St. Paul Travelers Insurance v. Century Asphalt Materials, LLC (In Re Contractor Technology, Ltd.) , 529 F.3d 313 ( 2008 )


Menu:
  •                                  REVISED JUNE 3, 2008
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    May 23, 2008
    No. 07-20483
    Charles R. Fulbruge III
    Clerk
    In The Matter Of: CONTRACTOR TECHNOLOGY, LTD
    Debtor
    ---------------------------------------------------------------------------------
    ST. PAUL TRAVELERS INSURANCE COMPANY
    Appellee
    v.
    CENTURY ASPHALT MATERIALS, LLC
    Appellant
    Appeal from the United States District Court
    for the Southern District of Texas
    Before HIGGINBOTHAM, BENAVIDES, and DENNIS, Circuit Judges.
    PATRICK E. HIGGINBOTHAM, Circuit Judge:
    Century Asphalt Materials, LLC, sold construction materials to Contractor
    Technology, Ltd., a general contractor for the State of Texas.                             Contractor
    Technology paid Century but before the checks cleared, the contractor filed for
    bankruptcy. The bankruptcy court held that Contractor Technology’s payments
    to Century were unauthorized post-petition transfers and ordered that Century
    No. 07-20483
    return the payments to the Trustee. On summary judgment, the court, after
    “returning” the parties to the positions they were in when the checks were
    delivered, held that Century had with this reset of time perfected its bond claims
    for the materials. Century had sent the claims to St. Paul Travelers Insurance
    Company, Contractor Technology’s surety, after it had returned the payments
    to the Trustee. St. Paul appealed to the district court, which reversed. Century
    appealed.
    I
    In March 2005, Century delivered materials to Contractor Technology, a
    contractor involved in various public works improvement projects for the State
    of Texas. Contractor Technology had retained St. Paul as a surety to provide
    payment bonds for its suppliers. As payment for the materials, Contractor
    Technology issued its first check for $33,454.75 to Century on April 30, 2005,
    and its second check for $84,104.64 on May 10, 2005. These checks cleared on
    May 16 and 19, 2005, but not before Contractor Technology filed for bankruptcy
    on May 13, 2005. Contractor Technology’s Chapter 7 Trustee filed an adversary
    proceeding against Century on November 8, 2005, urging that the checks were
    unauthorized post-petition transfers.1 Realizing that under the bankruptcy
    proceeding it might have to relinquish the payments that it had received from
    Contractor Technologies, on December 8, 2005, Century filed a third-party
    complaint against St. Paul in bankruptcy court.         On July 17, 2006, the
    bankruptcy court avoided and rescinded Contractor Technology’s transfers to
    Century, as Century had feared it would do. The Trustee and Century disputed
    the actual amount due and settled at $115,000. On August 15, 2006, the
    bankruptcy court issued an Order Approving Compromise and Settlement
    1
    See 11 U.S.C. § 549.
    2
    No. 07-20483
    requiring Century to pay $84,104.64 and $30,895.36 to the Trustee within ten
    days of the order. The order stated,
    On the date that the First Settlement Payment is delivered to the
    Trustee (the “First Repayment Date”), the parties are returned to
    their respective positions as they existed on May 10, 2005 with
    respect to the obligations owed by the Debtor to Century Asphalt
    that were originally satisfied. . . . Any and all applicable deadlines
    existing on May 10, 2005 with respect to the claim satisfied by the
    delivery of . . . [the first check] shall continue to run from the First
    Repayment Date.
    The order contained identical language for the second check, replacing
    “First Repayment Date” with “Second Repayment Date” and “May 10, 2005” with
    April 30, 2005.” Having returned the payments it originally received, Century
    then attempted to obtain payment for the materials by making a bond claim. On
    August 28, 2006, Century sent notice and a sworn statement of account to St.
    Paul pursuant to the procedures required for bond claims under Texas
    Government Code Chapter 2253, also known as the McGregor Act.2
    St. Paul filed a motion for summary judgment with the bankruptcy court,
    arguing, inter alia, that Century had failed to meet the Act’s notice requirements
    with respect to timing. Section 2253.041 of the Act, “Notice Required for Claim
    for Payment for Labor or Material,” provides in relevant part,
    (a) To recover in a suit under Section 2253.073 on a payment bond
    for a claim for payment for public work labor performed or public
    work material delivered, a payment bond beneficiary must mail to
    the prime contractor and the surety written notice of the claim.
    (b) The notice must be mailed on or before the 15th day of the third
    month after each month in which any of the claimed labor was
    performed or any of the claimed material was delivered.
    2
    See, e.g., Suretec Ins. Co. v. Myrex Indus., 
    232 S.W.3d 811
    , 813 (Tex. App.–Beaumont
    2007, pet. filed) (describing Chapter 2253 of the Texas Government Code as “the McGregor
    Act”).
    3
    No. 07-20483
    (c) The notice must be accompanied by a sworn statement of account
    that states in substance:
    (1) the amount claimed is just and correct; and
    (2) all just and lawful offsets, payments, and credits known to the
    affiant have been allowed.3
    St. Paul maintained that because Century delivered the materials in March
    2005, under the Act it was required to provide notice of a bond claim on or before
    June 15, 2005, the fifteenth day of the third month after the materials were
    delivered, and that it failed to meet this deadline. St. Paul further argued that
    Century had failed to meet several of the Act’s substantive notice requirements,4
    and that Century could not claim the broad protections contained within the Act
    for material suppliers to state contractors, as it was requesting funds that had
    been transferred in bankruptcy, not reimbursement for defaulted materials
    payments. Finally, it asserted that the bond claim failed because “Century
    Asphalt has already been paid and therefore, it cannot satisfy the Texas
    Government Code for recovery on a bond claim.” In other words, it urged that
    bond claims under the McGregor Act are for defaulted payments, not payments
    made and later rescinded in bankruptcy.
    Century filed a cross motion for summary judgment, asserting that it had
    met all of the Act’s substantive requirements. Its central argument was that the
    bankruptcy court’s avoidance of the payments brought the parties back to their
    original positions, making Century an unpaid supplier subject to the Act’s broad
    protections. Century maintained that its bond notice of August 28, 2006, was
    3
    Tex. Gov’t Code § 2253.041.
    4
    It urged that “Century Asphalt failed to provide notice, a sworn statement of account
    and failed to satisfy all of the requirements to properly perfect its bond claim in anyway [sic]
    under the Texas Government Code. It also failed to identify the specific payment bond and
    project for which it is seeking recovery.”
    4
    No. 07-20483
    timely because the bankruptcy court’s order provided that applicable deadlines
    for claims originally satisfied by delivery of the checks would run from the dates
    on which Century had to return the money to the Trustee – the repayment dates.
    In other words, pursuant to the court’s order the repayment dates became the
    dates when Contractor Technology “defaulted” on its payments to Century.
    Because Century “furnished the bond notice within three days of the repayment
    date,” Century argued, it furnished bond notice well within Chapter 2253’s
    three-month window. Century also argued that Texas courts have held that
    Chapter 2253 should be liberally construed, that the Act only requires
    “substantial compliance,” and that the Texas legislature intended for the Act to
    protect material suppliers like Century. In a footnote, Century urged the court
    to apply equitable tolling because “Chapter 2253’s limitations would effectively
    bar Century Asphalt, through no fault of its own, from seeking to recover on the
    payment bonds . . . .”
    The bankruptcy court denied St. Paul’s motion for summary judgment and
    granted Century’s cross motion. Its holding rested on two central points of
    reasoning. First, the court held that “in determining a bond beneficiary’s
    compliance with the notice requirements of Chapter 2253, ‘substantial
    compliance’ is considered all that is necessary to properly perfect a claim.” The
    court determined that because it avoided now-bankrupt Contractor Technology’s
    payments to Century for materials, Contractor Technology’s payments were
    payments that “never occurred.” Therefore, the “repayment dates” – the dates
    on which the court ordered Century to return the payments to the trustee –
    became the dates on which Contractor Technology failed to pay Century for its
    materials. Under the bankruptcy court’s reasoning, Century need only have
    provided notice of a bond claim to St. Paul on the fifteenth day of the third
    month after Century returned the funds to the Trustee. The bankruptcy court
    concluded that it would “consider Century as never having been paid for its
    5
    No. 07-20483
    public work material provided” and that, as a result, “Century falls within the
    bounds of requesting payment from the surety as provided” by Chapter 2253.
    The bankruptcy court’s second line of reasoning rested on equitable tolling.
    It observed that
    the present case may . . . be differentiated [from traditional
    equitable tolling] in that equitable tolling . . . deals with the tolling
    of statutes of limitation. The notice requirement under the
    McGregor Act is not a statute of limitation. It is a statutorily
    defined condition precedent to filing a bond claim.
    The bankruptcy court held that although Chapter 2253’s notice requirement is
    not a statute of limitation, it could apply equitable tolling to further the
    McGregor Act’s purpose of protecting entities that provide materials and labor
    to Texas public works projects. It also concluded that equitable tolling was
    applicable because “[t]he present case certainly falls within the category of
    ‘extraordinary circumstances’ making it impossible for plaintiff to timely assert
    his claim.”
    St. Paul appealed, and the district court reversed, remanding to the
    bankruptcy court for entry of summary judgment in St. Paul’s favor.5 The
    district court held that
    [e]ven if the effect of Century Asphalt’s settlement with the Trustee
    was to return Century Asphalt to the position it would have held in
    May 2005 if the Debtor (Contractor Technology) had not paid for the
    material Century Asphalt provided, Century Asphalt would still be
    required under § 2253.041 to provide written notice “on or before the
    15th day of the third month after . . . any of the claimed material
    was delivered.” The parties have not cited and this Court has not
    located any legal authority that enables an avoidance under the
    5
    Because the court reversed and remanded with a specific order to enter summary
    judgment in favor of St. Paul – a ministerial task – we have jurisdiction. See In re Caddo
    Parish-Villas S., Ltd., 
    174 F.3d 624
    , 628 (5th Cir. 1999).
    6
    No. 07-20483
    Bankruptcy Code of a transfer to excuse compliance with state
    statutory prerequisites such as the § 2253.041 notice requirement.6
    The district court also held that equitable tolling did not permit the
    bankruptcy court to extend the notice deadline for the bond claim, as the notice
    requirement is not a statute of limitations, and equitable tolling applies only “‘to
    the affirmative defense of limitations.’”7 Furthermore, the court held, even if it
    could apply the doctrine, it could not apply it to the extent that it overruled
    legislative choices, and Century Asphalt failed to act diligently in providing
    notice. Century knew no later than November 2005, when it received notice of
    the adversary bankruptcy proceeding, that the payments were likely to be
    avoided.
    Century appeals from the district court’s order, urging that because
    Chapter 2253 is remedial and aims to protect material suppliers like Century,
    the district court should have liberally construed the statute. The avoided
    transfer brought the parties back to their position prior to receiving the
    payments, it urges, and because Century provided notice of its bond claim three
    days after the due date for repayments ordered by the court, it essentially
    provided notice on May 13, 2005 – three days after the first materials were
    delivered and “well before the June 15, 2005 notice date.” Furthermore, Century
    argues, the district court’s strict construction of the statute results in “absolute
    protection for the surety,” contrary to the statute’s purpose of protecting
    suppliers of material and labor, and leads to absurd results. “Under the district
    court’s holding,” it maintains, “the only way a supplier could protect its statutory
    rights under Chapter 2253 would be to furnish bond notices on every single
    6
    In re St. Paul Fire and Marine Ins. Co. v. Century Asphalt Materials, LLC, No.
    05-3808, 
    2007 WL 1468549
    at *2 (S.D. Tex. May 18, 2007) (internal citation omitted).
    7
    
    Id. at *3
    (quoting Heart Hosp. IV, L.P. v. King, 
    116 S.W.3d 831
    , 836 (Tex. App.–
    Austin 2003, rhr’g overruled, rev. denied)).
    7
    No. 07-20483
    project, every single time it furnished material, regardless of whether it had
    already been paid for the material . . . .” Finally, Century urges that the district
    court erred in holding that the doctrine of equitable tolling does not apply and
    improperly construed Chapter 2253’s notice requirement as a jurisdictional
    prerequisite.
    St. Paul disagrees, arguing that construing Chapter 2253 to permit late
    notice would write an exemption into the statute and that equitable tolling
    applies only to statutes of limitations. Its central argument lies in the timing.
    It maintains,
    It is undisputed that the materials for which Century Asphalt seeks
    recovery were delivered in March 2005. Given this undisputed fact,
    notice under Chapter 2253 of the Texas Government Code for such
    labor or materials was due by June 15, 2005. It is also undisputed
    that Century Asphalt did not provide notice of any payment bond
    claim by the date. . . . Therefore, Century Asphalt did not perfect a
    payment bond claim under the provisions of the Texas Government
    Code.
    We first address the timing arguments and then equitable tolling.
    II
    We review the district court’s reversal of the bankruptcy court’s grant of
    summary judgment de novo.8 We are persuaded that no matter how liberally we
    construe Chapter 2253,9 it does not contain a notice exemption for bond claims
    8
    See In re Robertson, 
    203 F.3d 855
    , 858 (5th Cir. 2000).
    9
    See, e.g., Redland Ins. Co. v. Sw. Stainless, L.P., 
    181 S.W.3d 509
    , 512 (Tex. App. –
    Fort Worth 2005, no pet.) (quoting Featherlite Bldg. Prods. Corp. v. Constructors Unlimited,
    Inc., 
    714 S.W.2d 68
    , 69 (Tex. App.–Houston 1986, writ ref’d n.r.e.)) (“Because the McGregor
    Act is remedial in nature, ‘it is to be given the most comprehensive and liberal construction
    possible.’”); S.A. Maxwell Co. v. R.C. Small & Assoc., Inc., 
    873 S.W.2d 447
    , 454 (Tex. App.–
    Dallas 1994, writ denied) (holding that “[t]he notice requirements of the McGregor Act are to
    be liberally construed”); City of LaPorte v. Taylor, 
    836 S.W.2d 829
    , 832 (Tex. App. – Houston
    1992, no writ) (holding that Chapter 2253’s predecessor, Article 5160, is “highly remedial in
    nature and courts should construe it liberally to accomplish its purposes”); Baxter Constr. Co.
    v. Hou-Tex Prods., Inc., 
    718 S.W.2d 355
    , 358 (Tex. App.–Houston 1986, writ ref’d n.r.e.)
    8
    No. 07-20483
    on payments that were avoided in bankruptcy. Even if the bankruptcy court’s
    order had the effect of reverting the parties to their original positions, as if
    Contractor Technologies had never paid Century, Chapter 2253’s notice
    provisions are grounded in the date of delivery, not in the date of payment or
    failure to pay. Chapter 2253 requires that the notice “be mailed on or before the
    15th day of the third month after each month in which any of the claimed labor
    was performed or any of the claimed material was delivered.”10 The Texas Court
    of Appeals has observed,
    In 1959, the McGregor Act was rewritten to provide that the notice
    limitations period begins in ‘each month in which the labor was
    done or performed, in whole or in part, or material was delivered, in
    whole or in part.’ Although the statute was again amended in 1989,
    this language defining when the notice limitations period begins
    remained unchanged. Beginning the notice limitations period in
    each month in which even a partial delivery occurs shows a
    legislative intent to continue the case law interpretation that the
    actual physical delivery is controlling in determining the notice
    limitations period.11
    Century does not argue that the bankruptcy court’s avoidance of the
    transfer reverted the parties to a position wherein the materials were somehow
    “undelivered.” Century delivered the materials in March 2005, and it did not
    provide notice on the bond claim by June 15, 2005, as required by the terms of
    the statute. The bankruptcy court’s avoidance of the payments does not change
    these facts.
    (quoting United Benefit Fire Ins. Co. v. Metro. Plumbing Co., 
    363 S.W.2d 843
    , 847
    (Tex.Civ.App.– El Paso 1963, no writ)) (holding that Article 5160 should be “‘accorded the most
    comprehensive and liberal construction of which it is susceptible in order to accomplish the
    legislative purpose’”); Gen. Elec. Supply Co. v. Epco Constructors, Inc., 
    332 F. Supp. 112
    , 114
    (S.D. Tex. 1971) (holding that Article 5160’s “notice requirements . . . are to be liberally
    construed”).
    10
    Tex. Gov’t Code § 2253.041(b) (emphasis added).
    11
    S.A. Maxwell 
    Co., 873 S.W.2d at 453
    (internal citations omitted).
    9
    No. 07-20483
    Nor are we convinced that the failure to read a notice exemption for
    avoided transfers into the Act defeats its purpose or leads to “absurd” results.
    The purpose of the Act and its provisions for notice of claims on payment bonds
    is to “protect claimants who provide labor or materials in the construction of
    public works,”12 and also “‘to provide a simple and direct method of giving notice
    and perfecting’” payment bond claims.13 Reading the Act by its terms does not
    by necessity frustrate these purposes or create an absurd construction.
    In Waggoner v. Gonzales, we recognized that “the common mandate of
    statutory construction [is] to avoid absurd results.”14 To avoid absurd results in
    that case, we interpreted the statute by looking to the language of the statute as
    a whole as well as the “plain language of the statute. . . and [its] . . . other
    analogous . . . exceptions.”15 We held, “Although we may well conclude a
    different result is more appropriate, when a statute is clear on its face, we must
    faithfully interpret it.”16 Reading Chapter 2253 by its unambiguous terms,
    which require suppliers to provide notice of a bond claim by the fifteenth day of
    the third month following delivery, does not lead to absurd results. The statute
    says nothing of bankruptcy or of the protections afforded to material suppliers
    when contractors who have purchased supplies file for bankruptcy. Reading an
    exemption into the notice requirement for bankruptcy would create substantial
    questions regarding the proper boundary of inquiry into third party liability for
    the avoided payments.
    12
    Redland Ins. 
    Co., 181 S.W.3d at 511
    .
    13
    
    Id. (quoting Capitol
    Indem. Corp. v. Kirby Rest. Equip. & Chem. Supply Co., 
    170 S.W.3d 144
    , 147 (Tex. App.–San Antonio 2005, pet. filed)).
    14
    
    488 F.3d 632
    , 638 (5th Cir. 2007).
    15
    
    Id. 16 Id.
    at 636.
    10
    No. 07-20483
    Finally, we are unconvinced that by sending a notice claim within three
    days after the date of repayment established by the bankruptcy court,
    approximately 17 months after its delivery of material, Century “substantially
    complied” with Chapter 2253’s notice requirements. Parties have “substantially
    complied” with the notice requirements of the Act and the former versions of the
    Act where their notice used language that was not identical to that contained
    within the Act but conveyed the message of that language,17 or where they sent
    timely and adequate notice by “first-class regular mail instead of certified
    mail.”18      But timing requirements are different.                As the court in Wesco
    Distribution, Inc. v. Westport Group, Inc. held with respect to the materialmen’s
    lien statute, which is also to be liberally construed to protect materialmen,
    “Liberal construction cannot read the timing requirements out of the statute.”19
    III
    Century argues that the district court erred in holding that equitable
    tolling does not apply to its bond claim. We review de novo the district court’s
    interpretation of § 2253.041’s timing provision as a “jurisdictional statutory
    prerequisite” rather than a statute of limitations.20
    As the district court observed, the Texas Court of Civil Appeals held in
    Bunch Electric Co. v. Tex-Craft Builders, Inc. that a notice requirement for
    17
    See, e.g., Featherlite Bldg. Prods. 
    Corp., 714 S.W.2d at 69
    .
    18
    See, e.g., Redland Ins. 
    Co., 181 S.W.3d at 512
    .
    19
    
    150 S.W.3d 553
    , 557, 558 (Tex. App.–2004, no pet.); see also S.A. Maxwell 
    Co., 873 S.W.2d at 453-56
    (sustaining a point of error for untimely notice with respect to a claim under
    Art. 5160, Chapter 2253’s predecessor, but overruling other points of error where the supplier
    provided timely notice and substantially complied with other substantive requirements).
    20
    
    Id. (“De novo
    review applies where a district court ‘interprets a statute or regulation
    to prohibit tolling.’”).
    11
    No. 07-20483
    unpaid bills for materials and labor,21 the now-repealed predecessor to Chapter
    2253,22 was “not a mere statute of limitation, but is a substantive condition
    precedent to the existence of the cause of action.”23 In an unreported opinion, the
    Texas Court of Appeals more recently affirmed that Chapter 2253’s notice
    requirement “is not a mere statute of limitation, but is a substantive condition
    precedent to the existence of a cause of action on the surety bond.”24 Equitable
    tolling does not apply to a “jurisdictional statutory prerequisite,”25 and the court
    did not err in so holding. Concededly, there are occasions where the bankruptcy
    court can override state law which frustrates its statutory mission. Here,
    however, the bonding company’s duty to pay rested in state law. And the power
    of the bankruptcy court did not extend to creating liabilities existing neither in
    federal or state law.
    21
    
    480 S.W.2d 42
    , 45 (Tex. Civ. App. – Tyler 1972, no pet.) (quoting Tex. Rev. Civ. Stat.
    art. 5160). The requirement provided,
    Such claimant shall have given within ninety (90) days after the 10th
    day of the month next following each month in which the labor was done
    or performed, in whole or in part, or material was delivered, in whole or
    in part, for which such claim is made, written notices of the claim by
    certified or registered mail, addressed to the prime contractor at his last
    known business address, or at his residence, and to the surety or
    sureties.
    22
    See S.A. Maxwell 
    Co., 873 S.W.2d at 449
    n.1 (“The legislature repealed article 5160
    effective September 1, 1993, and adopted titles 5, 6, and 10 of the Texas Government Code.
    See Act of May 22, 1993, 73rd Leg., R.S., ch. 268, §§ 1, 46(1), 1993 Tex. Gen. Laws 986. The
    statutory provisions governing public work performance and payment bonds are recodified in
    title 10 of the Texas Government Code.” (citing Tex. Gov’t Code § 2253, et seq.))).
    23
    Bunch Elec. 
    Co., 480 S.W.3d at 45
    .
    24
    Harvest Const. Team v. Hartford Fidelity & Bonding, No. 05-03-00006-CV, 
    2003 WL 23095668
    at *2 n.1 (Tex. App.–Dallas Dec. 31, 2003, rev. denied, rhr’g of pet. denied) (citing
    
    Bunch, 480 S.W.3d at 45
    ).
    25
    See, e.g., Heart Hosp. IV, L.P. v. King, 
    116 S.W.3d 831
    , 836 (Tex. App.– Austin 2003,
    rhr’g overruled; rev. denied) (holding that “ the case before us does not present a limitations
    issue, but rather a jurisdictional statutory prerequisite” and that equitable tolling did not
    apply).
    12
    No. 07-20483
    The district court also held that even if equitable tolling somehow applied,
    Century did not act diligently in providing notice to St. Paul once Century
    learned that its payments would be avoided. We need not address this holding,
    as we affirm the district court’s holding that Chapter 2253’s notice requirement
    is not a statute of limitations.
    AFFIRMED.
    13