Fisk Electric Company v. Woodrow Wilson Const Co I ( 2016 )


Menu:
  •            IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    United States Court of Appeals
    No. 15-30684
    Fifth Circuit
    FILED
    March 8, 2016
    FISK ELECTRIC COMPANY,                                           Lyle W. Cayce
    Clerk
    Plaintiff - Appellee
    v.
    WOODROW WILSON CONSTRUCTION COMPANY, INCORPORATED,
    Defendant - Appellant
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    Before STEWART, Chief Judge, and OWEN, and COSTA, Circuit Judges.
    PER CURIAM:
    This appeal arises out of a subcontract dispute and resulting award of a
    statutory penalty and attorney’s fees pursuant to Louisiana’s Prompt Pay
    Statute, La. Stat. § 9:2784. The district court ruled on summary judgment that
    Woodrow Wilson Construction Company, a general contractor, did not have
    “reasonable cause” under the statute to withhold payment to its subcontractor,
    Fisk Electric Company. Because we find this determination to be at odds with
    Louisiana courts’ interpretation of reasonable cause under § 9:2784, we
    reverse.
    No. 15-30684
    I.
    Wilson hired Fisk to perform electrical work on a school construction
    project for the Orleans Parish School Board. The total subcontract was for
    $2,672,613.03, after inclusion of approved change orders. During construction,
    Wilson periodically submitted Applications of Payment to Orleans Parish
    School Board. These applications included requests for work done by Fisk,
    based on periodic invoices Fisk submitted to Wilson. The subcontract provided
    that Fisk would receive monthly payments, and that when Wilson received
    payments from the school board, it would make approved progress payments
    to Fisk within seven days.         As of April, 2012, Wilson had paid Fisk
    $2,117,215.86 under the subcontract; the remaining balance was $555,397.17.
    In June 2012, a Fisk subcontractor—Chubb—filed a sworn statement of
    claim worth over $82,000. Just a few weeks later, Fisk recorded its own sworn
    statement of claim against Wilson for $1,270,443.15.             This included the
    remaining subcontract balance, as well as charges for project changes and
    extended labor and job expenses. 1 Wilson did not make any payment to Fisk
    at this time, nor when it received additional payments from the school board
    over the next year and a half. During this period, Orleans Parish School Board
    retained certain funds for “punch list” items—work not conforming to the
    contract that must be completed for final payment—some of which was
    attributable to Fisk. In March 2013, Chubb filed suit in state court against
    Fisk and Wilson to collect on its claim. Three months later, Fisk paid all
    outstanding money owed to Chubb and Chubb dropped its suit, but did not
    execute a cancellation of the bond for removal of lien and its recorded
    1 According to both the district court and Wilson—and as Fisk does not seem to
    contest—Fisk had submitted only $145,829.70 in invoices that were unpaid at this date.
    2
    No. 15-30684
    statement of claim until December. Approximately three weeks later, Wilson
    paid Fisk $459,832.80.
    The subcontract between Wilson and Fisk includes an article on Final
    Payment that requires Fisk to provide Wilson with evidence that “all payrolls,
    bills for materials, equipment and services connected with the Work have been
    paid in full” and further requires that all work be turned over “free and clear
    of all claims, encumbrances, and liens for labor, services, equipment or
    materials.” It also notes that Wilson “may withhold said amounts, including
    such amounts as may be necessary with said claims, encumbrances, liens or
    attachments from monies otherwise” owed to Fisk.
    II.
    Fisk filed a separate federal suit against Wilson to enforce a lien based
    on its sworn statement of claim and to obtain damages. The district court
    granted partial summary judgment for Fisk, finding that Wilson owed
    $466,625.89 2: the $555,397.17 subcontract balance less $6,700 in punch list
    items and Chubb’s $82,071.28 lien claim.          The parties settled several
    outstanding issues, leaving only a claim for violation of Louisiana’s Prompt
    Payment Statute § 9:2784, which includes entitlement to reasonable attorney’s
    fees. The parties filed cross-motions for summary judgment. Fisk asserted that
    Wilson owed it a penalty for late payment plus attorney’s fees; Wilson
    contended that it had “reasonable cause” to not pay and was entitled to
    attorney’s fees for defending against Fisk’s non-meritorious claim.
    The district court entered summary judgment in favor of Fisk. The court
    noted that it did not have enough information “to determine, with specificity,
    the entirety of the exact amounts and chronology of the work completed by
    2 The amount the court determined Wilson owed did not take into account the
    $459,832.80 Wilson paid Fisk 14 days prior to the summary judgment ruling.
    3
    No. 15-30684
    Plaintiff, the exact dates on which Defendant sought and received payment, in
    full . . . for work completed by Plaintiff, or the exact dollar amounts and dates
    on which Plaintiff affirmatively sought payment from Defendant.”          But it
    nonetheless concluded that, based on its prior summary judgment ruling and
    construing all additional facts in favor of Wilson, Wilson lacked “reasonable
    cause for not paying Plaintiff in the amounts and for the time periods listed
    below.” It then provided three overlapping time periods and equations to
    determine the amount that was unreasonably withheld. These formulas called
    for multiple deductions from the outstanding subcontract balance, including
    the amounts of Chubb’s lien and any premiums Wilson incurred to obtain a
    bond for the lien, punch list items, a counter-claim Wilson made against Fisk,
    and certain retainage. The court ordered Wilson to pay the statutory penalty
    rate—one half of one percent of the amount owed for each day the payment
    was late—with the total not to exceed the statutory maximum 15% of the
    outstanding balance.
    The parties agree that, using the formulas devised by the district court,
    Wilson did not owe anything for the first or second time periods, but owed
    $69,210.42 for the third time period. The district court later approved and
    entered the magistrate judge’s Report and Recommendation awarding
    $55,920.00 in attorney’s fees for work collecting the balance due under the
    subcontract. Wilson appeals both the summary judgment and the attorney’s
    fees award, which it argues is unreasonable even if it violated the prompt
    payment statute because it compensates work on claims outside the scope of
    collecting the subcontract balance.
    III.
    Wilson asserts that the district court erred in finding Wilson liable under
    Louisiana’s Prompt Payment Statute because it had reasonable cause to
    4
    No. 15-30684
    withhold payment.       It contends that the district court acknowledged
    reasonable cause in its penalty formulas, as it deducted numerous amounts
    that Wilson reasonably did not pay.
    As a federal court considering a question of Louisiana law, we look first
    to decisions of the state supreme court; “[i]n the absence of a final decision by
    the Louisiana Supreme Court, we must make an Erie guess and determine, in
    our best judgment, how that court would resolve the issue if presented with
    the same case.” In re Katrina Canal Breaches Litig., 
    495 F.3d 191
    , 206 (5th
    Cir. 2007).   Under Louisiana’s “civilian methodology,” we first examine
    primary sources of law, like the constitution and statutory text, and
    Louisiana’s intermediate courts serve as “secondary law” to guide our
    interpretation. 
    Id. (internal citations
    and quotations omitted).
    Louisiana’s Prompt Payment Statute provides in relevant part:
    A. When a contractor receives any payment from the owner for
    improvements to an immovable . . . the contractor shall promptly
    pay such monies received to each subcontractor and supplier in
    proportion to the percentage of work completed . . .
    ...
    C. If the contractor or subcontractor without reasonable cause fails
    to make any payment to his subcontractors and suppliers within
    fourteen consecutive days of the receipt of payment from the owner
    for improvements to an immovable, the contractor or
    subcontractor shall pay to the subcontractors and suppliers, in
    addition to the payment, a penalty in the amount of one-half of one
    percent of the amount due, per day, from the expiration of the
    period allowed herein for payment after the receipt of payment
    from the owner. The total penalty shall not exceed fifteen percent
    of the outstanding balance due. In addition, the contractor or
    subcontractor shall be liable for reasonable attorney fees for the
    collection of the payments due the subcontractors and suppliers.
    However, any claim which the court finds to be without merit shall
    subject the claimant to all reasonable costs and attorney fees for
    the defense against such claim.
    5
    No. 15-30684
    La. Stat. § 9:2784(A), (C) (emphasis added). The Supreme Court of Louisiana
    has not considered the meaning of “reasonable cause” within this statute. It
    has, however, emphasized that statutes providing for punitive penalties are
    rare, and as such, “when a statute does authorize the imposition of a penalty,
    it is to be strictly construed.” Int’l Harvester Credit Corp. v. Seale, 
    518 So. 2d 1039
    , 1041 (La. 1988).
    A few Louisiana intermediate courts have directly considered the
    meaning of reasonable cause to not make payment, and one involved a
    situation similar to this case.   In Contractors Supply & EQ-Orleans v. J.
    Caldarera & Co., 
    734 So. 2d 755
    (La. App. 5 Cir. 1999), a subcontractor had
    submitted a demand letter for payment seeking $20,668.40, whereas the
    contractor believed it owed only $2,911.00. 
    Id. at 757.
    The court ultimately
    determined that the contractor owed $6,479.93, but denied the subcontractor’s
    claim for a late payment penalty and attorney’s fees. 
    Id. at 761.
    The appellate
    court upheld the trial court’s determination that “the amount demanded by the
    plaintiff was out of proportion to the amount owed, therefore the defendant
    had reasonable cause to withhold payments.” 
    Id. at 759.
    Thus the contractor
    was not liable for a penalty or attorney’s fees under the prompt payment
    statute. 
    Id. at 761.
          Likewise in this case, Fisk’s sworn statement of claim asserted that
    Wilson owed over two times the amount remaining on the subcontract; the
    amount actually owed was even more disproportionate because the district
    court found that Wilson need not pay almost $90,000 of the subcontract. This
    “out of proportion” demand alone may be enough under Louisiana law to
    constitute reasonable cause not to pay. But the amount of Fisk’s demand was
    not the only outstanding dispute. Under the subcontract terms, Wilson could
    withhold the value of Chubb’s lien. This lien was not fully resolved until a few
    6
    No. 15-30684
    weeks before Wilson made its January 2014 payment. And other smaller
    amounts—punch list items, retainage, the value of Wilson’s counterclaim—
    that the district court deducted from its penalty calculation were all reasonably
    disputed. The district court could not discern the total value of these claims,
    even with the many stipulations and memoranda that the parties provided.
    The combined value of these items was so significant that for two of the district
    court’s three outlined time periods, Wilson did not actually owe Fisk any
    money. This substantial dispute about the amount owed makes this case
    unlike Unis v. JTS Constructors/Managers, Inc., 
    541 So. 2d 278
    (La. App. 3
    Cir. 1989), in which a Louisiana appellate court found there was no reason for
    a contractor to withhold payment because there was no dispute about the
    amount owed under a given contract. 
    Id. at 282.
          Although the Supreme Court of Louisiana has not opined on the meaning
    of “reasonable cause” under the prompt payment statute, its ruling in an
    analogous area of law leads us to believe it would follow the Calderara
    approach. When considering penalties for untimely payment of claims by
    insurance companies, it has held that “especially when there is a reasonable
    and legitimate question as to the extent and causation of a claim, bad faith
    should not be inferred from an insurer’s failure to pay within the statutory
    time limits when such reasonable doubt exists. . . .” Guillory v. Lee, 
    16 So. 3d 1104
    , 1127 (La. 2009) (emphasis added); see La. Stat. § 22:1892 (requiring that
    when an insurer does not make payment within thirty days of written proofs
    and demand, and “such failure is found to be arbitrary, capricious, or without
    probable cause, [this failure] shall subject the insurer to a penalty, in addition
    to the amount of the loss . . .”).
    Given these principles and the holding in Contractors Supply & EQ-
    Orleans v. J. Caldarera & Co., we conclude that a Louisiana court would find
    7
    No. 15-30684
    that Wilson had reasonable cause to withhold payment. Because Wilson had
    reasonable cause, Fisk is not entitled to attorney’s fees. We therefore need not
    reach whether the fee amount was reasonable.
    *     *     *
    We REVERSE the district court’s summary judgment in favor of Fisk
    and VACATE the award of attorney’s fees; we also REVERSE the denial of
    Wilson’s motion for summary judgment and RENDER summary judgment in
    its favor. The case is REMANDED for further proceedings consistent with this
    opinion.
    8