Barnard Const Co Inc v. City of Lubbock ( 2006 )


Menu:
  •                                                        United States Court of Appeals
    Fifth Circuit
    F I L E D
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT                   July 19, 2006
    _____________________
    Charles R. Fulbruge III
    No. 05-10582                        Clerk
    _____________________
    BARNARD CONSTRUCTION CO.,
    Plaintiff - Appellant,
    v.
    CITY OF LUBBOCK,
    Defendant - Appellee.
    _________________________________________________________________
    Appeal from the United States District Court
    for the Southern District of Texas
    No. 5:03-CV-269
    _________________________________________________________________
    Before JONES, Chief Judge, WIENER, and PRADO, Circuit Judges.
    PER CURIAM:*
    I
    Barnard Construction Co. (“Barnard”) sued the     City of
    Lubbock, Texas (“City”) for breach of contract in the Northern
    District of Texas.   The district court granted the City’s motion
    for summary judgment, and Barnard appeals.
    Barnard submitted the lowest bid for a pipeline construction
    contract to the City.    The City hired an independent engineering
    company to act as “Engineer” for the project.    The Engineer was
    *
    Pursuant to 5TH CIR. R. 47.5, the court has determined that
    this opinion should not be published and is not precedent except
    under the limited circumstances set forth in 5TH CIR. R. 47.5.4.
    1
    responsible for, inter alia, the bid form for the pipeline
    construction project.    The bid form included a line item for rock
    excavation, but only for one of the fifteen pipelines (Line A1),
    because the Engineer’s data suggested that rock excavation was
    needed only in the one pipeline.       Prior to the bidding process,
    the City expressly stated that the Engineer’s data was for
    informational purposes only, and that bidders had the opportunity
    to drill their own test holes.    The City also offered a question
    and answer session prior to bidding and made changes to the
    pipeline construction contract via addenda as a result of the
    question and answer session.    Barnard did not drill its own test
    holes.
    Barnard and the City entered into a written contract.      The
    City estimated that 410 cubic yards of rock would need excavating
    from Line A1; but whatever quantity of rock was excavated from
    Line A1, the City would pay Barnard at the unit price for which
    they bid ($200).    In performance of the contract, Barnard
    discovered lines other than Line A1 required rock excavation as
    well.    Barnard excavated rock from several lines other than Line
    A1.   After Barnard billed the City for all rock excavated, the
    City initially paid, but later offset payment for rock excavated
    outside of Line A1.    Barnard sued for breach of contract and on
    appeal argues for reversal of summary judgment.      First, Barnard
    argues that the City’s decision to pay for all rock excavated is
    a final, conclusive decision pursuant to the contract.      In
    2
    response, the City maintains it had communicated to Barnard
    before or at the time of payment that it might later offset
    payment for rock excavated outside of Line A1.1         In addition,
    Barnard argues that the contract is unambiguous in its terms
    requiring payment of all rock excavated, or alternatively, that
    it is ambiguous thereby warranting reversal of summary judgment.
    II
    We review an appeal from summary judgment de novo, applying
    the same standard as the district court.         Degan v. Ford Motor
    Co., 
    869 F.2d 889
    , 892 (5th Cir. 1989).         Summary judgment is
    appropriate if there is “no genuine issue as to any material fact
    and . . . the moving party is entitled to a judgment as a matter
    of law.”    FED. R. CIV. P. 56(c).       Because this suit is based on
    diversity jurisdiction, we apply Texas substantive law to
    determine whether the City was entitled to summary judgment.
    Fireman’s Fund Ins. Co. v. Murchison, 
    37 F.2d 204
    , 207 (5th Cir.
    1991).
    We review the interpretation of a contract, including the
    question of whether the contract is ambiguous, de novo.
    Constitution State Ins. Co. v. Iso-Tex Inc., 
    61 F.3d 405
    , 407
    (5th Cir. 1995) (citation omitted).
    III
    1
    Barnard contests the date this communication was made.
    3
    Barnard’s first argument, that the City’s decision to pay
    for all rock excavated is a final, conclusive decision pursuant
    to the contract, fails because the contract grants the City
    authority to make a final determination regarding the amount and
    quantity of work done by Barnard in excavating rock.     Paragraph
    47 of the General Conditions reads, in pertinent part:
    Any decision by the Owner’s Representative, or deemed denial
    by the Owner’s Representative, shall be final and conclusive
    in the absence of fraud.
    Paragraph 14 of the “General Conditions of the Agreement,”
    clearly states, in pertinent part:
    Unless otherwise specified, it is mutually agreed between
    the parties to this Agreement that the Owner’s
    Representative has the authority to review all work included
    herein. The Owner’s Representative has the authority to
    stop the work whenever such stoppage may be necessary to
    ensure the proper execution of the contract. The Owner’s
    Representative shall, in all cases, determine the amounts
    and quantities of the several kinds of work which are to be
    paid under the contract documents, and shall determine all
    questions in relation to said work and the construction
    thereof, and shall, in all cases, decide every question
    which may arise relative to the execution of this contract
    on the part of said Contractor.
    The record is clear that the City, via the Owner’s
    Representative, told Barnard that it was only considering
    Barnard’s request to pay for rock outside of Line A1.2    Barnard
    2
    While Barnard disputes the date on which the City informed
    Barnard that it would only consider the payment, the date is not
    dispositive; nor is the fact that the communication was made.
    The fact that Barnard was initially paid for the rock excavated
    outside of Line A1 is also irrelevant. The contract places
    authority over final decisions on the Owner’s Representative.
    After reviewing the City’s obligations under the contract, the
    City and the Owner’s Representative correctly determined that it
    4
    does not allege the City has committed fraud in making this
    decision.    The Owner’s Representative made a final decision as to
    the amount and quantity of excavated rock for which Barnard was
    to be paid when it determined under the contract that it need not
    pay for rock excavated outside of Line A1.
    IV
    Barnard’s second argument also fails.    First, it argues that
    the contract is unambiguous thereby requiring payment for rock
    excavated outside of Line A1.    Alternatively, Barnard argues the
    contract is ambiguous and therefore creates a genuine issue of
    material fact, requiring reversal and remand.      Whether a contract
    is ambiguous is a question of law for the court to decide.       Coker
    v. Coker, 
    650 S.W.2d 391
    , 394 (Tex. 1983).      If the written
    contract is worded such that it can be given a certain or
    definite legal meaning or interpretation, then it is not
    ambiguous and the court will construe the contract as a matter of
    law.    J.M. Davidson, Inc. v. Webster, 
    128 S.W.3d 223
    , 229 (Tex.
    2003); Coker, 650 S.W.2d at 393.       The court must give meaning to
    each of its provisions, in light of the circumstances surrounding
    the contract’s execution, excluding statements of the parties as
    to what they intended.    Davidson, 128 S.W.3d at 229; see also
    Universal C.I.T. Credit Corp. v. Daniel, 
    243 S.W.2d 154
    , 157
    (Tex. 1951).
    need not pay for rock excavated outside of Line A1.
    5
    First, Barnard argues that the following circumstances,
    which they contend were not taken into account by the district
    court, existing at the time of execution, support its
    interpretation that the contract is unambiguous: (1) the City
    provided all the forms for the bidding process and did not allow
    any alteration of the form or negotiation of the terms; (2) no
    bidder could bid on a unit price for rock anticipated to be
    encountered except on the blank provided for rock excavation on
    Line A1; and (3) no bidder could increase an amount for work
    performed on one line in order to “pad” or “cover” unpaid work
    performed on another line.   As the argument goes, because Barnard
    could not bid on rock outside of Line A1, it was irrelevant
    whether it took the opportunity to investigate the sub-surface
    conditions outside of Line A1.   However, Barnard neglects to
    consider that the City did allow for an opportunity for the
    bidders to ask questions, a process through which the contract
    could be changed and through which addenda were added to the
    contract.
    In the General Conditions section of the contract, under
    Paragraph 17, “Contractor’s Understanding,” it states:
    It is understood and agreed that the Contract has, by
    careful examination, satisfied itself as to the nature and
    location of the work, the confirmation of the ground, the
    character, quality and quantity of materials to be
    encountered, the character of equipment and facilities
    needed preliminary to and during the prosecution of the
    work, and the general and local conditions, and all other
    matters which in any way affect the work under the contract
    documents.
    6
    . . .
    Unless otherwise specified herein, all loss, expense, or
    damage to Contractor arising out of the nature of the work
    to be done, or from the action of the elements, or from any
    unforeseen circumstance and the prosecution of the work,
    shall be sustained and borne by the Contractor at its own
    cost and expense.
    Paragraph 17 of the General Conditions clearly places the risk of
    unforeseen circumstances on Barnard.     See I.O.I. Sys., Inc. v.
    City of Cleveland, 
    615 S.W.2d 786
    , 789 (Tex. App. 1980).     Barnard
    bore the risk in undertaking the project under the terms of the
    contract.
    Arguing that the City’s interpretation is unreasonable
    because it confers a windfall, Barnard maintains that Paragraph
    1.6 of Section 01020 of the contract unambiguously mandates
    payment for rock excavation, including “all of the extra cost of
    equipment and labor associated with the excavation of rock over
    and above the excavation of nonrock materials in a tunnel or
    trench.”     Section 01020 is titled, “Measurement and Payment.”
    Paragraph 1.6 appears in Part 1, titled, “General.”     The contract
    has both specific provisions, such as providing a line item for
    rock excavation only for Line A1, as well as general provisions,
    for example in Section 01020 in Paragraph 1.6 labeled “Rock
    Excavation,” in which it states, “[p]ayment will be made at the
    unit price bid for Rock Excavation.”     Where a contract “appears
    on the surface to be ambiguous . . . the apparent ambiguity may
    be resolved by the application of a well-settled rule of
    7
    construction, to wit: that if general terms appear in a contract,
    they will be overcome and controlled by specific language dealing
    with the same subject.”    City of San Antonio v. Heath & Stich,
    Inc., 
    567 S.W.2d 56
    , 60 (Tex. App. 1978).    The fact that the only
    place where a line item appears for rock excavation is for Line
    A1, a specific provision, suggests that the agreement between the
    parties was to pay for rock excavation only on Line A1.    This
    interpretation of the contract is further supported by the
    provision in Section 01020 entitled “Scope,” in which it states:
    The unit price bid on each item stated in the Bid Form shall
    include furnishing all labor, superintendence, machinery,
    materials, equipment and incidentals necessary to complete
    the various items of work in accordance with the plans and
    specification. Cost of work or materials shown on the plans
    and called for in the specifications for which no separate
    payment is made shall be included in the bid price on the
    various pay items.
    (emphasis added).    The contract clearly evinces a unit price for
    rock excavation only for the item Line A1.
    As an alternative argument, Barnard argues that the contract
    is ambiguous.    First, Barnard disagrees that the phrase “on each
    item stated in the Bid Form” in the “Scope” of Section 01020 is
    unambiguous.    It points to the fact that this is a unit price
    contract because the City had to make estimations for each line
    item, including an approximate amount of rock to be excavated.
    Barnard maintains that the phrase “on the project” at the end of
    Paragraph 38, “Quantities and Measurements,” found in the General
    8
    Conditions,3 refers to the project as a whole, not to rock
    excavation on Line A1.    As the argument goes, the City is
    therefore required to pay Barnard for all rock excavated on the
    whole project.    Barnard states, “[t]he term ‘project’ is not
    defined by the contract, but ‘Project Number’ is identified
    throughout the contract as ‘Project Number 293-6903 . . . .”
    Barnard’s invocation of Paragraph 38 is unavailing for the same
    reason its attempt to use Paragraph 1.6 of Section 01020 is.     The
    unit price bid blank found in Line A1 plainly evidences that the
    City expected drilling only on Line A1 and requested bids on rock
    excavation on that one line.4   Barnard ignores the fact that the
    City’s estimate of 410 cubic yards of rock was only for Line A1,
    and not for all of the lines in total.    We find that the contract
    between Barnard and the City is not ambiguous in its terms that
    3
    Paragraph 38 reads:
    Where the estimated quantities are shown, and only when same
    are expressly stated to be estimates, for the various
    classes of work to be done and material to be furnished
    under this contract, they are approximate and are to be used
    only as a basis for estimating the probable cost of the work
    and for comparing their bids offered for the work. In the
    event the amount of work to be done and materials to be
    furnished are expressly stated to be estimated, and only
    when same are expressly stated to be estimated, it is
    understood and agreed that the actual amount of work to be
    done and the materials to be furnished under this contract
    is the unit price method, payment shall be for the actual
    amount of work done and materials furnished on the project.
    4
    It bears repeating that Barnard had the opportunity to
    drill its own test holes prior to bidding. Instead, Barnard
    relied on the Engineer’s data.
    9
    rock excavation would be paid only for that performed on Line A1.
    V
    For the aforementioned reasons, we AFFIRM the district
    court’s grant of the City’s summary judgment motion.
    ENDRECORD
    10
    WIENER, Circuit Judge, dissenting:
    I respectfully dissent from the panel majority’s affirmance of
    the summary judgment for the City.     I do so because I am convinced
    that summary judgment was granted despite the existence of a
    genuine issue of material fact which cannot be resolved under the
    summary judgment record that was before the district court and is
    now before us.1
    None disputes that (1) a decision was made by the City on May
    22 to pay Barnard for all rock excavation, whether inside or
    outside Line A1 —— and indeed, the City did pay for it —— but (2)
    on June 17, the City reversed that decision and deducted from the
    next periodic payment the portion of the prior payment attributable
    to excavation outside Line A1.    The parties do vigorously contest,
    however, the correct way to classify the legal nature of the City’s
    May 22 decision and payment.    Barnard insists that under the terms
    of the construction contract, the May 22 decision was “final and
    conclusive,” making it binding on the City and not subject to
    subsequent unilateral reversal or change by the City. In contrast,
    the City pays little heed to this issue; and the panel majority
    opinion   demonstrates   an   unwillingness   even   to   recognize   the
    possibility that whether a particular decision by the City is
    “final and conclusive” is not simply whatever the City unilaterally
    1
    Summary judgment may be granted, of course, only if “there
    is no genuine issue as to any material fact ....” FED. R. CIV. P.
    56(c).
    11
    may say.2
    The contract states that “[a]ny decision by the [City’s]
    Representative ... shall be final and conclusive in the absence of
    fraud.”3      Although neither a definition nor an explanation of
    “final and conclusive” appears in the contract, the phrase is used
    in it.      For example, the contract gives the City’s representative
    authority to resolve “all questions of dispute or adjustment [that
    are    timely]     presented   by    the    Contractor”      to   the    City’s
    representative.          Elsewhere    in        the   contract,   the    City’s
    representative is given the authority and duty to, “in all cases,
    decide every question which may arise relative to the execution of
    this contract.”      Further, the contract deems each such decision to
    be    “conclusive   in   the   absence     of    written   objection    to   same
    delivered to Owner’s Representative within fifteen (15) calendar
    days of any decision or direction by [City’s] Representative.”
    Here, there were (1) an initial decision by the City on May 15
    to deny Barnard’s request to be paid for all rock excavation; (2)
    a timely objection by Barnard to that decision; (3) a decision
    favorable to Barnard made by the City on May 22, reversing its May
    15 decision and agreeing to pay Barnard for all excavation; and,
    finally (4) a third decision by the City, this one on June 17,
    purporting to reverse its own May 22 change of position from its
    2
    See footnote 2 in panel majority opinion, supra.
    3
    Emphasis added.
    12
    initial decision of May 15 —— a double flip-flop.
    I do not question that the City, acting through its designated
    representative, had the right vel non to make the May 22 decision;
    but given that decision, I do question how the City could then, on
    June 17, make a contrary decision on the same discrete issue.              I
    have found no principled way to interpret final and conclusive ——
    at least not without making this construction agreement a contract
    of adhesion —— to mean anything other than that an officially made,
    unqualified and unconditional decision by the City on any given
    issue, at any stage of the construction, is not merely final and
    conclusive, but is also just as unilaterally irreversible by, and
    binding on, the City as it is on Barnard.          As the contract is the
    law between the parties, contractual interpretation must provide
    the answer to the key question, “which of the City’s diametrically
    opposed, sequential decisions regarding rock excavation was the
    final   and   conclusive   one,   and    was   therefore   irrevocably   and
    irreversibly binding on both parties?”
    The summary judgment record makes clear, and none disputes,
    the relevant sequence of events.
    •    On May 15, the City made a “decision” to deny Barnard’s
    request to be paid for all rock excavation, not just that in
    Line A1.
    •    Barnard timely objected to that denial.
    •    On May 22, the City made a “decision” to reverse its May 15
    decision and to pay for all rock excavation (which it did).
    Thus, when we interpret the contract as a whole, with all relevant
    13
    provisions considered in pari materiae, this second “decision” by
    the City, the one on May 22 to reverse its May 15 decision and pay
    Barnard for all rock excavation, had to be “final and conclusive”
    —— unless, that is, the May 22 decision was expressly made subject
    to the putative condition subsequent, reserving to the City the
    power to reconsider and again reverse itself.          Unlike the May 15
    decision which was timely contested by Barnard pursuant to the
    contract, the May 22 decision was not contested or appealed by
    either party. Rather, the City just changed its mind weeks later.
    Crucially, then, for the May 22 decision not to be final and
    conclusive, and thus remain reversible by the City, this condition
    subsequent    would   have   to   have   been   made   by   the   City   and
    communicated to Barnard (1) in the May 22 decision, (2) before that
    decision was made, or (3) contemporaneously with that decision.
    Conversely, any subsequent attempt by the City to make its May 22
    commitment reversible would have been too late and thus ineffectual
    to render the May 22 decision anything other than final and
    conclusive.
    It follows that if, on the one hand, the question when that
    condition subsequent was made and communicated to Barnard is
    ultimately found to have been in the May 22 decision, or on or
    before May 22, then that decision would not have been “final and
    conclusive,” and the City would be entitled to change its mind, as
    it purported to do on June 17.     But if, on the other hand, the fact
    ultimately found is that communication of the reserved right to
    14
    change    its   mind   was    not    made    by   the   City   in,   before,   or
    contemporaneously with its May 22 decision, but only thereafter,
    the May 22 decision would be a “final and conclusive” decision on
    that one point, viz., to pay Barnard for all rock excavation.              This
    is why the answer to the question whether the May 22nd decision was
    final and conclusive and therefore not subject to a unilateral,
    post-hoc change of position by the City (as the City purported to
    do on June 17), is the crucial “genuine issue of material fact” on
    which this contract dispute turns.
    The panel majority appears to accept as a given the City’s
    representation to this court that “it had communicated to Barnard
    before or at the time of payment that it might later offset payment
    for rock excavated outside of Line A1.”             Yet the majority opinion
    also concedes that “Barnard contests the date this communication
    was made.”4     In the face of these irreconcilably opposed factual
    contentions of the parties, I cannot conclude, as did the district
    court and the panel majority, at least implicitly, that no genuine
    issue of material fact exists regarding the timing or sequence of
    the City’s reservation of that condition subsequent.                 Instead, I
    remain    convinced    that   this    material     fact   question    cannot   be
    resolved on the basis of the summary judgment record, either by the
    district court or by this court on de novo review.               Here’s why.
    In granting summary judgment, the district court stated as a
    4
    See footnote 1 in panel majority opinion, supra.
    15
    given that Barnard was “forewarned”5 —— shorthand for Barnard was
    informed of the condition subsequent by the City, before, in, or
    contemporaneously with its May 22 decision to pay Barnard for all
    rock excavation.    If that turns out to be how it happened, I would
    agree that the May 22 decision was conditional, preventing it from
    being deemed final and conclusive, and thus making it subject to
    reconsideration and change by the City.       I repeat for emphasis,
    however, that the district court’s conclusional statement that
    Barnard was “forewarned” simply is not supported by the summary
    judgment record, without which support that material fact issue
    remains genuinely contested and unresolved.
    By the district court’s own declaration, its determination
    that Barnard was “forewarned” by the City is based solely on one
    individual’s affidavit.     The problem is that the affidavit nowhere
    states, mentions, adverts to, or implies either (1) the precise
    calendar date of the City’s making and communicating the condition
    subsequent, or (2) the relative timing of that communication vis-à-
    vis the notification to Barnard of the City’s May 22 decision to
    pay for all rock excavation (itself a turn around from its May 15
    decision not to pay).     Whether Barnard was or was not “forewarned”
    remains an open genuinely contested issue of material fact.
    If this panel had reversed and remanded, the City as movant
    might well have been able to supply evidence of such date or timing
    5
    Emphasis mine.
    16
    to show that Barnard was indeed “forewarned”; and it might well be
    that Barnard would not have been able to controvert it.       But,
    without a summary judgment record sufficient to support the absence
    of a genuine issue of material fact, we should not affirm the
    summary judgment here being appealed.   This is why, with genuine
    respect for my colleagues of the panel majority and for the
    district court, I am compelled to dissent.
    17