Tennessee Gas Pipeline Co. v. F.E.R.C. ( 1994 )


Menu:
  •                   United States Court of Appeals,
    Fifth Circuit.
    No. 93-4089.
    TENNESSEE GAS PIPELINE CO., Petitioner,
    v.
    FEDERAL ENERGY REGULATORY COMMISSION, Respondent.
    March 25, 1994.
    Petition for Review of an Order of the Federal Energy Regulatory
    Commission.
    Before JOHNSON, HIGGINBOTHAM, and EMILIO M. GARZA, Circuit Judges.
    JOHNSON, Circuit Judge:
    On April 8, 1991, Tennessee Gas Pipeline Company ("Tennessee")
    and Flagg Energy Development Corporation ("Flagg") entered into a
    firm natural gas transportation contract.           Tennessee agreed to
    transport 4,140 dekatherms of natural gas each day from various
    points in and offshore Louisiana to Connecticut on Flagg's behalf.
    Tennessee also agreed to construct and operate the facilities
    necessary to transport the natural gas.             Flagg agreed to pay
    Tennessee for its services.
    Prior to entering into this contract, the Federal Energy
    Regulatory   Commission    ("FERC"   or   "the   Commission")   authorized
    Tennessee to charge Flagg certain rates for the transportation
    services.    The Commission also ruled that Tennessee could later
    seek changes to those rates, as allowed by section four of the
    Natural Gas Act ("NGA").      Tennessee sought to change the rates on
    February 28, 1992.        Flagg intervened and charged, among other
    things, that its gas transportation contract prohibited the type of
    1
    rate       changes   sought        by     Tennessee.                 The    Commission    agreed.
    Tennessee appeals.           We reverse.
    I. Facts and Procedural History
    Tennessee entered precedent agreements with seven different
    companies in the winter of 1988-89.                        The companies proposed to pay
    Tennessee      to    transport          natural       gas       to    various    points       in   the
    Northeast. Flagg entered such a precedent agreement with Tennessee
    on January 9, 1989.          It desired for Tennessee to transport natural
    gas from various points in and offshore Louisiana to New Britain,
    Connecticut, and Bloomfield, Connecticut. Tennessee agreed to seek
    authorization from FERC to build the facilities necessary to
    transport that natural gas.
    Consistent      with    the        precedent         agreements          with    the    seven
    different companies—including its agreement with Flagg—Tennessee
    sought FERC approval to construct and operate new facilities which
    would expand the capacity of its existing pipeline system. The new
    facilities      were    to    be    located           in    five      separate     zones,      which
    Tennessee      designated      Segments           U,       1,    2,    3,    and   4.     In       its
    application to FERC, Tennessee asserted that it would transport
    natural gas to Flagg through Segments U, 2, and 3 and would charge
    Flagg for the cost of operating those three facilities.1                                           Rate
    1
    There are two methods of charging for gas transportation:
    The "incremental cost allocation" method and the "rolled in"
    method. Under the incremental cost allocation method, the new
    customers pay for all of the costs of the new facilities. This
    method spares existing customers from having to pay for the
    expansion of the transportation system, even though they may use
    the expansion facilities. The rolled in method of charging for
    gas transportation requires each shipper—both old and new—to pay
    its share of the transportation costs based upon its
    2
    Schedule NET-EU set forth the rates which Tennessee proposed to
    charge.   However, Tennessee requested permission to change the
    rates if all of the proposed facilities were not approved by
    October 1, 1989.
    FERC approved the construction of three of the five Segments
    by May of 1990—Segments 1, 2, and 3.     See Tennessee Gas Pipeline
    Co., 
    51 FERC ¶ 61,113
    , 61,274, 61,275-276 and n. 22 (1990).
    Because FERC had not yet given Tennessee permission to construct
    the proposed   facilities   for   Segments   U    or    4,   it   disapproved
    Tennessee's request to charge Flagg for any use of Segment U in a
    May 2, 1990, order ("May Order").      
    Id.
           However, the Commission
    decided that Tennessee could seek to amend its NET-EU rates to
    "roll in"2 the costs associated with Segments U and 4 after those
    projects were approved and placed in service.                The Commission
    asserted that Tennessee could seek such a rate change at a later
    date through a section 4 proceeding.         
    Id. at ¶ 61,274
    .           FERC
    calculated a rate for Segment 4 in its September 13, 1990, order.
    However, it again refused to compute a rate for Segment U because
    the proposed facilities had still not been approved. Tennessee Gas
    Pipeline Co., 
    52 FERC ¶ 61,257
    , 61,930 (1990).
    Based upon, and specifically referring to, the May Order,
    Tennessee and Flagg entered a Firm Natural Gas Transportation
    Agreement ("contract") on April 8, 1991.               Tennessee agreed to
    proportionate use of the facility in question. Tennessee
    proposed to charge Flagg under the incremental cost allocation
    method.
    2
    See supra note 1.
    3
    construct the facilities needed to receive and deliver gas to
    Flagg.   The specific rate formula for transporting the gas was set
    out in section 8.2 of the contract.      However, section 8.4 of the
    contract provided that "pursuant to this Article VIII," Tennessee
    has the unilateral right "to file and make effective changes in the
    rates, charges, and conditions applicable to service."
    Consistent   with   its   construction   of   section   8.4   of   the
    contract, Tennessee filed a limited rate case under section 4 of
    the NGA to revise the rates in its NET-EU schedule.          Among other
    things, Tennessee sought to charge Flagg and another company,
    Capitol District Energy Center Cogeneration Associates ("Capitol
    District"), for their use of Segment U.3      Apparently complying with
    the Commission's May Order, Tennessee proposed to roll the Segment
    U charge into these companies' gas transportation charges.         See 51
    FERC at ¶ 61,274 (deciding that "Tennessee may seek to amend its
    NET-EU rates to reflect the rolling in of all costs associated with
    various Northeast projects by initiating a section 4 proceeding
    after all the projects have been approved and placed in service"
    (emphasis added)).
    Both Flagg and Capitol District filed motions to intervene.4
    3
    Flagg and Capitol District are the only NET-EU customers
    which use Segment U. Tennessee uses that Segment to transport
    natural gas from the Gulf Coast approximately 1400 miles north to
    various points in the Northeast on Flagg's and Capitol District's
    behalf. Unlike the gas transported for Flagg and Capitol
    District, the natural gas transported for the other NET-EU
    customers is both received and delivered in the Northeast.
    4
    Tennessee and Capitol District have settled their disputes
    in this matter.
    4
    Flagg proffered         numerous    objections   to   Tennessee's     proposals.
    Important for our purposes, Flagg contended that its contract with
    Tennessee prohibited Tennessee from charging Flagg for its use of
    Segment U. According to Flagg, Tennessee could only charge for the
    use of Segments 2 and 3.          Flagg requested FERC to review the matter
    in an expedited paper hearing, and FERC granted the request,
    limiting    its   review     to    deciding   whether     the   Tennessee-Flagg
    contract precluded Tennessee from charging Flagg for its Segment U
    use. Tennessee Gas Pipeline Co., 
    58 FERC ¶ 61,343
     (1992).               Finding
    the contract clear and unambiguous and basing its decision solely
    on the plain language of the contract, the Commission concluded
    that the contract did not allow Tennessee to charge Flagg for
    Segment U.      Tennessee Gas Pipeline Co., 
    60 FERC ¶ 61,261
     (1992).
    The Commission denied Tennessee's motion for rehearing on January
    21, 1993.    Tennessee appeals.
    II. Discussion
    A. Background
    As late as the mid-1940s, just after World War II, contracts
    between natural gas companies (e.g., suppliers and transporters)
    and   natural     gas    purchasers     (e.g.,   public     service   commodity
    companies) began to take one of two shapes with respect to rates.
    The contracts either set forth a specific, unchangeable rate for
    natural gas supply or they set no specific rate whatever.               Compare
    United Gas Pipe Line Co. v. Mobile Gas Service Corp., 
    350 U.S. 332
    ,
    
    76 S.Ct. 373
    , 
    100 L.Ed. 373
     (1956) with United Gas Pipe Line Co. v.
    Memphis Light, Gas and Water Division, 
    358 U.S. 103
    , 
    79 S.Ct. 194
    ,
    5
    
    3 L.Ed.2d 153
     (1958);   see also Federal Power Commission v. Sierra
    Pacific Power Co., 
    350 U.S. 348
    , 
    76 S.Ct. 368
    , 
    100 L.Ed. 388
    (1956).   As energy prices escalated, natural gas companies sought
    to unilaterally raise their prices by filing revised rate schedules
    with the, then, Federal Power Commission ("FPC").5         Needless to
    say, the natural gas purchasers were less than pleased.           They
    intervened in the section 4 proceedings and argued that the natural
    gas companies had no authority to unilaterally change their rates.
    By the mid to late 1950s these controversies made their way to
    the United States Supreme Court.        The first such case was United
    Gas Pipe Line Co. v. Mobile Gas Service Corp., 
    350 U.S. 332
    , 
    76 S.Ct. 373
    , 
    100 L.Ed. 373
     (1956).       There, United Gas Pipe Line Co.
    ("United") contractually agreed to furnish natural gas to Mobile
    Gas Service Co. ("Mobile") for a ten-year period at twelve cents
    per thousand cubic feet (MCF).         
    Id. at 336
    , 76 S.Ct. at 376-77.
    Seven years into the agreement, United, without Mobile's consent,
    filed a new rate schedule with the FPC, raising the rates to
    fourteen and one-half cents per MCF.       Mobile opposed the increase,
    arguing that it was contrary to the terms of its contract with
    United. United, however, contended that the NGA authorized natural
    gas companies to change their rate agreements unilaterally.
    The Supreme Court disagreed.        Id. at 337, 76 S.Ct. at 377.
    The Court found that the NGA evinced no intention to abrogate the
    rates set forth in private natural gas contracts.       The Court found
    5
    Section 4 of the NGA sets forth the procedures for changing
    rate schedules.
    6
    that   the   Act,     instead,   "expressly      recognizes     that    rates    to
    particular customers may be set by individual contracts."                  Id. at
    338, 76 S.Ct. at 378.       The primary focus, according to the Mobile
    Court, is the natural gas contract, not the Natural Gas Act:
    [E]xcept as specifically limited by the Act, the rate-making
    powers of natural gas companies [are] to be no different from
    those they would possess in the absence of the Act:        to
    establish ex parte, and change at will, the rates offered to
    prospective customers; or to fix by contract, and change only
    by mutual agreement, the rate agreed upon with a particular
    customer.
    Mobile Gas Service Corp., 
    350 U.S. at 343
    , 76 S.Ct. at 380.                     The
    Court determined that preserving the integrity of natural gas
    contracts aided the stability of supply arrangements, contributed
    to the health of the natural gas industry, and therefore promoted
    the purposes of the NGA.          Id. at 344, 76 S.Ct. at 380-81.                It
    therefore ruled that the Natural Gas Act did not empower natural
    gas companies to unilaterally change their contracts.                  Id. at 337,
    76 S.Ct. at 377.
    The   Supreme    Court    again       emphasized   the   importance       of
    contractual provisions in United Gas Pipe Line Co. v. Memphis
    Light, Gas and Water Division, 
    358 U.S. 103
    , 105, 
    79 S.Ct. 194
    ,
    195-96, 
    3 L.Ed.2d 153
     (1958). Unlike the contract in Mobile, which
    set forth a specific gas rate, the contract in Memphis required
    Memphis Light, Gas and Water Division ("Memphis") to pay United in
    accordance     with    United's    rate       schedule    "or   any     effective
    superseding rate schedules[ ] on file with the" FPC.                      Memphis
    Light, Gas and Water Division, 358 U.S. at 105, 79 S.Ct. at 196.
    In effect, Memphis bound itself to paying the "going" rate for the
    7
    gas.   Id. at 110, 79 S.Ct. at 198.         In accordance with the United-
    Memphis contract, United sought to raise the gas supply rates it
    charged by filing revised rate schedules with the FPC.                 Memphis
    protested.     Viewing Mobile as a sword—prohibiting natural gas
    companies    from    ever    seeking   unilateral    rate   revisions—Memphis
    contended that United's efforts ran afoul of the Supreme Court's
    decision in Mobile.         Id. at 108, 79 S.Ct. at 197.
    The Supreme Court read its Mobile decision otherwise.             Again
    focussing on the language in the contract, the Memphis Court ruled
    that a natural gas company is precluded from seeking unilateral
    changes in its rates only if its contract expressly precludes such
    changes.     Id. at 113, 79 S.Ct. at 200.           According to the Memphis
    Court, a gas company, "like the seller of an unregulated commodity,
    has the right in the first instance to change its rates as it will,
    unless it has undertaken by contract not to do so."            Id.   (Emphasis
    added).     As made clear in Mobile and Memphis, courts deciding
    whether a natural gas company may unilaterally change its rates
    must focus on the words of the natural gas contract.
    B. Standard of Review
    In light of Mobile and Memphis, we now turn to the firm
    natural gas agreement at issue in the case sub judice.               Flagg asks
    the Court to defer to FERC's construction of that agreement.             This,
    we cannot do.       It is well-settled in the Fifth Circuit that this
    Court will review the construction of natural gas contracts freely.
    El Paso Natural Gas Co. v. Federal Energy Regulatory Commission,
    
    881 F.2d 161
    , 164 (5th Cir.1989);           Pennzoil Co. v. Federal Energy
    8
    Regulatory Commission, 
    789 F.2d 1128
    , 1135-36 (5th Cir.1986). This
    Court will not defer to FERC's construction of such contracts
    unless FERC    relied     on   its   factual   or   technical    expertise     in
    reaching its conclusions.        Mid Louisiana Gas Co. v. Federal Energy
    Regulatory Commission, 
    780 F.2d 1238
    , 1243 (5th Cir.1986);                    see
    also El Paso Natural Gas, 881 F.2d at 164 (stating that "where the
    understanding of the problem is enhanced by the agency's expert
    understanding of the industry, this Court may defer to the views of
    the agency although those views are not conclusive" (emphasis
    added; internal quotations omitted)). In the case sub judice, the
    Commission relied solely on the words of the contract.                This Court
    will therefore review the construction of the gas transportation
    agreement de novo.
    C. Interpreting the Contract
    In interpreting a natural gas contract, courts should apply
    the normal rules of contract interpretation.                Mid Louisiana Gas,
    780 F.2d at 1242-43.      In section 16.4 of their contract, Flagg and
    Tennessee agreed that the Texas rules of contract interpretation
    would control in any contract disputes.                 A cardinal rule of
    contract interpretation in Texas requires courts to review the
    entire contract in order to determine its meaning;               courts should
    not consider      any   single   provision     in   isolation.     Eagle      Life
    Insurance   Co.    v.   G.I.C.   Insurance     Co.,   
    697 S.W.2d 648
    ,   650
    (Tex.App.—San Antonio 1985, writ ref'd n.r.e.).               To the contrary,
    the goal of contract interpretation is to determine the parties'
    intentions by harmonizing and giving effect to each provision
    9
    within    the   contract    such   that      none   is   rendered     meaningless.
    Railroad Co. v. Androscoggin Mills, 89 U.S. (22 Wall.) 594, 
    22 L.Ed. 724
     (1874);       Woods v. Sims, 
    154 Tex. 59
    , 
    273 S.W.2d 617
    , 620-
    21 (1954);      Universal C.I.T. Credit Corp. v. Daniel, 
    150 Tex. 513
    ,
    
    243 S.W.2d 154
    , 158 (1951);          Eagle Life Insurance Co., 697 S.W.2d
    at 650;      see also Duracon, Inc. v. Price, 
    817 S.W.2d 147
    , 149
    (Tex.App.—El Paso 1991, writ denied) (stating that courts are to
    presume that      the   parties    intended     every     clause     to   have   some
    effect).     Not only must courts give meaning to each provision,
    courts must also give meaning, effect, and purpose to every word in
    the contract, if at all possible. TM Productions, Inc. v. Nichols,
    
    542 S.W.2d 704
    , 708 (Tex.App.—Dallas 1976, writ ref'd n.r.e.).
    The starting place for construing a contract is its language.
    Mid Louisiana, 780 F.2d at 1243.             The provisions in dispute here
    are located in Article VIII, which is entitled "Rates For Service."
    The most     important     of   those   provisions       for   our   purposes    are
    sections 8.2 and 8.4.           Those sections are the second and fourth
    paragraphs in Article VIII.          They provide the following:
    8.2 Transportation Rates—Beginning on the Commencement Date,
    the compensation to be paid by Shipper to Transporter for the
    transportation service provided for herein shall be payable
    monthly in accordance with Article X hereof and shall be equal
    to the sum of the following: (a) the product of (1) the sum
    of the "D-1" charges for Segments 2 and 3 under Transporter's
    NET-EU Rate Schedule and (2) the Transportation Quantity, (b)
    the product of (1) the sum of the "D-2" charges for Segments
    2 and 3 under Transporter's NET-EU Rate Schedule and (2) the
    "D-2 Billing Determinant" for the applicable billing period as
    set forth in Exhibit B hereto, (c) the product of (1) the sum
    of the "Commodity" charges for Segments 2 and 3 under
    Transporter's NET-EU Rate Schedule and any applicable
    surcharges as included in Transporter's effective FERC Gas
    Tariff and (2) the quantity of gas delivered by Transporter to
    Shipper during the applicable billing period.
    10
    References herein to Transporter's NET-EU Rate Schedule shall
    include any successor or substitute rate schedules....
    8.4 Rate Changes—Shipper agrees that Transporter shall have
    the unilateral right pursuant to this Article VIII to file and
    make effective changes in the rates, charges, and conditions
    applicable to service pursuant to the Rate Schedule under
    which this service is rendered and/or any provisions of the
    General Terms and Conditions of Transporter's FERC Gas Tariff
    Volume No. 1 as such Tariff may be revised or replaced from
    time to time. Without prejudice to Shipper's right to contest
    such charges, Shipper agrees to pay the effective rate for
    service rendered pursuant to this Agreement, subject to FERC
    review and adjustment. (Emphasis added).
    1. FERC'S Construction
    Reviewing section 8.2, the Commission correctly determined
    that that section requires Flagg to compensate Tennessee according
    to a set formula which includes variables for Demand ("D-1" and "D-
    2") and Commodity charges for Segments 2 and 3.     The Commission
    also determined that section 8.4 "arguably does give[ ] Tennessee
    the right to unilaterally file changes to two parts of its tariff:
    the rates, charges, and conditions for the service ... and the
    tariff's general terms and conditions."      60 FERC at ¶ 61,865.
    However, the Commission determined that the emphasized portion of
    section 8.4—"pursuant to this Article VIII"—limited Tennessee's
    right to file revised rates.     According to the Commission, any
    changes under section 8.4 must be consistent with section 8.2.
    Since section 8.2 allows Demand and Commodity charges solely for
    Segments 2 and 3—not for Segment U—the Commission concluded that
    adding charges for Segment U is inconsistent with section 8.2.   The
    Commission therefore ruled that the "pursuant to" phrase prohibited
    Tennessee from unilaterally adding a Segment U charge for the NET-
    EU service.   Id.   In essence, the Commission decided that section
    11
    8.4 allows for changes in Segments 2 and 3 charges only.
    Here, on appeal, FERC adds that the definition of "pursuant
    to" supports the Commission's conclusion.             FERC asserts that
    "pursuant to" is a restrictive phrase which means "in conformance
    to or agreement with" or "according to."           FERC quotes BLACK'S LAW
    DICTIONARY as providing that "when [the words "pursuant to' are] used
    in a statute ... [they constitute a] restrictive term."            FERC's
    Brief at 22-23 (quoting BLACK'S LAW DICTIONARY 1236 (6th ed. 1990)).
    We disagree with both the Commission's construction of the
    contract and FERC's interpretation of the "pursuant to" language.
    In our view, the construction proffered by FERC effectively deletes
    section 8.4     from   the   contract.   Section    8.2—even   absent    the
    language in section 8.4—authorizes Tennessee to unilaterally change
    the costs associated with Segments 2 and 3.        Section 8.2 sets forth
    a formula for charging for the use of Segments 2 and 3.                 That
    formula includes four variables—D-1 charges, D-2 charges, Commodity
    charges, and a D-2 Billing Determinant.     The dollar amount for each
    variable is set out, not in the contract, but in the NET-EU Rate
    Schedule.    Hence, a unilateral change in the NET-EU Rate Schedule,
    which is expressly permitted by section 8.2,6 changes the dollar
    6
    The second paragraph in section 8.2 states that references
    to the NET-EU Rate Schedule "shall include any successor or
    substitute rate schedules." That language is strikingly similar
    to the provision which was at issue in Memphis. There, the
    contract provided that "[a]ll gas delivered hereunder shall be
    paid for by Buyer under Seller's Rate Schedule ... or any
    effective superseding rate schedules." 358 U.S. at 105, 79 S.Ct.
    at 196 (emphasis in the original). The Supreme Court ruled that
    that language authorized the Seller to unilaterally change the
    rates. Id. at 110, 79 S.Ct. at 198-99.
    12
    amount      of   each   variable.    A   change       in   the   variable   amounts
    necessarily changes the charges for Segments 2 and 3. Hence, under
    the Commission's construction, section 8.4 is mere surplusage. The
    Commission's construction gives section 8.4 no independent meaning
    of its own.         Section 8.4 simply mimics section 8.2;                  it adds
    nothing to the contract.
    FERC's     restrictive    definition      of    "pursuant    to"     likewise
    eviscerates section 8.4 from the contract.7                 In FERC's view, the
    first sentence in section 8.4 allows Tennessee to change the rates
    and charges as long as those changes are "in agreement with"
    section 8.2.       This argument, when taken to its logical conclusion
    is nonsensical, for absent section 8.4, the rate formula outlined
    in section 8.2 can never change.              Yet, under FERC's construction,
    absent a change in section 8.2, Tennessee cannot exercise its right
    to change section 8.2.          In other words, section 8.2 has to first
    change before it can be changed.          If it does not change on its own,
    it cannot be changed under the authority of section 8.4.                       This
    construction not only make no sense, but it also negates section
    8.4:       It, in effect, requires the rate formula to remain constant,
    since section 8.2 clearly cannot change on its own.                       Thus, the
    section 8.4 language which provides Tennessee with the right to
    make unilateral changes in the transportation rates is, again,
    rendered meaningless and ineffective.             Such a construction clearly
    7
    We also note that the restrictive definition proffered by
    FERC is inapplicable in this case. BLACK'S LAW DICTIONARY makes
    clear that the "pursuant to" phrase is restrictive "when used in
    a statute." BLACK'S LAW DICTIONARY 1237 (6th ed. 1990) (emphasis
    added). A contract—not a statute—is at issue here.
    13
    violates the elementary rules of contract interpretation which
    require courts to give meaning to each term, phrase, and provision
    of a contract.    See Androscoggin Mills, 89 U.S. (22 Wall.) 594, 
    22 L.Ed. 724
     (1874) (requiring courts to give effect to all of a
    contract's provisions);      TM Productions, Inc., 542 S.W.2d at 708
    (stating that courts must give effect and purpose to each word in
    a contract).
    Our construction of the contract does not violate these
    contract interpretation rules. This Court's review of the contract
    reveals a more coherent interpretation, one which gives meaning and
    effect to both section 8.2 and section 8.4. Another interpretation
    of the "pursuant to" phrase aids in our task.        WEBSTER'S NEW COLLEGIATE
    DICTIONARY and BLACK'S LAW DICTIONARY first define "pursuant to" as
    meaning "in carrying out" or "in the course of carrying out."
    WEBSTER'S NEW COLLEGIATE DICTIONARY 930 (1979);   BLACK'S LAW DICTIONARY 1237
    (6th ed. 1990).    Using this definition, the pertinent sentence in
    section 8.4 provides Tennessee with the unilateral right, in
    carrying out Article VIII, to file and make effective changes in
    the   transportation    rates.     Because   Article     VIII   establishes
    Tennessee's authority to charge Flagg for the gas transportation,
    Tennessee "carries out" the terms of Article VIII by charging
    Flagg. Hence, section 8.4 simply provides Tennessee with the right
    to change transportation rates when carrying out its charging
    authority.
    Our construction of section 8.4 is consistent with other
    provisions in the contract—section 16.1, in particular.             Section
    14
    16.1 prohibits the modification of any of the terms of the contract
    absent written consent by both parties.    By using the "pursuant to
    this Article VIII" language in section 8.4, the parties completely
    removed Article VIII from the ambit of section 16.1.     The parties
    provided that contrary to the modification prohibition in section
    16.1, unilateral changes in Article VIII are permissible.
    2. Flagg's View
    Flagg offers a second interpretation of the contract.        It
    contends that the terms "rates" and "charges" are used synonymously
    in section 8.4 and are distinct from the terms "cost allocation"8
    and "compensation," terms which refer to the amount Flagg owes to
    Tennessee for the gas transportation.     Using this reading of the
    contract, Flagg reaches FERC's conclusion:      while Tennessee may
    revise the "charges" for Segments 2 and 3, Tennessee may not change
    the overall gas transportation rates by, for example, including
    charges for Segment U.
    Besides completely negating the effect of section 8.4, as
    discussed in part II(C)(1) of this opinion, Flagg's construction
    improperly renders the word "rates" superfluous. Fort Worth Lloyds
    Insurance    Co.     v.    Willham,       
    406 S.W.2d 76
    ,    79
    (Tex.Ct.Civ.App.—Amarillo 1966) (stating that "courts are without
    authority to needlessly reject any words or terms used in contracts
    by the parties or delete any clause therein as surplusage, unless
    such action is judicially mandatory").     A careful reading of the
    contract reveals that the words "rates" and "charges" are used
    8
    The term "cost allocation" is not used in the contract.
    15
    distinctly.           Section    8.2       associates         the    word     "charges"       with
    specific costs connected with three of the four NET-EU variables.
    That       section    provides       for    "D-1      charges,"       "D-2        charges,"    and
    "Commodity charges."            (Emphasis added;                  internal quotation marks
    omitted).
    The word "rates" is used more globally.                          That word is used
    just four times in the contract.                       Section 8.4 is entitled "Rate
    Changes," and it provides Tennessee with the "unilateral right ...
    to file and make effective changes in the rates."                             Article VIII is
    entitled        "Rates   For     Service,"            and    section        8.2    is     entitled
    "Transportation Rates."              The word "rates," as used in these latter
    two    locations,        alludes,          not    to        the    Demand     and       Commodity
    variables—as does the word "charges."                        Using the ordinary meaning
    of the word and construing "rates" in the context of the entire
    contract, we find that that word means the overall price for the
    gas    transportation.9              The   word       "rates"       found    in     section    8.4
    necessarily has the same definition as does the word "rates" found
    in the title to Article VIII and in section 8.2.                              See Gonzalez v.
    Mission American Insurance Co., 
    795 S.W.2d 734
    , 736 (Tex.1990)
    (deciding that in general, a word which is used in one sense in one
    part       of   a   contract    is    presumed         to    retain    that        same    meaning
    throughout the contract, absent indications to the contrary);
    9
    Indeed, WEBSTER'S NEW COLLEGIATE DICTIONARY defines "rate" as "a
    charge, payment, or price fixed according to a ratio." WEBSTER'S
    NEW COLLEGIATE DICTIONARY 950 (1979). Flagg is therefore correct in
    arguing that the term "rates" is not synonymous with the term
    "compensation." Although the amount of compensation equals the
    transportation rates, "compensation" refers to the amount Flagg
    owes Tennessee, not the price of the transportation services.
    16
    Johnson v. Dick, 
    281 S.W.2d 171
    , 175 (Tex.Ct.Civ.App.—San Antonio
    1955) (same);      Green Avenue Apartments, Inc. v. Chambers, 
    239 S.W.2d 675
    , 685 (Tex.Civ.App.—Beaumont 1951) (same).        Thus, in
    authorizing Tennessee to change the "rates," section 8.4 gave
    Tennessee the authority to completely revise the prices for its gas
    transportation services.   Tennessee's right to make such revisions
    is limited only by procedural and other requirements in the Natural
    Gas Act.   Memphis, 358 U.S. at 110, 79 S.Ct. at 198-99.
    Flagg contends that such an interpretation fails to consider
    the technical manner in which the term "rates" is used and renders
    section 8.2 nugatory.   Neither argument is persuasive.    First, the
    contract does not indicate that the word "rates" is used in any
    technical sense.    In fact, FERC, itself, used the term "rates" as
    meaning the total costs for the gas transportation throughout the
    course of this controversy.      See, e.g., 60 FERC at ¶ 61,863
    (stating that "Tennessee filed a general rate case ... seeking to
    increase the rates for most of its services");       Tennessee Gas
    Pipeline Co., 
    59 FERC ¶ 61,175
     (1992) (stating that "the Commission
    rejected Tennessee Gas Pipeline Company's ... proposal to increase
    its rates for transportation services under Rate Schedule NET-EU
    "); Tennessee Gas Pipeline Co., 
    58 FERC ¶ 61,343
     (1992) (asserting
    that Tennessee "filed a limited rate case proposing to increase
    Rate Schedule NET-EU rates");   Tennessee Gas Pipeline Co., 
    58 FERC ¶ 61,160
     (1992) (stating that Tennessee "filed a tariff sheet
    reflecting increased rates for transportation service rendered
    under its Rate Schedule NET-EU") (emphasis added).
    17
    Second, this Court's construction of section 8.4 does not make
    section 8.2 meaningless. This Court's construction of the contract
    simply makes the authority of section 8.2 temporary.           The clear
    intent of the parties, as revealed in the contract, was that the
    specific rate guidelines set forth in section 8.2 would be viable
    only until Tennessee chose to revise the transportation rates in a
    manner consistent with the NGA.
    In this case, Tennessee has filed revisions to its NET-EU Rate
    Schedule to include charges for Segment U.          This Court does not
    determine whether those revisions are consistent with the NGA, nor
    has it been asked to do so.       However, a clear reading of the gas
    transportation contract at issue here reveals that the Flagg-
    Tennessee agreement unambiguously authorizes Tennessee to file such
    unilateral changes.    Any other reading would impermissibly negate
    portions of the contract.10
    III. Conclusion
    For   the   aforementioned   reasons,   this   Court   REVERSES   the
    decision of the Federal Energy Regulatory Commission.
    10
    Tennessee has presented numerous other arguments and
    counter-arguments in support of its position. In light of our
    construction of the contract here, we need not address those
    arguments.
    18