Mabey v. Dixie Elec Mbrship ( 2007 )


Menu:
  •                                               No. 06-30774
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT        United States Court of Appeals
    Fifth Circuit
    FILED
    August 7, 2007
    No. 06-30774
    Charles R. Fulbruge III
    Clerk
    Ralph R. Mabey
    Appellee
    v.
    Dixie Electric Membership Corp.
    Appellant
    Appeal from the United States for the Middle District of Louisiana, Baton Rouge Division
    USDC No. 3:06-CV-11
    Before DENNIS, CLEMENT, and PRADO, Circuit Judges.
    PER CURIAM:*
    Plaintiff Mabey, as bankruptcy trustee for Cajun Electric Power Cooperative (“Cajun”), sued
    to recover $2,754,760.04 for 39 months of electricity received by defendant Dixie Electric
    Membership Corporation (“DEMCO”) but unmetered (and therefore not billed) by Cajun until a
    calibration error in a transformer at a power substation was discovered. The bankruptcy court granted
    Cajun’s motion for summary judgment and denied DEMCO’s motion; the district court affirmed
    without oral argument. After review of the record and the parties' arguments, we agree. The judgment
    of the district court is therefore AFFIRMED.
    I.
    Cajun is a nonprofit corporation that generates and transmits electricity to members of the
    cooperative as well as non-members. The cooperative's members, including DEMCO, are also
    *
    Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be published
    and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4.
    No. 06-30774
    non-profit electric distribution cooperatives, who sell and distribute power to the end consumer.
    DEMCO was required by a contract known as the 1976 Wholesale Power Supply Agreement
    (“WPSA”) to purchase from Cajun at wholesale all of its electric power requirements. The WPSA
    contains, inter alia, the following provisions:
    1. GENERAL. The Seller [Cajun] shall sell and deliver to the Member [DEMCO] and
    the Member shall purchase and receive from the Seller all electric power and energy
    which the Member shall require for the operation of the Member's system to the
    extent that the Seller shall have such power and energy and facilities available;
    provided, however, that the Member shall have the right to continue to purchase
    electric power and energy under any existing contract or contracts with a supplier
    other than the Seller during the remainder of the term thereof. If the Member
    continues to purchase electric power and energy under a contract or contracts with
    a supplier or suppliers other than the Seller, then the power and energy purchased
    under such contract or contracts shall be paid for by Seller for the account of the
    Member, and the Member shall be billed by Seller for such power and energy in
    accordance with the terms and conditions of [Article] 4 hereof.
    3. DELIVERY FACILITIES. The Seller shall be responsible for the facilities to
    deliver power and energy to the Point or Points of Connection [e.g., a power
    substation]. The Member shall be responsible for providing the facilities necessary to
    take and use the power and energy from the Point or Points of Connection. The
    parties shall provide and maintain, or cause to be provided and maintained, switching
    and protective equipment which may be reasonably necessary to protect the system
    of the other. Meters and metering equipment shall be furnished, maintained, and read,
    or caused to be furnished, maintained, and read, by the Seller.
    4. RATE. .... The Member shall pay the Seller for all electric power and energy
    furnished hereunder at the rates and on the terms and conditions set forth in Rate
    Schedule A....
    6. METER TESTING AND BILLING ADJUSTMENT. The Seller shall test and
    calibrate or cause to be tested and calibrated meters by comparison with accurate
    standards at intervals of twelve (12) months. The Seller shall also make or cause to
    be made special meter tests at any time at the Member's request. . . . The readings of
    any meter which shall have been disclosed by test to be inaccurate shall be corrected
    for the ninety (90) days previous to such test in accordance with the percentage of
    inaccuracy found by such test. If any meter shall fail to register for any period the
    Member and the Seller shall agree as to the amount of energy furnished during such
    period and the Seller shall render a bill therefor.
    In the 1990s, DEMCO built the Vignes power substation; although constructed by DEMCO
    alone, the facility was jointly owned by DEMCO and Cajun. Entergy, per a contractual arrangement
    with Cajun, provided electricity through the substation to DEMCO for further distribution. The
    station had two meters: one, a "high side" meter, belonged to Cajun and measured electricity coming
    No. 06-30774
    into the station from Entergy's lines; the other, a "low side" meter, belonged to DEMCO and
    measured the electricity DEMCO received for distribution.
    The station became operational in September 1996. At that time, it is undisputed that Cajun's
    meter was incorrectly calibrated, such that it registered only half of the electricity entering the
    substation. Cajun's resulting bill to DEMCO therefore covered only half of the electricity provided.
    DEMCO, however, had a properly calibrated meter and was charging its customers for the full
    amount of electricity provided. The problem continued for 39 months until, in December 1999, an
    Entergy employee discovered the problem.
    The meter itself was corrected the same day. Entergy and Cajun executed a plan under which
    Cajun reimbursed Entergy for Entergy's share of the unmetered electricity delivered to DEMCO. In
    January 2000, Cajun made written demand on DEMCO for the unmetered electricity received but not
    billed, a total value of $2,754,760.04. The following month, DEMCO tendered a check for
    $179,483.82, citing to a provision under the WPSA known as the "reach back" provision that,
    DEMCO claimed, limited its liability for excess electricity to the excess received during the 90 days
    prior to discovery of the error. Cajun refused tender; the company subsequently underwent a
    bankruptcy reorganization.
    On February 17, 2003, the bankruptcy trustee sued DEMCO as a part of an adversary
    proceeding related to Cajun's declaration of bankruptcy under Chapter 11. The trustee sought to
    recover the entirety of the $2,754,760.04, asserting three different bases for recovery: (1) breach of
    contract; (2) indemnity (for the payments Cajun made to Entergy for the power sold to DEMCO);
    and (3) unjust enrichment. The trustee moved for summary judgment on the issue of liability in
    January 2005; DEMCO responded with a motion to dismiss for failure to state a claim or, in the
    alternative, for summary judgment. In September 2005, the bankruptcy court granted summary
    judgment for Cajun. DEMCO appealed both the grant of Cajun's motion and the denial of its own;
    at the same time, it also asserted that an order of the Louisiana Public Service Commission barred
    Cajun from seeking reimbursement for billing errors over six months old. In June 2006, the district
    court, without oral argument, affirmed the judgment of the bankruptcy court. DEMCO timely
    appeals.
    II.
    We review the bankruptcy court's grant of a motion for summary judgment de novo. In re:
    Ark-La-Tex Timber Co., 
    482 F.3d 319
    , 328 (5th Cir. 2007). Summary judgment is appropriate where
    the record shows “that there is no genuine issue as to any material fact and that the moving party is
    No. 06-30774
    entitled to a judgment as a matter of law.” FED. R. CIV. P. 56(c); Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 322 (1986). Facts and inferences reasonably drawn from those facts should be taken in the light
    most favorable to the non-moving party. 
    Ark-La-Tex, 482 F.3d at 329
    (citing Duckett v. City of
    Cedar Park, 
    950 F.2d 272
    , 276 (5th Cir. 1992)). Where the non-moving party fails to establish “the
    existence of an element essential to that party's case, and on which that party will bear the burden of
    proof at trial,” no genuine issue of material fact can exist. 
    Celotex, 477 U.S. at 322-23
    . “If the moving
    party meets the initial burden of showing there is no genuine issue of material fact, the burden shifts
    to the non-moving party to produce evidence or designate specific facts showing the existence of a
    genuine issue for trial.” 
    Ark-La-Tex, 482 F.3d at 329
    (citing Allen v. Rapides Parish Sch. Bd., 
    204 F.3d 619
    , 621 (5th Cir. 2000)).
    A.
    As a preliminary matter, DEMCO asserts that Cajun lacks standing to bring suit, arguing that
    under the WPSA, DEMCO is required to compensate Cajun only for the power provided by Cajun.
    Since the surplus energy was in fact provided by Entergy, DEMCO argues, under the language of
    Articles 1 and 4 of the WPSA, Cajun has no contractual right to seek payment from DEMCO for
    electricity provided by Entergy.
    DEMCO's argument fails. Even assuming, arguendo, as DEMCO urges that its principal
    obligation is to Entergy as the actual supplier, Louisiana law unequivocally establishes that Cajun is
    legally subrogated to Entergy's claim because Cajun has already entirely reimbursed Entergy for that
    company's share of the unmetered electricity. See LA. CIV. CODE ANN. art. 1829(3) (“Subrogation
    takes place by operation of law: . . . [i]n favor of an obligor who pays a debt he owes with others or
    for others and who has recourse against those others as a result of the payment[.]”); see also State
    Farm Mut. Auto. Ins. Co. v. Berthelot, 
    732 So. 2d 1230
    , 1233 (La. 1999) (“Subrogation is a legal
    fiction whereby payment by a third person . . . extinguishes an obligation of the original creditor. The
    third person then steps into the shoes of the original creditor, acquiring the right to assert the actions
    and rights of the original creditor.”). To the extent DEMCO argues that the record is devoid of
    evidence that Cajun paid Entergy for the electricity sold to DEMCO, the record belies that assertion:
    Mr. Elmer, Cajun's vice president for operations, testified before the bankruptcy court that Cajun had
    determined that Entergy was owed payment for its share of the delivered electricity and that Cajun
    accordingly reimbursed Entergy. DEMCO offers no evidence to rebut that testimony. We therefore
    hold that Cajun has standing to bring this suit.
    B.
    No. 06-30774
    On appeal, DEMCO argues that LA. CIV. CODE art. 2002, which requires an obligee to
    undertake reasonable efforts to mitigate damage resulting from an obligor's failure to perform, bars
    Cajun’s recovery because Cajun has not mitigated its damages. We disagree.
    The Louisiana Supreme Court has held that “[the] duty to mitigate . . . damages is not
    applicable where the party whose duty it is primarily to perform a contract ‘has equal opportunity for
    performance and equal knowledge of the consequences of nonperformance.’” Unverzagt v. Young
    Builders, Inc., 
    215 So. 2d 823
    , 828 (La. 1968) (quoting Parker v. Harris Pine Mills, Inc., 
    291 P.2d 709
    , 717 (Or. 1955). Moreover,
    [t]he injured person need not make extraordinary efforts or do what is unreasonable
    or impracticable in his efforts to minimize damages; reasonable diligence and ordinary
    care are all that is required to allow full recovery of all damages caused by the
    defendant's wrongful activity. More completely stated, the consequences of an injury
    are recoverable where the injured party acts with such care and diligence as a man of
    ordinary prudence would under the circumstances, and his efforts to minimize
    damages are determined by the rules of common sense, good faith, and fair dealing.
    What constitutes reasonable care depends upon the circumstances of the particular
    case, taking into consideration time, knowledge, opportunity, and expense.
    
    Id. at 825-26.
    The record indicates that once Cajun was notified of the problem by Entergy personnel,
    it took immediate steps to correct the issue: the meter was corrected that same day. In other words,
    Cajun appears to have taken the proper steps to mitigate as soon as it was aware that the problem
    existed.
    DEMCO, furthermore, admits that it knew that it was receiving twice the electricity it was
    paying for but argues that Cajun knew about the problem before Entergy's report. DEMCO asserts
    that it notified Cajun of the error at the outset, relying on testimony from Mr. Lindsley, its Vice
    President of Engineering and Operations. Mr. Lindsley testified that he believed DEMCO, in the
    person of Mike Landry, DEMCO's Construction Supervisor at Vignes, informed Bob Bayley, Cajun's
    Manager of Engineering and Maintenance at Vignes, of the error. During his deposition, however,
    Mr. Landry denied ever having a conversation with Mr. Bayley about the meter reading error. In
    short, no one could personally testify as to who personally informed Mr. Bayley of the metering error.
    On the other hand, Mr. Elmer testified that had Cajun been informed of the error, Mr. Elmer would
    have taken immediate action to correct the problem. In fact, that is precisely what occurred when
    Entergy notified Cajun of the error. The record does not, therefore, establish that DEMCO ever
    notified Cajun of the error such that Cajun should have begun mitigating damages at an earlier point
    in time.
    No. 06-30774
    DEMCO also argues, however, that the error resulted from Cajun's breach of Article 6 of the
    WPSA, which places responsibility for testing and calibration of the high-side meters with Cajun.
    Because Cajun did not set the proper transformer ratio and because Cajun failed to detect the error
    during routine testing, DEMCO asserts, Cajun breached its duties under the WPSA and therefore
    DEMCO is not responsible for the unmetered electricity it received. DEMCO cites no authority for
    the proposition that Cajun's error in failing to detect the error at the time the station became active
    precludes later recovery for DEMCO's breach of the WPSA terms requiring it to pay for all energy
    furnished to it by Cajun. Even assuming, however, that the duty to mitigate reaches back to the time
    of the initial error, it is not clear that Cajun's actions were deficient. The record indicates that the
    company performed its standard yearly tests at the station. Mr. Elmer testified that to detect the
    calibration error, the entire substation would have needed to be taken out of service. Mr. Elmer also
    testified that the only reason Entergy was able to detect the error without a complete shut-down was
    because its employee was using a recently acquired piece of specialized equipment. Given that
    evidence, it cannot be said that Cajun failed to perform any of the routine checks required of it under
    the WPSA. Furthermore, to the extent DEMCO is arguing that such a shut-down should have been
    performed, Cajun is only required to mitigate as a reasonable person would have done in those
    circumstances. 
    Unverzagt, 215 So. 2d at 825
    . With no notice from DEMCO that there was an error
    in the meter’s calibration, a reasonable person would not have undertaken to shut the entire substation
    down to test that calibration. We therefore find no failure to mitigate on Cajun’s part such as would
    restrict its ability to recover from DEMCO.
    C.
    DEMCO next argues that the error in the meter is, under the terms of Article 6 of the WPSA,
    an “inaccuracy” such that DEMCO must only pay Cajun for the amount of energy furnished during
    the 90-day period prior to the discovery of the problem. Cajun responds by asserting that the problem
    is, instead, better described as a “failure to register,” such that the parties shall agree to the amount
    of electricity furnished over that period - here, 39 months - and the provider shall be reimbursed for
    that amount.
    The bankruptcy court phrased the question as one of determining which provision of Article
    6 applies to the facts of this case and held, as a matter of law, that the contract could not be read in
    such a way that would permit the 90-day reach back period to apply to the circumstances in this case.
    In other words, the bankruptcy court held that as a matter of law, this situation could only be
    construed as a failure to register because
    No. 06-30774
    [t]he 90 day reachback [sic] provision is coupled with the requirement that Cajun test
    and calibrate the meters at intervals of 12 months. The underlying assumption is that
    any inaccuracy would be revealed through testing. Also since it would be impossible
    to determine when a meter started to read inaccurately, the parties agreed that the
    billing adjustment would be limited to 90 days, thereby limiting loss by either party.
    The premise underlying the 90 day reachback [sic] provision, however, does not exist
    in the present case. Cajun performed the required testing. The incorrect calibration,
    however, was not susceptible to discovery through routine testing. The defect could
    be discovered only if the substation were shut done [sic] for some major repair or
    service. As no major repairs occurred during the time period at issue, the error was
    not located. As this type of error could not be located during the testing referred to
    in Paragraph 6, the entire underlying premise of the 90-day reachback [sic] period
    fails.
    We agree with the bankruptcy court’s reasoning. Under Louisiana law, where “the words of
    a contract are clear and explicit and lead to no absurd consequences, no further interpretation may
    be made in search of the parties' intent.” LA. CIV. CODE ANN. art. 2046. Where a word is susceptible
    to “different meanings [, it] must be interpreted as having the meaning that best conforms to the
    object in the contract.” LA. CIV. CODE ANN. art. 2048. Moreover, “[e]ach provision in a contract
    must be interpreted in light of the other provisions so that each is given the meaning suggested by the
    contract as a whole.” LA. CIV. CODE ANN. art. 2050.
    The bankruptcy court properly determined that the meanings of the two phrases were clear.
    It held that as a matter of law, the type of error at issue in this case, where the meter read the
    information it received accurately but was, in fact, receiving the wrong information because of the
    wrong current transformer ratio, could only be read as a failure to register. We agree that to hold
    otherwise would not comport with the clear intent of the parties as expressed in the contract, which
    couples the 90-day reach back provision with calibration and standard testing requirements. We
    therefore affirm the grant of summary judgment on this issue.
    D.
    Finally, DEMCO asserts that certain General Orders of the Louisiana Public Service
    Commission limit Cajun's ability to seek unpaid electricity to correct billing errors occurring more
    than six months before the discovery of the error. We disagree.
    In 1975, the Louisiana Public Service Commission adopted a General Order that provides as
    follows:
    This Commission is mindful that controversies have arisen between utilities
    companies in attempting to levy charges for services furnished in the distant past, but
    which were not billed when furnished. Frequently, the problem has been one of a
    No. 06-30774
    faulty meter or meter reading or company billing errors.
    The Commission feels that is [sic] should, and by this order, does formulate a
    guideline for institution of actions to collect sums allegedly due by reason of faulty
    meter or readings thereof, on Company billing errors, excepting fraud. . . .
    Accordingly, this Commission hereby orders that no rate on file with this Commission
    and billing made pursuant thereto shall be effective against a consumer where the
    utility company has permitted twelve months to elapse between the rendition of the
    service and accurate billing therefor, incidences of consumer fraud, such as meter
    tampering, excepted.
    The Order was amended in 1993 to reduce the time to six months.
    DEMCO argues that the Order is intended to protect it from having to reimburse Cajun for
    anything more than six months. We disagree, for the reasons given by both the bankruptcy court and
    district court: the operative language in the order applies to back billing against a consumer - that is,
    the end user, rather than intermediate utilities like DEMCO. In 2002, the Louisiana Supreme Court
    defined a "consumer" in the context of power utilities as "the ultimate user of the electricity[.]" Cleco
    Evangeline, LLC v. La. Tax Comm'n, 
    813 So. 2d 351
    , 355 (La. 2002). In doing so, the court
    specifically excluded from that definition "the wholesaler or toller that purchases the output from the
    . . . plant . . . because both act as middle persons simply transferring the electricity to others that
    ultimately consume the electricity." 
    Id. DEMCO fits
    the second definition precisely; as such, it cannot
    receive protection clearly given to "consumers" in the express language of the order.
    III.
    The bankruptcy court properly granted summary judgment in this case: by the terms of the
    WPSA, DEMCO is bound to reimburse Cajun for the electricity received but not metered over the
    39-month period before the error was corrected. Cajun has not failed to mitigate its damages, and the
    Louisiana Public Service Commission’s orders do not apply to limit the period over which damages
    may be recovered. The judgment is therefore AFFIRMED.
    AFFIRMED.