Regions Financial Corp. v. Parish Partners Co. , 451 F. App'x 354 ( 2011 )


Menu:
  •      Case: 11-30294   Document: 00511632946   Page: 1   Date Filed: 10/14/2011
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    October 14, 2011
    No. 11-30294                     Lyle W. Cayce
    Summary Calendar                        Clerk
    REGIONS FINANCIAL CORPORATION; REGIONS BANK,
    Plaintiffs-Appellees
    v.
    PARISH PARTNERS COMPANY, L.L.C.,
    Defendant-Appellant
    PARISH PARTNERS COMPANY, L.L.C.,
    Plaintiff-Appellant
    v.
    REGIONS FINANCIAL CORPORATION,
    Defendant-Appellee
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    (08-CV-4301)
    Case: 11-30294       Document: 00511632946         Page: 2     Date Filed: 10/14/2011
    No. 11-30294
    Before KING, JOLLY, and GRAVES, Circuit Judges.
    PER CURIAM:*
    A dispute arose out of a commercial leasing contract between Parish
    Partners Company, L.L.C. (Parish Partners), as the lessor, and Regions Bank or
    Regions Financial Corporation (collectively, Regions), as the lessee, regarding
    a building that was substantially damaged by Hurricane Katrina on August 29,
    2005. On summary judgment, the district court found that Parish Partners
    failed to rebuild and make repairs within a reasonable time under the
    agreement and terminated the contract. Parish Partners challenges the district
    court’s ruling that it failed to restore the leased premises to the condition it was
    in before Hurricane Katrina. For the reasons discussed below, we AFFIRM.
    FACTS1
    Parish Partners was the successor-in-interest as the lessor under a written
    lease agreement dated October 1, 1992. Regions Bank was the successor-in-
    interest to Secor Bank and Federal Savings Bank, the original lessee. The
    leased premises consists of a portion of the first floor of a building and drive-
    through banking area located in New Orleans, Louisiana (Leased Premises).
    The original term of the lease ended on August 31, 2002, but Parish Partners
    and Regions signed a First Amendment to the lease, extending it through
    August 31, 2012.
    *
    Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH CIR.
    R. 47.5.4.
    1
    Procedural posture: On August 15, 2008, Parish Partners filed a petition for
    declaratory relief and damages against Regions Financial Corporation in the Civil District
    Court for the Parish of New Orleans, State of Louisiana (Regions Bank was not a defendant
    in this suit). Parish Partners sought unpaid rent and insurance proceeds. On August 28, 2008,
    Regions filed a complaint against Parish Partners in the Eastern District of Louisiana for
    declaratory judgment seeking the termination or dissolution of the lease effective August 29,
    2005. On September 9, 2008, Regions filed a notice of removal from the Civil District Court
    and the Eastern District of Louisiana ordered that the cases be consolidated.
    2
    Case: 11-30294       Document: 00511632946         Page: 3     Date Filed: 10/14/2011
    No. 11-30294
    Hurricane Katrina arrived on August 29, 2005, and caused severe
    damages to the Leased Premises. Damages included flood water in the building,
    roof damage, broken windows, and a variety of other damages caused by wind
    and rain. Parish Partners attempted to communicate with Regions from
    September, 2005, to discuss casualty loss, rent abatement, photographs, and
    information related to repairs. Parish Partners also communicated to Regions
    that it elected to make repairs under the lease agreement rather than cancelling
    the lease.2 Parish Partners discovered that Regions had hired an architect for
    design renovations and attempted communications to inquire about it. But
    Regions was non-responsive when Parish Partners inquired about the hire.
    Following Katrina, Parish Partners changed the locks to the Leased Premises
    to gain access in accordance with Section 18 of the lease agreement.3 Parish
    Partners gained access to the Leased Premises and made an assessment of the
    damages; it chose to rebuild, thus its obligations to make repairs came into
    existence on approximately October 30, 2005. Parish Partners’s obligation for
    repairs were subject to delays such as unavailability of materials or government
    regulation; however, these were non-factors for this construction project. Both
    parties agree that the Katrina-caused damages were extensive but repairs could
    be completed within 120 days because the required construction work was very
    typical of a branch bank. It is not clear, however, whether Parish Partners could
    have repaired the Leased Premises to pre-Katrina conditions within 120 days
    immediately after the Hurricane because New Orleans was shut down for at
    least thirty days after the storm. On the other hand, expert testimony provides
    2
    Under the lease agreement, it was required within sixty-days to exercise its option of
    terminating the lease agreement or making repairs to the property.
    3
    This Section discusses access to the Leased Premises by the lessor or lessor’s agents;
    the provision gives the lessor the right at all times to enter and examine the Leased Premises
    or make repairs to the property.
    3
    Case: 11-30294    Document: 00511632946      Page: 4   Date Filed: 10/14/2011
    No. 11-30294
    that contractors were on the ground within two weeks after Katrina’s landfall
    and were capable of completing construction work as necessary materials and
    manpower were available. As of August 12, 2006, the Leased Premises was in
    a shell condition, consisting of bare slab and Sheetrock walls. By this time,
    Parish Partners had replaced rusted studs and installed new ceiling tiles among
    other repairs. During the course of repairs, Parish Partners received some of the
    insurance proceeds to which it was entitled and was able to complete the
    restoration to a “rentable shell condition” by August 28, 2006.
    STANDARD OF REVIEW
    This court has jurisdiction under 28 U.S.C. § 1291 and reviews the district
    court's grant of summary judgment de novo, applying the same standard as the
    district court. Golden Bridge Tech., Inc., v. Motorola, Inc. 
    547 F.3d 266
    , 270 (5th
    Cir. 2008). The granting of summary judgment is appropriate if there is no
    genuine issue of material fact and the moving party is entitled to judgment as
    a matter of law. Fed. R. Civ. P. 56(a); Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 247 (1986). When the moving party has carried its burden, the non-moving
    party must demonstrate specific facts showing a genuine factual issue for trial.
    Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 
    475 U.S. 574
    , 587 (1986).
    DISCUSSION
    The crux of this dispute is the extent and timeliness of Parish Partners’s
    restoration of the damaged Leased Premises following Hurricane Katrina.
    Parish Partners contends that it has sufficiently performed under the lease
    agreement. Various repairs were made to the air-conditioning and heating
    system, all metal rusted studs were replaced, and the storefront was restored.
    Furthermore, Parish Partners argues that the district court erred in dissolving
    the contract because, at the very least, Parish Partners substantially performed
    under the lease agreement, and the remaining work could have been quickly
    completed.
    4
    Case: 11-30294    Document: 00511632946       Page: 5   Date Filed: 10/14/2011
    No. 11-30294
    Regions contends that Parish Partners decided to repair and rebuild the
    damaged property instead of terminating the lease agreement. And because
    Parish Partners did not exercise its right to terminate the lease within sixty
    days of Hurricane Katrina, it had an obligation to repair and restore the
    damaged premises with reasonable promptness. Reasonable promptness under
    the instant agreement is 120 days, or approximately four months after damages
    occurred.
    1) Timing of the Repairs
    Section 7 of the lease agreement discusses the parties’ rights and duties
    related to casualty and damages; this Section states in relevant part:
    “CASUALTY PROVISIONS: Lessee shall give lessor immediate
    notice of any damage to the Leased Premises caused by fire or other
    casualty. If the Leased Premises or Building is damaged by fire or
    other casualty to such an extent that same can be repaired within
    a period of one hundred twenty (120) days, Lessor may, at its option,
    rebuild or repair, as the case may be, or cancel and terminate this
    Lease. Unless Lessor notifies Lessee in writing within a period of
    sixty (60) days after the occurrence of the fire or other casualty that
    it does not intend to rebuild or repair, it shall then be obligated to
    rebuild or repair...All work of repairing or rebuilding shall be
    performed with reasonable promptness, due allowance being made
    for reasonable delay which may arise by reason of adjustment or
    loss under insurance policies on the part of Lessor or Lessee and for
    reasonable delay on account of strike, lockout, governmental
    regulation, or other cause beyond Lessor’s control...If Lessor elects
    to cancel by giving notice to Lessee within the 60-day period herein
    above provided, this Lease shall thereupon terminate and expire as
    of the date of the occurrence of the fire and other casualty...”
    The parties do not dispute that the Katrina-caused damages were within
    the extent that could be repaired in 120 days; an expert report on record
    provides that sufficient materials were available so that a reasonably competent
    general contractor could have restored the premises to pre-Katrina conditions.
    The construction work would be typical of a branch bank and there were no
    5
    Case: 11-30294      Document: 00511632946         Page: 6     Date Filed: 10/14/2011
    No. 11-30294
    logistical challenges that would have affected construction time. Moreover, the
    trial court accepted as true Parish Partners’s evidence that repairs could have
    been completed within 120-days. And because Parish Partners elected to make
    repairs rather than cancel the contract, it was obliged to complete the
    restoration within the contracted time frame.4
    Section 7 of the lease agreement requires Parish Partners to complete
    restoration of the Leased Premises within approximately four months after
    Hurricane Katrina struck. According to Parish Partners’s brief and sworn
    affidavit of Mokhtar Abelmalek, an employee of the construction company who
    oversaw the repairs to the Leased Premises, the property was ready to receive
    Regions on August 28, 2006. Basic repairs for things such as the cooling and
    heating unit and electricity were made by June-July, 2006. According to Parish
    Partners, the condition of the Leased Premises as of August 28, 2006 was a
    “shell condition,” which is all the lease requires of it.
    But the lease requires repair work to be completed approximately at the
    end of December, 2005. Even if the 120-days count down did not begin until
    after the sixty-day evaluation period discussed in Section 7 (the clock then would
    have begun on approximately October 30, 2005), the repairs should have been
    completed no later than February 28, 2006. Either application produces the
    same result: Parish Partners failed to complete its repair obligations with
    reasonable promptness under the leasing agreement. The parties agree that the
    property could have been repaired within 120-days. But as of January 27, 2010,
    Parish Partners had failed to repair the Leased Premises to a suitable condition
    for a branch bank. The record shows that Parish Partners had the ability
    4
    Parish Partners alleges that Regions failed to turnover insurance proceeds under the
    lease agreement, presumably to argue that Regions’s actions hindered Parish Partners from
    completing repairs on time. But full receipt of insurance proceeds did not financially hinder
    it from completing repairs as it was able to eventually complete the restoration work to a
    rentable shell condition.
    6
    Case: 11-30294      Document: 00511632946        Page: 7     Date Filed: 10/14/2011
    No. 11-30294
    (available general contractors and funding) to complete repairs but it did not.
    It points to Regions’s uncooperative behavior as a reason for its inability to
    complete the restoration project.5 But nothing in the record supports the notion
    that Regions caused Parish Partners’s inability to restore the Leased Premises
    to a condition similar to its pre-Katrina condition, which was suitable for an
    operational branch bank. General contractors with adequate manpower and
    materials were available for work, therefore Parish Partners had the necessary
    resources to complete the restoration project.
    2. The Leased Premises in a Shell Condition
    Parish Partners contends that it was obligated to restore the Leased
    Premises to a shell condition and it did so by August 28, 2006. It also holds that
    the lease agreement does not explicitly say that the 120-days time frame begins
    immediately after the damages are caused. But testimony by Ms. Denise
    Gaines6 established that the obligation to make repairs began on October 30,
    2005, allowing for the sixty-day evaluation period.
    Regions argues that by August, 2006, the Leased Premises lacked finished
    floors and interior doors. The district court found that, as of the day of summary
    judgment arguments, the Leased Premises still had not been restored to pre-
    Katrina conditions or similar to those conditions. The essence of Regions’s
    argument is that the Leased Premises in a “shell condition,” which lacks doors
    and door frames among other things, is not in a condition suitable to operate a
    branch bank. Therefore, dissolution of the lease is appropriate.
    5
    Parish Partners argues that Regions ignored essentially all communication from it.
    Many of Parish Partners’s communications related to requests for drawings, photographs, and
    other information regarding repair work. Regions hired architects to design renovations but
    ignored Parish Partners’s request for input.
    6
    Ms. Gaines is the Managing Director at Kailas Companies, which is a company that
    manages real estate property owned by Parish Partners. She has been employed there for
    fourteen years.
    7
    Case: 11-30294    Document: 00511632946       Page: 8   Date Filed: 10/14/2011
    No. 11-30294
    The lease does not discuss Regions’s remedies if Parish Partners defaults.
    Thus, its remedies are determined by the Louisiana Civil Code. Tetra Techs.,
    Inc., v. La. Fruit Co., 252 F. App’x 639, 644 (5th Cir.2007)(citing Tassin v. Slidell
    Mini-Storage, Inc., 
    396 So. 2d 1261
    , 1264 (La. 1981)). Parish Partners evaluated
    the damages caused by Katrina and decided to make repairs. Therefore, it was
    obliged to restore the Leased Premises to a condition adequate for operating a
    bank. La. Civ. Code 2682 (“The lessor is bound: (2) To maintain the thing in a
    condition suitable for the purpose of which it was leased...”). A failure to perform
    under the agreement may cause the lease to be cancelled. See Reed v. Classified
    Parking Sys., 
    232 So. 2d 103
    , 107 (La. App. Ct. 1970)(citations omitted); La. Civ.
    Code 2719 (stating that “[w]hen a party to the lease fails to perform his
    obligations under the lease or under this Title, the other party may obtain
    dissolution of the lease...”). The Louisiana Civil Code also states that “[w]hen
    the obligor fails to perform, the obligee has a right to the judicial dissolution of
    the contract or, according to the circumstances, to regard the contract as
    dissolved...” La. Civ. Code 2013. The record shows that as of August 28, 2006,
    one year after Katrina caused the damages, the Leased Premises was not
    restored to a condition similar to a pre-Katrina operational branch bank; in
    other words, it was not fit for occupancy for the intended use of a bank. And
    August 28, 2006, is clearly beyond the 120-days time frame (or 180-days if the
    sixty-day evaluation period is included) contemplated by the lease.
    Because Section 7 of the contract provides a time frame for casualty-
    related repairs and those repairs were not completed within the contemplated
    time (nor did Parish Partners substantially perform within the contemplated
    period), other arguments need not be addressed. The contractual duties were
    clear and Parish Partners failed to restore the Leased Premises within the
    contract period, therefore we AFFIRM the district court.
    8
    

Document Info

Docket Number: 11-30294

Citation Numbers: 451 F. App'x 354

Judges: King, Jolly, Graves

Filed Date: 10/14/2011

Precedential Status: Non-Precedential

Modified Date: 11/5/2024