Weeks Marine Inc v. Fireman's Fund Ins ( 2003 )


Menu:
  •                                                          United States Court of Appeals
    Fifth Circuit
    F I L E D
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT                      July 25, 2003
    __________________________           Charles R. Fulbruge III
    Clerk
    No. 02-40825
    __________________________
    WEEKS MARINE, INC.,
    Plaintiff-Appellant,
    versus
    FIREMAN’S FUND INSURANCE COMPANY
    Defendant-Appellee.
    ___________________________________________________
    Appeal from the United States District Court
    for the Eastern District of Texas
    ___________________________________________________
    Before JOLLY, WIENER, and, BARKSDALE, Circuit Judges.
    WIENER, Circuit Judge:
    Plaintiff-Appellant Weeks Marine, Inc.(“Weeks”) appeals the
    district court’s order denying its motion for summary judgment and
    granting Defendant-Appellee Fireman’s Fund Insurance Company’s
    (“FFIC”) motion for summary judgment. We reverse and remand for
    entry of judgment in favor of Weeks.
    I. FACTS AND PROCEEDINGS
    This surety contract dispute arises from dredging work that
    Weeks Marine completed for now-bankrupt shipbuilder Friede Goldman
    Offshore Texas, L.P. (“Friede Goldman”). In April 1998, Petrodrill
    Construction, Inc. (“Petrodrill”) contracted with Friede Goldman
    (“the shipbuilding contract”) for the construction of a semi-
    submersible drilling vessel ( “Hull 1829”). In conjunction with the
    shipbuilding   contract,   FFIC   issued   an   $84   million   Labor   and
    Material Payment Bond (“the bond”) to Friede Goldman. Under the
    terms of the bond, FFIC as surety and Friede Goldman as principal
    are “held and firmly bound unto Petrodrill Construction” as owner
    and obligee, for “the use and benefits of claimants.” A “claimant”
    is defined in the bond as
    one having a direct contract with the Principal or with
    a Subcontractor of the Principal for labor, material, or
    both, used or reasonably required for use in the
    performance of the Contract, labor and material being
    construed to include that part of water, gas, power,
    light, heat, oil, gasoline, telephone service or rental
    of equipment directly applicable to the Contract.
    Friede Goldman began construction of Hull 1829 at its shipyard
    in Pascagoula, Mississippi but eventually elected to complete
    construction at another shipyard in Orange, Texas. The parties
    vigorously dispute the cause of the move: FFIC maintains that
    Friede Goldman merely wanted to “keep that [Texas] yard busy”;
    Weeks asserts that the move was “necessary,” but offers no further
    explanation.     It   is   undisputed,     however,   that   all   parties
    (including FFIC) expressly approved the move.         In fact, Petrodrill
    and Friede Goldman agreed to a $3 million increase in the contract
    price, and FFIC consented to a corresponding increase in the amount
    of the bond.   These modifications were memorialized in “Amendment
    No. 2” to the shipbuilding contract.
    In connection with the move, Friede Goldman subcontracted with
    Weeks to dredge a slip extension at the Texas shipyard.             Weeks
    2
    completed the dredging work and submitted an invoice to Friede
    Goldman in the amount of $654,671.          To date, Weeks has not been
    paid for the dredging work; Friede Goldman filed for Chapter 11
    bankruptcy protection several months after Weeks completed the
    dredging and is not a party to this suit.
    Shortly after Friede Goldman filed for bankruptcy protection,
    Weeks filed suit against FFIC, invoking diversity jurisdiction and
    alleging that FFIC, as surety, is liable for the “labor performed
    and materials furnished” to Friede Goldman in connection with its
    performance of the shipbuilding contract.           FFIC denied liability
    and the parties filed cross-motions for summary judgment. The
    district court granted FFIC’s motion, concluding that “making FFIC
    pay   Weeks   would   not   serve   the   Bond’s   overriding   purpose   of
    preventing the attachment of liens to Petrodrill’s new vessel.”
    Weeks now appeals the denial of its motion and the grant of FFIC’s
    motion.
    II. ANALYSIS
    A.    Standard of Review
    We review a grant of summary judgment de novo, applying the
    same standard as the district court.1              A motion for summary
    judgment is properly granted only if there is no genuine issue as
    1
    Morris v. Covan World Wide Moving, Inc., 
    144 F.3d 377
    , 380
    (5th Cir. 1998).
    3
    to any material fact.2     An issue is material if its resolution
    could affect the outcome of the action.3      In deciding whether a
    fact issue has been created, we view the facts and the inferences
    to be drawn therefrom in the light most favorable to the nonmoving
    party.4
    B.   Merits
    The sole issue presented in this appeal is whether Weeks’s
    dredging of a slip extension at Friede Goldman’s Orange shipyard is
    “labor” “used or reasonably required for use” in building Hull
    1829. The construction of an unambiguous surety agreement is a
    question of law.5     Surety agreements, like other contracts, are
    “interpreted to ascertain the obligations intended by the parties,
    gathered from the instrument as a whole.”6       The liability of a
    surety is determined by the language of the bond.7     When, as here,
    2
    Fed.R.Civ.P. 56(c); Celotex Corp. v. Catrett, 
    477 U.S. 317
    ,
    322 (1986).
    3
    Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248 (1986).
    4
    See Olabisiomotosho v. City of Houston, 
    185 F.3d 521
    , 525
    (5th Cir. 1999).
    5
    Augusta Court Co-Owners’ Assoc. v. Levin, Roth & Kasner,
    P.C., 
    971 S.W.2d 119
    , 123 (Tex. App.—Houston[14th Dist.] 1998, pet.
    denied).
    6
    G.H. Bass & Co. v. Dalsan Props.—Abilene, 
    885 S.W.2d 572
    ,
    576 (Tex. App.—Dallas 1994, no writ).
    7
    Augusta Court, 971 S.W.2d at 123; see also DEUTSCH, KERRIGAN &
    STILES, CONSTRUCTION INDUSTRY INSURANCE HANDBOOK § 16.2, at 267 (1991)
    (explaining that “[c]onventional bonds are private agreements
    governed by general principles applicable to any private or
    commercial contract” and noting that “[t]he rights and obligations
    4
    the surety agreement is related to another contract, the two
    instruments   must    be   read   together    to   determine      the   parties’
    intent.8
    With these general rules of contract interpretation in mind,
    our analysis begins with the written terms of both the shipbuilding
    contract and the payment bond.           The shipbuilding contract called
    for Friede Goldman to construct Hull 1829 for Petrodrill and
    perform all associated engineering, launching, and testing of the
    completed   vessel.    This     contract    defines    “materials”      as   “all
    material and supplies, including without limitation all machinery,
    equipment, outfittings and spare parts...to the extent that same
    have been appropriated to, or incorporated in, the Vessel.”                    The
    shipbuilding contract does not define “labor.”
    The bond prescribes the obligations of FFIC.               The bond states
    expressly   that   FFIC    is   liable     only   if   Friede    Goldman     fails
    “promptly [to] make payment to all claimants” “for all labor and
    material used or reasonably required for use in the performance of
    the Contract.”     As noted earlier, the term “claimants” is defined
    in the bond, which also defines “labor and material” to include
    “water, gas, power, light, heat, oil, gasoline, telephone service
    or rental of equipment directly applicable to the Contract.”
    of the parties to a conventional bond are thus determined by the
    terms of the bond”).
    8
    Arceneaux v. Price, 
    468 S.W.2d 473
    , 474 (Tex. App.—Austin
    1971, no writ).
    5
    Even though they arrive at widely varying interpretations,
    both   parties   assert   that   the   terms   of   these   agreements   are
    unambiguous.     FFIC argues that the dredging work is not covered
    under the bond because Weeks did not provide “materials” that were
    incorporated in the vessel but undertook a capital improvement to
    Friede Goldman’s shipyard.       Weeks agrees that the dredging was not
    “materials” as defined in the shipbuilding contract, but insists
    that the work was “labor” “used” in the construction of the vessel.
    Weeks asserts that it qualifies as a “claimant” under the bond
    because (1) it had a direct contract with Friede Goldman; (2) it
    provided “labor”; and (3) the labor was used in the performance of
    the shipbuilding contract.
    Our resolution of this contract dispute rests on the plain
    language of the bond and the uncontroverted record evidence.              We
    have seen that, under the bond, a “claimant” is “one having a
    direct contract with the Principal [Friede Goldman]...for labor,
    materials or both, used or reasonably required for use in the
    performance” of the shipbuilding contract. The parties do not
    dispute that Weeks had a direct contract with Friede Goldman or
    that Weeks provided “labor.”      Rather, FFIC contends that the labor
    Weeks provided was not used “in the performance of the contract.”
    For at least three reasons, we disagree.
    First, in support of summary judgment, Weeks submitted the
    affidavit of Friede Goldman officer John Haley who stated that
    “[t]he labor and materials provided by Weeks” were “required by
    6
    [Friede Goldman] for the performance and completion of Hull 1829.”
    FFIC submitted no contradictory evidence on this crucial point.9
    Second, FFIC itself acknowledged (in a letter to Weeks’s counsel
    denying the claim) that the dredging was “required in order to
    fulfill   [Friede   Goldman]’s      obligation    under   the    [Petrodrill]
    contract.”    Third,   and   most   importantly,    all   of    the       parties,
    including FFIC, expressly contemplated the move before it took
    place, explicitly acceded to it, and increased the purchase price
    and bond accordingly, as documented in Amendment No. 2.                    Whether
    the move was necessary, or even prudent, is irrelevant; it was
    unquestionably made “in performance of the contract.”
    Finding little support in the express terms of the bond, FFIC
    relies on cases arising under the Miller Act and analogous state
    statutes to    support   its   argument   that     dredging     is    a    capital
    improvement and is not encompassed by a standard labor and material
    bond. Under these cases, “material” includes “things which will be
    incorporated into the project itself, such as steel beams, brick,
    window frames, flooring and roofing.”10          “Materials” also includes
    products that are not ultimately integrated into the project, but
    9
    The evidence FFIC submitted in opposition to Week’s motion
    and in support of its own motion for summary judgment included
    copies of the shipbuilding contracts and payment bonds; a letter
    from FFIC adjuster Fred Applewhite instructing Weeks’s counsel on
    the procedure for filing claims; a letter and completed proof of
    claim from Weeks’s counsel to Applewhite; and the affidavit of
    Applewhite.
    10
    Sunbelt Pipe Corp. v. United States Fid. & Guar. Co., 
    785 F.2d 468
    , 470 (4th Cir. 1986).
    7
    that are “reasonably expected to be consumed, or substantially
    consumed,       in   the   performance         of    the    work.”11       Thus,   capital
    equipment,       including     items      that       can    be   removed    and    used   on
    subsequent projects, are not “materials”; only those consumable
    items     that    will     “have    no    utility      or    economic      value   to     the
    contractor after the completion of the work” are covered under
    statutory bonds as “materials.”12
    FFIC’s reliance on these authorities is misplaced for several
    reasons. First, and most importantly, Weeks is seeking payment for
    “labor,” not “materials.”               Weeks agrees that the pipes, tools, and
    heavy machinery used to dredge the slip are not “materials” covered
    by the bond; Weeks only seeks payment for labor, and then only
    labor that was “used or reasonably required for use” in Friede
    Goldman’s        performance       of    the       shipbuilding     contract.      Perhaps
    understandably, FFIC largely ignores this fundamental distinction.13
    Second, even if we were to accept FFIC’s capital-improvement
    argument, the competent summary judgment evidence reveals that
    Weeks’s dredging was not a capital improvement to Friede Goldman’s
    11
    
    Id.
    12
    
    Id.
    13
    FFIC asserts summarily that this “difference is irrelevant”
    and notes that “[w]hether the capital improvement was something
    that was created by labor . . . or a material, is irrelevant.” This
    argument is unavailing for two reasons. First, the bond itself does
    distinguish between labor and materials, listing each as a separate
    qualification (“labor, material, or both”). Second, all of the case
    law that FFIC cites involves equipment and other tangible materials
    or repairs to such equipment.
    8
    shipyard. In a supplemental affidavit, Friede Goldman officer John
    Haley stated that the slip at issue began to fill with silt within
    ten months following Weeks’s dredging.                Haley further stated that
    the slip will “likely have to be dredged again” if Friede Goldman
    undertakes a project of similar scale.                       Thus, Weeks’s summary
    judgment evidence reflects that the dredging to extend the existing
    slip was largely “consumed” during the construction of Hull 1829
    and would not likely last more than one year.14
    The only evidence that FFIC proffered in support of its
    argument is the affidavit of FFIC claims adjuster Fred Applewhite,
    who stated conclusionally that “[m]aking a slip at a shipyard
    bigger by constructing a slip extension...is a capital improvement
    to [Friede Goldman]’s yard and clearly of a nature as to be
    available for use...for all of [Friede Goldman]’s projects.”                      On
    close       examination,    however,   it       is   obvious    that    Applewhite’s
    affidavit is merely a reiteration of FFIC’s legal argument, i.e.,
    that        dredging   is   always     a    capital      improvement.      Notably,
    Applewhite’s affidavit is bereft of any explanation or reasoning as
    to how he reached this bald conclusion. It never even indicates
    that    he     personally    inspected         the   slip.    “[S]uch    conclusory,
    unsupported assertions are insufficient to defeat a motion for
    14
    See, e.g., Seligman v. Comm’r, 
    796 F.2d 116
    , 119 (5th Cir.
    1986) (noting that “one year rule of thumb” is “the prominent, if
    not predominant characteristic of a capital item” under Tax Code)
    (internal quotations omitted).
    9
    summary judgment.”15
    The litany of cases that FFIC cites in support of its argument
    is equally unpersuasive. All these cases stand for the undisputed
    proposition   that    the   cost    of    capital   equipment     that   is   not
    “substantially consumed” during performance of a contract is not
    recoverable under a typical Miller Act payment bond.16 As we
    explained,    these   cases   are    inapposite     for   three    alternative
    reasons: (1) A cause of action under the Miller                    Act is not
    congruent with a claim under the particular language of a tailor-
    made bond; (2) Weeks is seeking to recover only for labor, not
    materials; and (3) the dredging at issue was, according to the
    uncontradicted statement of Friede Goldman officer John Haley,
    “substantially consumed” in the construction of Hull 1829.                     We
    again emphasize that Weeks, unlike the suppliers in the cases that
    FFIC cites, does not seek payment for pipes, machinery, tools, or
    15
    Marshall v. E. Carroll Parish Hosp. Serv. Dist., 
    134 F.3d 319
    , 324 (5th Cir. 1998).
    16
    Sunbelt Pipe, 
    785 F.2d at 471
     (“Since Sunbelt had no
    reasonable expectation that the pipe would be consumed in the
    performance of the contract, it is not a supplier of material
    within the meaning of the statute or of the bond.”); Transamerica
    Premier Ins. Co. v. Ober, 
    894 F. Supp. 471
    , 483 (D.Me. 1995)(“It is
    clear under the statute and case law that subcontractors and
    suppliers may not recover under a Miller Act payment bond for
    losses sustained to ‘capital equipment,’” i.e., “any thing which
    may reasonably be expected to be removed by the contractor and used
    in subsequent jobs”) (internal quotations omitted); Ibex Indus. v.
    Coast Line Waterproofing, 
    563 F. Supp. 1142
    , 1145-46 (D.D.C. 1983)
    (“Plaintiff cannot recover costs under the Miller Act for equipment
    that was not ‘substantially consumed’ during the construction
    project.”).
    10
    equipment     of   any   kind.   The    uncontroverted   record   evidence
    conclusively establishes that Weeks provided labor that was “used”
    in performance of the shipbuilding contract.        The bond, drafted by
    FFIC, requires no more.
    III. Conclusion
    For the foregoing reasons, we reverse and remand for entry of
    judgment in favor of Weeks in the principal amount of $654,671,
    together with any and all appropriate ancillary items, such as pre-
    and post-judgment interest and costs, including attorney’s fees, if
    applicable.
    REVERSED and REMANDED with instructions.
    11