen feet thick,
    between the fill area and the sand and gravel layer.                          These
    conditions affected seventy-four percent of the holes drilled and
    made the drilling plans impractical.               Millgard spent more money
    than it expected, completing the work in early January 1980.
    Millgard sought its additional costs, and McKee/Mays forwarded its
    claim to Dallas County.         Dallas County decided that the conditions
    were not materially different from those indicated by the contract
    documents and refused to adjust the contract price.
    Millgard brought this diversity suit in federal district court
    to recover its additional costs.               McKee/Mays filed a third-party
    claim for indemnity from Dallas County.               A jury trial followed.
    The district court redacted section 1.21(b)(3) of the instructions
    to bidders in the version of the contract that was introduced into
    evidence.      The deleted language read: "nor is [the soil report] a
    part    of    the   Contract    Documents."         The   court   also       excised
    4
    section 1.21(c)(2), which stated that the owner, architect, and
    McKee/Mays "disclaim any responsibility for the accuracy . . . of
    the soils investigation [and] interpretation of that data."                   The
    court forbade McKee/Mays and Dallas County to mention this language
    or to elicit it at trial.          The jury was asked whether Millgard
    "reasonably relied on the subsurface information furnished to it in
    its preparation of its bid" and whether conditions "differed
    materially   from    those   conditions      indicated    by   the   subsurface
    information."      The jury answered "yes" to both questions.                 The
    court denied defendants' motions to set aside the verdict and for
    judgment as a matter of law, entered judgment for Millgard, and
    ordered Dallas County to indemnify McKee/Mays for the full amount
    of the judgment. McKee/Mays and Dallas County appeal, and Millgard
    cross-appeals the rate of prejudgment interest.
    II.
    The district court reasoned that all of the parties "relied on
    the accuracy of the soil report" and that the disclaimers did not
    "preclude,   for     all   purposes,    reliance    on   the   soil    report."
    Instead, the court interpreted the disclaimers as insuring "that
    any inaccuracies in the soil report would be inadequate grounds to
    rescind, or excuse nonperformance of, [Millgard's] contractual
    obligation   to     construct    the   caissons."        The   district     court
    therefore    redacted      the   disclaimers       and   phrased      the   jury
    instructions to allow Millgard to recover an equitable adjustment
    based on its reliance on the soil reports.
    5
    Millgard does not rely upon the second half of the concealed
    conditions    clause,      dealing   with   conditions    not    "ordinarily
    encountered." Its sole theory of liability is a breach of contract
    claim resting on the first half of the clause, which permits a
    price adjustment if conditions are "at variance with the conditions
    indicated by the Contract Documents."
    One problem with this contention is that section 1.21(c)(2)
    "disclaim[s] any responsibility for the accuracy, true location and
    extent of the soils investigation," including data concerning "the
    presence,    level   and    extent   of   underground    water."       Section
    1.21(b)(3) is even more explicit: "The [soil] report is not a
    warranty of subsurface conditions, nor is it a part of the Contract
    Documents."      If the soil report is not part of the contract
    documents, it cannot form the basis of a claim that conditions were
    "at   variance   with   the    conditions   indicated    by     the   Contract
    Documents."      The district court's gossamer distinction between
    grounds for escaping the contract and grounds for claiming an
    equitable adjustment finds no anchor in the blunt contract language
    disavowing "any responsibility." Part 1.05 of the project manual's
    earthwork specifications underscores this point: "No allowance or
    extra payments will be made by reason of variation in types of soil
    encountered or variations in their moisture contents."
    Nor do we find persuasive case law holding that "conditions
    indicated by the Contract Documents" can embrace soil reports that
    are not themselves part of the contract documents.                    City of
    Columbia v. Paul N. Howard Co., 
    707 F.2d 338
    , 340 (8th Cir.), cert.
    6
    denied, 
    464 U.S. 893
    (1983); Fattore Co. v. Metropolitan Sewerage
    Comm'n, 
    454 F.2d 537
    , 542 (7th Cir. 1971), cert. denied, 
    406 U.S. 921
    (1972).       Either the soil report is part of the contract
    documents or it is not.        Whatever be the force of trade customs in
    the absence of controlling contract language, the plain language of
    section 1.21 "disclaim[s] any responsibility" and excludes the soil
    report from the contract documents.
    Millgard and the district court argue that giving effect to
    the literal wording of the disclaimers would gut the concealed
    conditions clause.       See Foster Constr. C.A. & Williams Bros. Co. v.
    United States, 
    435 F.2d 873
    , 888 (Ct. Cl. 1970) (collecting cases).
    But the converse holds true--allowing reliance on the soil reports
    under   the     concealed     conditions      clause    would     eviscerate      the
    disclaimers.      Nor is it true that the concealed conditions clause
    would lack meaning if the disclaimers are given effect.                           The
    concealed      conditions     clause    would   still    allow     for    equitable
    adjustment      based    on    subterranean      conditions       that     are    not
    "ordinarily encountered."              It would also allow for equitable
    adjustment based on variances from any contract documents, such as
    the blueprints and specifications.              These contract provisions do
    not   clash.      Even   if    they    did    clash,    we    would    enforce    the
    disclaimers      because      they      specifically         mention     the     soils
    investigation while the concealed conditions clause does not.                      It
    is a maxim of interpretation that when two provisions of a contract
    conflict, the specific trumps the general.                   United States Postal
    7
    Serv. v. American Postal Workers Union, 
    922 F.2d 256
    , 260 (5th
    Cir.), cert. denied, 
    112 S. Ct. 297
    (1991).
    In short, the disclaimers and the language of the project
    manual show that the parties placed the risk of underground water
    on Millgard.      Millgard took its chances by not boring its own hole
    and instead relying on the soil reports.                The bargain struck by the
    parties allocated the risk and there it ends.                       We enforce the
    contract.
    III.
    Because the disclaimers were effective as a matter of law to
    disavow   all     responsibility       for     the   soils    investigation,          the
    district court erred in redacting the contract, limiting argument
    and testimony, and phrasing the jury instructions.                         The district
    court should instead have granted the motions for judgment as a
    matter of law.         The district court was correct, however, in
    rejecting       McKee/Mays's      claim        against       Dallas        County     for
    reimbursement of its attorney's fees.                   Texas law grants Dallas
    County governmental immunity from such awards. See Tex. Loc. Gov't
    Code   Ann.   §   5.904      (Vernon   Supp.     1995);      City     of    Terrell    v.
    McFarland, 
    766 S.W.2d 809
    , 813 (Tex. App.--Dallas 1988, writ
    denied). We need not reach the other issues presented on appeal or
    cross-appeal.      We REVERSE the judgment of the district court on
    Millgard's claims and RENDER judgment for McKee/Mays.                        We AFFIRM
    the    portion    of   the    district        court's    judgment      that     rejects
    McKee/Mays's claim against Dallas County for its attorney's fees
    8
    and VACATE the judgment against Dallas County and in favor of
    McKee/Mays, there now being no award against McKee/Mays.
    AFFIRMED IN PART, VACATED IN PART, AND REVERSED IN PART.
    9
    

Document Info

Docket Number: 94-10066

Judges: Higginbotham, Smith, Stewart

Filed Date: 4/3/1995

Precedential Status: Precedential

Modified Date: 11/5/2024